CN209429124U - A kind of bored pile construction cleaning waste slag equipment - Google Patents
A kind of bored pile construction cleaning waste slag equipment Download PDFInfo
- Publication number
- CN209429124U CN209429124U CN201822211904.5U CN201822211904U CN209429124U CN 209429124 U CN209429124 U CN 209429124U CN 201822211904 U CN201822211904 U CN 201822211904U CN 209429124 U CN209429124 U CN 209429124U
- Authority
- CN
- China
- Prior art keywords
- driving mechanism
- hopper
- bored pile
- pile construction
- cleaning waste
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model provides a kind of bored pile construction cleaning waste slag equipment.The bored pile construction cleaning waste slag equipment includes blanking plate;Supporting mechanism, the side of the supporting mechanism welding and the blanking plate;Driving mechanism, the driving mechanism are installed on the top of the supporting mechanism;Motor, the motor are installed on the side wall of the driving mechanism, are rotatablely connected between the motor and the driving mechanism;Charge mechanism, the charge mechanism is mounted equidistant in the side wall of the driving mechanism, the charge mechanism includes fixed link, hopper, feed hopper and feed inlet, the side wall of the driving mechanism is equidistantly fixedly connected with the fixed link, several fixed links weld the hopper away from one end of the driving mechanism, and the feed hopper opens up the feed inlet away from one end of the fixed link.Bored pile construction provided by the utility model is high-efficient with cleaning waste slag equipment reason, and waste residue is not easy to fall, highly-safe.
Description
Technical field
The utility model relates to technical field of buildings more particularly to a kind of bored pile construction cleaning waste slag equipment.
Background technique
Bored concrete pile system refers in engineering site through means such as machine drilling, steel pipe soil compaction or manpower excavations in foundation soil
Stake holes is formed, and places steel reinforcement cage, concrete perfusion and the stake being made into it, according to forming hole method difference, bored concrete pile again may be used
It is divided into several classes such as driven cast-in-place pile, cast-in-situ bored pile and digging hole filling pile.
Existing bored pile construction cleaning waste slag equipment is all to be manually entered to shaft bottom manually filling waste residue shovel
The blue inside of the transport of soil, lifting machine can only once lift by crane a basket soil, and speed is slow, and lifting machine processing waste residue is easy to fall,
Risk is big.
Therefore, it is necessary to provide a kind of new bored pile construction cleaning waste slag equipment solution above-mentioned technical problem.
Utility model content
The technical issues of the utility model solves is to provide a kind for the treatment of effeciency height, and waste residue is not easy to fall, highly-safe
Bored pile construction cleaning waste slag equipment.
In order to solve the above technical problems, bored pile construction cleaning waste slag equipment provided by the utility model includes:
Blanking plate;Supporting mechanism, the side of the supporting mechanism welding and the blanking plate;Driving mechanism, the driving mechanism installation
In the top of the supporting mechanism;Motor, the motor are installed on the side wall of the driving mechanism, the motor and the driving
It is rotatablely connected between mechanism;Charge mechanism, the charge mechanism are mounted equidistant in the side wall of the driving mechanism, the charger
Structure includes fixed link, hopper, feed hopper and feed inlet, and the side wall of the driving mechanism is equidistantly fixedly connected with the fixed link, if
It does the fixed link and welds the hopper, the side wall away from the fixed link of the hopper away from one end of the driving mechanism
It is welded with the feed hopper, the feed hopper opens up the feed inlet away from one end of the fixed link.
Preferably, the supporting mechanism includes bracket, the first fixed frame, connecting column and the second fixed frame, the driving machine
Structure is installed between four brackets, and the bottom of four brackets is welded in described first that cross section is rectangle structure
The top of fixed frame, the welding connecting column at the bottom four corners of first fixed frame, the bottom weldering of four connecting columns
Second fixed frame that cross section is rectangle structure is connect, the area of second fixed frame is greater than first fixed frame
Area, the blanking plate be welded in two groups described between bracket.
Preferably, the driving mechanism includes live-roller, conveyer belt, mounting plate, position-arresting disk and stiffening plate, is located at described the
Four brackets of edge are oppositely arranged two-by-two at the top of one fixed frame, and the installation is welded between bracket described in two of them
Plate welds the mounting plate between bracket described in another two, and the bottom of two mounting plates is equipped with and bracket described in two groups welds
The stiffening plate is connect, the inside of two mounting plates and first fixed frame is rotatably connected to the transmission respectively
Roller, conveyer belt described in the surface wrap of two live-rollers, the opposite flank of two stiffening plates is sequentially connected with and institute
The position-arresting disk for stating conveyer belt conflict, between less than two fixed links of the distance between two described position-arresting disks away from
From, and the length of the fixed link is greater than the diameter of the position-arresting disk, the motor with it is described positioned at the mounting plate side
It is rotatablely connected between live-roller.
Preferably, the charge mechanism further includes push plate, sliding rail, sliding block and spring, the inner top of several hoppers, interior
Top is opposite to weld the sliding rail, and the internal slide of the sliding rail connects the sliding block, pacifies between the sliding block and the sliding rail
The spring is filled, welds the push plate between two sliding blocks.
Preferably, feed hopper structure funnel-shaped, and the section of the hopper of the feed hopper one side wall is in ladder
Shape structure.
Preferably, the trapezoidal structure in section of the sliding block inside the sliding rail, it is described between two sliding blocks
The arc-shaped structure of push plate.
Compared with the relevant technologies, bored pile construction provided by the utility model cleaning waste slag equipment has as follows
The utility model has the advantages that
The utility model provides a kind of bored pile construction cleaning waste slag equipment, and the motor is powered on, real
One of them described live-roller rotation is showed, further realizes the conveyer belt rotation, due to the side wall of the conveyer belt
The distance between two described fixed links are greater than the distance between two described position-arresting disks, realize several hopper circulations
Dynamic, waste residue is shoveled the inside in the hopper of the conveyer belt side in shaft bottom by construction personnel, when the material for having waste residue
Case realizes blanking when being driven the conveyer belt of top, soil is fallen toward the blanking plate blanking, is finished down described after expecting
Spring opens, and the sliding block is mobile to the feed inlet direction, and the push plate resets feeding again.
Detailed description of the invention
Fig. 1 is a kind of knot of preferred embodiment of bored pile construction cleaning waste slag equipment provided by the utility model
Structure schematic diagram;
Fig. 2 is the portion A shown in FIG. 1 enlarged diagram;
Fig. 3 is charging structure schematic diagram shown in FIG. 1;
Fig. 4 is the portion B shown in Fig. 3 enlarged diagram.
Figure label: 1, supporting mechanism, 11, bracket, the 12, first fixed frame, 13, connecting column, the 14, second fixed frame, 2,
Blanking plate, 3, motor, 4, charge mechanism, 41, fixed link, 42, hopper, 43, feed hopper, 44, feed inlet, 45, push plate, 46, cunning
Rail, 47, sliding block, 48, spring, 5, driving mechanism, 51, live-roller, 52, conveyer belt, 53, mounting plate, 54, position-arresting disk, 55, reinforcement
Plate.
Specific embodiment
The utility model is described in further detail with embodiment with reference to the accompanying drawing.
Please refer to Fig. 1, Fig. 2, Fig. 3 and Fig. 4, wherein Fig. 1 is bored pile construction provided by the utility model use
A kind of structural schematic diagram of preferred embodiment of cleaning waste slag equipment;Fig. 2 is the portion A enlarged diagram shown in Fig. 1;Fig. 3 is figure
Charging structure schematic diagram shown in 1;Fig. 4 is the portion B shown in Fig. 3 enlarged diagram.Bored pile construction is set with cleaning waste slag
Standby includes: blanking plate 2;Supporting mechanism 1, the side of supporting mechanism 1 welding and the blanking plate 2;Driving mechanism 5, it is described
Driving mechanism 5 is installed on the top of the supporting mechanism 1;Motor 3, the motor 3 are installed on the side wall of the driving mechanism 3,
It is rotatablely connected between the motor 3 and the driving mechanism 5;Charge mechanism 3, the charge mechanism 3 are mounted equidistant in the drive
The side wall of motivation structure 5, the charge mechanism 3 include fixed link 41, hopper 42, feed hopper 43 and feed inlet 44, the driving machine
The side wall of structure 5 is equidistantly fixedly connected with the fixed link 41, and several fixed links 41 are welded away from one end of the driving mechanism 5
The sidewall weld away from the fixed link 41 of the hopper 42, the hopper 42 has the feed hopper 43, the feed hopper 43
The feed inlet 44 is opened up away from one end of the fixed link 41.
The supporting mechanism 1 includes bracket 11, the first fixed frame 12, connecting column 13 and the second fixed frame 14, the driving
Mechanism 5 is installed between four brackets 11, and the bottom of four brackets 11 is welded in cross section and is rectangle structure
The top of first fixed frame 12, the welding connecting column 13 at the bottom four corners of first fixed frame 12, described in four
The bottom welding cross section of connecting column 13 is rectangle second fixed frame 14 of structure, the area of second fixed frame 14
Greater than the area of first fixed frame 12, the blanking plate 2 be welded in two groups described between bracket 11, bracket 11 described in two groups
The installation to the driving mechanism 5 is realized, and overall structure is put into well realizes to integrally-built solid when in use
It is fixed.
The driving mechanism 5 includes live-roller 51, conveyer belt 52, mounting plate 53, position-arresting disk 54 and stiffening plate 55, is located at institute
Four brackets 11 for stating 12 top edge of the first fixed frame are oppositely arranged two-by-two, are welded between bracket 11 described in two of them
The mounting plate 53 is connect, the mounting plate 53 is welded between bracket 11 described in another two, the bottom of two mounting plates 53 is set
Have and welds the stiffening plate 55, two mounting plates 53 and first fixed frame 12 with bracket 11 described in two groups
Inside is rotatably connected to the live-roller 51, conveyer belt 52 described in the surface wrap of two live-rollers 51, two institutes respectively
The opposite flank for stating stiffening plate 55 is sequentially connected with the position-arresting disk 54 contradicted with the conveyer belt 52, two limits
The distance between disk 54 is less than the distance between two described fixed links 41, and the length of the fixed link 41 is greater than the limit
The diameter of disk 54, the motor 3 and is rotatablely connected between the live-roller 51 of 53 side of mounting plate, will be described
Motor 3, which powers on, realizes one of them described rotation of live-roller 51, further realizes that the conveyer belt 52 rotates, several
The hopper 42 circulation is dynamic, and waste residue is shoveled the inside in the hopper 42 of 52 side of conveyer belt in shaft bottom by construction personnel,
Realize blanking when being driven the conveyer belt 52 of top with the hopper 42 of waste residue, soil is fallen toward under described
2 blanking of flitch, has raised operating rate.
The charge mechanism 4 further includes push plate 45, sliding rail 46, sliding block 47 and spring 48, the interior top of several hoppers 42
Portion, the opposite welding sliding rail 46 of inner top, the internal slide of the sliding rail 46 connect the sliding block 47, the sliding block 47 and institute
State and the spring 48 be installed between sliding rail 46, the push plate 45 is welded between two sliding blocks 47, in blanking the push plate 45 by
Gravity in itself realizes the push plate 45 to 44 direction of feed inlet movement, and the sliding block 47 is in the sliding rail 46
Portion's sliding further realizes the spring and opens 48, keeps blanking more comprehensive.
The feed hopper 43 structure funnel-shaped, and the section of the hopper 42 of 43 one side wall of the feed hopper is trapezoidal
Structure facilitates feeding, and surface feeding is splashed, and has saved the time of feeding.
The trapezoidal structure in section of the sliding block 47 inside the sliding rail 46, described between two sliding blocks 47 push away
The arc-shaped structure of plate 45 scrapes the inside soil of the sliding rail 46 when the sliding block 47 slides, and it is stifled to avoid the sliding rail 46
Plug.
The working principle of bored pile construction cleaning waste slag equipment provided by the utility model is as follows: will bore bored concrete pile
Well be drilled after fix the tops of two mounting plates 53 with lifting machine, overall structure is put into using lifting machine and is accomplished fluently
Inside well, worker enter back into inside construct, using tool by waste residue shovel to the inside of the feed hopper 43, it is described
The section of feed hopper 43 is conducive to blanking in funnel-shaped structure, and further waste residue flows to the hopper 42 from the feed hopper 43
Inside, the spring 48 is shunk at this time, and the sliding block 47 is slided away from 44 direction of feed inlet, and the push plate 45 is away from described
The sliding of 44 direction of feed inlet;The motor 3 is powered on, one of them described live-roller 51 is realized and rotates, further
Realize that the conveyer belt 52 rotates, since the distance between two described fixed links 41 of the side wall of the conveyer belt 52 are greater than two
The distance between a described position-arresting disk 54, the circulation of the hopper 42 for realizing the trapezoidal structure in several sections is dynamic, construction personnel
In shaft bottom by waste residue shovel in the inside of the hopper 42 of 52 side of conveyer belt, when the hopper 42 with waste residue is by band
Blanking is realized when moving the conveyer belt 52 of top, soil is fallen toward 2 blanking of blanking plate, and the bullet after material is finished down
Spring 48 opens, and the sliding block 47 is mobile to 44 direction of feed inlet, and the push plate 45 of arc-shaped structure resets, and has raised work
Make speed, carries out feeding again after the completion of batch turning, improve work efficiency, safe construction.
Compared with the relevant technologies, bored pile construction provided by the utility model cleaning waste slag equipment has as follows
The utility model has the advantages that
The utility model provides a kind of bored pile construction cleaning waste slag equipment, and the motor 3 is powered on, real
One of them described live-roller 51 is showed to rotate, has further realized that the conveyer belt 52 rotates, due to the conveyer belt 52
The distance between described fixed link 41 of two of side wall is greater than the distance between two described position-arresting disks 54, realizes several described
The circulation of hopper 42 is dynamic, and waste residue is shoveled the inside in the hopper 42 of 52 side of conveyer belt in shaft bottom by construction personnel, works as band
There is the hopper 42 of waste residue to realize blanking when being driven the conveyer belt 52 of top, soil is fallen toward the blanking plate
2 blankings, the spring 48 opens after being finished down material, and the sliding block 47 is mobile to 44 direction of feed inlet, and the push plate 45 resets
Feeding again.
The above description is only the embodiments of the present invention, and therefore it does not limit the scope of the patent of the utility model, all
Equivalent structure or equivalent flow shift made based on the specification and figures of the utility model, is applied directly or indirectly in
Other relevant technical fields, are also included in the patent protection scope of the utility model.
Claims (6)
1. a kind of bored pile construction cleaning waste slag equipment characterized by comprising
Blanking plate;
Supporting mechanism, the side of the supporting mechanism welding and the blanking plate;
Driving mechanism, the driving mechanism are installed on the top of the supporting mechanism;
Motor, the motor are installed on the side wall of the driving mechanism, are rotatablely connected between the motor and the driving mechanism;
Charge mechanism, the charge mechanism are mounted equidistant in the side wall of the driving mechanism, the charge mechanism include fixed link,
Hopper, feed hopper and feed inlet, the side wall of the driving mechanism are equidistantly fixedly connected with the fixed link, several fixed link back
The hopper is welded in one end from the driving mechanism, and the sidewall weld away from the fixed link of the hopper has the charging
Bucket, the feed hopper open up the feed inlet away from one end of the fixed link.
2. bored pile construction according to claim 1 cleaning waste slag equipment, which is characterized in that the supporting mechanism
Including bracket, the first fixed frame, connecting column and the second fixed frame, the driving mechanism is installed between four brackets, and four
The bottom of a bracket is welded in the top that cross section is rectangle first fixed frame of structure, first fixed frame
Bottom four corners at the welding connecting column, the bottom welding cross section of four connecting columns is rectangle described the of structure
Two fixed frames, the area of second fixed frame are greater than the area of first fixed frame, and the blanking plate is welded in two groups of institutes
It states between bracket.
3. bored pile construction according to claim 2 cleaning waste slag equipment, which is characterized in that the driving machine root
Include live-roller, conveyer belt, mounting plate, position-arresting disk and stiffening plate according to cast-in-situ bored pile structure described in claim 1, is located at described
Four brackets of edge are oppositely arranged two-by-two at the top of first fixed frame, and the peace is welded between bracket described in two of them
Loading board welds the mounting plate between bracket described in another two, and the bottom of two mounting plates is equipped with and bracket described in two groups
The inside of the welding stiffening plate, two mounting plates and first fixed frame is rotatably connected to the biography respectively
Dynamic roller, conveyer belt described in the surface wrap of two live-rollers, the opposite flank of two stiffening plates be sequentially connected with
The position-arresting disk that the conveyer belt contradicts, between less than two fixed links of the distance between two described position-arresting disks away from
From, and the length of the fixed link is greater than the diameter of the position-arresting disk, the motor with it is described positioned at the mounting plate side
It is rotatablely connected between live-roller.
4. bored pile construction according to claim 1 cleaning waste slag equipment, which is characterized in that the charge mechanism
It further include push plate, sliding rail, sliding block and spring, inner top, the inner top of several hoppers are opposite to weld the sliding rail, the cunning
The internal slide of rail connects the sliding block, and the spring is installed between the sliding block and the sliding rail, is welded between two sliding blocks
The push plate.
5. bored pile construction according to claim 1 cleaning waste slag equipment, which is characterized in that the feed hopper is in
Funnel-shaped structure, and the trapezoidal structure in section of the hopper of the feed hopper one side wall.
6. bored pile construction according to claim 4 cleaning waste slag equipment, which is characterized in that inside the sliding rail
The sliding block the trapezoidal structure in section, the arc-shaped structure of the push plate between two sliding blocks.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822211904.5U CN209429124U (en) | 2018-12-27 | 2018-12-27 | A kind of bored pile construction cleaning waste slag equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822211904.5U CN209429124U (en) | 2018-12-27 | 2018-12-27 | A kind of bored pile construction cleaning waste slag equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209429124U true CN209429124U (en) | 2019-09-24 |
Family
ID=67973978
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822211904.5U Active CN209429124U (en) | 2018-12-27 | 2018-12-27 | A kind of bored pile construction cleaning waste slag equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209429124U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116752538A (en) * | 2023-08-23 | 2023-09-15 | 济南新芯微电子有限公司 | Automatic drilling of clearance hole soil fills stake mechanism |
-
2018
- 2018-12-27 CN CN201822211904.5U patent/CN209429124U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116752538A (en) * | 2023-08-23 | 2023-09-15 | 济南新芯微电子有限公司 | Automatic drilling of clearance hole soil fills stake mechanism |
CN116752538B (en) * | 2023-08-23 | 2023-12-08 | 济南新芯微电子有限公司 | Automatic drilling of clearance hole soil fills stake mechanism |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106276056B (en) | Multi-segmental combined type earthwork perpendicular lifting apparatus | |
CN107288171B (en) | Bore and prop integral type shaft pore-forming device | |
CN113006042B (en) | Construction process for reinforcing foundation of large hydraulic structure on construction waste land layer | |
CN111926804A (en) | Grouting device for building pile foundation construction | |
CN109680953B (en) | Discharging and mixing vibrating device for self-moving regenerated block | |
JPS62233328A (en) | Method and apparatus for setting retaining wall by excavator | |
CN209429124U (en) | A kind of bored pile construction cleaning waste slag equipment | |
CN111395437A (en) | Deep foundation pit earthwork transportation device and construction method | |
CN113152547B (en) | Rapid foundation pit excavation equipment and excavation method | |
CN206844193U (en) | Bore support integral type pile hole forming device | |
CN202389890U (en) | Drop-preventing chain type bucket elevator | |
CN210434599U (en) | Building waste crushing treatment device | |
CN217810999U (en) | Bearing pile machine | |
CN213770543U (en) | Environment-friendly transfer box | |
CN103061343A (en) | Automatic discharge hopper | |
CN214993858U (en) | Hole digging pile lifting and unearthing device | |
CN213171212U (en) | A hoisting apparatus for building engineering | |
CN210164190U (en) | Building site floor rubbish clearance passageway | |
CN210888941U (en) | A prevent swift current sediment hole blocking device for construction of tunnel shaft raise-shaft method | |
CN110217607B (en) | Bucket-wheel stacker-reclaimer | |
EP1614813A1 (en) | Screw equipment for digging to construct diaphragms | |
CN205471247U (en) | Lifting machine for building engineering | |
CN205637600U (en) | High fall concrete grouting machine | |
CN215291526U (en) | Concrete pouring device | |
CN220334633U (en) | Frame type artificial hole digging pile lifting frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |