- CN209464652U CN209464652U CN201920004274.6U CN201920004274U CN209464652U CN 209464652 U CN209464652 U CN 209464652U CN 201920004274 U CN201920004274 U CN 201920004274U CN 209464652 U CN209464652 U CN 209464652U
- Authority
- CN
- China
- Prior art keywords
- cleaning
- cesspool
- steel pipe
- gas source
- axle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Cleaning In General (AREA)
Abstract
The utility model relates to a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge, including axle, the wheel hub set for being symmetrically arranged at axle both ends, the gas source steel pipe being located on axle and the gas-distributing pipe being located on gas source steel pipe, one end of gas-distributing pipe be connected to gas source steel pipe.Gas source steel pipe is equipped with pull ring, and pull ring is equipped with traction rope.Reinforcing rib is fixed on gas source steel pipe, the other end of reinforcing rib is fixed on axle.Wheel hub set includes surrounding the axis circular array of change with the change of axle rotation connection, the support spoke being fixed in change and the wheel hub being located on support spoke, support spoke.When carrying out positioning cleaning work using the utility model, staff is always positioned at ground, can either guarantee the safety of operation, and can be improved cleaning efficiency.
Description
Technical field
The utility model relates to the technical fields of sewage treatment plant's cesspool bottom deposit sludge positioning cleaning, especially relate to
And it is a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge.
Background technique
Sewage treatment plant is carrying out checking maintenance, technology upgrading, is mentioning in mark transformation process, can be potentially encountered not cut off the water and does not drop mark
Construction requirement.
In use, bottom of pond can deposit a large amount of sludge to cesspool, dirty if you need to bottom of pond newly added equipment pipeline etc. in pond
Mud sedimentary can cause to hinder to normal mounting, it is therefore desirable to carry out bottom of pond settled sludge prune job.When not cutting off the water,
Personnel's underwater operation is generallyd use, mainly there is following problem at present:
1. cesspool in the case that do not cut off the water target does not drop and, bottom of pond visibility is very low, and searchlight is not available, most of
In the case of personnel can only be by feeling and experience operation, cleaning efficiency is very low;
2. equipment is numerous in sludge-tank, in the case where sight is heavily disturbed, it is easy to happen the safety such as collide with, get an electric shock
Accident;
3. manual cleaning needs to increase corresponding rescue personnel and equipment, cleaning speed is slow, and time-consuming, and construction cost is very
It is high.
Utility model content
The purpose of the utility model is to provide a kind of easy to use for carrying out positioning cleaning to cesspool base sludge
Cleaning tool.
The above-mentioned purpose of the utility model has the technical scheme that
It is a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge, including axle, be symmetrically arranged at axle
The wheel hub set at both ends, the gas source steel pipe being located on axle and the gas-distributing pipe being located on gas source steel pipe;
One end of the gas-distributing pipe is connected to gas source steel pipe.
By using above-mentioned technical proposal, the utility model is sunk to cesspool bottom and is connected to external air source by staff
On gas source steel pipe, gas source steel pipe is then pushed, it is made to do straight reciprocating motion in sewage bottom of pond portion.In motion process, compression is empty
Gas is sprayed from gas source steel pipe and gas-distributing pipe, and the sludge of sewage bottom of pond portion can blow off.Staff is begun in entire scale removal process
Final position ground, operation sight is good, can either guarantee the personal safety of staff, and can be improved cleaning efficiency.
The utility model is further arranged to: the gas source steel pipe is equipped with pull ring.
By using above-mentioned technical proposal, another staff may stand in the other side of cesspool, use length
The staff that the tools such as ditch catch on after pull ring and opposite bank pulls the utility model to be located at the partial movement of bottom of pond together, can drop
Low labor intensity improves operating efficiency.
The utility model is further arranged to: the pull ring is equipped with traction rope.
By using above-mentioned technical proposal, the utility model provides traction rope and uses to opposite bank staff, traction rope
It is light-weight, it is more convenient to use convenient for storage.
The utility model is further arranged to: being fixed with reinforcing rib on the gas source steel pipe;
The other end of the reinforcing rib is fixed on axle.
By using above-mentioned technical proposal, reinforcing rib can be improved the bonding strength of gas source steel pipe and axle, avoid making
With being broken in the process.
The utility model is further arranged to: the wheel hub set includes the change being rotatablely connected with axle, is fixed on change
On support spoke and be located at support spoke on wheel hub;
The support spoke surrounds the axis circular array of change;
One end of the support spoke and the outer surface of change connect, and the inner surface of the other end and wheel hub connects.
By using above-mentioned technical proposal, the utility model provides a kind of specific structure of wheel hub set, and wheel hub set is whole
It being made of profile, hardness is high, and it is corrosion-resistant, it can adapt to use environment severe under cesspool.
The utility model is further arranged to: the wheel hub is steel wheel hub.
By using above-mentioned technical proposal, the direct contact chamber bottom of steel wheel hub is convenient to pass through touching in sludge scale removal process
Sense perception cleaning situation.
The utility model is further arranged to: the gas source steel pipe is equipped with auxiliary positioning bar.
By using above-mentioned technical proposal, auxiliary positioning bar can avoid deviateing as the reference by location in scale removal process
The cleaning area of delimitation.
The utility model is further arranged to: the auxiliary positioning bar is hinged on gas source steel pipe;
The auxiliary positioning bar is equipped with floater shot.
By using above-mentioned technical proposal, floater shot can be swum on the water surface as the reference by location in scale removal process,
It is big to float sphere volume, bright-colored, observation gets up to be more easier.
The utility model is further arranged to: the free end of the auxiliary positioning bar is equipped with baffle ring;
The floating ball cover is on auxiliary positioning bar.
By using above-mentioned technical proposal, floater shot can slide on auxiliary positioning bar, can float on the surface always.
The utility model is further arranged to: steel rake is hinged on the axle.
By using above-mentioned technical proposal, steel rake, which can be stirred the stiff mud at cesspool bottom, is loosely more easier it
Cleaning, the personnel of working at the same time can determine whether bottom of pond is cleaned out by shock conditions.
In conclusion the advantageous effects of the utility model are as follows:
1. the utility model uses the working method cleared up on ground, by axle, wheel hub set and part gas source steel
After pipe sinks to cesspool bottom, it is pushed to move back and forth at cesspool bottom.It is sprayed in moving process by gas source steel pipe and gas-distributing pipe
Compressed air out blows off sludge, both avoids underwater operation, ensure that the personal safety of staff, and can be improved clear
Manage efficiency.
2. the utility model increases pull ring and traction rope on gas source steel pipe, in scale removal process, two staff point
The utility model Zhan not be pulled to be located at underwater partial movement by gas source steel pipe and traction rope on the both sides of cesspool, it can
Labor intensity is effectively reduced, improves cleaning efficiency.
3. the utility model increases auxiliary positioning bar and floater shot on gas source steel pipe, in scale removal process, floater shot begins
Final position can provide accurate reference by location to staff, avoid deviateing the cleaning area delimited on the water surface.
4. the utility model increases steel rake on axle, can be stirred the stiff mud at cesspool bottom loosely makes it more
Add easy cleaning, and staff can determine whether bottom of pond is cleaned out by shock conditions.
Detailed description of the invention
Fig. 1 is the use schematic diagram of the utility model.
Fig. 2 is the main view of the utility model.
Fig. 3 is the left view of the utility model.
In figure, 11, axle;12, gas source steel pipe;13, gas-distributing pipe;2, pull ring;3, traction rope;4, reinforcing rib;51, change;
52, spoke is supported;53, wheel hub;6, auxiliary positioning bar;7, floater shot;8, baffle ring;9, steel is harrowed.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Firstly the need of explanation, positioning cleaning is not cleared up sludge to outside pond, and the sludge for drafting position is clear
Reason transfer, vacates installation site to equipment pipe.
It referring to Figures 1 and 2, is disclosed by the utility model a kind of for carrying out positioning cleaning to cesspool base sludge
The components such as cleaning tool, including axle 11, wheel hub set, gas source steel pipe 12 and gas-distributing pipe 13.
Using the galvanized pipe of DN25, length determines gas source steel pipe 12 according to the size of cesspool, guarantees that one end can begin
Final position is more than the water surface.It is more convenient for description, the left end of gas source steel pipe 12 is known as holding end, right end is known as working
End.Axle 11 is welded on the working end of gas source steel pipe 12, while in order to reinforce, and two reinforcing ribs 4 are symmetrically welded on axle 11,
The other end of reinforcing rib 4 is welded on gas source steel pipe 12.Two gas-distributing pipes 13 are also symmetrically welded on gas source steel pipe 12, the two
Junction is got through.The air that gas source steel pipe 12 sprays when work blows afloat the sludge of bottom of pond, and the air that gas-distributing pipe 13 sprays will be dirty
Mud blows to two sides.
Wheel hub set is made of change 51, support spoke 52 and 53 three parts of wheel hub.Wherein 51 sets of change on axle 11, wheel
Hub 53 and change 51 are concentric, and support spoke 52 is as the connection support between wheel hub 53 and change 51.
It is welded with pull ring 2 on the middle section of gas source steel pipe 12, traction rope 3 is tied up on pull ring 2.
Steel rake 9 is hinged on axle 11, is moved with the movement of axle 11.
Referring to Fig. 3, gas source steel pipe 12 is also hinged with an auxiliary positioning bar 6, the upper set of auxiliary positioning bar 6 floating
Ball 7 is welded with a baffle ring 8 on the other end of auxiliary positioning bar 6, can intercept floater shot 7, avoid it from auxiliary positioning bar 6
On fall off.In order to be more easier to identify, the appearance color of floater shot 7 selects red or yellow
The implementation principle of the present embodiment are as follows:
It is first to prepare for work, compressed air source is connected to beside cesspool with rubber tube, is then connected rubber tube
Onto gas source steel pipe 12.Starting compressed air source and working end and the gas-distributing pipe 13 for checking gas source steel pipe 12, being capable of normal jet
Compressed air source is closed afterwards, traction rope 3 is bonded on pull ring 2, finally by axle 11, the work of wheel hub set and gas source steel pipe 12
End is sunk in cesspool.
Staff is divided into two groups, is stood respectively in the two sides of cesspool, is responsible for for one group pushing gas source steel pipe 12, one group is responsible for
Pull traction rope 3.Start compressed air source, starts to carry out positioning cleaning work, two groups of staff firmly, drive this reality simultaneously
Straight reciprocating motion is done in cesspool with the novel part being in water.
In motion process, compressed air continues to spray from the working end of gas source steel pipe 12 and gas-distributing pipe 13.Gas source steel pipe 12
The air that working end sprays blows afloat the sludge on cesspool bottom surface, and sludge is blowed to two sides by the air that gas-distributing pipe 13 sprays.
Two groups of staff need the floater shot 7 on the moment observation water surface, and observation period at moment and object of reference during this
The distance between, it is adjusted in time when deviateing, practical cleaning area is avoided to deviate.In scale removal process, floater shot 7 is auxiliary
It helps in locating rod 6 and slides, swim on the water surface always.
Staff at 12 holding end of gas source steel pipe also needs the case where knowing cesspool bottom surface by vibration, vibration
Illustrate that sludge settling is more when frequently.Because wheel hub 53 is steel wheel hub and is fitted without rubber tyre, belong to bottom of pond cement
Bottom of pond situation can be passed to staff by vibration by hard contact.
Left and right, amount of sludge can be decreased obviously three times for reciprocal cleaning, and steel rake 9 can be in contact with remaining stiff mud, at this time
Vibration it is intermittent, need to clear up vibration region repeatedly, when in entire cleaning area without obvious vibration, illustrate pond
Bottom is substantially cleaned.
The embodiment of present embodiment is the preferred embodiment of the utility model, and not limitation is originally practical new according to this
The protection scope of type, therefore: the equivalence changes that all structures, shape, principle according to the utility model are done should all be covered by practical
Within novel protection scope.
Claims (10)
1. it is a kind of for cesspool base sludge carry out positioning cleaning cleaning tool, it is characterised in that: including axle (11),
It is symmetrically arranged at the wheel hub set at axle (11) both ends, the gas source steel pipe (12) that is located on axle (11) and is symmetrically arranged at gas source steel pipe
(12) gas-distributing pipe (13) on;
One end of the gas-distributing pipe (13) is connected to gas source steel pipe (12).
2. it is according to claim 1 a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge, it is special
Sign is: the gas source steel pipe (12) is equipped with pull ring (2).
3. it is according to claim 2 a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge, it is special
Sign is: the pull ring (2) is equipped with traction rope (3).
4. it is according to claim 1 a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge, it is special
Sign is: being fixed with reinforcing rib (4) on the gas source steel pipe (12);
The other end of the reinforcing rib (4) is fixed on axle (11).
5. it is according to claim 1 a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge, it is special
Sign is: the wheel hub set includes and the change (51) of axle (11) rotation connection, the support spoke being fixed on change (51)
(52) and be located at support spoke (52) on wheel hub (53);
Support spoke (52) surrounds the axis circular array of change (51);
One end of support spoke (52) is connect with the outer surface of change (51), and the inner surface of the other end and wheel hub (53) connects
It connects.
6. it is according to claim 1 a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge, it is special
Sign is: the wheel hub (53) is steel wheel hub.
7. a kind of for carrying out the clear of positioning cleaning to cesspool base sludge described in any one of -6 according to claim 1
Science and engineering tool, it is characterised in that: the gas source steel pipe (12) is equipped with auxiliary positioning bar (6).
8. it is according to claim 7 a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge, it is special
Sign is: the auxiliary positioning bar (6) is hinged on gas source steel pipe (12);
The auxiliary positioning bar (6) is equipped with floater shot (7).
9. it is according to claim 8 a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge, it is special
Sign is: the free end of the auxiliary positioning bar (6) is equipped with baffle ring (8);
The floater shot (7) covers on auxiliary positioning bar (6).
10. it is according to claim 1 a kind of for carrying out the cleaning tool of positioning cleaning to cesspool base sludge, it is special
Sign is: steel rake (9) is hinged on the axle (11).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920004274.6U CN209464652U (en) | 2019-01-02 | 2019-01-02 | It is a kind of for cesspool base sludge carry out positioning cleaning cleaning tool |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920004274.6U CN209464652U (en) | 2019-01-02 | 2019-01-02 | It is a kind of for cesspool base sludge carry out positioning cleaning cleaning tool |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209464652U true CN209464652U (en) | 2019-10-08 |
Family
ID=68092566
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920004274.6U Active CN209464652U (en) | 2019-01-02 | 2019-01-02 | It is a kind of for cesspool base sludge carry out positioning cleaning cleaning tool |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209464652U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111389829A (en) * | 2019-01-02 | 2020-07-10 | 河北省安装工程有限公司 | Cleaning tool for positioning and cleaning sludge at bottom of sewage pool and working method thereof |
-
2019
- 2019-01-02 CN CN201920004274.6U patent/CN209464652U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111389829A (en) * | 2019-01-02 | 2020-07-10 | 河北省安装工程有限公司 | Cleaning tool for positioning and cleaning sludge at bottom of sewage pool and working method thereof |
CN111389829B (en) * | 2019-01-02 | 2021-11-09 | 河北省安装工程有限公司 | Cleaning tool for positioning and cleaning sludge at bottom of sewage pool and working method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11674286B2 (en) | Dredge head assembly and related diver-assisted dredging system and methods | |
CN209464652U (en) | It is a kind of for cesspool base sludge carry out positioning cleaning cleaning tool | |
CN105064266B (en) | Fine sand sludge pneumatic removing device based on river water energy | |
CN101368386A (en) | Pile extractor and construction method for pile extraction | |
CN201074340Y (en) | Pile-drawing machine | |
CN107653858A (en) | The removable piling platform of the stake top of jack up waterborne and its construction method | |
CN206452740U (en) | A kind of municipal administration fertilizing equipment of watering flowers | |
CN208191298U (en) | A kind of garden landscape irrigation rig | |
CN2772954Y (en) | Plastic float with light materials inside | |
CN204816068U (en) | Utilize portable sedimentation tank to filter spray set of foundation ditch precipitation | |
CN206374947U (en) | A kind of dredger device for high-efficiency cleaning | |
CN110306737A (en) | A kind of precast bridge concreting rain-proof constructing device | |
CN214574048U (en) | Construction rainfall drainage device | |
CN111389829B (en) | Cleaning tool for positioning and cleaning sludge at bottom of sewage pool and working method thereof | |
CN207619960U (en) | A kind of cleaning plant being convenient to clean offshore production platform spud leg aufwuch | |
CN208597276U (en) | A kind of weathering soil of tea oil tree is dug a pit, hole, etc. device | |
CN209741735U (en) | Novel fender is enclosed to mechanical type safety for building site | |
CN207176655U (en) | The removable piling platform of the stake top of jack up waterborne | |
CN207331951U (en) | A kind of sewage conduct dredger | |
CN204002793U (en) | A kind of dustless development machine | |
CN211849669U (en) | Auxiliary device for improving floating force of sludge pump | |
CN103703911A (en) | Lotus root harvester | |
CN217629914U (en) | Underwater mud cleaning equipment | |
CN206202630U (en) | Hull cleans monitoring underwater robot right angle axle bed with water | |
CN201115844Y (en) | Rising globule separation fountain |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |