CN209601970U - A kind of fixed device of electronic winch hoister - Google Patents

A kind of fixed device of electronic winch hoister Download PDF

Info

Publication number
CN209601970U
CN209601970U CN201920251991.9U CN201920251991U CN209601970U CN 209601970 U CN209601970 U CN 209601970U CN 201920251991 U CN201920251991 U CN 201920251991U CN 209601970 U CN209601970 U CN 209601970U
Authority
CN
China
Prior art keywords
steel pipe
vertical
vertical steel
pipe
level
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920251991.9U
Other languages
Chinese (zh)
Inventor
邴兴飞
宋雅东
刘海冰
曹晓明
张军山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongjia Jiansheng Construction Engineering Group Co ltd
Zhongqing Jianan Construction Group Co Ltd
Original Assignee
Zhongqing Jianan Construction Group Co Ltd
Qingdao Zhongjia Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongqing Jianan Construction Group Co Ltd, Qingdao Zhongjia Construction Group Co Ltd filed Critical Zhongqing Jianan Construction Group Co Ltd
Priority to CN201920251991.9U priority Critical patent/CN209601970U/en
Application granted granted Critical
Publication of CN209601970U publication Critical patent/CN209601970U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model proposes a kind of fixed devices of electronic winch hoister, the fixation device includes the first vertical steel pipe, the second vertical steel pipe, first level steel pipe and the second horizontal steel tube, the bottom end of the first vertical steel pipe and the second vertical steel pipe and ground connect, and it is perpendicular to the ground, the top of the first vertical steel pipe and the second vertical steel pipe and ceiling connect;Respectively with the first vertical steel pipe and the second vertical steel pipe is vertical connect, the other side of the first level steel pipe and the second horizontal steel tube is overlapped on the windowsill of reserved window, and is extended to outside reserved window for the side of the first level steel pipe and the second horizontal steel tube;The first fixed steel pipe is vertically connected on the first level steel pipe and the second horizontal steel tube, and electronic winch hoister is fixedly mounted on the described first fixed steel pipe.The utility model carries out setting up assembling suspension using steel pipe, at low cost, significantly offer working efficiency, reduces labor intensity of workers.

Description

A kind of fixed device of electronic winch hoister
Technical field
The utility model relates to a kind of fixed devices of electronic winch hoister, belong to technical field of building construction.
Background technique
The vertical lifting equipment in building engineering construction later period has been removed substantially, is not had for the decoration construction material in portion within doors There is corresponding transporting equipment to be transported, or in the walk-up house ornamentation engineering of multilayer, most of construction and ornament materials are adopted Manually carry.Building materials use manual handling, and labor intensity of workers is larger, inefficiency, and cost is high.
Utility model content
The utility model is to solve the problems of the prior art and propose, technical solution is as follows,
A kind of fixed device of electronic winch hoister, the fixation device include the first vertical steel pipe, the second vertical steel pipe, the The bottom end and ground of one horizontal steel tube and the second horizontal steel tube, the first vertical steel pipe and the second vertical steel pipe connect, And it is perpendicular to the ground, the top of the first vertical steel pipe and the second vertical steel pipe and ceiling connect;First water The side of flat steel pipe and the second horizontal steel tube respectively with the first vertical steel pipe and the second vertical steel pipe is vertical connect, first water The other side of flat steel pipe and the second horizontal steel tube is overlapped on the windowsill of reserved window, and is extended to outside reserved window;It is described The first fixed steel pipe is vertically connected on first level steel pipe and the second horizontal steel tube, and electricity is fixedly mounted on the described first fixed steel pipe Dynamic winch hoister.
Preferably, chock is equipped between the described first vertical steel pipe and the top and ceiling of the second vertical steel pipe, it is described The top and bottom end of first vertical steel pipe and the second vertical steel pipe respectively with chock connect, chock respectively with ceiling and ground Face contact connection.
Further, the bottom end of the described first vertical steel pipe and the second vertical steel pipe is equipped with adjustable seats, the adjustable supporting The bottom end of seat and chock connect.
Further, the adjustable seats include top plate and bottom plate, are equipped with tapped through hole, the bottom plate among the top plate It is fixedly connected with threaded post, the threaded post is threadedly coupled with tapped through hole;The first vertical steel pipe and the second vertical steel pipe Bottom end is connect with top plate, and threaded post can protrude into the inside of the first vertical steel pipe and the second vertical steel pipe.
Preferably, the upper, middle and lower of the described first vertical steel pipe and the second vertical steel pipe is respectively perpendicular connection Two fixed steel pipes, to enhance stability;Second positioned at the described first vertical steel pipe and the second vertical steel pipe medium position is solid Determine steel pipe and meanwhile respectively with first level steel pipe and the second horizontal steel tube is vertical connect.
Preferably, chock, the first level are equipped between the windowsill and first level steel pipe and the second horizontal steel tube Steel pipe and the second horizontal steel tube are overlapped on chock, and two are separately connected on the first level steel pipe and the second horizontal steel tube admittedly Fixed card pipe, the fixing card pipe are close to the setting of windowsill two sides.
Preferably, which further includes square bar pipe support, and the square bar pipe support is connected by four steel pipes and formed, institute The one end for stating square bar pipe support is connect with the middle and upper part of the first vertical steel pipe and the second vertical steel pipe respectively, the square bar pipe support The other end connect respectively with the middle part of first level steel pipe and the second horizontal steel tube;The square bar pipe support, the first vertical steel Pipe, the second vertical steel pipe, first level steel pipe and the second horizontal steel tube connect to form triangular frame structure.
Further, the second fixed steel pipe positioned at the first vertical steel pipe and the second vertical steel pipe medium position uses trigone Right-angle coupler is connect with the described first vertical steel pipe, the second vertical steel pipe, first level steel pipe and the second horizontal steel tube respectively;Position In the first vertical steel pipe and the second vertical steel pipe upper and lower part position the second fixed steel pipe using right-angle coupler respectively with institute State the first vertical steel pipe and the second vertical steel pipe connection.
Further, the described first fixed steel pipe and fixing card pipe using right-angle coupler respectively with first level steel pipe and the The connection of two horizontal steel tubes.
Further, the square bar pipe support using right-angle coupler respectively with the first vertical steel pipe, the second vertical steel pipe, the One horizontal steel tube and the connection of the second horizontal steel tube.
The utility model carries out setting up assembling suspension using steel pipe, at low cost, significantly offer working efficiency, reduces worker's labor Fatigue resistance.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of the fixed device of electronic winch hoister of the utility model.
Fig. 2 is a kind of side view of the fixed device of electronic winch hoister of the utility model.
Fig. 3 is the result schematic diagram of the utility model adjustable seats.
In figure: 1, the first vertical steel pipe;2, the second vertical steel pipe;3, first level steel pipe;4, the second horizontal steel tube;5, pre- Stay window;6, the first fixed steel pipe;7, electronic winch hoister;8, chock;9, adjustable seats;901, top plate;902, bottom plate; 903, threaded post;10, the second fixed steel pipe;11, fixing card pipe;12, square bar pipe support.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
As shown in Figure 1-3, a kind of fixed device of electronic winch hoister, which includes the first vertical steel pipe 1, the Two vertical steel pipes 2, first level steel pipe 3 and the second horizontal steel tube 4, the bottom of the first vertical steel pipe 1 and the second vertical steel pipe 2 End is connected with ground, and perpendicular to the ground, top and the ceiling of the first vertical steel pipe 1 and the second vertical steel pipe 2 It connects, the first vertical steel pipe 1 and the second vertical steel pipe 2 are set side by side;The first level steel pipe 3 and the second horizontal steel tube Respectively with the first vertical steel pipe 1 and the second vertical steel pipe 2 is vertical connect, the first level steel pipe 3 and second is horizontal for 4 side The other side of steel pipe 4 is overlapped on the windowsill of reserved window 5, and is extended to outside reserved window 5;The first level steel pipe 3 Steel pipe 6 is fixed with vertically connecting first on the second horizontal steel tube 4, electronic elevator is fixedly mounted on the described first fixed steel pipe 6 and mentions Rise machine 7.
Between the first vertical steel pipe 1 and the top and ceiling of the second vertical steel pipe 2 be equipped with chock 8, described first The top and bottom end of vertical steel pipe 1 and the second vertical steel pipe 2 are connected with chock 8 respectively, the chock 8 respectively with ceiling It is connected with ground.Chock is equipped between the windowsill and first level steel pipe 3 and the second horizontal steel tube 4 of the reserved window 5 8, the first level steel pipe 3 and the second horizontal steel tube 4 are overlapped on chock 8, and chock 8 is used to prevent ground, ceiling and window Original structure is damaged along concentration stress.Two fixing cards are separately connected on the first level steel pipe 3 and the second horizontal steel tube 4 Pipe 11, the fixing card pipe 11 are close to the setting of windowsill two sides;Fixing card pipe 11 is horizontal to fixed first level steel pipe 3 and second Steel pipe 4 prevents from moving around.
The bottom end of the first vertical steel pipe 1 and the second vertical steel pipe 2 is equipped with adjustable seats 9, the bottom of the adjustable seats 9 End is connected with chock 8.The adjustable seats 9 include top plate 901 and bottom plate 902, are led among the top plate 901 equipped with screw thread Hole, the bottom plate 902 are fixedly connected with threaded post 903, and the threaded post 903 is threadedly coupled with tapped through hole;Described first is vertical The bottom end of steel pipe 1 and the second vertical steel pipe 2 is connect with top plate 901, and threaded post 902 can protrude into the first vertical steel pipe 1 and second The inside of vertical steel pipe 2.Using adjustable seats 9 top and bottom of first vertical steel pipe 1 and the second vertical steel pipe 2 are held out against Ceiling and ground, so that fixation is stronger, and when being installed and removed the first vertical steel pipe 1 and the second vertical steel pipe 2 It is more convenient.
It is fixed that the upper, middle and lower of the first vertical steel pipe 1 and the second vertical steel pipe 2 is respectively perpendicular connection second Steel pipe 10;Positioned at the described first vertical steel pipe 1 and the second vertical 2 medium position of steel pipe the second fixed steel pipe 10 simultaneously respectively with First level steel pipe 3 and the second vertically connection of horizontal steel tube 4, the second fixed steel pipe 10 are used to enhance the stability of frame structure.
The fixation device further includes square bar pipe support 12, and the square bar pipe support 12 is connected by four steel pipes and formed, described One end of square bar pipe support 12 is connect with the middle and upper part of the first vertical steel pipe 1 and the second vertical steel pipe 2 respectively, the rectangular steel tube The other end of frame 12 is connect with the middle part of first level steel pipe 3 and the second horizontal steel tube 4 respectively;The square bar pipe support 12, One vertical steel pipe 1, the second vertical steel pipe 2, first level steel pipe 3 and the connection of the second horizontal steel tube 4 form triangular frame structure, The stability of triangular frame structure is stronger.
The second fixed steel pipe 10 positioned at the first vertical steel pipe 1 and the second vertical 2 medium position of steel pipe uses trigone right angle Fastener is connect with the described first vertical steel pipe 1, the second vertical steel pipe 2, first level steel pipe 3 and the second horizontal steel tube 4 respectively;Position The second fixed steel pipe 10 in the first vertical steel pipe 1 and the second vertical 2 upper and lower part position of steel pipe is distinguished using right-angle coupler It is connect with the described first vertical steel pipe 1 and the second vertical steel pipe 2.Described first fixed steel pipe 6 and fixing card pipe 11 use right angle Fastener is connect with first level steel pipe 3 and the second horizontal steel tube 4 respectively.The square bar pipe support 12 using right-angle coupler respectively with First vertical steel pipe 1, the second vertical steel pipe 2, first level steel pipe 3 and the connection of the second horizontal steel tube 4.Using right-angle coupler and three The mounting means of rib right-angle coupler, so that installation and removing more convenient, and stability is high, compares, does not deposit with welding The rosin joint the case where, security risk is relatively fewer, and convenient for disassembly and assembly, improves working efficiency.Using trigone right-angle coupler, button is reduced Number of packages amount, avoids two fasteners while use generates security risk there are eccentricity.
The trigone right-angle coupler fastener body and tightening buckle, set that there are three sections to be semicircular on the fastener body Groove, semi-circular cross-section extending direction of three grooves on fastener body are mutually perpendicular to intersect, and a groove is horizontal cross, One groove is vertical direction, and a groove is horizontal longitudinal direction, and three grooved semicircular profile sections extend mutually not to outside fastener body Interference, hinged respectively with groove cooperation in the tightening buckle in complete circle section on fastener body, the other end of tightening buckle passes through It being bolted on fastener body, the inner surface of the groove and tightening buckle is equipped with several Saw blades, to increase frictional force, So that trigone right-angle coupler and the first vertical steel pipe 1, the second vertical steel pipe 2, first level steel pipe 3, the second horizontal steel tube 4 and The two fixed fixations of steel pipe 10 are stronger, improve security performance.
Electronic winch hoister 7 is passed through to the steel pipe for being easy to gather materials on the spot, carries out setting up assembling suspension, it is at low cost, significantly Working efficiency is provided, labor intensity of workers is reduced, design of coupler scaffold replacement can be used in steel pipe, and construction site utilization rate is most, It gathers materials on the spot conveniently.
Although the utility model is described in detail with reference to the foregoing embodiments, come for those skilled in the art Say, it is still possible to modify the technical solutions described in the foregoing embodiments, or to part of technical characteristic into Row equivalent replacement, within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on should all It is included within the scope of protection of this utility model.

Claims (10)

1. a kind of fixed device of electronic winch hoister, it is characterised in that: the fixation device includes the first vertical steel pipe (1), the Two vertical steel pipes (2), first level steel pipe (3) and the second horizontal steel tube (4), the first vertical steel pipe (1) and second is vertically The bottom end and ground of steel pipe (2) connect, and perpendicular to the ground, the first vertical steel pipe (1) and the second vertical steel pipe (2) Top and ceiling connect;The side of the first level steel pipe (3) and the second horizontal steel tube (4) is perpendicular with first respectively Straight steel pipe (1) and the second vertical steel pipe (2) vertically connect, the first level steel pipe (3) and the second horizontal steel tube (4) it is another Side is overlapped on the windowsill of reserved window (5), and it is external to extend to reserved window (5);The first level steel pipe (3) and second First fixed steel pipe (6) are vertically connected on horizontal steel tube (4), and electronic elevator is fixedly mounted on described first fixed steel pipe (6) and mentions It rises machine (7).
2. the fixed device of a kind of electronic winch hoister according to claim 1, it is characterised in that: the first vertical steel It manages and is equipped with chock (8) between (1) and the top and ceiling of the second vertical steel pipe (2), the first vertical steel pipe (1) and second The top and bottom end of vertical steel pipe (2) are connected with chock (8) respectively, and the chock (8) connects with ceiling and ground respectively Touching connection.
3. the fixed device of a kind of electronic winch hoister according to claim 2, it is characterised in that: the first vertical steel The bottom end for managing (1) and the second vertical steel pipe (2) is equipped with adjustable seats (9), and bottom end and the chock (8) of the adjustable seats (9) connect Touching connection.
4. the fixed device of a kind of electronic winch hoister according to claim 3, it is characterised in that: the adjustable seats (9) include top plate (901) and bottom plate (902), tapped through hole is equipped among the top plate (901), the bottom plate (902) is fixed to be connected It connects threaded post (903), the threaded post (903) is threadedly coupled with tapped through hole;The first vertical steel pipe (1) and second is vertically The bottom end of steel pipe (2) is connect with top plate (901), and threaded post (903) can protrude into the first vertical steel pipe (1) and the second vertical steel pipe (2) inside.
5. the fixed device of a kind of electronic winch hoister according to claim 1, it is characterised in that: the first vertical steel The upper, middle and lower of pipe (1) and the second vertical steel pipe (2) is respectively perpendicular connection second fixed steel pipe (10), to enhance Stability;Simultaneously positioned at second fixed steel pipe (10) of the described first vertical steel pipe (1) and the second vertical steel pipe (2) medium position Respectively with first level steel pipe (3) and the second horizontal steel tube (4) is vertical connect.
6. the fixed device of a kind of electronic winch hoister according to claim 1, it is characterised in that: the reserved window (5) chock (8) are equipped between windowsill and first level steel pipe (3) and the second horizontal steel tube (4), the first level steel pipe (3) it is overlapped on chock (8) with the second horizontal steel tube (4), divides on the first level steel pipe (3) and the second horizontal steel tube (4) Not Lian Jie two fixing card pipes (11), the fixing card pipe (11) is close to the setting of windowsill two sides.
7. the fixed device of a kind of electronic winch hoister according to claim 1, it is characterised in that: the fixation device also wraps It including square bar pipe support (12), square bar pipe support (12) the You Sigen steel pipe connects to be formed, and the one of the square bar pipe support (12) End connect respectively with the middle and upper part of the first vertical steel pipe (1) and the second vertical steel pipe (2), the square bar pipe support (12) it is another End is connect with the middle part of first level steel pipe (3) and the second horizontal steel tube (4) respectively;The square bar pipe support (12), first are erected Straight steel pipe (1), the second vertical steel pipe (2), first level steel pipe (3) and the second horizontal steel tube (4) connection form triangular framing Structure.
8. the fixed device of a kind of electronic winch hoister according to claim 5, it is characterised in that: be located at the first vertical steel Second fixed steel pipe (10) for managing (1) and the second vertical steel pipe (2) medium position use trigone right-angle coupler respectively with described the One vertical steel pipe (1), the second vertical steel pipe (2), first level steel pipe (3) and the second horizontal steel tube (4) connection;It is perpendicular positioned at first The second of straight steel pipe (1) and the second vertical steel pipe (2) upper and lower part position fixed steel pipe (10) using right-angle coupler respectively with The first vertical steel pipe (1) and the second vertical steel pipe (2) connection.
9. the fixed device of a kind of electronic winch hoister according to claim 6, it is characterised in that: the described first fixed steel Pipe (6) and fixing card pipe (11) are connect with first level steel pipe (3) and the second horizontal steel tube (4) respectively using right-angle coupler.
10. the fixed device of a kind of electronic winch hoister according to claim 7, it is characterised in that: the rectangular steel tube Frame (12) using right-angle coupler respectively with the first vertical steel pipe (1), the second vertical steel pipe (2), first level steel pipe (3) and second Horizontal steel tube (4) connection.
CN201920251991.9U 2019-02-28 2019-02-28 A kind of fixed device of electronic winch hoister Expired - Fee Related CN209601970U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920251991.9U CN209601970U (en) 2019-02-28 2019-02-28 A kind of fixed device of electronic winch hoister

