CN209539369U CN201920008560.XU CN201920008560U CN209539369U CN 209539369 U CN209539369 U CN 209539369U CN 201920008560 U CN201920008560 U CN 201920008560U CN 209539369 U CN209539369 U CN 209539369U
Authority
CN
China
Prior art keywords
crossbeam
leg
arch
tunnel
welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920008560.XU
Other languages
Chinese (zh)
Inventor
宋二龙
练远平
王笑
应世明
张雨宾
杜辉
王涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, China Communications Road and Bridge North China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201920008560.XU priority Critical patent/CN209539369U/en
Application granted granted Critical
Publication of CN209539369U publication Critical patent/CN209539369U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a kind of Super-large-section tunnel secondary lining automatic spray health trolley, including crossbeam, cross rail top setting and the consistent sparge pipe of tunnel arch radian, crossbeam bottom sets wheeled supporting leg, wherein one end connection of the supporting leg and crossbeam of side, the supporting leg of the other side is arranged in the middle part of crossbeam between the crossbeam other end, under the premise of making trolley span be able to satisfy tunnel width, it avoids being arranged in adjuncts such as one crosswind bands of tunnel, can in tunnel normal pass, comprehensive spray is carried out to tunnel double-lining and is conserved.

Description

A kind of Super-large-section tunnel secondary lining automatic spray health trolley
Technical field
The utility model relates to highway tunnel construction technical fields, and in particular to a kind of pair of Super-large-section tunnel secondary lining The trolley of concrete progress automatic spray health.
Background technique
Tunnel Second Lining needs to carry out spray maintenance to concrete after the completion of pouring.Since tunnel vault height is higher, Artificial spray is more difficult, and costly using fog gun machine spraying health promotion, easy maintenance is not in place, and secondary lining concrete is caused to support Raw initial stage heat loss is slow, and surface temperature is constantly in higher state, and part is cracked, and intensity rises slow.Chinese patent Shen Numbers 201620331513.5 the device of a kind of entitled " Tunnel Second Lining spraying health promotion trolley " please be disclosed, use one Formula frame is able to achieve in gate-type frame two sides and top installation water pipe and spray head to the automatic health of tunnel double-lining.But the device is only suitable for Ordinary crossing, to Four-Lane Road Super-large-section tunnel, since tunnel side is equipped with wind band and other attached settings, if gate-type frame Its too big supporting leg of span is easy to be interfered by affiliated facility, and span is too small and easy maintenance is not in place.
Summary of the invention
The purpose of this utility model is that the problem difficult for the maintenance of Super-large-section tunnel secondary lining, provides a kind of special Door is used for Super-large-section tunnel secondary lining automatic spray health trolley, not only realizes automatic maintenance, but also can guarantee that health is imitated Fruit.
The technical solution of the utility model is as follows:
A kind of Super-large-section tunnel secondary lining automatic spray health trolley, it is characterised in that: including two it is vertically arranged, It is parallel to each other and arch at regular intervals, each arch includes the crossbeam of a certain altitude from the ground, and every crossbeam passes through perpendicular Supported to the first leg of setting and the second supporting leg, wherein the upper end of first leg and one end of crossbeam are welded, first leg with The first hound is welded between crossbeam, the lower end of the first hound and the lower end of first leg are welded, the upper end of the first hound It is welded on the position between crossbeam and first leg;The upper end of second supporting leg is welded in the middle part of crossbeam between the crossbeam other end Position is welded with the second hound between the lower end and the crossbeam other end of the second supporting leg;The lower end of first leg and the second supporting leg point It An Zhuan not traveling wheel;More vertically arranged perpendicular struts, more perpendicular strut parts from crossbeam are welded at the top of the crossbeam It is not reduced successively to crossbeam both ends height, between every two adjacent perpendicular strut ends, and the perpendicular support close to crossbeam both ends Between boom end and beam-end, connecting rod is respectively welded;Divide between the crossbeam of two arches and between the connecting rod of two arches It is not connected by more lateral bars;Between the connecting rod of two arches, it is erected with from crossbeam both ends to crossbeam middle part top successively Raised step;Two arches first leg outside be arranged a ladder, the two sides of the ladder pass through respectively singletree with The first leg of two arches connects;More upright bars are set in the connecting rod of an arch, and more upright bars are from face tunnel vault It is successively reduced to height on both sides, the end of every upright bar is welded with an arch sparge pipe respectively, the arch sparge pipe and tunnel Arch radian it is consistent, arch sparge pipe is closed at both ends, is arranged one on arch sparge pipe at spacing intervals towards tunnel double-lining The spray head of concrete;A water supplying pipe is connected on the outside of the first leg of an arch, described water supplying pipe one end sets an external water pipe and connects Mouthful, the other end is connected to the sparge pipe.
The utility model is designed for Super-large-section tunnel, and the maintenance of entire tunnel double-lining, knot are able to satisfy on horizontal span It is avoided that on structure and conflicts with adjuncts such as the air hoses of tunnel-side setting again, preferably solve especially big Tunnel Second Lining health and ask Topic, improves construction efficiency, ensure that two lining health quality.
Detailed description of the invention
Fig. 1 is the front view of the utility model;
Fig. 2 is the side view of the utility model;
Fig. 3 is the use state diagram of the utility model.
Specific embodiment
As shown in Figure 1 and Figure 2, a kind of Super-large-section tunnel secondary lining automatic spray health platform provided by the utility model Vehicle, including two it is vertically arranged, be parallel to each other and arch at regular intervals, each arch includes a certain altitude from the ground Crossbeam 1, every crossbeam 1 are supported by vertically arranged first leg 2 and the second supporting leg 3, wherein the upper end of first leg 2 and cross One end of beam 1 is welded, and the first hound 4, the lower end of the first hound 4 and first leg are welded between first leg 2 and crossbeam 1 2 lower end welding, the upper end of the first hound 4 is welded on the position between crossbeam 1 and first leg 2;The upper end of second supporting leg 3 It is welded on the position between 1 middle part of crossbeam and the crossbeam other end, is welded with second between the lower end and the crossbeam other end of the second supporting leg 3 Hound 5;Traveling wheel 6 is installed in the lower end of first leg 2 and the second supporting leg 3 respectively;The top of the crossbeam 1 is welded with more and erects To the perpendicular strut 7 of setting, more perpendicular struts 7 are successively reduced to crossbeam both ends height respectively from the middle part of crossbeam, adjacent at every two 7 end of perpendicular strut between, and close to crossbeam both ends 1 end of 7 end of perpendicular strut and crossbeam between, connecting rod is respectively welded 8;It is connected (in lateral bar figure not by more lateral bars respectively between the crossbeam 1 of two arches and between the connecting rod 8 of two arches It shows);Between the connecting rod 8 of two arches, it is erected with from crossbeam both ends to crossbeam middle part top successively raised step 9;? A ladder 10 is arranged in the outside of the first leg 2 of two arches, and the two sides of the ladder 10 pass through singletree 11 and two arches respectively First leg 2 connect;More upright bars 12 are set in the connecting rod of an arch, more upright bars 12 from face tunnel vault to Height on both sides successively reduce, and the end of every upright bar 12 is welded with an arch sparge pipe 13 respectively, the arch sparge pipe 13 with The arch radian in tunnel is consistent, and arch sparge pipe 13 is closed at both ends, and a direction is arranged on arch sparge pipe 13 at spacing intervals The spray head 14 of tunnel double-lining concrete;A water supplying pipe 15, described 15 one end of water supplying pipe are connected on the outside of the first leg 2 of an arch If an external water pipe interface, the other end are connected to the sparge pipe.
The utility model is when it is implemented, steel pipe can be used in the water supplying pipe 15 being arranged in arch first leg, with spray Water pipe connecting pin first along first leg 2 upwards, then lead in the middle part of crossbeam along arch crossbeam 1, be divided into two-way in the middle part of crossbeam 1, two Road is connected to the sparge pipe 13 respectively.Mode of communicating can the aperture on sparge pipe, water supplying pipe nozzle and the weldering of sparge pipe tapping It connects.
As shown in figure 3, the utility model avoids the wind band 17 in tunnel 16 in structure, by the arch crossbeam 1 Height from the ground is set above the apical side height of the wind band 17 in tunnel-side.Second hound 5 is used from beam-end Intilted mode can avoid other adjuncts below wind band 17 and wind band.
Construction personnel can be by walking along step, overhauling to equipment on ladder to arch, and checks two lining maintenance effects Fruit.
The utility model structure is huger, and motor driven can be used in walking manner.It is arranged one in the upper side of traveling wheel Platform, the distribution box and motor of setting driving traveling wheel walking on platform.

Claims (3)

1. a kind of Super-large-section tunnel secondary lining automatic spray health trolley, it is characterised in that: including two vertically arranged, phases Mutually parallel and arch at regular intervals, each arch include the crossbeam of a certain altitude from the ground, and every crossbeam passes through vertical The first leg of setting and the support of the second supporting leg, wherein the upper end of first leg and one end of crossbeam are welded, first leg and cross The first hound is welded between beam, the lower end of the first hound and the lower end of first leg are welded, the upper end weldering of the first hound Connect the position between crossbeam and first leg;The upper end of second supporting leg is welded on the portion in the middle part of crossbeam between the crossbeam other end Position, is welded with the second hound between the lower end and the crossbeam other end of the second supporting leg;The lower end of first leg and the second supporting leg difference Traveling wheel is installed;More vertically arranged perpendicular struts, more perpendicular struts difference from the middle part of crossbeam are welded at the top of the crossbeam It is successively reduced to crossbeam both ends height, between every two adjacent perpendicular strut ends, and the perpendicular strut close to crossbeam both ends Between end and beam-end, connecting rod is respectively welded;Distinguish between the crossbeam of two arches and between the connecting rod of two arches It is connected by more lateral bars;Between the connecting rod of two arches, it is erected with the middle part top from crossbeam both ends to crossbeam and successively rises High step;One ladder is set in the outside of the first leg of two arches, the two sides of the ladder pass through singletree and two respectively The first leg of arch connects;More upright bars are set in the connecting rod of an arch, more upright bars from face tunnel vault to Height on both sides successively reduce, and the end of every upright bar is welded with an arch sparge pipe respectively, the arch sparge pipe and tunnel Arch radian is consistent, and arch sparge pipe is closed at both ends, and it is mixed towards tunnel double-lining to be arranged one on arch sparge pipe at spacing intervals Coagulate the spray head of soil;A water supplying pipe is connected on the outside of the first leg of an arch, described water supplying pipe one end sets an external water pipe interface, The other end is connected to the sparge pipe.
2. Super-large-section tunnel secondary lining automatic spray health trolley according to claim 1, it is characterised in that: setting Water supplying pipe in arch first leg, it is first upward along first leg with sparge pipe connecting pin, then lead to cross along arch crossbeam In the middle part of beam, two-way is divided into the middle part of crossbeam and is connected to respectively with the sparge pipe.
3. Super-large-section tunnel secondary lining automatic spray health trolley according to claim 1, it is characterised in that: described The height of crossbeam from the ground is higher than the apical side height of the air hose in tunnel-side.
CN201920008560.XU 2019-01-04 2019-01-04 A kind of Super-large-section tunnel secondary lining automatic spray health trolley Active CN209539369U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920008560.XU CN209539369U (en) 2019-01-04 2019-01-04 A kind of Super-large-section tunnel secondary lining automatic spray health trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920008560.XU CN209539369U (en) 2019-01-04 2019-01-04 A kind of Super-large-section tunnel secondary lining automatic spray health trolley

Publications (1)

Publication Number Publication Date
CN209539369U true CN209539369U (en) 2019-10-25

Family

ID=68268420

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920008560.XU Active CN209539369U (en) 2019-01-04 2019-01-04 A kind of Super-large-section tunnel secondary lining automatic spray health trolley

Country Status (1)

Country Link
CN (1) CN209539369U (en)

Similar Documents

Publication Publication Date Title
CN103015325B (en) Construction method of cast-in-place concrete crash barrier with eaves
CN203007849U (en) Movable construction device for cast-in-place concrete crash barriers with hanging eaves
CN106480828A (en) A kind of small radius T beam bridge formation machine and rotation construction method of installation
CN105484164B (en) Spanning type bailey beam bracket and construction method thereof
CN203977309U (en) A kind of shuttle type culvert linear steel form carrier
CN108316152A (en) A kind of high pier capping beam construction mobile formwork and its construction technology
CN205474844U (en) Straddle type beiLei beam support
CN205934735U (en) A operation platform for stretch -draw of cantilever bent cap
CN209539369U (en) A kind of Super-large-section tunnel secondary lining automatic spray health trolley
CN208151861U (en) The traversing supporting leg of Bridge Erector
CN204625045U (en) A kind of steel structure hoisting door shaped stent formula hanging apparatus
CN207004536U (en) A kind of constructing tunnel inverted arch chassis
CN206873495U (en) A kind of Portable piping lane side wall formwork jumbo
CN207062771U (en) A kind of H types Pier Formwork platform integrated apparatus
CN206298830U (en) Cast-in-Situ Continuous Beam automatic spray curing system
CN106284989A (en) The sliding form bracing system of double track and complete construction method
CN110080117A (en) Portable simplified concrete barrier formwork vehicle and preparation method thereof
CN205474847U (en) Bridge water -drain mast installation platform truck
CN205936646U (en) A trolley -bus formworking jumbo for tunnel side wall concrete construction
CN204959611U (en) A lifting device for highway construction bridge railing base template
WO2019047304A1 (en) Protection roof for use in cantilever form traveler construction
CN211200116U (en) Protective frame for construction of mid-span closure section steel shell of continuous beam of cross highway
CN208995926U (en) The mechanism poured for the wet joint concrete of section assembling box beam
CN107856595A (en) Box culvert transport vehicle and box culvert construct method
CN210589859U (en) Movable precast beam concrete cloth construction platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant