- CN209429385U CN209429385U CN201822001236.3U CN201822001236U CN209429385U CN 209429385 U CN209429385 U CN 209429385U CN 201822001236 U CN201822001236 U CN 201822001236U CN 209429385 U CN209429385 U CN 209429385U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- reinforcing bar
- hole
- secondary reinforcing
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of steel pipe concrete profiled piles, including outer layer, concrete main body and the first secondary reinforcing bar, the outer layer is internally provided with concrete main body, and concrete main body is internally provided with the first steel pipe, the outer surface of first steel pipe offers link slot, and the right end of link slot and the second steel pipe is connected with each other, the right end of second steel pipe offers first through hole, and first through hole and main reinforcement are connected with each other, the second through-hole is offered on second steel pipe, and second through-hole be located at the left of first through hole, described first secondary reinforcing bar and the second through-hole are connected with each other, and first secondary reinforcing bar through the second steel pipe and the second secondary reinforcing bar interconnection.The steel pipe concrete profiled pile, for staff in the work welded to the second steel pipe, the second steel pipe carries out the restriction work of position by link slot, effectively reduces staff's probability that the second steel pipe is displaced when welding.
Description
Technical field
The utility model relates to Special-Shaped Column technical field, specially a kind of steel pipe concrete profiled pile.
Background technique
Special-Shaped Column can effectively avoid common frame column from occurring the problem of protrusion indoors, and effective increase house is whole
The usable floor area of body, while convenient for mitigating the self weight of building.
Peace generally is fixed using reinforcing bar and reinforcing bar during being assembled in common Special-Shaped Column currently on the market
The work of dress, or when being assembled using steel pipe, stability when being welded between steel pipe and reinforcing bar is inadequate, steel pipe and steel
The phenomenon that dislocation is easy to happen between muscle, in view of the above-mentioned problems, carrying out innovative design on the basis of original Special-Shaped Column.
Summary of the invention
The purpose of this utility model is to provide a kind of steel pipe concrete profiled piles, to solve to propose in above-mentioned background technique
Special-Shaped Column common currently on the market, the work of installation is generally fixed using reinforcing bar and reinforcing bar during being assembled
When making, or being assembled using steel pipe, stability when being welded between steel pipe and reinforcing bar is inadequate, between steel pipe and reinforcing bar
The problem of the phenomenon that being easy to happen dislocation.
To achieve the above object, the utility model provides the following technical solutions: a kind of steel pipe concrete profiled pile, including outer
The secondary reinforcing bar of layer, concrete main body and first, the outer layer is internally provided with concrete main body, and the inside of concrete main body is set
It is equipped with the first steel pipe, the outer surface of first steel pipe offers link slot, and the right end of link slot and the second steel pipe mutually interconnects
It connects, the right end of second steel pipe offers first through hole, and first through hole and main reinforcement are connected with each other, and main reinforcement runs through
Second steel pipe offers the second through-hole on second steel pipe, and the second through-hole is located at the left of first through hole, and described first is secondary
Reinforcing bar and the second through-hole are connected with each other, and the first secondary reinforcing bar is connected with each other through the second steel pipe and the second secondary reinforcing bar, and second
Secondary reinforcing bar and main reinforcement are connected with each other.
Preferably, second steel pipe be by link slot and the first steel pipe be connected together, and the left end of the second steel pipe and
Link slot is arcuate structure.
Preferably, the number of second steel pipe is provided with 4, and 4 the second steel pipes angularly divide on the first steel pipe
Cloth.
Preferably, the number of the main reinforcement is provided with 2, and longitudinal centre line of 2 main reinforcements about the first steel pipe
It is symmetrical, and main reinforcement constitutes slide construction by first through hole and the second steel pipe.
Preferably, the described first secondary reinforcing bar constitutes slide construction, and the first secondary reinforcing bar by the second through-hole and the second steel pipe
The equidistantly distributed on the second steel pipe.
