CN209603069U - A kind of analysis on aqueduct structure - Google Patents
A kind of analysis on aqueduct structure Download PDFInfo
- Publication number
- CN209603069U CN209603069U CN201920096968.7U CN201920096968U CN209603069U CN 209603069 U CN209603069 U CN 209603069U CN 201920096968 U CN201920096968 U CN 201920096968U CN 209603069 U CN209603069 U CN 209603069U
- Authority
- CN
- China
- Prior art keywords
- cell wall
- built structure
- wall built
- bar
- fastening
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a kind of analysis on aqueduct structure, including the slot bottom built structure being placed on the ground, it is set to the first cell wall built structure and the second cell wall built structure of slot bottom built structure upper surface, first cell wall built structure and the second cell wall built parallelism structural are arranged and the two is perpendicular to slot bottom built structure, first cell wall built structure, slot bottom built structure and the second cell wall built structure surround groove, the outside of the first cell wall built structure and the upper surface of slot bottom built structure are provided with first support bar, the outside of the second cell wall built structure and the upper surface of slot bottom built structure are provided with second support bar, the first cell wall built structure setting, which has, several sockets bar, the second cell wall built structure setting, which has, several sockets pipe, it is described to socket pipe and socket bar and be oppositely arranged, and what is be oppositely arranged described sockets pipe and drawing Extension bar socket, it is described socket pipe and socket fixed mechanism is provided between bar.The utility model has the advantages that structural strength is high.
Description
Technical field
The utility model relates to hydraulic engineering technical field, in particular to a kind of analysis on aqueduct structure.
Background technique
Aqueduct is a kind of aerial water conveyance structure built, usually because the barriers such as channel and road, a stretch of flatland in a hilly area, the mouth of a valley intersect
Shi Xiujian occupies an important position in canal system water conveyance structure, is using one of more extensive crossing.
Trough inner water body is fluid with Free Surface, by abutment wall and restriction from soleplate.Due to trough inner water body and slot body
Dynamic interaction, so the cell wall of aqueduct bears the active force of sizable trough inner water body.Under the active force of trough inner water body,
Two cell walls of aqueduct have the tendency that being located remotely from each other, once two cell wall run-off the straights of aqueduct, aqueduct just lose guide functions.
Utility model content
In view of the deficienciess of the prior art, there is knot the purpose of this utility model is to provide a kind of analysis on aqueduct structure
The high advantage of structure intensity.
The above-mentioned technical purpose of the utility model has the technical scheme that
A kind of analysis on aqueduct structure, including be placed on the ground slot bottom built structure, be set to slot bottom built structure upper surface
The first cell wall built structure and the second cell wall built structure, the first cell wall built structure and the second cell wall built parallelism structural are set
It sets and the two is perpendicular to slot bottom built structure, the first cell wall built structure, slot bottom built structure and the second cell wall built structure are enclosed
At groove, the inner wall of the groove is equipped with antiseepage cloth, and the top of the first cell wall built structure is provided with first and cods bag,
Described first bag of codding extends in groove and inside of the pocket facing together in antiseepage cloth of codding, the top of the second cell wall built structure
End is provided with second and cods bag, described second cod bag extend in groove and cod pocket facing together in antiseepage cloth inside, it is described
The outside of first cell wall built structure and the upper surface of slot bottom built structure are provided with first support bar, the second cell wall built
The outside of structure and the upper surface of slot bottom built structure are provided with second support bar, if the first cell wall built structure setting has
Dry drawing extension bar, the second cell wall built structure setting have it is several socket pipe, it is described socket pipe and socket bar be oppositely arranged, and phase
To socketing pipe described in setting and socket rod set and connect, it is described socket pipe and socket fixed mechanism is provided between bar.
By using above-mentioned technical proposal, in active force of the cell wall built structure to trough inner water body, two cell wall builts
Structure has the tendency that being located remotely from each other, and connects socketing pipe and socketing bar and be fixed together for socket setting by fixed mechanism,
To carry out drawknot to two cell wall built structures, reduce the trend that two cell wall built structures are located remotely from each other, enhancing is originally practical
The structural strength of novel analysis on aqueduct structure.
The utility model is further arranged to: the fixed mechanism includes deformation split ring, the socket end for socketing pipe
Offer deformation recessing groove, the deformation split ring be arranged it is described socket at the deformation recessing groove of pipe, the deformation split ring
Two open ends are respectively arranged with latch, are provided with locking assembly between two latch.
By using above-mentioned technical proposal, between adjustable two latch being set on deformation split ring of locking assembly
Distance is in tightening state or releases tightening state, and then realizes and socket bar and socket pipe relative position to make to socket bar
It adjusts.
The utility model is further arranged to: the locking assembly includes connecting rod, and two latch open up respectively
There is locking hole, connecting rod is arranged in two locking holes, and one end of the connecting rod is provided with anchorage bar, and one end of anchorage bar is opened
Equipped with mounting groove, connecting rod offers the first connecting hole, and the two sidewalls of mounting groove offer the second connecting hole, connecting rod and fastening
Bar realizes the hinged of the two by rotation axis, and anchorage bar is set as extrados, extrados and second in the connecting pin with connecting rod
The distance of connecting hole is progressively longer, and one end of the connecting rod is provided with the locating part for preventing connecting rod abjection locking hole.
By using above-mentioned technical proposal, needs to socket bar according to aqueduct width adjusting and socket the relative position between pipe
When, anchorage bar is moved, two latch being set on deformation split ring is located remotely from each other, sockets the deformation recessing groove of pipe upper end
Loosen, sockets bar in state is moved freely, be adjusted and socket bar and socket the relative position of pipe, socket bar and drawing when being adjusted to
When required relative position between adapter tube, anchorage bar is moved again, keeps two latch being set on deformation split ring mutual
Close, deformation recessing groove is squeezed to socketing on bar outer wall, is made to socket bar and be in locking state, is socketed bar to realize and is socketed
The adjusting and fixation of pipe relative position.
The utility model is further arranged to: the locating part includes stop nut, the connecting rod be provided with it is locking
The compatible external screw thread of nut.
By using above-mentioned technical proposal, locating part is set as stop nut, convenient for the installation of locking assembly, prevents from locking
Component loosens, and then prevents from increasing and deform due to two latch distance to socket bar caused by recessing groove loosens and socket pipe producing
The case where raw relative displacement, occurs.Therefore, it enhances and sockets bar and socket the stability connected between pipe.
The utility model is further arranged to: the connecting rod is provided with gasket, gasket between anchorage bar and latch
It is provided with the intrados to match with extrados.
By using above-mentioned technical proposal, convenient for rotation anchorage bar, to control the distance of two latch.
The utility model is further arranged to: the first cell wall built structure is installed with the first fixed link, and first is fixed
Rod set is equipped with the first split ring, sockets bar and is fixedly arranged on the positive camber of the first split ring, two openings of first split ring
End is respectively arranged with the first fastening plates, is provided with the first fastening assembly between two the first fastening plates.
By using above-mentioned technical proposal, it is fixedly arranged on the first split ring socketed on bar and is sheathed on and be fixedly arranged on the first cell wall and take
In the first fixed link in frame structure, then it is tight by two first that are set to the first split ring open end by the first fastening assembly
Solid plate is fastened, and sockets being fixedly connected between bar and the first cell wall built structure to realize.
The utility model is further arranged to: first fastening assembly includes the first fastening bolt and the first fastening spiral shell
Mother, first fastening plates offer the first fastener hole, and first fastening bolt is arranged in after two the first fastener holes with
One fastening nut screws.
By using above-mentioned technical proposal, structure is simple, easy to connect.
The utility model is further arranged to: the second cell wall built structure is installed with the second fixed link, and described second
Fixed link is arranged with the second split ring, the positive camber for socketing pipe and being fixedly arranged on the second split ring, and the two of second split ring
A open end is respectively arranged with the second fastening plates, is provided with the second fastening assembly between two the second fastening plates.
By using above-mentioned technical proposal, it is fixedly arranged on the second split ring socketed on pipe and is sheathed on and be fixedly arranged on the second cell wall and take
In the second fixed link in frame structure, then it is tight by two second that are set to the second split ring open end by the second fastening assembly
Solid plate is fastened, and sockets being fixedly connected between pipe and the second cell wall built structure to realize.
