CN209672579U CN201920369646.5U CN201920369646U CN209672579U CN 209672579 U CN209672579 U CN 209672579U CN 201920369646 U CN201920369646 U CN 201920369646U CN 209672579 U CN209672579 U CN 209672579U
Authority
CN
China
Prior art keywords
triple valve
water pipe
heat exchanger
wall
burner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920369646.5U
Other languages
Chinese (zh)
Inventor
张禄勤
张红莒
张超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Sheng Kai Thermal Equipment Co Ltd
Original Assignee
Guangdong Sheng Kai Thermal Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Sheng Kai Thermal Equipment Co Ltd filed Critical Guangdong Sheng Kai Thermal Equipment Co Ltd
Priority to CN201920369646.5U priority Critical patent/CN209672579U/en
Application granted granted Critical
Publication of CN209672579U publication Critical patent/CN209672579U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Steam Or Hot-Water Central Heating Systems (AREA)

Abstract

The utility model is more particularly to the wall-hung boiler for being a kind of anti-dry, including body, burner is equipped in body, the top of burner is equipped with first-class heat exchanger, first-class heat exchanger is connected with burner, the top of first-class heat exchanger is equipped with blower, the air inlet of blower is connected with the inner cavity of first-class heat exchanger, wherein the combustion gas input terminal of burner is connected with gas ratio valve, first-class heat exchanger is respectively equipped with the second water pipe and the 4th water pipe, second water pipe and the 4th water pipe are connected, second water pipe one end is connected with the first triple valve, 4th water pipe one end is connected with the second triple valve, it is connected between first triple valve and the second triple valve by bypassing device, first triple valve is equipped with water pump.The beneficial effects of the utility model are: this structure can make the first triple valve and the second triple valve be connected by bypassing device, and implement to circulate, avoids first-class heat exchanger overheat that dry combustion method phenomenon is caused to occur.

Description

A kind of wall-hung boiler of anti-dry
Technical field
The utility model relates to wall-hung boiler technical field, the wall-hung boiler of specifically a kind of anti-dry.
Background technique
Wall-hung boiler is exactly the abbreviation of burnt gas wall hanging furnace in fact.Fuel wall hanging formula heating stove is the maturation for being in fashion European decades Product." wall-hung boiler " word term foreign word, full name is: " fuel wall hanging formula heating stove ", the standard call of our countries are as follows: " the quick heater of water for heating of fuel wall hanging formula ", but it is not traditional gas heater, has essence with water heater Difference.It is a variety of with anti-frost protection, anti-dry protection, accident extinguishing protection, the excessively high protection of temperature, the anti-jamming protection of water pump etc. Safety precautions.It can be with external indoor thermostat, to realize that personalized temperature is adjusted and energy-efficient purpose.
For this purpose, the burnt gas wall hanging furnace of anti-dry is built in modern house with the continuous improvement of modern urban construction level It is more and more widely used in building, heating or hot water supply applied to each family etc..For this purpose, anti-dry Burnt gas wall hanging furnace is a very accurate heating system, if any one component, which goes wrong, can all lead to wall-hung boiler It cannot normally work, not only influence the normal use of people, bring greatly life inconvenient, and maintenance needs professional people Scholar causes maintenance cost to improve thus.
Existing wall-hung boiler typically controls the operation of entire wall-hung boiler, in reality by pressure type hydraulic pressure switch As long as will light in use, one detects signal, it would not care for whether water pump delivers water into furnace at this time, so, it is existing With the presence of the certain risk of structure, dry combustion method phenomenon, or even damage whole system occurs, causes unnecessary loss to client, The defect of existing product thus, has much room for improvement!
From the foregoing, it will be observed that it has been extremely urgent for solving these problems!
In view of this, the present inventor has done in-depth study, and by feat of experience engaged in relevant industries for many years and reality It tramples, designs a kind of burnt gas wall hanging furnace of anti-dry, can solve deficiency in the prior art, structure is simply exquisite, prevents dry combustion method The appearance of phenomenon, improves the running safety coefficient of whole system, thus this case generates.
Summary of the invention
The purpose of the utility model is to overcome above-mentioned the deficiencies in the prior art, provide one kind and avoid first-class heat exchanger mistake The wall-hung boiler for the anti-dry that thermal conductivity causes dry combustion method phenomenon to occur.
A kind of wall-hung boiler of anti-dry of the utility model description, including body, body is interior to be equipped with burner, burner Top be equipped with first-class heat exchanger, first-class heat exchanger is connected with burner, the top of first-class heat exchanger equipped with blower, blower Air inlet is connected with the inner cavity of first-class heat exchanger, and wherein the combustion gas input terminal of burner is connected with gas ratio valve, and level-one is changed Hot device is respectively equipped with the second water pipe and the 4th water pipe, and the second water pipe and the 4th water pipe are connected, and second water pipe one end is connected with One triple valve, the 4th water pipe one end are connected with the second triple valve, pass through bypass device phase between the first triple valve and the second triple valve Connection, the first triple valve are equipped with water pump.
Specific further, the bypass device is equipped with temperature sensor, the delivery outlet of temperature sensor and the second triple valve phase Connection.
Specific further, second triple valve is respectively equipped with first interface and second interface.
Specific further first triple valve is equipped with the 5th interface, the 6th interface and the 7th interface, and water pump is installed on the On six interfaces.
Specific further, the first-class heat exchanger is additionally provided with secondary heat exchanger, and second water pipe one end is connected to secondary heat exchange Device is connected between secondary heat exchanger and first-class heat exchanger by the first water pipe.
Specific further the burner is equipped with third water pipe, and third water pipe is connected with the second water pipe, third water pipe one End is placed in burner.
Specific further, the bypass device is equipped with third interface and the 4th interface.
Specific further second triple valve is equipped with motor, and motor is connected with reversing shaft, and reversing shaft is inserted in second In triple valve.
It is specific to be further respectively equipped with the first demarcation plate and the second demarcation plate in the bypass device, the first demarcation plate and the Two compartment plate constitutes detour water channel.
It is specific further, expansion tank is equipped at the back side of the body, expansion tank is connected with the first triple valve, swollen The diameter of swollen water tank and the width of body are equal.
The beneficial effects of the utility model are: this structure can make the first triple valve and the second triple valve be connected by bypassing device It is logical, and implement to circulate, avoid first-class heat exchanger overheat that dry combustion method phenomenon is caused to occur.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the intracorporal first angled arrangement schematic diagram of the machine of the utility model.
Fig. 3 is second angled arrangement schematic diagram of Fig. 2.
Fig. 4 is the third angled arrangement schematic diagram of Fig. 2.
Fig. 5 is the bypass device structural schematic diagram of the utility model.
Fig. 6 is another angled arrangement schematic diagram of Fig. 5.
Fig. 7 is the schematic diagram of internal structure for bypassing device.
The icon of the following drawings illustrates:
Body 1;Water pump 2;Gas ratio valve 3;First triple valve 4;5th interface 401;6th interface 402;7th interface 403;Second triple valve 5;Temperature sensor 501;First interface 502;Second interface 503;Motor 504;Burner 6;Level-one is changed Hot device 7;Blower 8;Secondary heat exchanger 9;First water pipe 10;Second water pipe 11;Third water pipe 12;4th water pipe 13;Bypass device 14; Third interface 1401;4th interface 1402;First demarcation plate 1403;Second demarcation plate 1404;Expansion tank 15.
Specific embodiment
The embodiments of the present invention are described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning Same or similar element or element with the same or similar functions are indicated to same or similar label eventually.Below by ginseng The embodiment for examining attached drawing description is exemplary, and is only used for explaining the utility model, and should not be understood as to the utility model Limitation.
As shown in Figures 1 to 7, the wall-hung boiler of a kind of anti-dry of the utility model description, including body 1 are set in body 1 There is burner 6, the top of burner 6 is equipped with first-class heat exchanger 7, and first-class heat exchanger 7 is connected with burner 6, first-class heat exchanger 7 top is equipped with blower 8, and the air inlet of blower 8 is connected with the inner cavity of first-class heat exchanger 7, wherein the combustion gas input of burner 6 End is connected with gas ratio valve 3, and first-class heat exchanger 7 is respectively equipped with the second water pipe 11 and the 4th water pipe 13, the second water pipe 11 and the Four water pipes 13 are connected, and 11 one end of the second water pipe is connected with the first triple valve 4, and 13 one end of the 4th water pipe is connected with the second triple valve 5, it is connected between the first triple valve 4 and the second triple valve 5 by bypassing device 14, the first triple valve 4 is equipped with water pump 2.
This structure can make the first triple valve 4 be connected with the second triple valve 5 by bypassing device 14, and implement to circulate, Avoid the overheat of first-class heat exchanger 7 that dry combustion method phenomenon is caused to occur.More specifically: opening water pump 2 and tap water from the first triple valve 4 Into water, and under the action of water pump 2, cold water supplies water from the second water pipe 11 to first-class heat exchanger 7, and gas ratio valve 3 is to combustion Burner 6 is implemented for combustion gas, and burner 6 carries out burning after ignition electrode point combustion and heats to first-class heat exchanger 7, level-one heat exchange Device 7 carries out heat exchange, so that cold water is become hot water, and flow to from the 4th water pipe 13 of first-class heat exchanger 7, the 4th water pipe 13 is again The output of the second triple valve 5 is inputted,
Second triple valve 5 is connected to floor heating pipe and heater, and interior is heated in floor heating pipe and heater implementation. The surface temperature of first-class heat exchanger 7 is more than predetermined value, and bypass device 14 is connected the first triple valve 4 and is connected to the second triple valve 5, makes one Implement circulation between grade heat exchanger 7, the second water pipe 11, the 4th water pipe 13, the first triple valve 4 and the second triple valve 5, bypasses Device 14 implements heat dissipation, and gas ratio valve 3 stops making burner 6 stop working for combustion gas, first-class heat exchanger being avoided to cross thermal conductivity Dry combustion method phenomenon is caused to occur.
Wherein the second water pipe 11 is connected with the 4th water pipe 13 and is arranged in detour shape in first-class heat exchanger 7, makes one The rate of heat exchange of grade heat exchanger 7 is further promoted, and first-class heat exchanger 7 includes that multiple fins are formed by stacking, the second water pipe 11 It is each passed through fin with the 4th water pipe 13 and is connected and be welded.
Blower 8 is located at the top of first-class heat exchanger 7, and when blower 8 starts, the cigarette that burner 6 is generated is discharged outside body 1. First-class heat exchanger 7 and burner 6 using welding or can be spirally connected or snap implements connection.It welds or is spirally connected or snap It is the prior art respectively, no longer deeply discusses.In addition, gas ratio valve 3 implements control gas proportion output, best gas supply is provided Amount.
Bypass device 14 described in the utility model is equipped with temperature sensor 501, the delivery outlet of temperature sensor 501 and the two or three Port valve 5 is connected.Temperature sensor 501 is used to detect the second triple valve 5 and bypasses the water temperature flowed through between device 14, and water temperature reaches When designated value, temperature sensor 501 exports electric signal;In addition, second triple valve 5 is respectively equipped with first interface 502 and Two interfaces 503.Furthermore first triple valve 4 is equipped with the 5th interface 401, the 6th interface 402 and the 7th interface 403, water pump 2 It is installed on the 6th interface 402.First interface 502, second interface 503, the 5th interface 401, the 6th interface 402 and the 7th interface 403 are connected to floor heating pipe, heater and running water pipe, floor heating pipe, heater and running water pipe respectively with the first triple valve 4 The mode that is connected with the second triple valve 5 is the prior art, and not the object of the invention, no longer discusses how to install.
First-class heat exchanger 7 described in the utility model is additionally provided with secondary heat exchanger 9, and 11 one end of the second water pipe is connected to second level and changes Hot device 9 is connected between secondary heat exchanger 9 and first-class heat exchanger 7 by the first water pipe 10.Secondary heat exchanger 9 can be to the first water The water flowed through in pipe 10 is preheated, and is inputted the hot gas of first-class heat exchanger 7 in secondary heat exchanger 9 by blower 8.Separately Outside, the burner 6 is equipped with third water pipe 12, and third water pipe 12 is connected with the second water pipe 11, and 12 one end of third water pipe is placed in In burner 6.Furthermore the bypass device 14 is equipped with third interface 1401 and the 4th interface 1402.On second triple valve 5 Equipped with motor 504, motor 504 is connected with reversing shaft, and reversing shaft is inserted in the second triple valve 5.Motor 504 can drive reversing shaft Rotation makes the water outlet of the second triple valve 5 change flow direction, so that hot water is flowed into bypass device 14 from the second triple valve 5, wherein hot water It is flowed into bypass device 14 again by the test side of temperature sensor 501.
It is respectively equipped with the first demarcation plate 1403 and the second demarcation plate 1404 in bypass device 14 described in the utility model, first point Partition 1403 and the second demarcation plate 1404 constitute detour water channel, and so that hot water is flowed through bypass device 14 makes water flow further cool down, and are promoted Heat dissipation effect.Second demarcation plate 1404 is located at the centre of the first demarcation plate 1403, and there are space, energy between the first demarcation plate 1403 It allows hot water to pass through, and is in contact with the inner wall of bypass device 14, implement heat transfer effect.First demarcation plate 1403 and second point Also there are certain spaces between partition 1404, also function to secondary buffer effect.
Expansion tank 15 is equipped at the back side of body 1 described in the utility model, expansion tank 15 is connected with the first triple valve 4 It connects, the diameter of expansion tank 15 is equal with the width of body 1.Expansion tank 15 plays the role of reducing hydraulic pressure, and swelling water The size of case 15 further increases, and provides the effect that buffering hydraulic pressure is implemented in bigger space.
Expansion tank 15 is in rounded shape, plays water pressure energy and is uniformly distributed in expansion tank 15.The entrance of expansion tank 15 In the lower end of expansion tank 15, convenient for being connected with the first triple valve 4, in this attached drawing without display, general technology people can be passed through It is to implement connection function using conduit that member, which is appreciated that, and conduit is connected using screw connection manner.
Upper is only the preferred embodiment of the utility model, is not intended to limit the utility model, all practical new at this Made any modification, equivalent replacement or improvement etc., should be included in the protection of the utility model within the spirit and principle of type Within the scope of.

Claims (10)

1. a kind of wall-hung boiler of anti-dry, including body (1), body (1) is interior to be equipped with burner (6), the top of burner (6) Equipped with first-class heat exchanger (7), first-class heat exchanger (7) is connected with burner (6), and the top of first-class heat exchanger (7) is equipped with blower (8), the air inlet of blower (8) is connected with the inner cavity of first-class heat exchanger (7), it is characterised in that: the combustion gas of burner (6) inputs End is connected with gas ratio valve (3), and first-class heat exchanger (7) is respectively equipped with the second water pipe (11) and the 4th water pipe (13), the second water Pipe (11) is connected with the 4th water pipe (13), and the second water pipe (11) one end is connected with the first triple valve (4), the 4th water pipe (13) one End is connected with the second triple valve (5), is connected between the first triple valve (4) and the second triple valve (5) by bypassing device (14), the One triple valve (4) is equipped with water pump (2).
2. a kind of wall-hung boiler of anti-dry according to claim 1, it is characterised in that: the bypass device (14) passes equipped with temperature The delivery outlet of sensor (501), temperature sensor (501) is connected with the second triple valve (5).
3. a kind of wall-hung boiler of anti-dry according to claim 1, it is characterised in that: second triple valve (5) sets respectively There are first interface (502) and second interface (503).
4. a kind of wall-hung boiler of anti-dry according to claim 1, it is characterised in that: first triple valve (4) is equipped with the Five interfaces (401), the 6th interface (402) and the 7th interface (403), water pump (2) are installed on the 6th interface (402).
5. a kind of wall-hung boiler of anti-dry according to claim 1, it is characterised in that: the first-class heat exchanger (7) is additionally provided with Secondary heat exchanger (9), the second water pipe (11) one end are connected to secondary heat exchanger (9), secondary heat exchanger (9) and first-class heat exchanger (7) it is connected between by the first water pipe (10).
6. a kind of wall-hung boiler of anti-dry according to claim 1, it is characterised in that: the burner (6) is equipped with third water It manages (12), third water pipe (12) is connected with the second water pipe (11), and third water pipe (12) one end is placed in burner (6).
7. a kind of wall-hung boiler of anti-dry according to claim 1, it is characterised in that: the bypass device (14) connects equipped with third Mouth (1401) and the 4th interface (1402).
8. a kind of wall-hung boiler of anti-dry according to claim 1, it is characterised in that: second triple valve (5) is equipped with Motor (504), motor (504) are connected with reversing shaft, and reversing shaft is inserted in the second triple valve (5).
9. a kind of wall-hung boiler of anti-dry according to claim 1, it is characterised in that: be respectively equipped in the bypass device (14) First demarcation plate (1403) and the second demarcation plate (1404), the first demarcation plate (1403) and the second demarcation plate (1404) constitute detour Water channel.
10. a kind of wall-hung boiler of anti-dry according to claim 1, it is characterised in that: be equipped at the back side of the body (1) Expansion tank (15), expansion tank (15) are connected with the first triple valve (4), diameter and body (1) of expansion tank (15) Width is equal.
CN201920369646.5U 2019-03-22 2019-03-22 A kind of wall-hung boiler of anti-dry Expired - Fee Related CN209672579U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920369646.5U CN209672579U (en) 2019-03-22 2019-03-22 A kind of wall-hung boiler of anti-dry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920369646.5U CN209672579U (en) 2019-03-22 2019-03-22 A kind of wall-hung boiler of anti-dry

Publications (1)

Publication Number Publication Date
CN209672579U true CN209672579U (en) 2019-11-22

Family

ID=68572460

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920369646.5U Expired - Fee Related CN209672579U (en) 2019-03-22 2019-03-22 A kind of wall-hung boiler of anti-dry

Country Status (1)

Country Link
CN (1) CN209672579U (en)

Similar Documents

Publication Publication Date Title
CN107477860A (en) A kind of double thermal source gas-heating water heaters with zero cold water function
CN205561228U (en) Gas water heater
CN205002407U (en) Constant -temperature gas water heater
CN107726428A (en) The heating system of domestic solar heat collector condensing gas wall hanging stove
CN108895672A (en) Burnt gas wall hanging furnace
CN106091357A (en) Gas heater
CN206055937U (en) Gas heater
CN205825411U (en) A kind of gas heater of band heating function
CN209672579U (en) A kind of wall-hung boiler of anti-dry
CN207515033U (en) The heating system of domestic solar heat collector-condensing gas wall hanging stove
CN112283948B (en) Gas heating water heater with zero cold water function
CN108844220A (en) A kind of gas heater with heating function
CN212006196U (en) Wall-hanging stove hot water system
CN210624878U (en) Sleeve type wall-mounted furnace
CN208606376U (en) A kind of shunt gas heater with ever-burning flame and zero cold water
CN209027098U (en) Zero cold water structure of one kind and dual-purpose stove
CN203586524U (en) Domestic water heater with gas-electric hybrid heating dual working condition complementary work mode
CN205690506U (en) Wall-hung boiler
CN213984066U (en) Gas heating water heater with zero cold water function
CN208154802U (en) Gas heater
CN209726492U (en) A kind of wall-hung boiler of the pre- heat function of waste heat
CN211204401U (en) Wall-mounted stove
CN219494223U (en) Solar energy and gas heating water heater combined dual-energy heating system
CN215412557U (en) Safety protection structure for long open fire of gas water heater
CN217209535U (en) Wall-mounted furnace

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191122