CN209496131U - A kind of electric energy meter battery consumption detection system - Google Patents
A kind of electric energy meter battery consumption detection system Download PDFInfo
- Publication number
- CN209496131U CN209496131U CN201920000029.8U CN201920000029U CN209496131U CN 209496131 U CN209496131 U CN 209496131U CN 201920000029 U CN201920000029 U CN 201920000029U CN 209496131 U CN209496131 U CN 209496131U
- Authority
- CN
- China
- Prior art keywords
- electric energy
- energy meter
- detection
- rack
- consumption
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Arrangements For Transmission Of Measured Signals (AREA)
- Manipulator (AREA)
Abstract
The utility model discloses a kind of electric energy meter battery consumption detection system, is related to intelligent electric energy meter operational reliability the field of test technology, and the system comprises rack, pipeline, power supply and consumption detection units;The rack is the structure carrier of detection system;The pipeline is arranged on the rack upper layer, for transmitting electric energy meter;The consumption detection unit is arranged in the rack, for detecting the battery power consumption of electric energy meter;It is wherein provided with manipulator on the consumption detection unit, is provided with needle plate below the manipulator, the consumption detection unit carries out battery current measurement under energized state or off-position, and will test result input MES system and be managed.The utility model in the case where unmanned intervene, can be completed at the same time the battery power consumption detection of three pieces of electric energy meters in 8 seconds, and the error range that probe is inserted into electric energy meter detection hole is 0-0.1mm, and accuracy is high, substantially reduces detection time, save human cost.
Description
Technical field
The utility model relates to intelligent electric energy meter operational reliability the field of test technology, and relate more specifically to one kind and be used for
The detection system of the battery power consumption of electric energy meter.
Background technique
With the iterative method of State Grid Corporation of China's power information acquisition system construction project, more and more intelligence electric energy
Table has been put into live operation, the electrical energy measurement of intelligent electric energy meter, periodically freeze, the functions such as load record all be unable to do without its electricity
The power supply in pond, therefore, electric energy meter power consumption situation be unable to do without the normal power supply of battery, at present battery in state's net electric energy meter design scheme
As Clock battery and two kinds of purposes of standby working power.To the electric energy meter of actual motion on site, when power network line normally supplies
When electric, battery is same when battery makees standby working power when power network line is in power failure only to clock module for power supply
When support CPU, liquid crystal, clock chip, the multichannels module for power supply such as storage capacitor, once battery can not normal power supply, it will induce
Electric energy meter catastrophe failure related with timing.Therefore, being related to electric energy meter to the measurement of the battery power consumption situation of electric energy meter just
Often an important factor for work.
Consumption detection is detected also in manual operation equipment in current electronic electric energy meter production process, is greatly increased
Production cost, and efficiency is extremely low, how to realize automation and quickly battery power consumption detection be current technology urgently to be solved
Problem.
Utility model content
Deficiency in view of the above technology, the utility model disclose a kind of detection system of battery power consumption for electric energy meter,
The battery power consumption detection of three pieces of electric energy meters can be automatically performed simultaneously in 8 seconds in the case where unmanned intervene, probe is inserted into electric energy
The error range of table detection hole is 0-0.1mm, and accuracy is high, shortens detection time, saves human cost.
The utility model uses following technical scheme: a kind of electric energy meter battery consumption detection system, including rack, the system
System further includes pipeline, power supply and consumption detection unit;Wherein the rack is the structure carrier of the detection system;It is described
Pipeline is arranged on the rack upper layer, for transmitting electric energy meter;The consumption detection unit is arranged in the rack, is used for
Detect the battery power consumption of electric energy meter;It is provided with manipulator on the consumption detection unit, is provided with needle plate below the manipulator,
The consumption detection unit is used to carry out battery current measurement under energized state or off-position, and will test result and be input to
MES system is managed.
As the further technical solution of the utility model, the manipulator is arranged to discharge side by side three manipulators,
Three manipulators work independently.
As the further technical solution of the utility model, the manipulator carries needle plate, for detecting electric energy meter
Battery power consumption.
As the further technical solution of the utility model, the needle plate carries at least 30 probes, the probe and is used for
It is inserted into the detection hole of electric energy meter when detecting, the error range of the probe insertion detection hole is 0-0.1mm.
As the further technical solution of the utility model, Z axis cylinder is provided on the manipulator, the manipulator is logical
It crosses the Z axis cylinder and carries needle plate up and down motion, the needle plate is placed on the conveyor line.
As the further technical solution of the utility model, it is additionally provided with positioning device in the rack, for positioning electricity
It can the position of table on the conveyor line.
As the further technical solution of the utility model, the location hole of positioning pin is provided in the positioning device,
And the quantity of the location hole is at least 2.
As the further technical solution of the utility model, the positioning time of the positioning device and the consumption detection list
The sum of detection time of member is no more than 8 seconds, and the consumption detection unit is arranged above the positioning device.
As the further technical solution of the utility model, the bottom of the frame is configured with return wire, and the rack
On be additionally provided with photoelectric sensor.
Positive beneficial effect:
The utility model can be automatically performed simultaneously the battery power consumption of three pieces of electric energy meters in the case where unmanned intervene in 8 seconds
Detection, the error range that probe is inserted into electric energy meter detection hole is 0-0.1mm, and accuracy is high, shortens detection time, saves manpower
Cost.
Detailed description of the invention
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment
Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only
It is some embodiments of the utility model, for those of ordinary skill in the art, before not making the creative labor property
It puts, is also possible to obtain other drawings based on these drawings, in which:
Fig. 1 is the structural schematic diagram of the utility model electric energy meter battery consumption detection system;
Fig. 2 is the location structure schematic diagram of carrier bottom plate in the utility model electric energy meter battery consumption detection system;
Fig. 3 is flow diagram of the utility model for the battery power consumption detecting step of electric energy meter;
Attached drawing mark: 1- rack;2- pipeline;3- needle plate;4-Z axis cylinder;5- consumption detection unit;6- manipulator;7-
Location hole.
Specific embodiment
It is illustrated below in conjunction with preferred embodiment of the attached drawing to the utility model, it should be understood that reality described herein
It applies example to be only used for describing and explaining the present invention, is not used to limit the utility model.
As shown in Figure 1, a kind of electric energy meter battery consumption detection system, wherein the system also includes pipeline 2, power supply with
And consumption detection unit 5;Wherein the rack 1 is the structure carrier of the detection system;The pipeline 2 is arranged in the machine
1 upper layer of frame, for transmitting electric energy meter;The consumption detection unit 5 is arranged in the rack 1, for detecting the electricity of electric energy meter
Pond power consumption;It is provided with manipulator 6 on the consumption detection unit 5, needle plate 3, the power consumption inspection are provided with below the manipulator 6
Survey unit 5 be used under energized state or off-position carry out battery current measurement, and will test result be input to MES system into
Row management.
In the above-described embodiments, pipeline 2 is that adjustable-width pipeline (checks and accepts carrier 250*300 charging/discharging, carrier
Bottom is adjustable far from ground 900 millimeters+- 20), 1 bottom of rack configures return wire (on the belt on return wire identity distance 280 millimeters).
In a further embodiment, the manipulator 6 is arranged to discharge side by side three manipulators, three machinery
Hand works independently.At work, consumption detection unit 5 can be connected to a branch of communication and power supply line.
In a further embodiment, the manipulator 6 carries needle plate 3, for detecting electric energy meter battery power consumption.
In a further embodiment, the needle plate 3 carries at least 30 probes, and the probe for being inserted into when detecting
The error range of the detection hole of electric energy meter, the probe insertion detection hole is 0-0.1mm.
In a further embodiment, Z axis cylinder 4 is provided on the manipulator 6, the manipulator 6 passes through the Z axis
Cylinder 4 carries needle plate 3 and moves up and down, and the needle plate 3 is placed on pipeline 2.