The utility model is further arranged to: second fastening assembly includes the second fastening bolt and the second fastening spiral shell
Mother, second fastening plates offer the second fastener hole, and second fastening bolt is arranged in after two the second fastener holes with
Two fastening nuts screw.
By using above-mentioned technical proposal, structure is simple, easy to connect.
In conclusion the utility model has the following beneficial effects: in cell wall built structure to the active force of trough inner water body
When, two cell wall built structures have the tendency that being located remotely from each other, and connect socketing for socket setting by fixed mechanism and pipe and socket bar
It is fixed together, to carry out drawknot to two cell wall built structures, reduces what two cell wall built structures were located remotely from each other
Trend enhances the structural strength of the utility model analysis on aqueduct structure.
Detailed description of the invention
Fig. 1 is the plan view of embodiment;
Fig. 2 is the axonometric drawing of embodiment;
Fig. 3 is the portion the A enlarged drawing in Fig. 2;
Fig. 4 is the portion the B enlarged drawing in Fig. 2;
Fig. 5 is the portion the C enlarged drawing in Fig. 2;
Fig. 6 is to socket bar, fixed mechanism in embodiment, socket the connection relationship diagram between pipe.
In figure, 1, slot bottom built structure;11, horizontal steel form;12, longitudinal I-steel;13, lateral I-beam;14, it stands
Column;15, backing plate;2, the first cell wall built structure;21, the first vertical steel form;22, the first steel pipe;23, the first vertical I-shaped
Steel;3, the second cell wall built structure;31, the second vertical steel form;32, the second steel pipe;33, the second vertical I-steel;4, antiseepage
Cloth;51, it first cods bag;52, it second cods bag;61, first support bar;62, second support bar;71, the first fixed link;72,
First split ring;721, the first fastening plates;8, bar is socketed;9, fixed mechanism;91, split ring is deformed;911, latch;92, it locks
Tight component;921, connecting rod;922, anchorage bar;9221, mounting groove;923, rotation axis;924, gasket;925, stop nut;10,
Socket pipe;101, recessing groove is deformed;111, the second split ring;1111, the second fastening plates;112, the second fixed link.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment: being a kind of analysis on aqueduct structure disclosed by the utility model, including the slot bottom being placed on the ground referring to Fig.1
Built structure 1, the first cell wall built structure 2 and the second cell wall built structure 3 for being set to 1 upper surface of slot bottom built structure.
Slot bottom built structure 1 includes that several perpendicular to the lateral I-beam 13 of water (flow) direction and several edges, direction is set downstream
The top of the longitudinal I-steel 12 set, several longitudinal direction I-steel 12 is welded with horizontal steel form 11, and lateral I-steel is welded in vertical
To the lower section of I-steel 12, several columns 14 are welded with below lateral I-steel, the lower end of column 14 is welded with backing plate 15.
First cell wall built structure 2 includes the several first vertical I-steel 23, several first vertical 23 edges of I-steel
Direction is arranged downstream, and several first vertical I-steel 23 are welded with several edges the first steel pipe 22, Ruo Gan that direction is arranged downstream
One steel pipe 22 is intervally arranged along the short transverse of the first vertical I-steel 23, and several first steel pipes 22 are in far from the first vertical I-shaped
The side of steel 23 is welded with the first vertical steel form 21.
Second cell wall built structure 3 includes the several second vertical I-steel 33, several second vertical 33 edges of I-steel
Direction is arranged downstream, and several second vertical I-steel 33 are welded with several edges the second steel pipe 32, Ruo Gan that direction is arranged downstream
Two steel pipes 32 are intervally arranged along the short transverse of the second vertical I-steel 33, and several second steel pipes 32 are in far from the second vertical I-shaped
The side of steel 33 is welded with the second vertical steel form 31.
First cell wall built structure 2 and the second cell wall built structure 3 are arranged in parallel, and under the first cell wall built structure 2
The lower end vertical welding of end and the second cell wall built structure 3 is in the upper surface of slot bottom built structure 1.
First cell wall built structure 2, slot bottom built structure 1 and the second cell wall built structure 3 surround groove, the inner wall of groove
It is equipped with antiseepage cloth 4, the top of the first cell wall built structure 2 is provided with first and cods bag 51, and first cods bag 51 by first
In on the first steel pipe 22 of the first cell wall built structure 2, the first bag 51 of codding is extended in groove and first hangs for flexible strand binding
Sand pocket 51 fits in the inside of antiseepage cloth 4;The top of second cell wall built structure 3 is provided with second and cods bag 52, and second cods
Bag 52 is bound by the second flexible strand on the second steel pipe 32 of the second cell wall built structure 3, and the second bag 52 of codding extends to ditch
In slot and the second bag 52 of codding fits in the inside of antiseepage cloth 4.
The outside of first cell wall built structure 2 and the upper surface of slot bottom built structure 1 are provided with first support bar 61, and first
The lower thread of support rod 61 connects or is welded in the upper surface of slot bottom built structure 1, the threaded upper ends of first support bar 61
It connects or is welded on the first vertical I-steel 23 of the first cell wall built structure 2;The outside of second cell wall built structure 3 and
The upper surface of slot bottom built structure 1 is provided with second support bar 62, and the lower thread of second support bar 62 is connected or is welded in
The threaded upper ends of the upper surface of slot bottom built structure 1, second support bar 62 connect or are welded in the second cell wall built structure 3
On second vertical I-steel 33.
First cell wall built structure 2 be provided with it is several socket bar 8, the second cell wall built structure 3, which is provided with, several sockets pipe
10, it sockets pipe 10 and sockets bar 8 and be oppositely arranged, what is be oppositely arranged sockets pipe 10 and socket the socket of bar 8, sockets pipe 10 and sockets bar
Fixed mechanism 9 is provided between 8.
In conjunction with shown in Fig. 2 and Fig. 3, the first vertical I-steel 23 in the first cell wall built structure 2 is higher than the first steel pipe 22
With the height of the first vertical steel form 21.The first fixed link 71 is welded on the outside of the high outlet of first vertical I-steel 23, the
One fixed link 71 is arranged along direction downstream, and the first fixed link 71 is arranged with the first split ring 72, sockets the non-socket end welding of bar 8
In on the positive camber of the first split ring 72, two open ends of the first split ring 72 respectively integrally formed with the first fastening plates 721,
Two the first fastening plates 721 offer the first fastener hole respectively, and two the first fastener holes are oppositely arranged, in two the first fastener holes
It is equipped with the first fastening bolt, the end thread of the first fastening bolt is connected with the first fastening nut.
In conjunction with shown in Fig. 2 and Fig. 4, the second vertical I-steel 33 in the second cell wall built structure 3 is higher than the second steel pipe 32
With the height of the second vertical steel form 31.The second fixed link 112 is welded on the outside of the high outlet of second vertical I-steel 33, the
Two fixed links 112 are arranged along direction downstream, and the second fixed link 112 is arranged with the second split ring 111, sockets the non-socket end of pipe 10
It is welded on the positive camber of the second split ring 111, two open ends of the second split ring 111 are respectively integrally formed with the second fastening
Plate 1111, two the second fastening plates 1111 offer the second fastener hole respectively, and two the second fastener holes are oppositely arranged, and two second
The second fastening bolt is equipped in fastener hole, the end thread of the second fastening bolt is connected with the second fastening nut.
In conjunction with shown in Fig. 2 and Fig. 5, fixed mechanism 9 includes deformation split ring 91, and the socket end for socketing pipe 10 offers deformation
Recessing groove 101, deformation split ring 91 are arranged at the deformation recessing groove 101 for socketing pipe 10, deform two open ends of split ring 91
It is respectively arranged with latch 911, is provided with locking assembly 92 between two latch 911.
As shown in fig. 6, locking assembly 92 includes connecting rod 921, two latch 911 offer locking hole respectively, connect
Bar 921 is arranged in two locking holes, and one end of connecting rod 921 is provided with anchorage bar 922, and one end of anchorage bar 922 offers
Mounting groove 9221, connecting rod 921 offer the first connecting hole, and the two sidewalls of mounting groove 9221 offer the second connecting hole, connection
By the hinged of both realizations of rotation axis 923, anchorage bar 922 is set in the connecting pin with connecting rod 921 for bar 921 and anchorage bar 922
Be set to extrados, the distance of extrados and the second connecting hole is progressively longer, connecting rod 921 in anchorage bar 922 and latch 911 it
Between be arranged with gasket 924, gasket 924 is provided with the intrados to match with extrados.One end of connecting rod 921 is provided with and prevents
Connecting rod 921 deviates from the stop nut 925 of locking hole, and connecting rod 921 is provided with external screw thread compatible with stop nut 925.
The embodiment of present embodiment is the preferred embodiment of the utility model, and not limitation is originally practical new according to this
The protection scope of type, therefore: the equivalence changes that all structures, shape, principle according to the utility model are done should all be covered by practical
Within novel protection scope.
Claims (9)
1. a kind of analysis on aqueduct structure, including be placed on the ground slot bottom built structure (1), be set in slot bottom built structure (1)
The first cell wall built structure (2) and the second cell wall built structure (3) on surface, the first cell wall built structure (2) and the second cell wall
Built structure (3) is arranged in parallel and the two is perpendicular to slot bottom built structure (1), the first cell wall built structure (2), slot bottom built knot
Structure (1) and the second cell wall built structure (3) surround groove, and the inner wall of the groove is equipped with antiseepage cloth (4), first cell wall
The top of built structure (2) is provided with first and cods bag (51), and the described first bag (51) of codding extends in groove and bag of codding
The inside of antiseepage cloth (4) is fitted in, the top of the second cell wall built structure (3) is provided with second and cods bag (52), described
Second bag (52) of codding extends in groove and inside of the pocket facing together in antiseepage cloth (4) of codding, the first cell wall built structure
(2) upper surface in outside and slot bottom built structure (1) is provided with first support bar (61), the second cell wall built structure
(3) upper surface in outside and slot bottom built structure (1) is provided with second support bar (62), it is characterised in that: first slot
Wall built structure (2) be provided with it is several socket bar (8), the second cell wall built structure (3) be provided with it is several socket pipe (10),
It is described socket pipe (10) and socket bar (8) be oppositely arranged, and be oppositely arranged it is described socket pipe (10) and socket bar (8) be socketed,
It is described socket pipe (10) and socket fixed mechanism (9) are provided between bar (8).
2. a kind of analysis on aqueduct structure according to claim 1, it is characterised in that: the fixed mechanism (9) includes deformation opening
Ring (91), the socket end for socketing pipe (10) offer deformation recessing groove (101), and the deformation split ring (91) is arranged described
It sockets at the deformation recessing groove (101) of pipe (10), two open ends of deformation split ring (91) are respectively arranged with latch
(911), locking assembly (92) are provided between two latch (911).
3. a kind of analysis on aqueduct structure according to claim 2, it is characterised in that: the locking assembly (92) includes connecting rod
(921), two latch (911) offer locking hole respectively, and connecting rod (921) is arranged in two locking holes, described
One end of connecting rod (921) is provided with anchorage bar (922), and one end of anchorage bar (922) offers mounting groove (9221), connecting rod
(921) the first connecting hole is offered, the two sidewalls of mounting groove (9221) offer the second connecting hole, connecting rod (921) and fastening
Bar (922) realizes the hinged of the two by rotation axis (923), and anchorage bar (922) is set as in the connecting pin with connecting rod (921)
The distance of extrados, extrados and the second connecting hole is progressively longer, and one end of the connecting rod (921), which is provided with, prevents connecting rod
(921) deviate from the locating part of locking hole.
4. a kind of analysis on aqueduct structure according to claim 3, it is characterised in that: the locating part includes stop nut (925),
The connecting rod (921) is provided with and stop nut (925) compatible external screw thread.
5. a kind of analysis on aqueduct structure according to claim 3, it is characterised in that: the connecting rod (921) is in anchorage bar (922)
It is provided between latch (911) gasket (924), gasket (924) is provided with the intrados to match with extrados.
6. a kind of analysis on aqueduct structure according to claim 1, it is characterised in that: the first cell wall built structure (2) is fixed
Have the first fixed link (71), the first fixed link (71) is arranged with the first split ring (72), sockets bar (8) and is fixedly arranged on the first split ring
(72) on positive camber, two open ends of first split ring (72) are respectively arranged with the first fastening plates (721), and two
One fastening plates are provided with the first fastening assembly between (721).
7. a kind of analysis on aqueduct structure according to claim 6, it is characterised in that: first fastening assembly includes the first fastening
Bolt and the first fastening nut, first fastening plates (721) offer the first fastener hole, and first fastening bolt is arranged in
It is screwed after two the first fastener holes with the first fastening nut.
8. a kind of analysis on aqueduct structure according to claim 1, it is characterised in that: the second cell wall built structure (3) is fixed
Have the second fixed link (112), second fixed link (112) is arranged with the second split ring (111), and described to socket pipe (10) fixed
Two open ends of the positive camber in the second split ring (111), second split ring (111) are respectively arranged with the second fastening plates
(1111), the second fastening assembly is provided between two the second fastening plates (1111).
9. a kind of analysis on aqueduct structure according to claim 8, it is characterised in that: second fastening assembly includes the second fastening
Bolt and the second fastening nut, second fastening plates (1111) offer the second fastener hole, and second fastening bolt is worn
It is screwed after two the second fastener holes with the second fastening nut.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920096968.7U CN209603069U (en) | 2019-01-21 | 2019-01-21 | A kind of analysis on aqueduct structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920096968.7U CN209603069U (en) | 2019-01-21 | 2019-01-21 | A kind of analysis on aqueduct structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209603069U true CN209603069U (en) | 2019-11-08 |
Family
ID=68401445
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920096968.7U Expired - Fee Related CN209603069U (en) | 2019-01-21 | 2019-01-21 | A kind of analysis on aqueduct structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209603069U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116084261A (en) * | 2023-01-05 | 2023-05-09 | 安徽省交通规划设计研究总院股份有限公司 | Seamless self-telescopic aqueduct and construction method |
-
2019
- 2019-01-21 CN CN201920096968.7U patent/CN209603069U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116084261A (en) * | 2023-01-05 | 2023-05-09 | 安徽省交通规划设计研究总院股份有限公司 | Seamless self-telescopic aqueduct and construction method |
CN116084261B (en) * | 2023-01-05 | 2023-10-20 | 安徽省交通规划设计研究总院股份有限公司 | Seamless self-telescopic aqueduct and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209603069U (en) | A kind of analysis on aqueduct structure | |
CN109972730A (en) | Assembled I-steel laminated floor slab mounting structure | |
CN209353708U (en) | Upper anti-bank template reinforcing device | |
CN214143565U (en) | Hydraulic engineering construction channel lateral wall strutting arrangement | |
CN109208393A (en) | A kind of track girder steel reinforcement cage bolt embedment structure | |
CN103967020B (en) | A kind of prestressing force suspension device for elongated rectangular shape foundation ditch | |
CN209669815U (en) | Analysis on aqueduct structure | |
CN208934007U (en) | A kind of connection structure of pipe gallery | |
CN209083020U (en) | A kind of recyclable foundation bolt rapid fixing | |
KR102135568B1 (en) | Box supporting beam structure for soil retaining wall | |
CN203846514U (en) | Supporting structure for short edge of long-strip rectangular foundation pit | |
CN206616692U (en) | A kind of adjustable building truss structure | |
CN204530510U (en) | A kind of assembling tilt adjustable is from falling frame pier-side bracket | |
CN206015909U (en) | A kind of tie rod and purlin attachment structure | |
CN213330017U (en) | Square column template reinforcement locking device | |
CN210002469U (en) | mud scraper for sewage treatment | |
CN112095442A (en) | Replaceable bridge damping energy-consumption connecting piece structure | |
CN208236444U (en) | Tunnel waterstop fixes device | |
CN208219388U (en) | Modular glass spray of molten steel slot and its drainage system on a kind of newly building bridge | |
CN209039878U (en) | Track girder steel reinforcement cage bolt embedment structure | |
CN107869257B (en) | Interior arch underpins boom device | |
CN207063676U (en) | Swing suspension column | |
CN219863037U (en) | Supporting structure capable of being used across pipeline | |
CN209874252U (en) | Steel structure crossbeam | |
CN217601709U (en) | Steel member with adjustable inclination angle direction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191108 Termination date: 20220121 |
|
CF01 | Termination of patent right due to non-payment of annual fee |