Preferably, the described second secondary reinforcing bar and the first secondary reinforcing bar are to be welded to connect, and the second secondary reinforcing bar and main reinforcement are weldering
It connects in succession.
Compared with prior art, the utility model has the beneficial effects that the steel pipe concrete profiled pile,
1, for staff in the work welded to the second steel pipe, the second steel pipe carries out the limit of position by link slot
Fixed work, effectively reduces staff's probability that the second steel pipe is displaced when welding;
2, the entire length of main reinforcement is greater than the first secondary reinforcing bar, consequently facilitating the first secondary reinforcing bar and main reinforcement carry out welding company
It connects, while increasing stability of the Special-Shaped Column after having poured concrete;
3, main reinforcement and the first secondary reinforcing bar are installed on the second steel pipe by first through hole and the second through-hole, to make first
Secondary reinforcing bar is distributed at equal intervals on the second steel pipe, while facilitating staff to the position of main reinforcement and the first secondary reinforcing bar
It carries out smoothly adjusting work.
Detailed description of the invention
Fig. 1 is that the utility model integrally faces the schematic diagram of the section structure;
Fig. 2 is enlarged structure schematic diagram at A in the utility model Fig. 1;
Fig. 3 is the utility model entirety positive structure diagram.
In figure: 1, outer layer;2, concrete main body;3, the first steel pipe;4, link slot;5, the second steel pipe;6, first through hole;7,
Main reinforcement;8, the second through-hole;9, the first secondary reinforcing bar;10, the second secondary reinforcing bar.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-3 is please referred to, the utility model provides a kind of technical solution: a kind of steel pipe concrete profiled pile, including outer layer
1, concrete main body 2 and the first secondary reinforcing bar 9, outer layer 1 is internally provided with concrete main body 2, and the inside of concrete main body 2 is set
It is equipped with the first steel pipe 3, the outer surface of the first steel pipe 3 offers link slot 4, and link slot 4 and the right end of the second steel pipe 5 mutually interconnect
It connects, the right end of the second steel pipe 5 offers first through hole 6, and first through hole 6 and main reinforcement 7 are connected with each other, and main reinforcement 7 passes through
The second steel pipe 5 is worn, the second through-hole 8 is offered on the second steel pipe 5, and the second through-hole 8 is located at the left of first through hole 6, first is secondary
Reinforcing bar 9 and the second through-hole 8 are connected with each other, and the first secondary reinforcing bar 9 is connected with each other through the second steel pipe 5 and the second secondary reinforcing bar 10, and
And second secondary reinforcing bar 10 be connected with each other with main reinforcement 7;
Second steel pipe 5 is connected together by link slot 4 with the first steel pipe 3, and the left end of the second steel pipe 5 and link slot 4
It is arcuate structure, the effective stability for improving the second steel pipe 5 when being welded reduces what shifting occurred in the second steel pipe 5
Phenomenon;
The number of second steel pipe 5 is provided with 4, and 4 the second steel pipes 5 are in 3 spaced at equal angles around of the first steel pipe, effectively
The overall stability of the Special-Shaped Column is increased, while convenient for the installation to main reinforcement 7 and the first secondary reinforcing bar 9;
The number of main reinforcement 7 is provided with 2, and 2 main reinforcements 7 are symmetrical about the longitudinal centre line of the first steel pipe 3,
And main reinforcement 7 constitutes slide construction by first through hole 6 and the second steel pipe 5, convenient for making staff by main reinforcement 7 and second
Steel pipe 5 is attached, while the adjustment convenient for setting main reinforcement 7 in the enterprising line position of the second steel pipe 5;
First secondary reinforcing bar 9 constitutes slide construction by the second through-hole 8 and the second steel pipe 5, and the first secondary reinforcing bar 9 is in the second steel
Equidistantly distributed on pipe 5 is conducive to staff and is attached the first secondary reinforcing bar 9 with the second steel pipe 5, while facilitating first
The adjustment that secondary reinforcing bar 9 is set in the enterprising line position of the second steel pipe 5;
Second secondary reinforcing bar 10 and the first secondary reinforcing bar 9 are to be welded to connect, and the second secondary reinforcing bar 10 is that welding connects with main reinforcement 7
It connects, the further connectivity increased between the first pair reinforcing bar 9, while the first secondary reinforcing bar 9 being made to pass through the second secondary reinforcing bar 10 and master
Reinforcing bar 7 is attached.
Working principle: according to Fig. 1-2, the second steel pipe 5 is engaged on the first steel pipe 3 manually by link slot 4 first, is made
Second steel pipe 5 keeps stablizing in the first steel pipe 3, to make staff that the second steel pipe 5 are welded to the first steel by electric welding machine
On pipe 3, then remaining second steel pipe 5 is in turn mounted on the first steel pipe 3 according to above-mentioned principle;
According to Fig. 1-2, then main reinforcement 7 is slidably mounted on the second steel pipe 5 by first through hole 6, then by main steel
Muscle 7 slides into suitable position on the second steel pipe 5, main reinforcement 7 is welded on the second steel pipe 5 by electric welding machine, then hand
It is dynamic to be slidably mounted to the first secondary reinforcing bar 9 on second steel pipe 5 by the second through-hole 8, then by the first secondary reinforcing bar 9 in the second steel pipe
Suitable position is slided on 5, the first secondary reinforcing bar 9 is welded on the second steel pipe 5 by electric welding machine, then manually by the second pair
Reinforcing bar 10 is welded on the first secondary reinforcing bar 9 and main reinforcement 7 by electric welding machine, then according to above-mentioned principle, successively by remaining master
The secondary reinforcing bar 9 of reinforcing bar 7, first and the second secondary reinforcing bar 10 carry out welding installation;
According to Fig. 1 and Fig. 3, the outside of the secondary reinforcing bar 9 of main reinforcement 7, first and the second secondary reinforcing bar 10 is then installed into outer layer 1
Afterwards, concrete main body 2 is filled into the inside of outer layer 1 by watering appliance, to make concrete main body 2 to main reinforcement 7, first
Secondary reinforcing bar 9 and the second secondary reinforcing bar 10 are covered, and can complete the operating of the steel pipe concrete profiled pile in this way, such a
Steel pipe concrete profiled pile is convenient for people to use.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of steel pipe concrete profiled pile, including the secondary reinforcing bar (9) of outer layer (1), concrete main body (2) and first, feature exists
In: the outer layer (1) is internally provided with concrete main body (2), and concrete main body (2) is internally provided with the first steel pipe
(3), the outer surface of first steel pipe (3) offers link slot (4), and link slot (4) and the right end of the second steel pipe (5) are mutual
Connection, the right end of second steel pipe (5) offer first through hole (6), and first through hole (6) and main reinforcement (7) are connected with each other,
And main reinforcement (7) runs through the second steel pipe (5), offers the second through-hole (8) on second steel pipe (5), and the second through-hole (8)
Positioned at the left of first through hole (6), the described first secondary reinforcing bar (9) and the second through-hole (8) are connected with each other, and the first secondary reinforcing bar (9)
It is connected with each other through the second steel pipe (5) and the second secondary reinforcing bar (10), and the second secondary reinforcing bar (10) mutually interconnects with main reinforcement (7)
It connects.
2. a kind of steel pipe concrete profiled pile according to claim 1, it is characterised in that: second steel pipe (5) passes through
Link slot (4) is to be connected together, and the left end of the second steel pipe (5) and link slot (4) are arcuate structure with the first steel pipe (3).
3. a kind of steel pipe concrete profiled pile according to claim 1, it is characterised in that: of second steel pipe (5)
Number is provided with 4, and 4 the second steel pipes (5) are in the first steel pipe (3) spaced at equal angles around.
4. a kind of steel pipe concrete profiled pile according to claim 1, it is characterised in that: the number of the main reinforcement (7)
2 are provided with, and 2 main reinforcements (7) are symmetrical about the longitudinal centre line of the first steel pipe (3), and main reinforcement (7) passes through
First through hole (6) and the second steel pipe (5) constitute slide construction.
5. a kind of steel pipe concrete profiled pile according to claim 1, it is characterised in that: the described first secondary reinforcing bar (9) is logical
It crosses the second through-hole (8) and the second steel pipe (5) and constitutes slide construction, and the first secondary reinforcing bar (9) is equidistantly divided on the second steel pipe (5)
Cloth.
6. a kind of steel pipe concrete profiled pile according to claim 1, it is characterised in that: the second secondary reinforcing bar (10) with
First secondary reinforcing bar (9) is to be welded to connect, and the second secondary reinforcing bar (10) and main reinforcement (7) are to be welded to connect.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822001236.3U CN209429385U (en) | 2018-11-30 | 2018-11-30 | A kind of steel pipe concrete profiled pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822001236.3U CN209429385U (en) | 2018-11-30 | 2018-11-30 | A kind of steel pipe concrete profiled pile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209429385U true CN209429385U (en) | 2019-09-24 |
Family
ID=67970301
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822001236.3U Expired - Fee Related CN209429385U (en) | 2018-11-30 | 2018-11-30 | A kind of steel pipe concrete profiled pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209429385U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112681613A (en) * | 2021-01-11 | 2021-04-20 | 胡兵 | Assembled steel construction concrete building body |
-
2018
- 2018-11-30 CN CN201822001236.3U patent/CN209429385U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112681613A (en) * | 2021-01-11 | 2021-04-20 | 胡兵 | Assembled steel construction concrete building body |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202831233U (en) | Connected node of protracting inner diaphragm steel girder and concrete-filled steel-tubular columns inscribed a pipe coat | |
CN209429385U (en) | A kind of steel pipe concrete profiled pile | |
CN106332825A (en) | Improved main frame of offshore net cage | |
CN206752698U (en) | A kind of steel construction single-layer latticed shell rice font node | |
CN208089308U (en) | A kind of sharp radius curve shield duct piece water sealing structure | |
CN109339818A (en) | A kind of compound tunnel segment structure of Mechanical Method service channel portal fringing | |
CN207609427U (en) | A kind of simple multispan formula tunnel inverted arch trestle structure | |
CN215104349U (en) | Prevent enhancement road bed road surface structure of ponding | |
CN206054469U (en) | A kind of service tee | |
CN211371551U (en) | Anti-leakage pipeline control assembly | |
CN208251085U (en) | A kind of building engineering construction prestress pulling resistant pilework | |
CN208934700U (en) | A kind of track engineering shield tunnel pipe of concrete slice mounting structure | |
CN208309868U (en) | A kind of buckling restrained brace device | |
CN206554938U (en) | A kind of simple and practical shield machine articulated mounting | |
CN206245290U (en) | A kind of Flood discharge safety dyke-dam | |
CN216379572U (en) | Slope support anti-collapse device | |
CN205935194U (en) | Many steel structural framework for high -rise building | |
CN215891535U (en) | Stainless steel elbow | |
CN111173196A (en) | Giant circular steel tube concrete column for super high-rise building structure | |
CN205576765U (en) | Tip additional strengthening suitable for bevel corrugated steel pipe | |
CN211113652U (en) | A soil body shunt for piping lane foundation ditch symmetry is backfilled | |
CN214695492U (en) | Irrigation diverging device of water economy resource | |
CN218050913U (en) | Water and electricity installation steel pipe fast weld interfacing apparatus | |
CN207814690U (en) | A kind of nozzle hair side flat mouth pipe outstanding | |
CN215483142U (en) | Stagnant water steel sheet with prevent scraping wearability |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190924 Termination date: 20201130 |
|
CF01 | Termination of patent right due to non-payment of annual fee |