CN209584871U - A kind of only column great cantilever Coping Construction bracket of high pier - Google Patents

A kind of only column great cantilever Coping Construction bracket of high pier Download PDF

Info

Publication number
CN209584871U
CN209584871U CN201920031656.8U CN201920031656U CN209584871U CN 209584871 U CN209584871 U CN 209584871U CN 201920031656 U CN201920031656 U CN 201920031656U CN 209584871 U CN209584871 U CN 209584871U
Authority
CN
China
Prior art keywords
bracket
pier
vertical
plate
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920031656.8U
Other languages
Chinese (zh)
Inventor
张何
田连民
杨晓光
彭园
张雨宾
王伟申
刘乐乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, China Communications Road and Bridge North China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201920031656.8U priority Critical patent/CN209584871U/en
Application granted granted Critical
Publication of CN209584871U publication Critical patent/CN209584871U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of high only column great cantilever Coping Construction brackets of pier, including the shelf bracket being arranged in the opposite two side walls of pier stud, each shelf bracket includes two A-frames, each A-frame includes vertical bar, cross bar and hound, vertical bar lower end is supported on the bracket being installed on pier stud side wall, bracket is bolted with the bracket built-in fitting being embedded in pier shaft, the lower end of vertical bar and the top plate of bracket pass through flanged joint, the upper end of two vertical bars and a horizontally disposed distribution beam pass through flanged joint, it is close to pier stud side wall in the side of distribution beam, the other side is connect with one end of the cross bar of two A-frames by pin shaft, the other end of cross bar and the lower end of vertical bar are connected by pin shaft;By being connected to pull rod between two distribution beams of pier stud two sidewalls.The utility model is improved than existing carrier structure overall stiffness, stability and safety.

Description

A kind of only column great cantilever Coping Construction bracket of high pier
Technical field
The utility model belongs to technical field of bridge construction, is related to the bracket of bridge coping construction, especially a kind of high pier Only column great cantilever Coping Construction bracket.
Background technique
Great cantilever Prestressed Slab Beams are common in municipal overpass engineering, on across town road, have that span ability is strong, construction Speed is fast, and the advantages that lack occupied road area.Municipal overpass great cantilever Prestressed Slab Beams are usually to use floor stand method Construction, because floor stand structure designs relative maturity, stability is also preferable.
In mountain area, complicated landform bridge is frequently with high pier.The high pier construction period is long, and risk is big.Use for reference great cantilever prestressing force lid The advantages of beam, at present in Bridges in Mountainous Areas construction, monoblock type bridge pier top is also designed frequently with great cantilever Prestressed Slab Beams, makes bridge Beam or so width bridge shares a pier shaft and is shortened the construction period with reducing high pier quantity, saves cost.But because alpine terrain and pier shaft are high Degree limitation, can not be using landing cast-in-place support method construction;It is complete frequently with Bracket method one-time-concreting to guarantee Coping Construction quality At.
Traditional bent cap bracket is usually that hole is preset on pier shaft, penetrates rod iron as load-bearing fulcrum, but easily cause hole Hole circumferential concrete pours not full, generates certain influence to pier shaft structure;Or using steel plate welding embedding anchor bolts in pier With, bracket is welded on the steel plate, shelf bracket is installed, but overhead welding quality is difficult to control on bracket, bracket load-bearing capacity It cannot be guaranteed that overall weight is big due to bent cap arm length, superelevation idle job in addition is affected by the wind larger, has larger safety Hidden danger.
Summary of the invention
The purpose of this utility model is that being provided a kind of only suitable for high pier for deficiency existing for current bent cap bracket Column great cantilever Coping Construction bracket, improves the form of existing carrier structure and load-bearing fulcrum, with improve carrier structure overall stiffness, Stability and safety, and reduce the influence to pier shaft structure.
The technical solution of the utility model is as follows:
A kind of only column great cantilever Coping Construction bracket of high pier, including the triangle support being arranged in the opposite two side walls of pier stud Frame, the shelf bracket on each side wall include two A-frames disposed in parallel, each A-frame include vertical bar, cross bar and The vertical bar lower end of hound, each A-frame is supported on the bracket being installed on pier stud side wall, it is characterised in that: the ox Leg is bolted with the bracket built-in fitting being embedded in pier shaft, and the top plate of the lower end of the vertical bar and the bracket passes through method Orchid connection, the upper end of two vertical bars of two A-frames of the every side of pier stud passes through flange with a horizontally disposed distribution beam respectively Pier stud side wall is close in the side of connection, the distribution beam, and the other side is connect with one end of the cross bar of two A-frames by pin shaft, The other end of the cross bar is connect with the lower end of the vertical bar by pin shaft;Pass through between two distribution beams of pier stud two sidewalls Pull rod is connected.
Further, in the only column great cantilever Coping Construction bracket of above-mentioned high pier, the bracket built-in fitting being embedded in pier shaft, It is parallel to each other including muti-piece and the vertical plate with horizontal plane, has certain intervals, one end of every piece of vertical plate and one between adjacent vertical plate Connecting plate welding;The plate face of the connecting plate is vertical with the plate face of the vertical plate, on connecting plate between every two pieces of vertical plates Multiple screw holes are set along the direction parallel with vertical plate plate face, on connecting plate and the one side of vertical plate welding, at each screw hole Weld an aperture and the consistent nut of screwhole diameter, and the horizontal sealing end steel pipe of corresponding each nut setting one, each sealing end steel One end of pipe and connecting plate weld and by a nut cover in nozzle;Multiple rows of through-hole is provided on every piece of vertical plate, each vertical plate just Pair through-hole in intert horizontally disposed transverse reinforcement, a bulkhead is respectively welded in the end of each row's transverse reinforcement;It is described Vertical plate, connecting plate, transverse reinforcement and bulkhead are embedded in bridge pier shaft concrete, and the side plate face of the connecting plate is exposed It in pier shaft outer wall, flushes with pier shaft wall surface, and is bolted with the side plate of bracket.
Each inter-module of the utility model mainly passes through bolt or pin shaft connection, avoids the risk of overhead welding operation;It adopts With bracket shearing resistance, bracket built-in fitting is embedded in pier shaft as bracket load-bearing fulcrum in advance, is easy to position, and uses high-strength bolt with bracket Connection, quality of connection are easily controllable;Using to pull system antidumping, the bracket of pier shaft two sides is connected as one by pull rod, and Prestressing force is applied to pull rod, integral strength, bearing capacity and the stability of bracket is substantially increased, ensure that superelevation idle job mistake The safety of operating personnel in journey.
Detailed description of the invention
Fig. 1 is the schematic view of facade structure of the utility model;
Fig. 2 is the planar structure schematic diagram of the utility model;
Fig. 3 is the side structure schematic view of the utility model;
Fig. 4 is the enlarged drawing of bracket built-in fitting shown in Fig. 1, it is shown that bracket built-in fitting and its connect with bracket The side view of structure;
Fig. 5 is the enlarged drawing of bracket built-in fitting shown in Fig. 2, it is shown that the plan view of bracket built-in fitting;
Fig. 6 is the enlarged drawing of bracket built-in fitting shown in Fig. 3, it is shown that the front view of bracket built-in fitting.
Specific embodiment
As shown in Figure 1, Figure 2, Figure 3 shows, the utility model includes the triangle support being arranged in the opposite two side walls of pier stud 1 Frame, the shelf bracket on each side wall includes two A-frames disposed in parallel, and each A-frame includes vertical bar 2, cross bar 3 Be supported on the bracket 5 being installed on pier stud side wall with 2 lower end of vertical bar of hound 4, each A-frame, the bracket 5 with The bracket built-in fitting 6 being embedded in pier shaft is connected by bolt 7, and the top plate of the lower end of the vertical bar 2 and the bracket 5 passes through method Orchid connection, the upper end of two vertical bars 2 of two A-frames of the every side of pier stud passes through method with a horizontally disposed distribution beam 8 respectively 1 side wall of pier stud is close in orchid connection, the side of the distribution beam 8, and the other side and one end of the cross bar 3 of two A-frames pass through pin shaft Connection, the other end of the cross bar 3 are connect with the lower end of the vertical bar 2 by pin shaft;Two distribution beams 8 positioned at pier stud two sidewalls Between by pull rod 9 connect.
Bed die distribution beam 10 is on the cross bar 3 for setting up each shelf bracket.Coping Construction is set up at the top of bed die distribution beam 10 The components such as template.
In an Application Example of the utility model, each pier spacing 50m of the bridge constructed is all made of hollow pier, The average high 68m of pier, pier top section 8m × 2.6m, pier top use super large cantilever Prestressed Slab Beams, are current domestic solely pillar height Dun Gai The maximum design of cantilever in beam, lateral length 25.1m, longitudinal width 3m, unilateral arm length 8.55m, all using the utility model Bracket construction.When it is implemented, the clipping room of two A-frames of the every side of pier stud is away from for 1.7m, bracket distribution beam is by -20mm Steel plate group weldering, bracket upper lever, column and brace are by bis- [36b channel steel group welderings.4 are used to pull rod32 finish rolling screw threads Steel, 10 tons of every root application Prestressing.Bracket built-in fitting is embedded in pier stud concrete according to preset absolute altitude when pier stud is constructed In.
As shown in Fig. 4, Fig. 5, Fig. 6, the bracket built-in fitting 6 being embedded in pier shaft, including muti-piece be parallel to each other and with The vertical plate 61 of horizontal plane, there is certain intervals between adjacent vertical plate 61, and one end of every piece of vertical plate 61 and a connecting plate 62 weld;Institute The plate face for stating connecting plate 62 is vertical with the plate face of the vertical plate 61, on connecting plate 62 between every two pieces of vertical plates 61 along with it is vertical Multiple screw holes are arranged in the parallel direction of plate plate face, and on connecting plate and the one side of vertical plate welding, one is welded at each screw hole Aperture and the consistent nut 63 of screwhole diameter, and the horizontal sealing end steel pipe 64 of corresponding each setting of nut 63 one, each sealing end steel One end of pipe 64 and connecting plate 62 weld and cover on a nut 63 in nozzle;Multiple rows of through-hole, In are provided on every piece of vertical plate 61 Intert horizontally disposed transverse reinforcement 65 in the through-hole of each vertical plate face, is respectively welded one in the end of each row's transverse reinforcement 65 Bulkhead 66.
The vertical plate 61, connecting plate 62, transverse reinforcement 65 and bulkhead 66 are embedded in bridge pier shaft concrete, described The side plate face of connecting plate 62 exposes to 1 outer wall of pier shaft, flushes with pier shaft wall surface, and is connected with the side plate of bracket 5 by bolt 7 It connects.
On the one hand the effect of the bulkhead 66 is positioned to entire built-in fitting, transverse reinforcement 65 and pier shaft are on the other hand made Reinforcing bar 11 connects integral.When pre-buried in pier shaft, bulkhead 66 is arranged in the outside of pier shaft reinforcing bar 11, and with pier shaft steel Muscle 11 welds.
The structure of above-mentioned bracket built-in fitting, vertical plate pass through transverse reinforcement and bulkhead and pier shaft as main stress component Built-in fitting and pier shaft are formed entirety, greatly enhance the stress performance of bracket built-in fitting by structure reinforcing bars connection.Bracket built-in fitting with Bracket is connected using high-strength bolt, can be to avoid the hole surrounding coagulation being easy to appear in traditional bracket built-in fitting work progress Situations such as soil is not full, overhead welding quality is not easy to control, reduces security risk.

Claims (3)

1. a kind of only column great cantilever Coping Construction bracket of high pier, including the triangle support being arranged in the opposite two side walls of pier stud Frame, the shelf bracket on each side wall include two A-frames disposed in parallel, each A-frame include vertical bar, cross bar and The vertical bar lower end of hound, each A-frame is supported on the bracket being installed on pier stud side wall, it is characterised in that: the ox Leg is bolted with the bracket built-in fitting being embedded in pier shaft, and the top plate of the lower end of the vertical bar and the bracket passes through method Orchid connection, the upper end of two vertical bars of two A-frames of the every side of pier stud passes through flange with a horizontally disposed distribution beam respectively Pier stud side wall is close in the side of connection, the distribution beam, and the other side is connect with one end of the cross bar of two A-frames by pin shaft, The other end of the cross bar is connect with the lower end of the vertical bar by pin shaft;Pass through between two distribution beams of pier stud two sidewalls Pull rod is connected.
2. the only column great cantilever Coping Construction bracket of high pier according to claim 1, it is characterised in that: described to be embedded in pier shaft In bracket built-in fitting, be parallel to each other including muti-piece and the vertical plate with horizontal plane, there is certain intervals between adjacent vertical plate, every piece One end of vertical plate and a connecting plate weld;The plate face of the connecting plate is vertical with the plate face of the vertical plate, is located on connecting plate Multiple screw holes are set along the direction parallel with vertical plate plate face between every two pieces of vertical plates, in the one side of connecting plate and vertical plate welding On, an aperture and the consistent nut of screwhole diameter, and the horizontal sealing end of corresponding each nut setting one are welded at each screw hole Steel pipe, one end of each sealing end steel pipe and connecting plate weld and by a nut cover in nozzle;It is provided on every piece of vertical plate multiple rows of Through-hole interts horizontally disposed transverse reinforcement in the through-hole of each vertical plate face, welds respectively in the end of each row's transverse reinforcement Connect a bulkhead;The vertical plate, connecting plate, transverse reinforcement and bulkhead are embedded in bridge pier shaft concrete, the connection The side plate face of plate exposes to pier shaft outer wall, flushes with pier shaft wall surface, and is bolted with the side plate of bracket.
3. the only column great cantilever Coping Construction bracket of high pier according to claim 2, it is characterised in that: the bulkhead is located at On the outside of pier shaft reinforcing bar, and with pier shaft reinforcement welding.
CN201920031656.8U 2019-01-08 2019-01-08 A kind of only column great cantilever Coping Construction bracket of high pier Active CN209584871U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920031656.8U CN209584871U (en) 2019-01-08 2019-01-08 A kind of only column great cantilever Coping Construction bracket of high pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920031656.8U CN209584871U (en) 2019-01-08 2019-01-08 A kind of only column great cantilever Coping Construction bracket of high pier

Publications (1)

Publication Number Publication Date
CN209584871U true CN209584871U (en) 2019-11-05

Family

ID=68351065

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920031656.8U Active CN209584871U (en) 2019-01-08 2019-01-08 A kind of only column great cantilever Coping Construction bracket of high pier

Country Status (1)

Country Link
CN (1) CN209584871U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528376A (en) * 2019-09-16 2019-12-03 中建五局土木工程有限公司 Buck plate component, load carrier and construction technology
CN111088760A (en) * 2019-12-26 2020-05-01 中交武汉港湾工程设计研究院有限公司 Large-height large-cantilever concrete structure prefabricated construction support and installation method thereof
CN112538822A (en) * 2020-11-30 2021-03-23 中建五局第三建设有限公司 Bridge rectangular high-pier single-pier capping beam triangular bracket system and construction method
CN115012309A (en) * 2022-05-20 2022-09-06 中建八局第二建设有限公司 Overhead supporting device for large cantilever bent cap and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528376A (en) * 2019-09-16 2019-12-03 中建五局土木工程有限公司 Buck plate component, load carrier and construction technology
CN111088760A (en) * 2019-12-26 2020-05-01 中交武汉港湾工程设计研究院有限公司 Large-height large-cantilever concrete structure prefabricated construction support and installation method thereof
CN112538822A (en) * 2020-11-30 2021-03-23 中建五局第三建设有限公司 Bridge rectangular high-pier single-pier capping beam triangular bracket system and construction method
CN115012309A (en) * 2022-05-20 2022-09-06 中建八局第二建设有限公司 Overhead supporting device for large cantilever bent cap and construction method

Similar Documents

Publication Publication Date Title
CN209584871U (en) A kind of only column great cantilever Coping Construction bracket of high pier
CN105256917B (en) A kind of precast shear wall perps combined connecting structure and its construction method
CN106567458B (en) Assembled steel-is mixed to combine Beam-post Frame Structure system
CN104631343A (en) Self-travelling diamond-shaped pin-connected truss-type form traveler structure and form traveler travelling and constructing method
CN204690605U (en) The self-propelled triangular truss hanging basket of large span beam bridge
CN205012666U (en) High altitude steel construction vestibule integrally lift up support structure
CN204023411U (en) Novel assembled bracket bracket construction equipment
CN103410102A (en) H-shaped double column pier wide-bridge-surface cantilever temporary consolidation structure and construction method thereof
DE112014001605T5 (en) PCSS shear connection structure
CN215925691U (en) Bearing support for casting No. 0 block of bridge
CN104047233B (en) Method for construction of continuous beam linear segment without floor stand
CN109853365A (en) A kind of high pier construction of modularization prefabrication and assembly construction based on high-strength bolt connection and production method
CN109235280A (en) The operation platform and construction method of bridge coping
CN109930469B (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail
CN104233961A (en) Triangular supporting bracket of suspended cast bridge block 0
CN211815595U (en) Lower tower column tension and compression structure for cable tower
CN209194347U (en) The operation platform of bridge coping
CN208869942U (en) A kind of long-span continuous rigid-framed bridge external prestressing load system
CN206607506U (en) A kind of through type adds the capping construction support of passive stress trapezoid block
CN215629471U (en) Bridge cantilever structure does not have bracket articulated formula bracket strutting arrangement
CN210828440U (en) Concrete floor reinforcing structure before expiration of building
CN209162662U (en) A kind of continuous T beam bridge is without bracket maintenance and reinforcement operation platform
CN103526698B (en) Cast-in-cantilever construction 0# block concrete supporting system and construction method
CN217419324U (en) Turnover main side pier triangular support of large-span suspension casting box girder
CN209636617U (en) A kind of Composite Steel-Concrete Bridges with novel deck structrue

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant