- CN209555758U CN209555758U CN201920076617.XU CN201920076617U CN209555758U CN 209555758 U CN209555758 U CN 209555758U CN 201920076617 U CN201920076617 U CN 201920076617U CN 209555758 U CN209555758 U CN 209555758U
- Authority
- CN
- China
- Prior art keywords
- attachment strap
- abutment
- anchor pole
- uhpc
- oblique anchor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000011374 ultra-high-performance concrete Substances 0.000 title claims abstract description 23
- 238000010276 construction Methods 0.000 title claims abstract description 20
- 241001669679 Eleotris Species 0.000 claims abstract description 12
- 239000004567 concrete Substances 0.000 claims abstract description 9
- 238000005266 casting Methods 0.000 claims abstract description 4
- 239000000463 material Substances 0.000 claims description 4
- 229910001220 stainless steel Inorganic materials 0.000 claims description 3
- 239000010935 stainless steel Substances 0.000 claims description 3
- 238000005336 cracking Methods 0.000 abstract description 6
- 238000004062 sedimentation Methods 0.000 abstract description 5
- 239000002689 soil Substances 0.000 abstract description 4
- 238000012423 maintenance Methods 0.000 abstract description 2
- 238000010008 shearing Methods 0.000 description 5
- 238000013461 design Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 201000010099 disease Diseases 0.000 description 2
- 208000037265 diseases, disorders, signs and symptoms Diseases 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 206010039203 Road traffic accident Diseases 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 238000007569 slipcasting Methods 0.000 description 1
- 230000000192 social effect Effects 0.000 description 1
Landscapes
- Road Paving Structures (AREA)
Abstract
The embed-type UHPC lap slab of bridge construction of multistage fixed with oblique anchor pole, the lap slab of bridge being connected including abutment with abutment, attachment strap is made of the prefabricated laying of UHPC and normal concrete, attachment strap has certain slope, it is higher close to abutment side, and close abutment side is the prefabricated attachment strap of UHPC, other is the prefabricated attachment strap of normal concrete, two attachment strap junctions and attachment strap and roadbed junction are provided with concave character type sleeper beam, two layers of TGXG is provided with above attachment strap and roadbed junction, it is to banket above attachment strap, it is road surface on banketing, attachment strap and abutment junction are provided with bracket, bracket and abutment one-piece casting, it is connected between bracket and UHPC attachment strap with oblique anchor pole.Compared with existing construction, the utility model hazard to bridge's pier construction has prevented attachment strap between roadbed and the sedimentation and abutment and attachment strap of back filling behind abutment soil substantially and has been broken caused pavement cracking, later maintenance cost is low, greatly improves the service life of hazard to bridge's pier, securely and reliably.
Description
Technical field
The utility model relates to science of bridge building fields, and in particular to a kind of embed-type UHPC bridge of multistage fixed with oblique anchor pole
Beam attachment strap construction.
Background technique
China's construction of road and bridge is now in Rapid development stage, and the abutment and attachment strap, attachment strap and roadbed in bridge construction connect
The place's of connecing cracking is the Common Diseases of bridge.Abutment and attachment strap, attachment strap and roadbed junction pavement cracking cause to seep water at this, are seeping
Under the action of water and vehicle roll repeatedly, abutment and attachment strap can be gradually detached from, and cause crack increasing.In high speed traveling
In, crack can make driver and passenger experience discomfort of jolting while increase, and traffic accident is even easily caused when serious.It causes
Abutment and attachment strap, attachment strap and roadbed junction cracking and Slope protection has very much, wherein it is most important the reason is that abutment and attachment strap,
Attachment strap and roadbed two sides sedimentation it is inconsistent cause attachment strap fracture and roadbed side sedimentation it is excessive.In addition, formation and the attachment strap in crack
The connection structure form of material, attachment strap and abutment and attachment strap and roadbed also has relationship.In consideration of it, solving abutment and attachment strap junction
Problem of Cracking have huge social effect.
Summary of the invention
In order to solve the problems, such as abutment and attachment strap, attachment strap and roadbed junction pavement cracking and destroy, the utility model is mentioned
The embed-type UHPC lap slab of bridge construction of multistage fixed for oblique anchor pole.
A kind of technical solution of the utility model is a kind of embed-type UHPC lap slab of bridge structure of multistage fixed with oblique anchor pole
Make, including the lap slab of bridge that abutment is connected with abutment, attachment strap is laid with by multistage is prefabricated, two attachment strap junctions and attachment strap with
Roadbed junction is provided with sleeper beam, and two layers of TGXG is provided with above attachment strap and roadbed junction, is to banket above attachment strap, fills out
It is road surface on soil, attachment strap and abutment junction are provided with bracket, bracket and abutment one-piece casting, with oblique anchor between bracket and attachment strap
Bar connection.
Further, it is formed close to Abutment attachment strap by UHPC is prefabricated, other attachment straps are formed by normal concrete is prefabricated.
Further, the sleeper beam of setting is concave character type.
Further, the material of oblique anchor pole is stainless steel.
Further, the position that oblique anchor pole is stretched out at bracket is bracket upper side plane.
Further, the gradient that attachment strap is laid with is 2%-8%, and high close to abutment side.
It is connected in a manner of oblique anchor pole between abutment and attachment strap, the presence of oblique anchor pole can reinforce the entirety of attachment strap and abutment
Property, attachment strap can greatly enhance attachment strap in the mechanical properties such as the shearing resistance of bracket junction, reinforcement structure durability using UHPC.Attachment strap
Multistage design main purpose be to reduce adjacent sedimentation difference at two sections, can effectively inhibit the generation of pavement crack.Sleeper beam
It is designed to that concave character type is the straight skidding of attachment strap in order to prevent.Simultaneously as it is opposite smaller by shearing far from abutment side attachment strap, from
Economic aspect considers, using normal concrete attachment strap.
Compared with prior art, the utility model has the following beneficial effects:
(1) pavement crack of abutment Yu attachment strap and attachment strap and road surface junction has been prevented.
(2) durability of attachment strap is enhanced, later maintenance investment significantly reduces, and structure is safe and reliable.
(3) mechanical properties such as shearing resistance of attachment strap are significantly increased, and the diseases such as attachment strap fracture effectively reduce.
(4) it effectively prevent being detached between attachment strap and abutment.
Detailed description of the invention
It is that the technical solution of the utility model is described in conjunction with attached drawing below, attached drawing is only used for showing specific implementation
The purpose of example, and it is not considered as limitations of the present invention.
Fig. 1 is a kind of embed-type UHPC lap slab of bridge organigram of the multistage fixed with oblique anchor pole.
1 UHPC attachment strap in figure, 2 oblique anchor poles, 3 abutments, 4 brackets, 5 sleeper beams, 6 TGXG, 7 road surfaces, 8 normal concretes
Attachment strap.
Specific embodiment
Specifically describing the embodiments of the present invention with reference to the accompanying drawing, wherein attached drawing constitutes part of this application,
And it is used to illustrate the principles of the present invention together with the embodiments of the present invention.
A kind of embed-type UHPC lap slab of bridge of multistage fixed with oblique anchor pole constructs the construction of the present embodiment as shown in Figure 1:,
Including the lap slab of bridge 1 that abutment 3 is connected with abutment 3, attachment strap is laid with by multistage is prefabricated, two attachment strap junctions and attachment strap with
8 roadbed junctions are provided with sleeper beam 5, and two layers of TGXG 6 is provided with above attachment strap 8 and roadbed junction, are to fill out above attachment strap
Soil, banket on for road surface 7, attachment strap 1 and 3 junction of abutment are provided with bracket 4, bracket 4 and 3 one-piece casting of abutment, 4 He of bracket
It is connected between attachment strap 1 with oblique anchor pole 2.
In the present embodiment, it is formed close to Abutment attachment strap 1 by UHPC is prefabricated, other attachment straps 8 are prefabricated by normal concrete
It forms.
In the present embodiment, the sleeper beam 5 of setting is concave character type.
In the present embodiment, the material of oblique anchor pole 2 is stainless steel.
In the present embodiment, the position that oblique anchor pole 2 is stretched out at bracket is 4 upper side plane of bracket.
In the present embodiment, the gradient that attachment strap is laid with is 2%-8%, and high close to 3 side of abutment.
In the present embodiment, it is connected in a manner of oblique anchor pole 2 between abutment 3 and attachment strap 1, the presence of oblique anchor pole 2 can add
The globality of strong attachment strap 1 and abutment 3, attachment strap 1 can greatly enhance attachment strap in mechanical property such as the shearing resistances of 5 junction of bracket using UHPC
Can, reinforcement structure durability.The multistage design main purpose of attachment strap is the sedimentation difference reduced at adjacent two sections, can effectively be pressed down
The generation in 7 crack of road surface processed.Sleeper beam 5 is designed to that concave character type is the straight skidding of attachment strap in order to prevent.Simultaneously as far from abutment
3 side attachment straps 8 are opposite smaller by shearing, from the economic viewpoint, using normal concrete attachment strap 8.
The construction procedure of above-described embodiment are as follows:
In the construction process, abutment 3 is formed by normal concrete is cast-in-place, and reserves oblique anchor pole duct;
Attachment strap 1 and attachment strap 8 are prefabricated in the factory molding, wherein 1 reserving hole channel of attachment strap, and side embeds axle sleeve, convenient for oblique
The fixed construction of anchor pole;
In the work progress of attachment strap, it is embedded in sleeper beam 5 in banketing, then with evener compacting filling soil, the corresponding gradient is set,
It is laid with two kinds of prefabricated attachment straps later, oblique anchor pole 2 and Grouting Pipe pass through in axle sleeve and reserving hole channel insertion abutment 3, and slip casting is shut
Duct simultaneously flattens;
Attachment strap 8 is then directly placed on sleeper beam 5;
After the completion of attachment strap construction, then backfill, and twice geotechnique's lattice are set at roadbed in roadbed and 8 end of attachment strap
Grid 6;
It is flattened and is compacted with evener after the completion of backfill, be finally laid with road surface 7.
Content described in this specification embodiment is only an enumeration of the implementation forms of the utility model concept, this is practical new
The protection scope of type should not be construed as being limited to the specific forms stated in the embodiments, the protection scope of the utility model also and
In those skilled in the art according to the utility model design it is conceivable that equivalent technologies mean.
Claims (6)
1. a kind of embed-type UHPC lap slab of bridge construction of the oblique anchor pole multistage of band, it is characterised in that be connected including abutment with abutment
Lap slab of bridge, attachment strap are laid with by multistage is prefabricated, and two attachment strap junctions and attachment strap and roadbed junction are provided with sleeper beam, attachment strap
With two layers of TGXG is provided with above roadbed junction, banket above attachment strap, banket on connect for road surface, attachment strap and abutment
The place of connecing is provided with bracket, bracket and abutment one-piece casting, is connected between bracket and attachment strap with oblique anchor pole.
2. the embed-type UHPC lap slab of bridge construction of the oblique anchor pole multistage of a kind of band according to claim 1, it is characterised in that: lean on
Nearly Abutment attachment strap is formed by UHPC is prefabricated, and other attachment straps are formed by normal concrete is prefabricated.
3. the embed-type UHPC lap slab of bridge construction of the oblique anchor pole multistage of a kind of band according to claim 1, it is characterised in that: set
The sleeper beam set is concave character type.
4. the embed-type UHPC lap slab of bridge construction of the oblique anchor pole multistage of a kind of band according to claim 1, it is characterised in that: tiltedly
The material of anchor pole is stainless steel.
5. the embed-type UHPC lap slab of bridge construction of the oblique anchor pole multistage of a kind of band according to claim 1, it is characterised in that: ox
The position that oblique anchor pole is stretched out at leg is bracket upper side plane.
6. the embed-type UHPC lap slab of bridge construction of the oblique anchor pole multistage of a kind of band according to claim 1, it is characterised in that: take
The gradient that plate is laid with is 2%-8%, and high close to abutment side.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920076617.XU CN209555758U (en) | 2019-01-17 | 2019-01-17 | The embed-type UHPC lap slab of bridge construction of multistage fixed with oblique anchor pole |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920076617.XU CN209555758U (en) | 2019-01-17 | 2019-01-17 | The embed-type UHPC lap slab of bridge construction of multistage fixed with oblique anchor pole |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209555758U true CN209555758U (en) | 2019-10-29 |
Family
ID=68308084
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920076617.XU Expired - Fee Related CN209555758U (en) | 2019-01-17 | 2019-01-17 | The embed-type UHPC lap slab of bridge construction of multistage fixed with oblique anchor pole |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209555758U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109594468A (en) * | 2019-01-17 | 2019-04-09 | 浙江工业大学 | The embed-type UHPC lap slab of bridge construction of multistage fixed with oblique anchor pole |
-
2019
- 2019-01-17 CN CN201920076617.XU patent/CN209555758U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109594468A (en) * | 2019-01-17 | 2019-04-09 | 浙江工业大学 | The embed-type UHPC lap slab of bridge construction of multistage fixed with oblique anchor pole |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104695289B (en) | A kind of put line construction for middle the low of low speed magnetic suspension traffic engineering embankment location | |
CN105862538B (en) | The oblique bond-retarded prestressed concrete pavement structure of assembled | |
CN204418003U (en) | A kind of bridge platform post processing combined system | |
CN104328730B (en) | The construction method of embedded reinforcement bitumen layer transformation cement concrete pavement | |
CN107805987A (en) | The hassock layer Foam lightweight soil road structure and construction method in deep soft foundation section | |
CN208380592U (en) | On the contignation across existing proximity tunnel | |
CN202390857U (en) | Inspection wellhead reinforcement structure | |
CN110195406A (en) | A kind of seamless bridge abutment structure | |
CN209555758U (en) | The embed-type UHPC lap slab of bridge construction of multistage fixed with oblique anchor pole | |
CN207017093U (en) | New-old concrete bond widens seam-line removal structure | |
CN108487234B (en) | Construction method of cast-in-situ pile plate type platform wall | |
CN109594468A (en) | The embed-type UHPC lap slab of bridge construction of multistage fixed with oblique anchor pole | |
CN206298822U (en) | The seamless pavement structure that optimization CRCP is connected with floorings | |
CN207452609U (en) | A kind of hassock layer Foam lightweight soil road structure in deep soft foundation section | |
CN209260449U (en) | In-expansive rock or expansive soils non-fragment orbit foundation stabilization construct by force | |
CN204174495U (en) | Embedded reinforcement bitumen layer transformation cement concrete pavement structure | |
CN105113384A (en) | Z-shaped bridge end transition slab structure and construction method thereof | |
CN206157485U (en) | Moderate -low speed magnetic levitation single line excavation location pile foundation combined type support rail roof beam transition section structure | |
CN214529999U (en) | Anti-crack road with gradient structure | |
CN210262550U (en) | Asphalt pavement structure based on cement pavement | |
CN114293430A (en) | Urban road reconstruction method and structure jointly built with flood control wall and prop platform | |
CN210737257U (en) | Road tunnel transition structure and traffic line | |
CN112962383A (en) | Asphalt pavement structure capable of preventing crack propagation and construction method | |
CN111926649A (en) | Reinforced integrally-built crossing plate for railway special line and line rail fixing device | |
CN206127741U (en) | Moderate -low speed magnetic levitation single line excavation location detached pier column type support rail roof beam transition section structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |