CN218050913U - Water and electricity installation steel pipe fast weld interfacing apparatus - Google Patents

Water and electricity installation steel pipe fast weld interfacing apparatus Download PDF

Info

Publication number
CN218050913U
CN218050913U CN202023030115.5U CN202023030115U CN218050913U CN 218050913 U CN218050913 U CN 218050913U CN 202023030115 U CN202023030115 U CN 202023030115U CN 218050913 U CN218050913 U CN 218050913U
Authority
CN
China
Prior art keywords
bucket
wall
steel pipe
fixed plate
installation steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202023030115.5U
Other languages
Chinese (zh)
Inventor
林岳角
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Yuhui Construction Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202023030115.5U priority Critical patent/CN218050913U/en
Application granted granted Critical
Publication of CN218050913U publication Critical patent/CN218050913U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/10Greenhouse gas [GHG] capture, material saving, heat recovery or other energy efficient measures, e.g. motor control, characterised by manufacturing processes, e.g. for rolling metal or metal working

Landscapes

  • Arc Welding In General (AREA)

Abstract

The utility model provides a water and electricity installation steel pipe fast weld interfacing apparatus, connect bucket and right side including a left side and connect the bucket, the right side of connecting the bucket on a left side is closely laminated and is connected the bucket on the right side, the equal fixed mounting of last lower extreme of connecting bucket outer wall and right side is connected on a left side has the connecting piece, it is equipped with the gim peg all to insert between the connecting piece of bucket and right side connection bucket on a left side, the outer wall of connecting bucket and right side connection bucket on a left side all inserts and is equipped with the gim peg, the equal opening in inside of connecting bucket and right side connection bucket is provided with the inside groove, the last lower extreme of connecting bucket and right side connection bucket outer wall all rotates and is connected with the regulating wheel, the outer wall fixed mounting of regulating wheel has the external tooth, the inside of connecting bucket and right connection bucket all imbeds and is provided with the reinforcement ring, the equal opening in inside of reinforcement ring is provided with interior hidden groove, the equal fixedly connected with spring of inner wall in hidden groove. The utility model discloses fixed effect to the steel pipe is better, is difficult to among the steel pipe welding process rock, and the adjustable welded position who rotates steel pipe adjustment steel pipe simultaneously uses more conveniently.

Description

Water and electricity installation steel pipe fast weld interfacing apparatus
Technical Field
The utility model relates to a water and electricity erection equipment technical field especially relates to a water and electricity installation steel pipe fast weld interfacing apparatus.
Background
The water and electricity installation generally refers to the installation contents of water supply, water drainage, heating and electricity (strong and weak electricity such as illumination and communication) matched in public buildings or residential buildings. In the process of hydroelectric installation, steel pipes are frequently used, the steel pipes are provided with hollow sections, the length of the steel pipes is far longer than the diameter or the circumference of steel, and the steel pipes are divided into round, square, rectangular and special-shaped steel pipes according to the shapes of the sections; the steel pipe is divided into a carbon structural steel pipe, a low alloy structural steel pipe, an alloy steel pipe and a composite steel pipe according to the material quality, is divided into a steel pipe for a conveying pipeline, an engineering structure, a thermal equipment, a petrochemical industry, a machine manufacturing, a geological drilling, a high pressure equipment and the like according to the application, is divided into a seamless steel pipe and a welded steel pipe according to the production process, and when the steel pipe is installed, the welded steel pipe needs to be welded and lengthened sometimes. Traditional steel pipe welding is put and welds again after butt joint on the workstation generally, and is relatively poor to the fixed effect of steel pipe, and the inconvenient reversal of steel pipe during the welding, and the welding is very inconvenient.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problems existing in the prior art and providing a water and electricity installation steel pipe fast welding butt joint device.
In order to realize the purpose, the utility model adopts the following technical scheme:
the utility model provides a water and electricity installation steel pipe fast weld interfacing apparatus, connects the bucket including a left side and the right side, the right side of connecting the bucket in a left side closely laminates and has the right side to connect the bucket, the equal fixed mounting of last lower extreme of connecting bucket outer wall and right side connects the connecting piece, all transversely insert between the connecting piece of bucket and right side connection bucket and be equipped with the adjusting bolt, the outer wall of connecting bucket and right side connection bucket in a left side all inserts and is equipped with the gim peg, the equal opening in inside of connecting bucket and right side connection bucket is provided with the inside groove, the last lower extreme of connecting bucket and right side connection bucket outer wall all rotates and is connected with the regulating wheel, the outer wall fixed mounting of regulating wheel has the external tooth, the inside of connecting bucket and right side connection bucket all imbeds and is provided with the reinforcement ring, the equal opening in inside of reinforcement ring is provided with interior hidden groove, the equal fixedly connected with spring in interior hidden groove, the equal fixedly connected with fixed plate in one side that the spring is close to the reinforcement ring middle part, the equal fixedly connected with non-slip surface in one side that the fixed plate is close to the reinforcement ring middle part.
Preferably, the left connecting barrel and the right connecting barrel are symmetrically arranged, and the threads on the outer wall of the adjusting bolt are meshed with the threads in the connecting piece on the left connecting barrel.
Preferably, the inside of reinforcing ring all imbeds and sets up three fixed plate, the fixed plate is the ring form setting around the middle part of reinforcing ring.
Preferably, the fixing plate is embedded in an inner hidden groove of the reinforcing ring, and the fixing plate slides in the reinforcing ring in a horizontal direction.
Preferably, the outer teeth of the outer wall of the adjusting wheel are meshed with the clamping teeth of the outer wall of the reinforcing ring.
Preferably, the left side outer wall of the left side connecting barrel and the right side outer wall of the right side connecting barrel are inserted with fixing bolts, and the adjusting bolts inserted on the left side connecting barrel and the right side connecting barrel are respectively arranged in a cross shape around the middle parts of the left side connecting barrel and the right side connecting barrel.
Preferably, the threads on the outer wall of the adjusting bolt are engaged with the threads on the inner walls of the left connecting barrel and the right connecting barrel.
The utility model provides a water and electricity installation steel pipe fast weld interfacing apparatus has following beneficial effect:
1. this kind of water and electricity installation steel pipe fast weld interfacing apparatus is through being provided with fixed plate and gim peg for after the steel pipe imbeds respectively in the inside of connecting bucket and right side connection bucket on a left side, the non-skid surface of fixed plate hugs closely at the outer wall of steel pipe, twists the gim peg of connecting bucket outer wall on a left side and right side simultaneously, makes the gim peg closely paste and carries out the secondary at the steel pipe outer wall and fix the steel pipe, slides when preventing the steel pipe welding, and is better to the fixed effect of steel pipe.
2. This kind of water and electricity installation steel pipe fast weld interfacing apparatus is through being provided with the anchor ring for when the welding angle at the adjustment steel pipe, promote the regulating wheel through unscrewing behind the gim peg and rotate, make the regulating wheel drive the anchor ring and connect the inside rotation of bucket or right connection bucket at a left side, realize connecting bucket or right connection bucket internal fixation steel pipe's position to a left side and rotate the adjustment, the flexibility ratio is higher, and it is more convenient to use.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a right side sectional view of the partial structure of the middle right connecting barrel of the present invention;
FIG. 3 is a left side view of the partial structure of the middle reinforcing ring of the present invention;
fig. 4 is the left side schematic view of the local structure of the middle adjusting wheel of the present invention.
Illustration of the drawings:
1-left connecting barrel, 2-right connecting barrel, 3-connecting piece, 4-adjusting bolt, 5-fixing bolt, 501-inner groove, 6-adjusting wheel, 601-outer tooth, 7-reinforcing ring, 8-inner hidden groove, 9-spring, 10-fixing plate and 11-antiskid surface.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person skilled in the art without making creative efforts belong to the protection scope of the present invention.
Referring to fig. 1-4, a water and electricity installation steel pipe fast welding interfacing apparatus, including left side connection bucket 1 and right side connection bucket 2, the right side of left side connection bucket 1 closely laminates and has right side connection bucket 2, the equal fixed mounting in upper and lower end of left side connection bucket 1 and right side connection bucket 2 outer wall has connecting piece 3, all transversely insert between left side connection bucket 1 and the connecting piece 3 of right side connection bucket 2 and be equipped with adjusting bolt 4, the outer wall of left side connection bucket 1 and right side connection bucket 2 all inserts and is equipped with gim peg 5, the equal opening in inside of left side connection bucket 1 and right side connection bucket 2 is provided with inside groove 501, the equal rotation of upper and lower extreme of connecting bucket 1 and right side connection bucket 2 outer wall is connected with regulating wheel 6, the outer wall fixed mounting of regulating wheel 6 has external tooth 601, the inside of connecting bucket 1 and right side connection bucket 2 all imbeds and is provided with reinforcement ring 7, the equal opening in inside of reinforcement ring 7 is provided with interior hidden groove 8, the equal fixedly connected with spring 9 in the inner wall of interior hidden groove 8, spring 9 is close to the equal fixedly connected with fixed plate 10 in one side at the middle part of fixed plate 7, the equal fixedly connected with reinforcement face 11.
In this embodiment, the left connecting barrel 1 and the right connecting barrel 2 are symmetrically arranged, the thread on the outer wall of the adjusting bolt 4 is engaged with the thread in the connecting piece 3 on the left connecting barrel 1, and the adjusting bolt 4 on the connecting piece 3 is screwed to adjust the position between the left connecting barrel 1 and the right connecting barrel 2, so that the steel pipes fixed in the left connecting barrel 1 and the right connecting barrel 2 are tightly attached together.
In this embodiment, the inside of reinforcing ring 7 all imbeds and sets up three fixed plate 10, fixed plate 10 is the ring form setting around the middle part of reinforcing ring 7, make when the steel pipe embedding is in the left side and connect bucket 1 and the inside of right side connection bucket 2, the steel pipe is through promoting three fixed plate 10 and remove to the interior groove 8 that hides, spring 9 compression in the extrusion in the hidden groove 8, follow-up spring 9 produces the anti-skidding face 11 that bounce-force promoted three fixed plate 10 and hugs closely at the outer wall of steel pipe, increase and the effort between the steel pipe outer wall, the realization is fixed the steel pipe.
In this embodiment, the fixed plate 10 embedding sets up in the interior hidden groove 8 of reinforcing ring 7, and fixed plate 10 is the horizontal direction and slides in reinforcing ring 7 for when the steel pipe embedding is in the inside of left side connection bucket 1 and right side connection bucket 2, the steel pipe removes to interior hidden groove 8 through promoting fixed plate 10, and the compression of spring 9 in the hidden groove 8 in the extrusion, follow-up spring 9 produce the bounce and promote the non-skid surface 11 of fixed plate 10 and hug closely at the outer wall of steel pipe, realize fixing the steel pipe.
In this embodiment, the external tooth 601 of regulating wheel 6 outer wall meshes with the latch of reinforcing ring 7 outer wall mutually, when the welding angle at the adjustment steel pipe, promotes regulating wheel 6 and rotates after loosening gim peg 5 for regulating wheel 6 drives reinforcing ring 7 and connects bucket 1 or the inside rotation of connecting bucket 2 on the right side at a left side, realizes connecting bucket 1 or the position of connecting bucket 2 internal fixation steel pipe on the right side to a left side and rotates the adjustment, and the flexibility ratio is higher, and it is more convenient to use.
In this embodiment, the left side outer wall of connecting bucket 1 on a left side and the right side outer wall of connecting bucket 2 on a right side are all inserted and are equipped with gim peg 5, the gim peg 4 that establish is inserted respectively around the middle part of connecting bucket 1 and right side connecting bucket 2 on a left side to connecting bucket 1 and right side on a left side is connected bucket 2 on a left side and is "ten" word form range, make when the steel pipe embedding to the inside fixed back of reinforcing ring 7, twist simultaneously and move a plurality of gim pegs 5 of connecting bucket 1 and right side connecting bucket 2 outer wall, make a plurality of gim pegs 5 hug closely and carry out the secondary at the steel pipe outer wall and fix the steel pipe, slide when preventing the steel pipe welding, fixed effect to the steel pipe is better.
In this embodiment, the screw thread of adjusting bolt 4 outer wall meshes with the screw thread of connecting bucket 1 and 2 inner walls of right side connection bucket for after the steel pipe embedding is fixed to the inside of reinforcing ring 7, twist simultaneously and move the gim peg 5 of connecting bucket 1 and the 2 outer walls of right side connection bucket, make gim peg 5 hug closely and carry out the secondary at the steel pipe outer wall and fix the steel pipe, slide when preventing the pipe welding, fixed effect to the steel pipe is better.
The working principle is as follows: during the use, the steel pipe is embedded in the insides of the left connecting barrel 1 and the right connecting barrel 2 respectively, the steel pipe moves to the inner hidden groove 8 through pushing the fixing plate 10, the spring 9 in the inner hidden groove 8 is compressed in extrusion, the subsequent spring 9 generates rebound force to push the anti-slip surface 11 of the fixing plate 10 to cling to the outer wall of the steel pipe, simultaneously the fixing bolt 5 of the left connecting barrel 1 and the right connecting barrel 2 is screwed, the fixing bolt 5 clings to the outer wall of the steel pipe to secondarily fix the steel pipe, the steel pipe is prevented from sliding during welding, the fixing effect on the steel pipe is good, when the welding angle of the steel pipe is adjusted, the adjusting wheel 6 is pushed to rotate after the fixing bolt 5 is unscrewed, the adjusting wheel 6 drives the reinforcing ring 7 to rotate in the insides of the left connecting barrel 1 or the right connecting barrel 2, the rotation adjustment of the positions of the steel pipes fixed in the left connecting barrel 1 or the right connecting barrel 2 is realized, the flexibility is higher, the use is more convenient, and the adjusting bolt 4 on the movable connecting piece 3 is used for adjusting the positions between the left connecting barrel 1 and the right connecting barrel 2.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. The utility model provides a water and electricity installation steel pipe fast welding interfacing apparatus, connects bucket (1) and right side including a left side and connects bucket (2), the right side of connecting bucket (1) on a left side closely is laminated with the right side and connects bucket (2), a serial communication port, the equal fixed mounting of last lower extreme of connecting bucket (2) outer wall has connecting piece (3) on a left side, all transversely insert between connecting piece (3) of connecting bucket (1) and right side connection bucket (2) and be equipped with adjusting bolt (4), the outer wall of connecting bucket (1) on a left side and connecting bucket (2) on the right side all is inserted and is equipped with gim peg (5), the equal opening in inside of connecting bucket (1) on a left side and connecting bucket (2) on the right side is provided with inside groove (501), the last lower extreme of connecting bucket (2) outer wall all rotates and is connected with adjusting wheel (6) on the right side, the outer wall fixed mounting of adjusting wheel (6) has outer tooth (601), the equal fixed mounting of connecting bucket (1) and right side of connecting bucket (2) all is provided with the inside all imbeds with gusset plate (7), the equal opening of strengthening ring (7) is provided with the inner wall of hiding groove (8), one side fixed plate (10) that the equal opening of inner wall (10) is close to the equal fixed plate (10) of spring (10), the equal fixed plate (10) that the fixed plate (10) is connected with the fixed plate (10), the equal fixed plate (7) that the fixed plate (10) is connected with the fixed plate (10), the fixed plate (10) that the fixed plate (10) is connected with the fixed plate (10) all embedded in the fixed plate (10) that the fixed plate (10) is close to the fixed plate (10) all 11).
2. A water and electricity installation steel pipe fast welding interfacing apparatus of claim 1, characterized in that, be the symmetry setting between left side connection bucket (1) and the right side connection bucket (2), the screw thread of adjusting bolt (4) outer wall meshes with the screw thread in connecting piece (3) on the left side connection bucket (1).
3. A water and electricity installation steel pipe fast welding interfacing apparatus according to claim 1, characterized in that, the inside of reinforcement ring (7) all imbeds and sets up three fixed plate (10), fixed plate (10) are the ring shape around the middle part of reinforcement ring (7) sets up.
4. A water and electricity installation steel pipe fast welding interfacing apparatus according to claim 1, wherein, the fixed plate (10) is embedded in the inner hidden groove (8) of the reinforcing ring (7), and the fixed plate (10) slides in the reinforcing ring (7) in the horizontal direction.
5. A hydroelectric installation steel pipe fast welding and butting device according to claim 1, wherein the outer teeth (601) of the outer wall of the adjusting wheel (6) are meshed with the clamping teeth of the outer wall of the reinforcing ring (7).
6. The water and electricity installation steel pipe fast welding interfacing apparatus of claim 1, characterized in that, the left side outer wall of connecting bucket (1) on a left side and the right side outer wall of connecting bucket (2) on a right side all insert and be equipped with gim peg (5), the adjusting bolt (4) that establish is inserted to left side connecting bucket (1) and right connecting bucket (2) outer wall is the range of "ten" style of calligraphy around the middle part of left side connecting bucket (1) and right connecting bucket (2) respectively.
7. A hydroelectric installation steel pipe fast welding and butting device according to claim 1, wherein the threads on the outer wall of the adjusting bolt (4) are meshed with the threads on the inner walls of the left connecting barrel (1) and the right connecting barrel (2).
CN202023030115.5U 2020-12-16 2020-12-16 Water and electricity installation steel pipe fast weld interfacing apparatus Withdrawn - After Issue CN218050913U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023030115.5U CN218050913U (en) 2020-12-16 2020-12-16 Water and electricity installation steel pipe fast weld interfacing apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023030115.5U CN218050913U (en) 2020-12-16 2020-12-16 Water and electricity installation steel pipe fast weld interfacing apparatus

Publications (1)

Publication Number Publication Date
CN218050913U true CN218050913U (en) 2022-12-16

Family

ID=84398429

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023030115.5U Withdrawn - After Issue CN218050913U (en) 2020-12-16 2020-12-16 Water and electricity installation steel pipe fast weld interfacing apparatus

Country Status (1)

Country Link
CN (1) CN218050913U (en)

Similar Documents

Publication Publication Date Title
CN202380987U (en) Internal-external thread connector of thin-wall expansion pipe
CN2758349Y (en) Fast connected reinforced bar joint
CN218050913U (en) Water and electricity installation steel pipe fast weld interfacing apparatus
CN108756071A (en) A kind of straight screw sleeve for building
CN205226007U (en) Double -end spiro union formula connection structure
CN114458322B (en) Shield constructs quick-witted steel sleeve base additional strengthening that originates from with prevent stretch-break function
CN209855214U (en) Scissor-bracing steel pipe connector
CN213710335U (en) Steel pipe connecting mechanism for assembly type building
CN205688441U (en) A kind of casing bit pulling out anchor cable
CN214171056U (en) Connecting piece for escape pipeline socket joint
CN206478348U (en) Spigot-and-socket steel pipe anticreep mouthful device
CN205935423U (en) Construction steel bar connects external member
CN1274060A (en) Expansion shaped insertion-type steel tubes for both flexible and rigid joining and its manufacture technology
CN204174842U (en) A kind of concavo-convex bar splice
CN203716477U (en) Connecting tube for building exterior wall scaffold
CN204040936U (en) The female adapter of petroleum pipeline direct linkage type
CN207064897U (en) A kind of HDPE indoor drainage pipe groove pressure rings being easily installed
CN202519792U (en) Butt joint part using axial cross insertion plate to enable steel tubes to be in butt joint
CN202247967U (en) Spiral connection embedded pipe
CN201407039Y (en) Integral-type non-joint static penetration-testing probe rod
CN218150790U (en) Anti-tripping screen pipe coupling
CN219622648U (en) Geological casing connecting assembly
CN216430172U (en) Interim connector of length and pound level adjustable pipeline
CN221143286U (en) Prefabricated component steel bar connection structure
CN215498072U (en) High-strength cable protection pipe

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230616

Address after: 710016 Room 10810, Block A, Jingfa Building, north of Fengcheng Second Road and west of Weiyang Road, Economic Development Zone, Xi'an City, Shaanxi Province

Patentee after: Shaanxi Yuhui Construction Engineering Co.,Ltd.

Address before: 325200 Huling town Linxi Meian village Ruian City Wenzhou City Zhejiang Province

Patentee before: Lin Yuejiao

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20221216

Effective date of abandoning: 20230627

AV01 Patent right actively abandoned

Granted publication date: 20221216

Effective date of abandoning: 20230627