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920251991.9U CN209601970U (en) 2019-02-28 2019-02-28 A kind of fixed device of electronic winch hoister

Publications (1)

Publication Number Publication Date
CN209601970U true CN209601970U (en) 2019-11-08

Family

ID=68404899

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920251991.9U Expired - Fee Related CN209601970U (en) 2019-02-28 2019-02-28 A kind of fixed device of electronic winch hoister

Country Status (1)

Country Link
CN (1) CN209601970U (en)

Similar Documents

Publication Publication Date Title
CN213329955U (en) Flower basket diagonal rod type overhanging scaffold
CN105986664A (en) Hanging basket and roof reverse hanging plate operation platform with same
CN202099993U (en) Lift type external scaffold made of square steel pipes
CN206581579U (en) A kind of track-type facilities of elevating scaffold
CN108590151A (en) A kind of scalable elevator hanging basket in four sides
CN209601970U (en) A kind of fixed device of electronic winch hoister
CN205100531U (en) Lift scaffold support body assembly
CN205397785U (en) Construction elevator attaches wall interval superelevation subassembly
CN206448505U (en) Adjustable draw and insert-type all steel attachment type raise scaffold back cover panel assembly
CN109707084B (en) Flexible curtain wall elastic support and external ribbon system
CN204006613U (en) A kind of collector lifting fixed support
CN206110589U (en) Stone cladding process slabstone fixed knot constructs with high anti -shock function
CN205791306U (en) Cable testing bridge heavy duty suspension bracket
CN211691525U (en) Construction device for overhanging type inclined curtain wall
CN209817104U (en) House frame connection structure
CN209482584U (en) A kind of light steel building floor steelframe module
CN207277768U (en) A kind of aluminium alloy decorative lines mounting structure
CN205908008U (en) Dish knot formula scaffold external safety net coupling assembling of frame external corner and external safety net device
CN205000502U (en) Prevent wind structure
CN205077677U (en) Pull rod formula steel construction point type glass curtain wall
CN209099752U (en) Elevating scaffold wall-attaching base
CN205444459U (en) Biconjugate position steel construction
CN208363382U (en) A kind of steel broken line glass curtain wall
CN204740835U (en) Single pole bill -board
CN211286240U (en) Aluminum veneer ceiling system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 266000 Room 302, Building 29, 171 Jinshui Road, Licang District, Qingdao City, Shandong Province

Patentee after: Zhongjia Jiansheng Construction Engineering Group Co.,Ltd.

Patentee after: ZHONGQING JIANAN CONSTRUCTION GROUP Co.,Ltd.

Address before: 266000 Room 302, Building 29, 171 Jinshui Road, Licang District, Qingdao City, Shandong Province

Patentee before: QINGDAO ZHONGJIA CONSTRUCTION GROUP Co.,Ltd.

Patentee before: ZHONGQING JIANAN CONSTRUCTION GROUP Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191108