CN209652927U - A kind of Prestressed Rock soil anchor bolt - Google Patents

A kind of Prestressed Rock soil anchor bolt Download PDF

Info

Publication number
CN209652927U
CN209652927U CN201920090490.7U CN201920090490U CN209652927U CN 209652927 U CN209652927 U CN 209652927U CN 201920090490 U CN201920090490 U CN 201920090490U CN 209652927 U CN209652927 U CN 209652927U
Authority
CN
China
Prior art keywords
anchor
reinforcing steel
free
presstressed reinforcing
anchoring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201920090490.7U
Other languages
Chinese (zh)
Inventor
孟凡林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin Jianzhu University
Original Assignee
Jilin Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin Jianzhu University filed Critical Jilin Jianzhu University
Priority to CN201920090490.7U priority Critical patent/CN209652927U/en
Application granted granted Critical
Publication of CN209652927U publication Critical patent/CN209652927U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

A kind of Prestressed Rock soil anchor bolt, belong to Geotechnical Engineering field, the anchor pole includes anchor head and anchor rod body, anchor rod body includes the presstressed reinforcing steel being set in the drilling of foundation pit slope surface or side slope surface drilling, anchoring body and free body, presstressed reinforcing steel is continuous whole reinforcing bar, anchoring body and free body are set on presstressed reinforcing steel, the utility model proposes Prestressed Rock soil anchor bolt, it is to fill the free segment of rock soil anchor using foamed plastics, form flexible free segment, when anchor pole applies prestressing force, slide mass is compressed, due to the presence of flexible free segment, free segment and corresponding slide mass can be really achieved by anchor pole locking load compression, effective compressive pre-stress can be established in slide mass, sliding surface generates compression, to improve the shear resistance of sliding surface, so that the stabilization of foundation pit or side slope and safety can be guaranteed.

Description

A kind of Prestressed Rock soil anchor bolt
Technical field
The utility model belongs to Geotechnical Engineering field, is related to foundation pit and slope project, is related specifically to a kind of pre- Stress rock soil anchor.
Background technique
According to the basic principle and foundation pit of soil mechanics or the designing technique standard requirements of side slope, in the sliding of foundation pit or side slope Anchor bar body should be made into free segment in body section, and anchor bar body should be made into anchoring section in the liptinite section of foundation pit or side slope, pass through The frictional resistance that anchoring section anchor bar body provides prevents the production of sliding surface plus the effect constraint slide mass that is locked of anchor pole outer end It is raw, to realize the purpose to match with calculation model for design, to ensure the stabilization of foundation pit or slope project, guarantee engineering peace Entirely.
The mooring rod technique of existing foundation pit and slope project adds steel to twist using pea gravel concreten or mortar or cement paste The scheme of line or steel tendon or high tensile reinforcement, the practice of free segment and anchoring section for anchor bar body, practical engineering application process In, although having divided free segment and anchoring section in design drawing, there is no distinguish free segment different from the work of anchoring section mostly Method, but anchor bar body one is poured into bottom, or even give the differentiation scheme of free segment and anchoring section, do not reach but The effect of differentiation;Or propose technical solution is of poor quality, low efficiency, at high cost, it is difficult to promote and apply in practical projects.
Application No. is 201410030080.5 Chinese patent, a kind of multistage anchoring type resin anchor and its anchoring are disclosed Method, it includes anchor bar body and aperture preloader, and an anchoring section is equipped at intervals on anchor pole, remaining section is free segment;The point Anchoring section is that dentation cutting ring is machined on the anchor bar body of this section, and dentation cutting ring housing has a two-component resin anchoring cartridge, double groups Part resin anchoring cartridge both ends are cased with spacer ring, so that anchor bar body to be successively divided into the first free segment, the since aperture Some anchoring sections, the second free segment, second point anchoring section, third free segment, thirdly anchoring section, it is desirable that the first free segment is in The relaxation zone of country rock, thirdly anchoring section is in the elastic region of country rock, remaining section is in the plastic zone of country rock.The technical solution point The quantity and each section of length of anchoring section and free segment can be adjusted according to pressure from surrounding rock characteristic distributions, dispersed load, avoided Superpower stress occurs in anchor pole end to concentrate, the body of rod is prevented to be broken or extract anchoring body.The technical solution there are the problem of Be: complicated for operation, work efficiency is low, quality assurance difficulty is big, at high cost etc., especially quality problems, due to resin mobility and Permeability is extremely strong, the local sealing to consolidate and being limited in the region of one section of anticipation with the ground on periphery, in rock mass Has no possibility, resin is inevitable to be overflowed from anchoring section, causes to fail.
Application No. is 201520526632.1 Chinese patents, disclose a kind of water power side slope free section of anchor cable grouting knot Structure, including side slope surface and the anchor cable being set in side slope surface drilling, the anchor cable drilling is divided into anchoring section and free segment, Middle free segment is between anchoring section and side slope surface, including being socketed the anchor cable body being set in the anchor cable drilling, the anchor Grouting Pipe is provided in cable body, the outer rim that anchor cable body is located at the part of free segment is socketed with sealing wrap.The technical solution uses Geotextiles are that anchor bar body makees housing, it is intended to anchor bar body and rock mass be isolated, to achieve the purpose that reduce side friction, due to drilling The roughening and cement slurry of side wall can permeate the characteristic of geotextiles, and practical frictional resistance can be bigger, and free segment function is caused to lose Effect.
Application No. is 201410032446.2 Chinese patent, a kind of multistage anchoring type grouting rock bolt and its anchoring are disclosed Method, it includes anchor bar body and aperture preloader, and anchor pole is also equipped at intervals with free segment, and the free segment is on the anchor bar body It is cased with one section of plastic bushing, the both ends contractibility washer of plastic bushing is blocked or tightened, and the anchor bar body for being cased with plastic bushing is Free segment, the anchor bar body of remaining section are a point anchoring section, so that anchor bar body to be successively divided into the first free segment, the since aperture Some anchoring sections, the second free segment, second point anchoring section, third free segment, thirdly anchoring section, it is desirable that the first free segment is in The relaxation zone of country rock, thirdly anchoring section is in the elastic region of country rock, remaining section is in the plastic zone of country rock.Technical solution examination Figure makes anchor bar body become free segment in its section by plastic bushing, still, due to the frictional resistance between anchor bar body and rock mass Or cohesive force still has, by the transmitting of anchor bar body Compressive Bearing Capacity, the frictional resistance or cohesive force of this section anchor bar body are still Reinforcing bar, steel tendon or steel strand wires can be passed to by the anchor bar body of adjacent anchoring section, the free segment can not play free segment Effect.
Application No. is 201510434626.8 Chinese patents, disclose a kind of anchor cable subregion anchoring segmentation preload rock stratum control Method processed, this method implements subregion anchoring using anchor cable, segmentation pre-tightens.Subregion anchoring is directed to fracture area, plastic zone and elasticity Anchoring section is set separately in area, and anchoring sequence is followed successively by elastic region, plastic zone and fracture area, and elastic region anchoring section uses resin anchoring Agent anchoring, plastic zone and fracture area are anchored using slip casting;Segmentation pre-tightens after i.e. each anchoring is stablized except the anchoring section of aperture, right The free segment in anchoring section outer end to aperture carries out tensioning preload.The technical solution can effectively improve the reliability of cable bolting, Subregion setting anchoring section can effectively avoid whole failure of cable caused by anchor cable is locally broken, and slip casting anchoring has anchoring anchor Rope and the double action for reinforcing crack country rock;Segmentation, which pre-tightens, has anchor cable overall length compared with high pre-stress, and active support effect is obvious It improves, CONTROL OF STRATA MOVEMENT effect can be effectively improved.The technical solution is suitable for permanent anchor pole, for facing for base pit engineering When property anchor pole, this way is complicated for operation, work efficiency is low, long construction period, at high cost.
Realize the Free Transform effect of provisional free section, free segment is allowed for by Free Compression.Existing skill Art is unable to satisfy such requirement, therefore needs the new technical solution of one kind to solve these problems.
Utility model content
The technical problem to be solved by the utility model is to provide a kind of Prestressed Rock soil anchor bolts, so that foundation pit or side slope Anchor pole in slide mass section become can by anchor pole lock load compress free segment, anchor pole locking load have in sliding surface Effect generates compression, improves the shear resistance of sliding surface, it is ensured that the stabilization of foundation pit or slope project guarantees engineering safety.
Specifically the utility model adopts the following technical solutions: a kind of Prestressed Rock soil anchor bolt, it is characterised in that: the anchor pole Including anchor head and anchor rod body, the anchor rod body includes the prestressing force being set in the drilling of foundation pit slope surface or side slope surface drilling Muscle, anchoring body and free body, the presstressed reinforcing steel are continuous whole reinforcing bar, are divided into two parts, respectively anchoring section prestressing force Muscle and free segment presstressed reinforcing steel, free segment presstressed reinforcing steel drills close to foundation pit slope surface or the aperture side of side slope surface drilling, freely Anti-corrosion separation layer is enclosed with outside section presstressed reinforcing steel;The anchoring body is arranged outside anchoring section presstressed reinforcing steel, anchoring body and anchor Gu the anchoring section of section presstressed reinforcing steel composition anchor pole;The free body is arranged outside free segment presstressed reinforcing steel, free body and freedom Section presstressed reinforcing steel constitutes the free segment of anchor pole.
Through the above design, the utility model can be brought the following benefits: one kind provided by the utility model Prestressed Rock soil anchor bolt is to be filled the free segment of rock soil anchor using foamed plastics, forms flexible free segment, when anchor pole applies When prestressing force, slide mass is compressed, and due to the presence of flexible free segment, free segment and corresponding slide mass can be really achieved By anchor pole locking load compression, effective compressive pre-stress can be established in slide mass, sliding surface generates compression, to improve The shear resistance of sliding surface, so that the stabilization of foundation pit or side slope and safety can be guaranteed.
Detailed description of the invention
Fig. 1 is the Prestressed Rock soil anchor bolt schematic diagram referred in the utility model embodiment.
Fig. 2 is the free segment diagrammatic cross-section of the Prestressed Rock soil anchor bolt referred in the utility model embodiment.
Fig. 3 is the anchoring section diagrammatic cross-section of the Prestressed Rock soil anchor bolt referred in the utility model embodiment.
It is respectively marked in figure as follows: 1- anchoring section, 2- free segment, 3- Rock And Soil, 4- anchoring body, 5- free body, 6- prestressing force Muscle, 7- conduit.
Specific embodiment
Below with reference to the attached drawing of the utility model, the technical scheme in the embodiment of the utility model is carried out clear, complete Statement, the embodiment is only the utility model a part of the embodiment, instead of all the embodiments.It is practical new based on this Embodiment in type, those of ordinary skill in the art without making creative work, every other reality obtained Example is applied, the protection scope of the utility model is belonged to.
Refering to fig. 1~Fig. 3 proposes a kind of Prestressed Rock soil anchor bolt in the present embodiment, which includes anchor head and anchor pole The body of rod, the anchor rod body include being set to the drilling of foundation pit slope surface or presstressed reinforcing steel 6,4 and of anchoring body in side slope surface drilling Free body 5, the presstressed reinforcing steel 6 are continuous whole reinforcing bar, are divided into two parts, respectively anchoring section presstressed reinforcing steel and free segment Presstressed reinforcing steel, free segment presstressed reinforcing steel drills close to foundation pit slope surface or the aperture side of side slope surface drilling, free segment presstressed reinforcing steel Outside is enclosed with anti-corrosion separation layer;The anchoring body 4 is arranged outside anchoring section presstressed reinforcing steel, and anchoring body 4 and anchoring section are answered in advance The anchoring section 1 of power muscle composition anchor pole;The free body 5 is arranged outside free segment presstressed reinforcing steel, and free body 5 and free segment are answered in advance The free segment 2 of power muscle composition anchor pole;
The material of the anchoring body 4 uses cement base cementitious mixes;
The material of the free body 5 uses the foamed plastics of the factorial production.
The free segment preparation method of specific Prestressed Rock soil anchor bolt, which is characterized in that this approach includes the following steps,
Step 1: preparing free body 5
More than two free bodies 5 are prepared using polystyrene foam plastics or polyurethane foam plastics;Free body 5 is cylinder Shape, diameter are less than bore diameter 3mm~50mm for accommodating anchor rod body, segmentation or whole section of preparation;Each free body 5 it is total Length is 2 length of free segment of anchor pole used in free body 5;Elongated perforation circular hole is arranged in the center of free body 5, the circular hole Diameter is greater than outer diameter 2mm~20mm of 6 outside anti-corrosion separation layer of presstressed reinforcing steel;Apart from 5 outer wall clear distance 5mm~20mm of free body Position the circular pipe hole of one elongated perforation is set again, the diameter of conduit hole is greater than 7 outer diameter 2mm~20mm of conduit;
Step 2: Rock And Soil 3 drills
It drills in the slope surface of 3 foundation pit of Rock And Soil or side slope by the diameter of design requirement, length and the gradient;Hole depth is just It is the length of anchor rod body, i.e. the sum of the anchoring section 1 of anchor pole and the length of free segment 2;
Step 3: material prepares
Presstressed reinforcing steel 6 is prepared by the material of design requirement, quantity, specification and length, and inner end anchor is set by design requirement Head;Anti-corrosion separation layer is arranged in external in free segment presstressed reinforcing steel;In the range of 6 free segment of presstressed reinforcing steel, corresponding free body 5 Center hole, free body 5 prepared by step 1 is set on the outside of presstressed reinforcing steel 6;
Conduit 7 is run through to the conduit hole for being inserted through free body 5, keeps 7 inner end of conduit concordant with the inner end of presstressed reinforcing steel 6;
Step 4: joint bar is in the milk
The material that step 3 is prepared is sent into the hole of step 2 drilling, is prepared grouting material and is passed through conduit 7 to step It is in the milk in the hole of two drillings, when free body 5 is displaced outwardly or the gap between free body 5 and hole sidewalls has grouting material exudation Terminate grouting.
So far, the preparation method of Prestressed Rock soil anchor bolt free segment is completed.

Claims (1)

1. a kind of Prestressed Rock soil anchor bolt, which includes anchor head and anchor rod body, it is characterised in that: the anchor rod body includes Presstressed reinforcing steel (6), anchoring body (4) and the free body (5) being set in the drilling of foundation pit slope surface or side slope surface drilling, it is described pre- to answer Power muscle (6) is continuous whole reinforcing bar, is divided into two parts, respectively anchoring section presstressed reinforcing steel and free segment presstressed reinforcing steel, freely Section presstressed reinforcing steel drills close to foundation pit slope surface or the aperture side of side slope surface drilling, is enclosed with anti-corrosion outside free segment presstressed reinforcing steel Separation layer;The anchoring body (4) is arranged outside anchoring section presstressed reinforcing steel, and anchoring body (4) and anchoring section presstressed reinforcing steel constitute anchor The anchoring section (1) of bar;The free body (5) is arranged outside free segment presstressed reinforcing steel, free body (5) and free segment presstressed reinforcing steel Constitute the free segment (2) of anchor pole.
CN201920090490.7U 2019-01-21 2019-01-21 A kind of Prestressed Rock soil anchor bolt Withdrawn - After Issue CN209652927U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920090490.7U CN209652927U (en) 2019-01-21 2019-01-21 A kind of Prestressed Rock soil anchor bolt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920090490.7U CN209652927U (en) 2019-01-21 2019-01-21 A kind of Prestressed Rock soil anchor bolt

Publications (1)

Publication Number Publication Date
CN209652927U true CN209652927U (en) 2019-11-19

Family

ID=68521660

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920090490.7U Withdrawn - After Issue CN209652927U (en) 2019-01-21 2019-01-21 A kind of Prestressed Rock soil anchor bolt

Country Status (1)

Country Link
CN (1) CN209652927U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109706927A (en) * 2019-01-21 2019-05-03 吉林建筑大学 A kind of preparation method of Prestressed Rock soil anchor bolt and its free segment
CN111927514A (en) * 2020-08-03 2020-11-13 中国矿业大学 Prestress full-length anchoring system and method based on steel grit adding in post-grouting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109706927A (en) * 2019-01-21 2019-05-03 吉林建筑大学 A kind of preparation method of Prestressed Rock soil anchor bolt and its free segment
CN111927514A (en) * 2020-08-03 2020-11-13 中国矿业大学 Prestress full-length anchoring system and method based on steel grit adding in post-grouting method

Similar Documents

Publication Publication Date Title
Li et al. Failure mechanism of bolting support and high-strength bolt-grouting technology for deep and soft surrounding rock with high stress
CN1200199C (en) A pin timbering process and sectionalized hollow mud injecting stay bolt thereof
CN209652927U (en) A kind of Prestressed Rock soil anchor bolt
CN102704971B (en) Grouting grouting cable anchor in hole
CN108589723A (en) Band only starches the segmentation hollow grouting anchor of the segmenting slip casting of branch sleeve
CN104790394A (en) Pressure anchor cable structure with prefabricated anchor head and construction method of pressure anchor cable structure
CN109706927A (en) A kind of preparation method of Prestressed Rock soil anchor bolt and its free segment
CN103573280A (en) Method for supporting porous ooze invasion compound roof roadway
CN103147777B (en) Pumping paste prestress full bolting anchor rod/cable supporting method
CN203584447U (en) Anti-impact interval grouting anchor cable
CN108222022A (en) A kind of tubular type Soil-Nailing Wall Structure and its construction method
CN209779642U (en) Miniature pile with antiskid structure and retaining wall assembly thereof
CN209669868U (en) Cement base Prestressed Rock soil anchor bolt
CN109183786A (en) A kind of post-tensioned prestressing resistance to plucking small diameter long screw pouring piles and its construction method
CN109653199A (en) The partition method of cement base Prestressed Rock soil anchor bolt and anchor rod anchored section and free segment
CN2561935Y (en) Sectional hollow slip anchor rod
CN101649616B (en) Anchor part with controllable anchorage force
CN103938626B (en) A kind of post jacking pressure type anchor rod and its construction method
CN208701667U (en) Band only starches the segmentation hollow grouting anchor of the segmenting slip casting of connection sleeve
CN111910615A (en) Paste drilling, filling, impact extrusion and enlarged footing anchor rod structure system and construction method thereof
CN2443999Y (en) Anchor chock integrated tube type anchorage cable
CN107747498B (en) A kind of mould bag filled type anchor bolt grouting device and method
CN1331366A (en) High-pressure grouting technique for stiffening slope of anchor cable (rod) system
CN220953374U (en) Anchoring device
CN112211183B (en) Device for reducing drag by negative friction and transferring positive friction of precast pile and using method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20191119

Effective date of abandoning: 20230223

AV01 Patent right actively abandoned

Granted publication date: 20191119