CN209656029U - A kind of tunnel deformation observation mark - Google Patents

A kind of tunnel deformation observation mark Download PDF

Info

Publication number
CN209656029U
CN209656029U CN201920722103.7U CN201920722103U CN209656029U CN 209656029 U CN209656029 U CN 209656029U CN 201920722103 U CN201920722103 U CN 201920722103U CN 209656029 U CN209656029 U CN 209656029U
Authority
CN
China
Prior art keywords
anchoring section
observation mark
tunnel
sleeve
deformation observation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920722103.7U
Other languages
Chinese (zh)
Inventor
张宜鑫
常帅斌
陈明
张双龙
庞广龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201920722103.7U priority Critical patent/CN209656029U/en
Application granted granted Critical
Publication of CN209656029U publication Critical patent/CN209656029U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

A kind of tunnel deformation observation mark, including anchoring section, observation bid section and connection sleeve.Anchoring section is fixed in preliminary bracing gunite concrete, anchoring section is mechanically connected with sleeve one end is connect, connection sleeve other end welding observation mark, after the completion of Tunnel gunite concrete, it drills in deformation observation mark design position, deformation observation mark is installed, it is only mechanical to dismantle observation mark part when observation mark is removed, the processing is simple for such deformation observation mark, low in cost, construction dismounting is quick for installation, reduces the quality and security risk of conventional construction.

Description

A kind of tunnel deformation observation mark
Technical field
The utility model belongs to technical field of tunnel construction, and in particular to a kind of tunnel deformation observation mark.
Background technique
At present in constructing tunnel, deformation monitoring measurement is to guarantee the important means of tunnel safety construction, more in high-speed rail construction Using non-contact measurement, deformation observation target installation quality is directly related to the accuracy of deformation monitoring metric data, deformation Monitoring parameter measuring point is more, amount is big, and while removing after deformation monitoring measures faces splash guard and is laid with operating area, and when dismounting mostly uses Machine cuts, the deformation observation mark after cutting cancel, if cutting is not thorough, exposed parts will wear out splash guard, shadow The waterproof effect for ringing tunnel, causes hidden danger of quality.
Summary of the invention
In order to overcome the above-mentioned deficiencies of the prior art, the purpose of the utility model is to provide a kind of tunnel deformation observation mark, It is easy to process, it is low in cost, it firmly installs, can be recycled after dismounting, and there is no exposed parts after removing, ensure that tunnel The construction quality of the accurate and splash guard of deformation monitoring metric data.
In order to realize that above-mentioned the deficiencies in the prior art, the technical solution adopted in the utility model are:
A kind of tunnel deformation observation mark, including anchoring section, anchoring section are fixed in preliminary bracing gunite concrete, anchoring section It is mechanically connected with sleeve one end is connect, the connection sleeve other end welds observation mark.
The mechanical connection is to be threadedly coupled.
The anchoring section uses 22 steel bar meter of φ, after the completion of Tunnel gunite concrete, in design position It sets and drills, drilling depth guarantees that anchoring section anchors into 25~30cm of basement rock, is fixed with early strong Anchor Agent, anchoring section and connector sleeve The cylinder non-bulging gunite concrete face in coupling part.
The beneficial effects of the utility model are:
Deformation observation mark firmly installs, and the observation mark part of dismounting can recycle, and when dismounting is convenient and efficient, after dismounting Gunite concrete face does not have exposed parts, reduces the hidden danger of quality of splash guard construction.
Detailed description of the invention
Fig. 1 is the elevation of the utility model.
Wherein, 1 is anchoring section;2 be connection sleeve;3 be observation mark.
Specific embodiment
The utility model is further discussed below below in conjunction with attached drawing.
As shown in Figure 1, a kind of tunnel deformation observation mark, including anchoring section 1, it is mixed that anchoring section 1 is fixed on preliminary bracing injection In solidifying soil, anchoring section 1 welds observation mark 3 with 2 one end of sleeve mechanical connection, connection 2 other end of sleeve is connect.
The mechanical connection is to be threadedly coupled.
The anchoring section 1 uses 22 steel bar meter of φ, after the completion of Tunnel gunite concrete, in design position It sets and drills, drilling depth guarantees that anchoring section anchors into 25~30cm of basement rock, is fixed with early strong Anchor Agent, while guaranteeing to be welded with The anchoring section 1 of observation mark 3 with connect the non-bulging gunite concrete face in 2 coupling part of sleeve.Observation mark part and connection sleeve weldering It connects in succession, after deformation observation, when deformation observation mark is removed, removes exposed observation mark part and connection sleeve.

Claims (3)

1. a kind of tunnel deformation observation mark, including anchoring section (1), which is characterized in that anchoring section (1) is fixed on preliminary bracing injection In concrete, anchoring section (1) welds observation mark (3) with sleeve (2) one end mechanical connection, connection sleeve (2) other end is connect.
2. a kind of tunnel deformation observation mark according to claim 1, which is characterized in that the mechanical connection is screw thread company It connects.
3. a kind of tunnel deformation observation mark according to claim 1, which is characterized in that the anchoring section (1) uses φ 22 steel bar meters, anchoring section (1) drill after the completion of Tunnel gunite concrete in design position, and drilling is deep Degree guarantees that anchoring section anchors into 25~30cm of basement rock, is fixed with early strong Anchor Agent, anchoring section (1) with connect sleeve (2) coupling part Non-bulging gunite concrete face.
CN201920722103.7U 2019-05-20 2019-05-20 A kind of tunnel deformation observation mark Active CN209656029U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920722103.7U CN209656029U (en) 2019-05-20 2019-05-20 A kind of tunnel deformation observation mark

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920722103.7U CN209656029U (en) 2019-05-20 2019-05-20 A kind of tunnel deformation observation mark

Publications (1)

Publication Number Publication Date
CN209656029U true CN209656029U (en) 2019-11-19

Family

ID=68530249

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920722103.7U Active CN209656029U (en) 2019-05-20 2019-05-20 A kind of tunnel deformation observation mark

Country Status (1)

Country Link
CN (1) CN209656029U (en)

Similar Documents

Publication Publication Date Title
CN108468539B (en) Drill bit pressure real-time measuring device during construction of cement soil mixing pile
CN102251781A (en) Guiding horizontal jet grouting pile pre-support construction method for scattered particle rock surrounding tunnel
CN102926413A (en) Embedded pipe for sampling pile tip of filling pile
CN202793330U (en) Non-contact deformation monitoring and measuring element for tunnel
CN104373041A (en) Drilling deviation rectification method for 60-meter-long hole drilling of tunnel large pipe shed
CN103266603A (en) Construction method for pre-drilling hole-forming base-expanding and grouting of prestressed concrete special-shaped pile
CN210742096U (en) Device for measuring bonding strength of sprayed concrete and surrounding rock
US20180364377A1 (en) Test system for microseismic test of rock mass fractures
CN209656029U (en) A kind of tunnel deformation observation mark
CN103573269B (en) Shield tunnel grouting layer performance detection method
CN102605769B (en) Construction method of utilizing short-frame cement stirring pipe to produce cement stirring pile
CN204553471U (en) A kind of foundation ditch tool type guard rail fixing bolt
CN103453843A (en) Installation method of tunnel ruler-free measurement detachable reflector
CN102051916A (en) Construction method using concrete template pre-buried iron part
CN211499734U (en) Novel can dismantle instrument formula scaffold frame even wall spare
CN207123231U (en) A kind of positioning rule of embedded sleeve barrel and reserving hole channel after being used for prefabricated part hanging
CN204080882U (en) A kind of sound detecting pipe device detected for foundation pile supercritical ultrasonics technology
CN202881941U (en) Embedded pipe for sampling grouting pile end
CN206205012U (en) A kind of SMW engineering methods stake inclinometer pipe installation aiding device
CN110485413B (en) Combined type protection rapid hole forming method for pile foundation of viaduct adjacent to subway
CN205049135U (en) Solve inclinometer card gauge head unit
CN204557736U (en) A kind of slope deforming is monitored and prior-warning device automatically
CN204532429U (en) A kind of detachable and that precision is high convergence monitoring is linked up with
CN206830188U (en) Just prop up two lining contact measurement apparatus in tunnel
CN110145074B (en) Reinforcing steel bar connecting sleeve and reinforcing steel bar connecting method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant