CN209603512U CN201920231069.3U CN201920231069U CN209603512U CN 209603512 U CN209603512 U CN 209603512U CN 201920231069 U CN201920231069 U CN 201920231069U CN 209603512 U CN209603512 U CN 209603512U
Authority
CN
China
Prior art keywords
wall
welded
drainage conduit
pipe
engineering construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920231069.3U
Other languages
Chinese (zh)
Inventor
范张强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920231069.3U priority Critical patent/CN209603512U/en
Application granted granted Critical
Publication of CN209603512U publication Critical patent/CN209603512U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

Baiting structure is poured the utility model discloses a kind of highway engineering construction, including feeding connection bucket, the outer mounting hole for not being provided with two groups of equidistant annular spreads of the charging connection bucket, the bottom end of the charging connection bucket is welded with drainage conduit, and the inner wall of drainage conduit is successively welded with the bulk cargo bar of two groups of equidistant annular spreads from top to bottom, the bulk cargo bar is slant setting, the outer wall of the drainage conduit is welded with annular slab, and the outer wall of annular slab is welded with ring pipe, there are two sliding blocks for the outer wall socket of the ring pipe, and two sliding blocks are located at the two sides of drainage conduit, two sliding blocks are welded with two hemispheric first protrusions close to the side inner wall of drainage conduit, and first protrusion be distributed in above and below annular slab.The utility model is the baiting structure used when a kind of highway engineering construction is poured, and baiting structure adjusts the blanking direction of feeder pipe according to actual needs convenient for staff, improves the practicability of baiting structure.

Description

A kind of highway engineering construction pours baiting structure
Technical field
The utility model relates to pour under baiting structure technical field more particularly to a kind of pouring of highway engineering construction Expect structure.
Background technique
Highway is that a kind of mankind go on a journey one of commonly used communal facility, during highway engineering use, is needed pair Road surface is carried out with concreting, during pouring, is needed to use and relevant is poured baiting structure.
Currently, existing in the market pour baiting structure for highway engineering construction, during use, greatly Can mostly there be deficiency below: be not easy to the discharging direction that staff adjusts feeder pipe according to the actual situation, and in blanking In the process, concrete is easily blocked in feeder pipe, is not easy to staff and is dredged, to sum up, existing to be used for highway engineering The working baiting structure that pours cannot agree with actual needs well.
Utility model content
Purpose of the utility model is to solve disadvantages existing in the prior art, and a kind of highway engineering proposed is applied Work pours baiting structure.
To achieve the goals above, the utility model adopts the technical scheme that
A kind of highway engineering construction pours baiting structure, including charging connection bucket, the charging connection bucket it is outer not It is provided with the mounting hole of two groups of equidistant annular spreads, the bottom end of the charging connection bucket is welded with drainage conduit, and drainage conduit is interior Wall is successively welded with the bulk cargo bar of two groups of equidistant annular spreads from top to bottom, and the bulk cargo bar is slant setting, the row The outer wall of expects pipe is welded with annular slab, and the outer wall of annular slab is welded with ring pipe, and there are two the outer wall sockets of the ring pipe Sliding block, and two sliding blocks are located at the two sides of drainage conduit, two sliding blocks are welded with close to the side inner wall of drainage conduit Two hemispheric first protrusions, and the first protrusion is distributed in above and below annular slab, the ring pipe is close to drainage conduit Side outer wall open there are two annular groove, and the first one end grafting of the protrusion far from drainage conduit is in a ring groove, two cunnings The top inner wall and bottom interior wall of block are welded with hemispheric second protrusion, and one end of the second protrusion is contacted with ring pipe.
Further, the side outer wall of two sliding blocks is welded with the same lower hopper, and the bottom end welding of lower hopper There is feeder pipe.
Further, the bottom outer wall of the feeder pipe has been bolted vibrating motor, and outside the two sides of feeder pipe Wall center is provided with circular hole, and the inner wall of two circular holes is welded with bearing.
Further, the inner wall of two bearings is welded with the same round bar, and the outer wall welding in round bar middle position There is installing pipe.
Further, the outer wall of the installing pipe is welded with the material scraping plate of equidistant annular spread, and the radius of material scraping plate Specification is adapted with the radius specification of feeder pipe, and the curved wall of material scraping plate is provided with the groove equidistantly distributed.
Further, the both ends of the round bar are threaded with axle sleeve, and two axle sleeves are respectively positioned on outside feeder pipe.
Further, the outer wall of two axle sleeves is welded with bull stick, and the side outer wall of two bull sticks is welded with Rocking handle.
The utility model has the following beneficial effects:
1. lower hopper is connect by sliding block with drainage conduit, and due to sliding block and ring pipe by setting sliding block and ring pipe It is flexibly connected, so at the blanking direction for needing to adjust feeder pipe, the feeder pipe that connect with lower hopper can be rotated to suitable Orientation, and the setting of the first protrusion and the second protrusion is combined, since the first protrusion and the second protrusion are hemispherical, so can To reduce frictional force when rotation, so that more laborsaving when staff's rotation feeder pipe.
2., in blanking, concrete first reaches charging connection bucket by the bulk cargo bar of two groups of equidistant annular spreads of setting It is interior, and be discharged by drainage conduit, before drainage conduit is discharged to lower hopper and feeder pipe, the bulk cargo bar in drainage conduit will be to coagulation Soil is shunted, and then avoids having the appearance of the phenomenon that pockets of concrete in concrete.
3., in blanking, vibrating motor is connect with extraneous power supply, vibrating motor will be under drive by setting vibrating motor Expects pipe vibration, and then life is avoided the situation of blocking materials, and combine the setting of rocking handle, bull stick, round bar and material scraping plate, staff can To hold rocking handle and rotate, this will drive round bar and material scraping plate to rotate in feeder pipe, and the material scraping plate of rotation will be in feeder pipe Concrete scrapes, and then assists the blanking of concrete, and generation the phenomenon that again avoid putty.
Detailed description of the invention
Fig. 1 be the utility model proposes a kind of highway engineering construction pour baiting structure cross-section structure signal Figure;
Fig. 2 be the utility model proposes the structure of the part A for pouring baiting structure of highway engineering construction a kind of show It is intended to;
Fig. 3 be the utility model proposes a kind of highway engineering construction the material scraping plate that pours baiting structure and round bar Structural schematic diagram.
In figure: 1- feeds connection bucket, 2- mounting hole, 3- drainage conduit, 4- bulk cargo bar, 5- lower hopper, 6- feeder pipe, 7- scraper Plate, 8- installing pipe, 9- round bar, 10- vibrating motor, 11- ring pipe, the second protrusion of 12-, 13- sliding block, 14- annular slab, 15- One protrusion, 16- groove, 17- bearing, 18- axle sleeve, 19- rocking handle, 20- bull stick.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.
Referring to Fig.1-3, a kind of highway engineering construction pours baiting structure, including charging connection bucket 1, feeds connection bucket The bottom end of the 1 outer mounting hole 2 for not being provided with two groups of equidistant annular spreads, charging connection bucket 1 is welded with drainage conduit 3, and discharge The inner wall of pipe 3 is successively welded with the bulk cargo bar 4 of two groups of equidistant annular spreads from top to bottom, and bulk cargo bar 4 is slant setting, row The outer wall of expects pipe 3 is welded with annular slab 14, and the outer wall of annular slab 14 is welded with ring pipe 11, and the outer wall of ring pipe 11 is socketed with Two sliding blocks 13, and two sliding blocks 13 are located at the two sides of drainage conduit 3, side inner wall of two sliding blocks 13 close to drainage conduit 3 Two hemispheric first protrusions 15 are welded with, and the first protrusion 15 is distributed in above and below annular slab 14, ring pipe 11 open close to the side outer wall of drainage conduit 3 there are two annular groove, and the first protrusion 15 is plugged on annular far from one end of drainage conduit 3 In slot, the top inner wall and bottom interior wall of two sliding blocks 13 are welded with hemispheric second protrusion 12, and the second protrusion 12 One end is contacted with ring pipe 11, and the first protrusion 15 and the second protrusion 12 are hemispherical, frictional force when this rotates reduction, into And make staff more laborsaving when rotating feeder pipe 6.
In the utility model, the side outer wall of two sliding blocks 13 is welded with the same lower hopper 5, since lower hopper 5 passes through Sliding block 13 is connect with drainage conduit 3, and sliding block 13 is flexibly connected with ring pipe 11, so in the blanking side for needing to adjust feeder pipe 6 Xiang Shi can rotate the feeder pipe 6 that connect with lower hopper 5 to suitable orientation, and the bottom end of lower hopper 5 is welded with feeder pipe 6, The bottom outer wall of feeder pipe 6 has been bolted vibrating motor 10, and during blanking, vibrating motor 10 will drive blanking Pipe 6 vibrates, and then avoids the situation of blocking materials life, and the two sides outer wall center of feeder pipe 6 is provided with circular hole, two circular holes Inner wall be welded with bearing 17, the inner wall of two bearings 17 is welded with the same round bar 9, and the outer wall in 9 middle position of round bar It is welded with installing pipe 8, the outer wall of installing pipe 8 is welded with the material scraping plate 7 of equidistant annular spread, and the radius specification of material scraping plate 7 It is adapted with the radius specification of feeder pipe 6, in blanking, staff can hold rocking handle 19 and rotate, this will drive round bar 9 And material scraping plate 7 rotates in feeder pipe 6, the material scraping plate 7 of rotation scrapes the concrete in feeder pipe 6, and then assists concrete Blanking, and generation the phenomenon that again avoid putty, the curved wall of material scraping plate 7 are provided with the groove 16 equidistantly distributed, circle The both ends of bar 9 are threaded with axle sleeve 18, and two axle sleeves 18 are respectively positioned on outside feeder pipe 6, and the outer wall of two axle sleeves 18 welds It is connected to bull stick 20, and the side outer wall of two bull sticks 20 is welded with rocking handle 19.
Working principle: it is fixedly connected, will be vibrated with concrete discharge end in use, connection bucket 1 will be fed by mounting hole Motor 10 is connect with extraneous power supply, and in blanking, concrete is first reached in charging connection bucket 1, and is discharged by drainage conduit 3, In Drainage conduit 3 is discharged to before lower hopper 5 and feeder pipe 6, and the bulk cargo bar 4 in drainage conduit 3 will shunt concrete, and then keep away Exempt from have the appearance of the phenomenon that pockets of concrete in concrete, during blanking, vibrating motor 10 will drive feeder pipe 6 to shake It is dynamic, and then life is avoided the situation of blocking materials, and staff can hold rocking handle 19 and rotate, this will drive round bar 9 and scraper Plate 7 rotates in feeder pipe 6, and the material scraping plate 7 of rotation scrapes the concrete in feeder pipe 6, and then assists the blanking of concrete, And the phenomenon that again avoiding putty generation;Since lower hopper 5 is connect by sliding block 13 with drainage conduit 3, and sliding block 13 and annular Pipe 11 is flexibly connected, so the feeder pipe 6 connecting with lower hopper 5 can be rotated at the blanking direction for needing to adjust feeder pipe 6 To suitable orientation, and the first protrusion 15 and the second protrusion 12 are hemispherical, this will reduce frictional force when rotating, and then make It obtains more laborsaving when staff's rotation feeder pipe 6.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model Within enclosing.

Claims (7)

1. a kind of highway engineering construction pours baiting structure, including charging connection bucket (1), which is characterized in that the charging The outer mounting hole (2) for not being provided with two groups of equidistant annular spreads of connection bucket (1), the bottom end welding of charging connection bucket (1) Have drainage conduit (3), and the inner wall of drainage conduit (3) is successively welded with the bulk cargo bar (4) of two groups of equidistant annular spreads from top to bottom, The bulk cargo bar (4) is slant setting, and the outer wall of the drainage conduit (3) is welded with annular slab (14), and annular slab (14) Outer wall is welded with ring pipe (11), and there are two sliding block (13) for the outer wall socket of the ring pipe (11), and two sliding blocks (13) are divided Not Wei Yu drainage conduit (3) two sides, the side inner wall of two sliding blocks (13) close to drainage conduit (3) is welded with two hemisphere The first of shape is raised (15), and first raised (15) are distributed in above and below annular slab (14), and the ring pipe (11) is leaned on The side outer wall of nearly drainage conduit (3) opens that there are two annular grooves, and first raised (15) are plugged on ring far from the one end of drainage conduit (3) In shape slot, the top inner wall and bottom interior wall of two sliding blocks (13) are welded with hemispheric second raised (12), and the One end of two raised (12) is contacted with ring pipe (11).
2. a kind of highway engineering construction according to claim 1 pours baiting structure, which is characterized in that described in two The side outer wall of sliding block (13) is welded with the same lower hopper (5), and the bottom end of lower hopper (5) is welded with feeder pipe (6).
3. a kind of highway engineering construction according to claim 2 pours baiting structure, which is characterized in that the blanking The bottom outer wall of pipe (6) has been bolted vibrating motor (10), and the two sides outer wall center of feeder pipe (6) is provided with Circular hole, the inner wall of two circular holes are welded with bearing (17).
4. a kind of highway engineering construction according to claim 3 pours baiting structure, which is characterized in that described in two The inner wall of bearing (17) is welded with the same round bar (9), and the outer wall in round bar (9) middle position is welded with installing pipe (8).
5. a kind of highway engineering construction according to claim 4 pours baiting structure, which is characterized in that the installation The outer wall of pipe (8) is welded with the material scraping plate (7) of equidistant annular spread, and the radius specification of material scraping plate (7) and feeder pipe (6) Radius specification is adapted, and the curved wall of material scraping plate (7) is provided with the groove (16) equidistantly distributed.
6. a kind of highway engineering construction according to claim 4 pours baiting structure, which is characterized in that the round bar (9) both ends are threaded with axle sleeve (18), and two axle sleeves (18) are respectively positioned on feeder pipe (6) outside.
7. a kind of highway engineering construction according to claim 6 pours baiting structure, which is characterized in that described in two The outer wall of axle sleeve (18) is welded with bull stick (20), and the side outer wall of two bull sticks (20) is welded with rocking handle (19).
CN201920231069.3U 2019-02-25 2019-02-25 A kind of highway engineering construction pours baiting structure Expired - Fee Related CN209603512U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920231069.3U CN209603512U (en) 2019-02-25 2019-02-25 A kind of highway engineering construction pours baiting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920231069.3U CN209603512U (en) 2019-02-25 2019-02-25 A kind of highway engineering construction pours baiting structure

Publications (1)

Publication Number Publication Date
CN209603512U true CN209603512U (en) 2019-11-08

Family

ID=68403039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920231069.3U Expired - Fee Related CN209603512U (en) 2019-02-25 2019-02-25 A kind of highway engineering construction pours baiting structure

Country Status (1)

Country Link
CN (1) CN209603512U (en)

Similar Documents

Publication Publication Date Title
CN110106767A (en) A kind of laying of road construction concrete is vibrated integrated device
CN206780681U (en) A kind of construction of high-performance concrete Anti-solidification storage device
CN211142720U (en) Paving device for extremely thin wearing layer of asphalt
CN209603512U (en) A kind of highway engineering construction pours baiting structure
CN206987386U (en) A kind of building machinery engineering hopper
CN211273663U (en) Special high-efficient three-layer thickener of gold ore
CN211002861U (en) Dry-mixed mortar raw material storage device
CN215697732U (en) Mulling equipment is used in processing of nodular cast iron well lid
CN208436803U (en) Granulation device
CN107696280A (en) Cement sandstone agitating device for building
CN211104786U (en) Concrete mixing device for building construction site
CN211941458U (en) Concrete discharging device with prevent blockking up function
CN109168441B (en) Efficient topdressing and furrow closing machine for corn experimental field
CN115012987A (en) Tunnel lining trolley material distributing machine
CN208615049U (en) A kind of stirring integrated machine of cement slurrying
CN206088102U (en) Quick -witted equipment is carried to carbon black finished product fill
CN209095805U (en) A kind of magnetic separator of easy cleaning
CN210561615U (en) Foundation cement irrigation equipment is used in municipal administration
CN204914333U (en) Novel polymer material feeder hopper
KR20090099962A (en) Exhausting device for silo
CN217353689U (en) Device for plugging split bolt holes
CN206265684U (en) Refuse treatment plant
CN210545073U (en) Chemical reaction kettle
CN213792793U (en) Sand and stone separator's feeding structure
CN109016141A (en) Deep basal pit civil engineering construction casting rod milling sand slurry stirring system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191108