In a further embodiment, it is additionally provided with positioning device in the rack 1, for positioning electric energy meter in pipeline
Position on 2.The location hole 7 of positioning pin is provided in the positioning device, and the quantity of the location hole 7 is at least 2.
In a further embodiment, when the detection of the positioning time of the positioning device and the consumption detection unit 5
Between the sum of be no more than 8 seconds, and the consumption detection unit 5 be arranged above the positioning device.
In a further embodiment, 1 bottom of rack is configured with return wire, and is additionally provided in the rack 1
Photoelectric sensor.
The utility model is described further below with reference to the course of work, to more fully understand the utility model.
A kind of electric energy meter battery consumption detection method, comprising the following steps:
(1) in place: the PCB printed circuit board with carrier is sent into the consumption detection unit 5 by the pipeline 2;
(2) position: the bottom plate of the positioning device rises, and the location hole 7 of two pieces of positioning pin insertion carriers completes carrier
It is accurately positioned;
(3) detection preparation: the Z axis cylinder 4 declines, and is moved up and down by the needle plate 3 of carrying, until dropping to electricity
It can table portion to be detected;
(4) detect: consumption detection unit 5 starts electric energy power consumption test, electric energy power consumption test by the needle plate 3 on manipulator
Method are as follows:
The project that consumption detection unit 5 needs to detect is arranged in user in computer, is configured to detection project, then
Computer assigns sense command to consumption detection unit 5, and the consumption detection unit 5 orders execute detection based on the received
Task;Then manipulator 6 carries needle plate 3 and inserts a probe into electric energy meter detection hole, starts to detect, detection data uploads to host computer
Or MES system carries out data management, completes consumption detection,
(5) let pass: positioning pin is extracted from the location hole 7 on carrier, the bottom plate decline of positioning device, after detection
Electric energy meter is transported to next station.
The utility model can be automatically performed simultaneously the battery power consumption of three pieces of electric energy meters in the case where unmanned intervene in 8 seconds
Detection, the error range that probe is inserted into electric energy meter detection hole is 0-0.1mm, and accuracy is high, shortens detection time, saves manpower
Cost.
Although the foregoing describe specific embodiment of the present utility model, it will be appreciated by those of skill in the art that
These specific embodiments are merely illustrative of, and those skilled in the art is not departing from the principles of the present invention and essence
In the case of, various omissions, substitutions and changes can be carried out to the details of the above method and system.For example, merging above method step
Suddenly, to execute substantially identical function according to substantially identical method to realize that it is practical new that substantially identical result then belongs to this
The range of type.Therefore, the scope of the utility model is only limited by the claims that follow.
Claims (9)
1. a kind of electric energy meter battery consumption detection system, including rack (1), it is characterised in that: the system also includes pipelines
(2), power supply and consumption detection unit (5);Wherein the rack (1) is the structure carrier of the detection system;The conveying
Line (2) is arranged on the rack (1) upper layer, for transmitting electric energy meter;The consumption detection unit (5) is arranged in the rack
(1) on, for detecting the battery power consumption of electric energy meter;Manipulator (6), the machinery are provided on the consumption detection unit (5)
It is provided with needle plate (3) below hand (6), the consumption detection unit (5) under energized state or off-position for carrying out battery
Current measurement, and will test result and be input to MES system and be managed.
2. detection system according to claim 1, it is characterised in that: the manipulator (6) is arranged to discharge side by side three
A manipulator, three manipulators work independently.
3. detection system according to claim 1, it is characterised in that: the manipulator (6) carries needle plate (3), uses
In detection electric energy meter battery power consumption.
4. detection system according to claim 3, it is characterised in that: the needle plate (3) carries at least 30 probes, described
For probe for being inserted into the detection hole of electric energy meter when detecting, the error range of the probe insertion detection hole is 0-0.1mm.
5. detection system according to claim 3 or 4, it is characterised in that: be provided with Z axis cylinder on the manipulator (6)
(4), the manipulator (6) carries needle plate (3) by the Z axis cylinder (4) and moves up and down, and the needle plate (3) is placed on
On pipeline (2).
6. detection system according to claim 1, it is characterised in that: be additionally provided with positioning device on the rack (1), use
In position of the positioning electric energy meter on pipeline (2).
7. detection system according to claim 6, it is characterised in that: be provided with determining for positioning pin in the positioning device
Position hole (7), and the quantity of the location hole (7) is at least 2.
8. detection system according to claim 7, it is characterised in that: the positioning time of the positioning device and the power consumption
The sum of detection time of detection unit (5) is no more than 8 seconds, and the consumption detection unit (5) is arranged in the positioning device
Top.
9. detection system according to claim 6, it is characterised in that: rack (1) bottom is configured with return wire, and
Photoelectric sensor is additionally provided on the rack (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920000029.8U CN209496131U (en) | 2019-01-01 | 2019-01-01 | A kind of electric energy meter battery consumption detection system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920000029.8U CN209496131U (en) | 2019-01-01 | 2019-01-01 | A kind of electric energy meter battery consumption detection system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209496131U true CN209496131U (en) | 2019-10-15 |
Family
ID=68154325
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920000029.8U Active CN209496131U (en) | 2019-01-01 | 2019-01-01 | A kind of electric energy meter battery consumption detection system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209496131U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110568394A (en) * | 2019-01-01 | 2019-12-13 | 宁夏隆基宁光仪表股份有限公司 | system and method for detecting power consumption of battery of electric energy meter |
-
2019
- 2019-01-01 CN CN201920000029.8U patent/CN209496131U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110568394A (en) * | 2019-01-01 | 2019-12-13 | 宁夏隆基宁光仪表股份有限公司 | system and method for detecting power consumption of battery of electric energy meter |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106771041A (en) | A kind of dispensing and recovery method based on unmanned plane water quality on-line measuring device | |
CN205177145U (en) | Power consumption information acquisition test terminal | |
CN107942283A (en) | A kind of automatic calibration of electric energy meter assembly line condition monitoring system and method | |
CN201887127U (en) | Intelligent monitoring and repairing control system of lead-acid battery | |
CN107947371A (en) | A kind of wireline inspection fault fast positioning detecting system based on satellite communication | |
CN209496131U (en) | A kind of electric energy meter battery consumption detection system | |
CN105446197A (en) | Train control ground key data detecting device | |
CN106569165A (en) | Remote online detection system for metering performance of electronic electric energy meter | |
CN208399592U (en) | Cable through and insulation tester | |
CN202351940U (en) | Portable field equipment routing inspection apparatus | |
CN203287521U (en) | Online detection device for radar equipment | |
CN202600445U (en) | A temperature monitoring system used for patrol and detection of electric power operation | |
AU2014299212A1 (en) | Noise collection system for belt conveyor | |
CN209496130U (en) | A kind of electric energy meter component Function detection mechanism | |
CN110568393A (en) | mechanism and method for detecting functions of electric energy meter components | |
CN207832924U (en) | The short-circuit detecting and voltage detecting system of pcb board on a kind of assembly line | |
CN110293075A (en) | A kind of working method of novel meter semi-automatic test tooling | |
CN110568395A (en) | electric energy meter multi-signal detection, read-write device and implementation method | |
CN110568394A (en) | system and method for detecting power consumption of battery of electric energy meter | |
CN105626501A (en) | Fault diagnosis tester of electric submersible pump working condition monitor system | |
CN102594923A (en) | Thing internet system for electrical operation routine inspection | |
CN206594242U (en) | A kind of electric energy quality on-line monitoring device | |
CN105245009A (en) | Electric equipment networking manager | |
CN209496129U (en) | A kind of detection of electric energy meter multi signal, read-write equipment | |
CN204882850U (en) | A 0. 02 grade of miniature standard electric energy meter that is used for single -phase intelligent ammeter verification system repeatability experimental |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |