Railway tunnel eminence survey meter promotion locomotive Download PDFInfo
- Publication number
- CN209535057U CN209535057U CN201822190354.3U CN201822190354U CN209535057U CN 209535057 U CN209535057 U CN 209535057U CN 201822190354 U CN201822190354 U CN 201822190354U CN 209535057 U CN209535057 U CN 209535057U
- Authority
- CN
- China
- Prior art keywords
- survey meter
- railway tunnel
- support rod
- lift lever
- locomotive
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The utility model provides a kind of railway tunnel eminence survey meter promotion locomotive, belongs to construction of railways detection device technical field, including moving body, support frame, rotation seat, support rod and lift lever.The utility model is using lift lever as lever, by support frame using they sup-port to eminence as the fulcrum of lever, the survey meter for being located at promotion boom end is promoted to the top equal-height position position of railway tunnel, and pass through the setting of connection and moving body between lift lever, support rod and rotation seat, survey meter is freely moved in railway tunnel, and accurately corresponding with measuring point, flexible and convenient completion detects work, be conducive to improve detection efficiency, reduce testing cost.
Description
Technical field
The utility model belongs to construction of railways detection device technical field, is to be related to a kind of railway tunnel more specifically
Eminence survey meter promotion locomotive.
Background technique
Tunnel Engineering is engineering relatively conventional in construction of railways, and tunnel requires to carry out from excavation construction to maintenance is checked and accepted
A large amount of detection project, but since some tunnel tops are higher, can only set up after scaffold or dedicated rack above into
Row detection, since scaffold building process is complicated, and rack weight and volume is larger, mobile difficult, needs more people to cooperate, and examine
Survey personnel need to carry out high altitude operation above, have very big security risk, and risk is higher, and frequently certain survey meter
It is inconvenient, cause detection efficiency very low, removes scaffold or movable stand simultaneously because setting up, more people is needed to match
It closes, therefore testing cost is also relatively high.
Utility model content
It is existing to solve the purpose of this utility model is to provide a kind of railway tunnel eminence survey meter promotion locomotive
Railway tunnel present in technology detects the technical problem that risk is high and detection efficiency is low.
In order to achieve the above purposes, the technical solution adopted by the utility model is: provides a kind of railway tunnel eminence survey meter
With promotion locomotive, comprising: moving body is equipped with rail wheel, for mobile in orbit;Support frame is arranged in moving body
On;Rotation seat is arranged in support frame;Support rod, one end and rotation seat are rotatablely connected, and are rotated along own axes direction;And
Lift lever, middle part and the support rod other end are hinged, and hingedly vertical with the axis direction of support rod;Lift lever one end is used for and spy
Survey instrument connection.
Further, for railway tunnel eminence survey meter above-mentioned with being promoted in locomotive, rotation seat includes: support plate, is used
It is connect in support frame;And sleeve, fixed setting on the supporting plate, are used for and support rod grafting.
Further, for railway tunnel eminence survey meter above-mentioned with being promoted in locomotive, rotation seat further includes that setting is being propped up
Jacking cylinder on fagging, the position that support plate corresponds to sleeve inner are equipped with through-hole, and the cylinder column of jacking cylinder passes through through-hole and branch
Strut abuts.
Further, railway tunnel eminence survey meter above-mentioned is equipped between support rod and cylinder column with being promoted in locomotive
Bearing for making support rod and cylinder column relatively rotate.
Further, railway tunnel eminence survey meter above-mentioned is arranged with connection in the middle part of lift lever with being promoted in locomotive
Casing, connecting sleeve is hinged with support rod, and connecting sleeve is equipped with the fastening bolt for fastening connecting sleeve and lift lever.
Further, with being promoted in locomotive, lift lever upper end is equipped with and is used for railway tunnel eminence survey meter above-mentioned
The attachment base connecting with survey meter, attachment base are equipped with the connecting hole for connecting with survey meter fixing piece.
Further, for railway tunnel eminence survey meter above-mentioned with being promoted in locomotive, lift lever lower end is equipped with drawstring,
Moving body or support frame are equipped with the drawstring commutative ring passed through for drawstring.
Further, with being promoted in locomotive, moving body is equipped with for receiving railway tunnel eminence survey meter above-mentioned
Put the draw drum of drawstring and the power mechanism for driving draw drum to rotate;One end that drawstring is connect with lift lever is equipped with rope sling,
Lift lever lower end is equipped with the gear lattice part for preventing rope sling from sliding on lift lever.
Further, railway tunnel eminence survey meter above-mentioned is with being promoted in locomotive, support frame include several upper ends with
The hinged support rod of rotation seat, moving body are equipped with several limit connectors for respectively with support rod limit connection, if
Dry limit connector is not on the same line.
Further, railway tunnel eminence survey meter above-mentioned is in promotion locomotive, further includes: ladder, one end and shifting
Motor vehicles bodies connection, the other end are connect with rotation seat.
Railway tunnel eminence survey meter provided by the utility model is with the beneficial effect for promoting locomotive: with existing skill
Art is compared, and the utility model is using lift lever as lever, by support frame using they sup-port to eminence as the branch of lever
The survey meter for being located at promotion boom end, is promoted to the top equal-height position position of railway tunnel by point, and passes through lift lever, support rod
The setting of connection and moving body between rotation seat, enables survey meter freely to move in railway tunnel, and
Accurately corresponding with measuring point, flexible and convenient completion detects work, is conducive to improve detection efficiency, reduces testing cost.
Detailed description of the invention
It, below will be to embodiment or the prior art in order to illustrate more clearly of the technical scheme in the embodiment of the utility model
Attached drawing needed in description is briefly described, it should be apparent that, the accompanying drawings in the following description is only that this is practical new
Some embodiments of type for those of ordinary skill in the art without any creative labor, can be with
It obtains other drawings based on these drawings.
Fig. 1 is that the side view structure of railway tunnel eminence survey meter provided by the embodiment of the utility model promotion locomotive is shown
It is intended to.
Wherein, each appended drawing reference in figure:
10- moving body;11- rail wheel;12- drawstring commutative ring;
13- draw drum;14- power mechanism;15- limit connector;
20- support frame;21- support rod;
30- rotation seat;31- support plate;32- sleeve;
33- jacking cylinder;34- cylinder column;35- bearing;
40- support rod;
50- lift lever;51- connecting sleeve;52- fastening bolt;
53- attachment base;54- survey meter fixing piece;55- keeps off lattice part;56- drawstring;
60- ladder;
70- track;80- survey meter.
Specific embodiment
In order to which technical problem to be solved in the utility model, technical solution and beneficial effect is more clearly understood, with
Lower combination accompanying drawings and embodiments, the present invention will be further described in detail.It should be appreciated that specific reality described herein
Example is applied only to explain the utility model, is not used to limit the utility model.
Referring to Fig. 1, existing carry out a kind of railway tunnel eminence survey meter provided by the utility model with promotion locomotive
Explanation.Railway tunnel eminence survey meter promotion locomotive, comprising:
Moving body 10 is equipped with rail wheel 11, for moving on track 70;
Support frame 20 is arranged on moving body 10;
Rotation seat 30 is arranged in support frame 20;
Support rod 40, one end and rotation seat 30 are rotatablely connected, and are rotated along own axes direction;
And lift lever 50, middle part and 40 other end of support rod are hinged, and hingedly vertical with the axis direction of support rod 40;
50 one end of lift lever with survey meter 80 for connecting.
In use, operating personnel operates the other end of lift lever 50 after survey meter 80 to be mounted on to one end of survey meter 80
Survey meter 80 is promoted to tunnel top equal-height position to detect, after detecting at one, passes through operation lift lever 50 or movement
Moving body 10 carries out the detection at next place.
Railway tunnel eminence survey meter provided by the utility model is with locomotive is promoted, compared with prior art, using mentioning
Rising stem 50 is used as lever, and support rod 40 is supported to fulcrum of the eminence as lever by support frame 20, will be located at lift lever 50
The survey meter 80 of end is promoted to the top equal-height position position of railway tunnel, and passes through lift lever 50, support rod 40 and rotation seat
The setting of connection and moving body 10 between 30, enables survey meter 80 freely to move in railway tunnel, and quasi-
Really corresponding with measuring point, flexible and convenient completion detects work, is conducive to improve detection efficiency, reduces testing cost.
Further, specific with the one kind for promoting locomotive as railway tunnel eminence survey meter provided by the utility model
Embodiment, rotation seat 30 include support plate 31 for connecting with support frame 20 and are fixed in support plate 31 and are used for
With the sleeve 32 of 40 grafting of support rod.In use, support rod 40 can be connected in support plate 31 and rotate in sleeve 32.
Further, rotation seat 30 further includes the jacking cylinder 33 being arranged in support plate 31, the corresponding sleeve of support plate 31
Position inside 32 is equipped with through-hole, and the cylinder column 34 of jacking cylinder 33 passes through through-hole and abuts with support rod 40.Jacking cylinder 33 can be with
Certain adjustment is carried out to the height of survey meter 80.When needing to promote survey meter 80,33 cylinder column 34 of jacking cylinder can be passed through
Pushing tow increase support rod 40, so that lift lever 50 and survey meter 80 be driven to increase.
Further, it is equipped between support rod 40 and cylinder column 34 for making support rod 40 and cylinder column 34 relatively rotate
Bearing 35, to avoid the abrasion between support rod 40 and cylinder column 34.
Further, specific with the one kind for promoting locomotive as railway tunnel eminence survey meter provided by the utility model
Embodiment is arranged with connecting sleeve 51 in the middle part of lift lever 50, and connecting sleeve 51 and support rod 40 are hinged, set in connecting sleeve 51
There is the fastening bolt 52 for fastening connecting sleeve 51 and lift lever 50.51 one side of connecting sleeve can be used for adjusting two sides
50 length of lift lever, on the other hand the connection of two lift levers 50 can also be formed into a longer lift levers 50.
50 upper end of lift lever is equipped with attachment base 53 for connect with survey meter 80, attachment base 53 equipped with for spy
Survey the connecting hole that instrument fixing piece 54 connects.Survey meter fixing piece 54 can be U-shaped screw rod or strapping etc. can be tight by survey meter 80
The close part being connected on attachment base 53.
50 lower end of lift lever is equipped with drawstring 56, in order to which operating personnel operates lift lever 50 by drawstring, prevents
It is difficult to operate after only lift lever 50 is hanging.Moving body 10 or support frame 20 are equipped with the drawstring commutative ring passed through for drawstring 56
12, to commutate to drawstring 56, exert a force convenient for operating personnel, drawstring commutative ring 12 can provide frictional force, in order to mention
When rising stem 50 is motionless, operating personnel's physical strength is saved.Drawstring commutative ring 12 can be cyclic structure, be also possible to hook formation.Into
When row detection, drawstring 56 can be pulled by an operating personnel, determine the Position Approximate of survey meter 80, another operating personnel behaviour
Make lift lever 50 survey meter 80 is accurately positioned.
Further, moving body 10 is equipped with for the draw drum 13 of folding and unfolding drawstring 56 and for driving 13 turns of draw drum
Dynamic power mechanism 14 manually carries out folding and unfolding to drawstring 56 to substitute.One end that drawstring 56 is connect with lift lever 50 is equipped with rope sling,
50 lower end of lift lever is equipped with gear lattice part 55 for preventing rope sling from sliding on lift lever 50, in order to the disassembly of drawstring 56,
To wear or release on the drawstring commutative ring 12 of different location.
Further, specific with the one kind for promoting locomotive as railway tunnel eminence survey meter provided by the utility model
Embodiment, support frame 20 include several upper ends and the hinged support rod 21 of rotation seat 30, and moving body 10 is equipped with several use
In the limit connector 15 respectively with the limit connection of support rod 21, several limit connectors 15 are not on the same line.Limit connects
Fitting 15 can be the components such as limit card slot, limit plug or limit baffle.It, can be according to the length pair of support rod 21 before detection
The height of support frame 20 is adjusted.
Railway tunnel eminence survey meter promotion locomotive further include one end connect with moving body 10 and the other end with turn
The ladder 60 that dynamic seat 30 connects, in order to which operating personnel climbs to being maintained or replaced at rotation seat 30 to component.Ladder 60
It can be set on support rod 21.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this
Made any modifications, equivalent replacements, and improvements etc., should be included in the utility model within the spirit and principle of utility model
Protection scope within.
Claims (10)
1. a kind of railway tunnel eminence survey meter promotion locomotive characterized by comprising
Moving body is equipped with rail wheel, for mobile in orbit;
Support frame is arranged on the moving body;
Rotation seat is arranged in support frame as described above;
Support rod, one end and the rotation seat are rotatablely connected, and are rotated along own axes direction;And
Lift lever, middle part and the support rod other end are hinged, and hingedly vertical with the axis direction of the support rod;
Described lift lever one end with survey meter for connecting.
2. railway tunnel eminence survey meter as described in claim 1 promotion locomotive, which is characterized in that the rotation seat packet
It includes:
Support plate, for being connect with support frame as described above;And
Sleeve is fixed in the support plate, is used for and the support rod grafting.
3. railway tunnel eminence survey meter as claimed in claim 2 promotion locomotive, which is characterized in that the rotation seat is also
Including the jacking cylinder being arranged in the support plate, the position that the support plate corresponds to the sleeve inner is equipped with through-hole, institute
The cylinder column for stating jacking cylinder passes through the through-hole and abuts with the support rod.
4. railway tunnel eminence survey meter as claimed in claim 3 is with promoting locomotive, it is characterised in that: the support rod with
The bearing for making the support rod and the cylinder column relatively rotate is equipped between the cylinder column.
5. railway tunnel eminence survey meter as described in claim 1 promotion locomotive, it is characterised in that: in the lift lever
Portion is arranged with connecting sleeve, and the connecting sleeve and the support rod are hinged, and the connecting sleeve is equipped with for by the company
The fastening bolt of female connector pipe and lift lever fastening.
6. railway tunnel eminence survey meter as described in claim 1 promotion locomotive, it is characterised in that: on the lift lever
End is equipped with attachment base for connect with the survey meter, and the attachment base with survey meter fixing piece equipped with for connecting
Connecting hole.
7. railway tunnel eminence survey meter as described in claim 1 promotion locomotive, it is characterised in that: under the lift lever
End is equipped with drawstring, and the moving body or support frame are equipped with the drawstring commutative ring passed through for the drawstring.
8. railway tunnel eminence survey meter as claimed in claim 7 promotion locomotive, it is characterised in that: the moving body
It is equipped with the draw drum for being used for drawstring described in folding and unfolding and the power mechanism for driving the draw drum rotation;The drawstring and institute
The one end for stating lift lever connection is equipped with rope sling, and the lift lever lower end is equipped with for preventing the rope sling in the lift lever
The gear lattice part of sliding.
9. railway tunnel eminence survey meter as described in claim 1 promotion locomotive, it is characterised in that: if support frame includes
Dry upper end and the hinged support rod of the rotation seat, the moving body are equipped with several for limiting respectively with the support rod
The limit connector of connection, several limit connectors are not on the same line.
10. railway tunnel eminence survey meter as described in claim 1 promotion locomotive, which is characterized in that further include:
Ladder, one end are connect with the moving body, and the other end is connect with the rotation seat.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822190354.3U CN209535057U (en) | 2018-12-25 | 2018-12-25 | Railway tunnel eminence survey meter promotion locomotive |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822190354.3U CN209535057U (en) | 2018-12-25 | 2018-12-25 | Railway tunnel eminence survey meter promotion locomotive |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209535057U true CN209535057U (en) | 2019-10-25 |
Family
ID=68266079
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822190354.3U Expired - Fee Related CN209535057U (en) | 2018-12-25 | 2018-12-25 | Railway tunnel eminence survey meter promotion locomotive |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209535057U (en) |
-
2018
- 2018-12-25 CN CN201822190354.3U patent/CN209535057U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201753436U (en) | Detachable lift type bridge inspection vehicle | |
CN105019930B (en) | A kind of mine hydraulic bracket assembly platform | |
CN205315990U (en) | Outdoor survey and drawing frame | |
CN203760934U (en) | Pulley device for cable laying | |
CN209535057U (en) | Railway tunnel eminence survey meter promotion locomotive | |
CN204823586U (en) | Online safety inspection device of mine hoisting wire rope | |
CN202753947U (en) | Cableway large-dip-angle movable cable rope clip | |
CN209709643U (en) | A kind of city track traffic engineering cable bearer | |
CN104195943A (en) | Bridge inspection device capable of transmitting videos in real time | |
CN207004415U (en) | Power equipment maintaining folding ladder | |
CN103046469B (en) | Fast lifting platform of bridge inspection vehicle | |
CN103950872A (en) | Upright tube hoisting multifunctional tool of substation altitude plant | |
CN203185299U (en) | Composite lever-type electric hammer lifting auxiliary support | |
CN203833575U (en) | Vertical rod hoisting multifunctional tool of substation high-altitude device | |
CN111735602B (en) | Low-speed wind tunnel test model abdominal bracing system | |
CN104071687B (en) | Power station overhead traveling crane mechanism | |
CN209870398U (en) | Auxiliary withdrawing mechanism and rail-walking type motor train unit bottom detection device | |
CN208345627U (en) | A kind of semicircular ring rail crane | |
CN207782283U (en) | A kind of high pressure AC and DC line maintenance multipurpose aerial earth wire coaster | |
CN202659157U (en) | Novel three-section flexible driller room bracket | |
CN207569362U (en) | A kind of bearing diagonal bracket | |
CN206243950U (en) | It is a kind of to rail mechanism | |
CN201408947Y (en) | Transmission line high-altitude maintenance ladder | |
CN215867060U (en) | Portable cable conductor comprehensive tester | |
CN205778617U (en) | Oil pipe carrying device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191025 Termination date: 20211225 |
|