CN209413162U - A kind of guarded drainage daylighting roof construction - Google Patents

A kind of guarded drainage daylighting roof construction Download PDF

Info

Publication number
CN209413162U
CN209413162U CN201822155265.5U CN201822155265U CN209413162U CN 209413162 U CN209413162 U CN 209413162U CN 201822155265 U CN201822155265 U CN 201822155265U CN 209413162 U CN209413162 U CN 209413162U
Authority
CN
China
Prior art keywords
munnion
horizontal frame
main body
boss
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822155265.5U
Other languages
Chinese (zh)
Inventor
赵庆勇
陈晓颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Yuanda Aluminium Industry Group Co Ltd
Original Assignee
Shenyang Yuanda Aluminium Industry Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Yuanda Aluminium Industry Group Co Ltd filed Critical Shenyang Yuanda Aluminium Industry Group Co Ltd
Priority to CN201822155265.5U priority Critical patent/CN209413162U/en
Application granted granted Critical
Publication of CN209413162U publication Critical patent/CN209413162U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

A kind of guarded drainage daylighting roof construction, including support steel structure, munnion, horizontal frame, pad frame and light transmission plane materiel;The horizontal frame includes horizontal frame main body, support portion, horizontal frame boss, further includes the horizontal frame rhone made of the enclosing of part that is connected as support portion, main body, horizontal frame boss;The munnion includes munnion main body, support portion, and centre is equipped with munnion boss above main body, further includes the lower water slot made of the enclosing of part that is connected as support portion, main body, munnion boss;Buckle is snapped in munnion main body two sides.The utility model forms the through drainage channel of ladder by vertical and horizontal frame section, when first of sealant fails, it can be promptly by the rhone of the water guiding munnion in horizontal frame, finally under the action of potential energy, the drainage hole connecting with the external world being arranged along the inclined direction of munnion from lowest part flows out lighting top system, successfully solves lighting roof seepy question;And the convenience of installation is substantially increased, improve the aesthetics of lighting roof entirety.

Description

A kind of guarded drainage daylighting roof construction
Technical field
The utility model relates to glass curtain wall technical field, more particularly to a kind of guarded drainage daylighting roof construction, collect waterproof, Drain function is in one, especially suitable for requiring waterproofness relatively high daylighting roof construction.
Background technique
Lighting roof is also transparent roof, is made of light transmission plane materiel and support construction, is a complete independent structure system System, is the important component of building curtain wall.With the continuous enhancing of energy conservation and environmental consciousness, people's aesthetic level is constantly mentioned Height, lighting roof are increasingly appearing in modern designs, because it not only successfully solves sunshine and daylighting problem, are also existed The performance space that designer is bigger has been given in shape-designing, and becomes a main means for adjusting internal ambience.Due to adopting Spire is located at top of building, and for vertical curtain wall system, a possibility that rain-impact power is big, ponding accumulated snow is big, So waterproof is designed to key points and difficulties in the design of lighting roof.Current most of lighting roofs are sealed using wet process, merely Sealant between light transmission plane materiel carries out waterproof.But with the influence of time and illumination, sealant can continuous ageing failure, Cause lighting roof leak.
Summary of the invention
The purpose of the utility model is to provide a kind of daylighting roof constructions of guarded drainage, and the structure is in first of sealant aging When failure, also the water for entering lighting roof can successfully be emitted, it is indoor without flowing to, to solve in the prior art The problem of.
The utility model is achieved by the following technical solution: a kind of guarded drainage daylighting roof construction, including supporting steel knot Structure, the munnion matched with supporting steel, the horizontal frame matched with munnion, the pad frame being separately positioned on horizontal frame and munnion and with The light transmission plane materiel that pad frame matches, is equipped with sealant between adjacent light transmission plane materiel;
The horizontal frame includes the horizontal frame main body of hollow rectangle, and two sides are equipped with the support for being used to support pad frame above main body Portion, it is intermediate above main body to be equipped with horizontal frame boss, it further include that the part that is connected by support portion, main body, horizontal frame boss encloses Horizontal frame rhone;
The munnion includes the munnion main body of π font, and two sides are equipped with the branch for being used to support pad frame above munnion main body Support part, it is intermediate above main body to be equipped with munnion boss, further include be connected by support portion, main body, munnion boss part enclose and At lower water slot;Buckle is snapped in munnion main body two sides;
The pad frame is C-shaped, and lower end outside is equipped with the adhesive tape groove for installing adhesive tape, pads frame by being screwed on boss Pressing plate is crimped on above support portion;
The opening matched with the rhone of horizontal frame is equipped on munnion, horizontal frame rhone is beyond horizontal frame main body and extends to Above lower water slot;
The bottom level of the horizontal frame rhone is higher than lower water slot.
Further: the support portion is hollow cavity.
Further: the support steel structure is obliquely installed.
Further: the vertical portion of the munnion main body is vertically equipped with strip hole, sets in the outside side of vertical portion There is zigzag alveolus.
Further: the support steel structure is equipped with support chip, and support chip is equipped with circular hole, and fixing bolt passes through circular hole Supporting steel and munnion are fixed with strip hole, grooved metal gasket is equipped in the two sides that bolt is located at munnion main body, on grooved metal gasket Equipped with the serrate slot matched with zigzag alveolus.
The beneficial effects of the utility model are: the through drainage channel of ladder is formed by vertical and horizontal frame section, first It, can be promptly by the rhone of the water guiding munnion in horizontal frame, finally under the action of potential energy, along perpendicular when road sealant fails The drainage hole connecting with the external world that the direction of frame inclining is arranged from lowest part flows out lighting top system, successfully solves lighting roof Seepy question;Munnion is designed to the type of attachment cooperated with grooved metal gasket, easily solves height adjustment, installation, civil engineering The problems such as error, preferably realizes drainage grade;And design two sides and block buckle, the convenience of installation is substantially increased, and subtract Fastener is exposed less, improves the aesthetics of lighting roof entirety.
Detailed description of the invention
Fig. 1 is the horizontal frame cross-sectional view of the utility model structure;
Fig. 2 is the munnion cross-sectional view of the utility model structure;
Fig. 3 is part daylighting top frame schematic perspective view;
Fig. 4 is that the schematic diagram of internal structure of Fig. 3 and water flow move towards figure.
1. support steel structure of number explanation in figure, 2. buckles, 3. munnions, 4. pad frames, 5. light transmission plane materiels, 6. sealants, 7. Structure glue, 8. horizontal frames, 9. grooved metal gaskets, 10. adhesive tape, 11. pressing plates, 12. support portions, 13. munnion boss, 14. lower waters Slot, 15. horizontal frame boss, 16. horizontal frame rhones, 17. strip holes, 18. zigzag alveolus.
Specific embodiment
It is described in further details below with reference to Fig. 1-4 pairs of the utility model.
A kind of guarded drainage daylighting roof construction matches including support steel structure 1, the munnion matched with supporting steel 3, with munnion The horizontal frame 8 closed, the pad frame 4 that is separately positioned on horizontal frame and munnion and with the light transmission plane materiel 5 that pads frame and match, adjacent saturating Sealant 6 is equipped between smooth surface material;
The horizontal frame 8 includes the hollow horizontal frame main body of rectangle, and two sides are equipped with the support for being used to support pad frame above main body Portion 12, it is intermediate above main body to be equipped with horizontal frame boss 15, it further include the part enclosing that is connected by support portion, main body, horizontal frame boss Made of horizontal frame rhone 16;
The munnion includes the munnion main body of π font, and two sides are equipped with the branch for being used to support pad frame above munnion main body Support part 12, it is intermediate above main body to be equipped with munnion boss 13, it further include being connected partially to enclose by support portion, main body, munnion boss Lower water slot 14 made of conjunction;Buckle 2 is snapped in munnion main body two sides;
Horizontal frame and/or lower water slot are an open flute profile, and bottom is a part of horizontal frame and/or munnion main body, slot Two sides be respectively support portion and boss a part, three parts are connected to form a groove, and the rhone of munnion is elongated setting, The draining channel opening of horizontal frame is above lower water slot;
The pad frame is C-shaped (or perhaps rectangle open at one end), and lower end outside is equipped with the glue for installing adhesive tape 10 Bar groove, pad frame are crimped on above support portion by the pressing plate 11 being screwed on boss, and due to the presence of adhesive tape, crimping is soft Property connection, can effective shock and reduce noise;Adjacent two horizontal frame and munnion enclose a rectangle, and light transmission plane materiel and rectangular frame are logical Cross the mating connection of structure glue 7;Sealant is equipped between adjacent light transmission plane materiel;
The opening matched with the rhone of horizontal frame, horizontal frame draining are equipped on the munnion for the position that horizontal frame intersects with munnion Slot is extend into munnion inside beyond horizontal frame main body and from the opening, and horizontal frame draining channel opening makes cross above lower water slot Ponding in frame rhone is easily injected into lower water slot;
The bottom level of the horizontal frame rhone is higher than lower water trench bottom.
Preferred: the support portion is hollow cavity, internal filling with sealant.
Preferred: the support steel structure is obliquely installed, and is obliquely installed lower water slot equally, convenient for the discharge of water.
Preferred: the vertical portion of the munnion main body is vertically equipped with strip hole 17, sets in the outside side of vertical portion There is zigzag alveolus 18.
Preferred: the support steel structure is equipped with support chip, and support chip is equipped with circular hole, fixing bolt by circular hole and Strip hole fixes supporting steel and munnion, is equipped with grooved metal gasket 9 in the two sides that bolt is located at munnion main body, sets on grooved metal gasket There is the serrate slot matched with zigzag alveolus.
The utility model carries out waterproof by first of sealant between light transmission plane materiel;Pass through the height formed between vertical and horizontal frame To munnion, daylighting roof construction is discharged finally by the munnion with tilt angle in water flow in horizontal frame by degree difference.
The installation process of the utility model structure is as follows: first by the support steel structure of lighting roof 1, according to the gradient of ridge Direction arranges, and strip hole is arranged in the tooth form position of aluminium munnion 3, is cooperated by the circular hole and slotted hole of grooved metal gasket 9, is adjusted It after height and position, is connect with fastener with support steel structure 1, meets the requirement of lighting roof tilt angle.Finally munnion buckle 2 is pacified Install it is complete, to complete the hidden work of fastener.
When horizontal frame 8 is connect with munnion 3, the rhone extension of horizontal frame 8 is pressed onto the main body profile wall of munnion 3, is made vertical and horizontal The rhone up and down of frame section forms difference in height, and realizes vertical and horizontal rhone perforation, forms the drainage system of independent completion.With When first of waterproof gasket cement between convenient light transmission plane materiel fails, water can be smoothly through horizontal frame rhone and flow to munnion row In sink, daylighting roof construction is discharged eventually by the inclined angle of munnion 8, forms second effectively drainage system.
Using the form at 45 degree of group angles, vertical and horizontal pad frame 4 is combined, then passes through the pressing plate 11 and lighting roof of step-by-step arrangement Vertical and horizontal frame connection, in order to realize this type of attachment, therefore is designed to a boss structure for vertical and horizontal frame section section middle, uses It is fixed at fastener and boss, completes the connection of pad frame 4 and lighting roof aluminium keel.And between pad frame 4 and vertical and horizontal frame, if The soft connection for having set adhesive tape 10, not only reduces friction noise, also improves the sealing performance of structure.
It is finally by structure glue 7 that light transmission plane materiel 5 and pad frame 4 is fixed, and with sealant 6 by the gap sealing of light transmission plane materiel It is intact, form first of sealing system of lighting roof and outdoor contact.So far, anti-, row's dual fail-safe the lighting roof of complete set Structural system is installed.
In the utility model structure, especially suitable for the position with certain tilt angle.Lighting roof is generally divided into inclination Lighting roof and horizontal lighting roof, but certain drainage grade will be also arranged in even horizontal lighting roof.The utility model be exactly with It is designed based on horizontal lighting roof with certain drainage grade.Lighting roof support construction, edge are arranged by waterproof slope requirement first Gradient direction arrange lighting roof aluminium munnion elongatedly, in order to which the gradient is better achieved, prevent installation, civil engineering of steel pipe etc. accidentally The position that aluminium munnion is connect with support construction is designed to the profile section with zigzag alveolus, aluminium munnion is processed into perpendicular by difference To strip hole, cooperate with circular hole grooved metal gasket is processed into, be fixedly connected by fastener, adjusts installation height to reach vertical direction The purpose of degree.At the same time, the aluminium munnion two sides of lighting roof use the form of detachable buckle, complete in the fixed adjustment of fastener Afterwards, buckle is installed, the internal joint detail progress such as fastener is hidden, substantially increase aesthetics.
In order to realize the connection between lighting roof pad frame and the vertical and horizontal frame of lighting roof, the utility model is designed for use with segmentation pressure The type of attachment of plate, thus in one boss structure of the profile section medium design of vertical and horizontal frame, to facilitate the connection of fastener, Therefore two natural drainage channels are formd in boss two sides, the munnion of lighting roof is elongated, the general in the connection of vertical and horizontal frame The epicoele extension of horizontal frame is pressed onto the profile wall of munnion, plays lateral rhone directly with the rhone connection of munnion Come, and the rhone of horizontal frame forms difference of height, if first between plane materiel and plane materiel is close on the rhone of munnion When sealing is failed, designed by the step type of rhone, water in horizontal frame can be made to flow into the rhone of munnion, and munnion because To there is inclined angle, the potential energy that water flows downward is gathered, has easily been exported, will not enter the room.

Claims (5)

1. a kind of guarded drainage daylighting roof construction, including support steel structure, the munnion matched with supporting steel, match with munnion Horizontal frame, the pad frame being separately positioned on horizontal frame and munnion and the light transmission plane materiel matched with pad frame, in adjacent light transmission plane materiel Between be equipped with sealant;It is characterized by:
The horizontal frame includes the horizontal frame main body of hollow rectangle, and two sides are equipped with the support portion for being used to support pad frame above main body, It is intermediate above main body to be equipped with horizontal frame boss, it further include the horizontal frame made of the enclosing of part that is connected as support portion, main body, horizontal frame boss Rhone;
The munnion includes the munnion main body of π font, and two sides are equipped with the support portion for being used to support pad frame above munnion main body, It is intermediate above main body to be equipped with munnion boss, it further include being connected made of part encloses to erect as support portion, main body, munnion boss Frame rhone;Buckle is snapped in munnion main body two sides;
The pad frame is C-shaped, and lower end outside is equipped with adhesive tape groove for installing adhesive tape, and pad frame passes through the pressing plate that is screwed on boss It is crimped on above support portion;
The opening matched with the rhone of horizontal frame is equipped on munnion, horizontal frame rhone is beyond horizontal frame main body and extends to munnion Above rhone;
The bottom level of the horizontal frame rhone is higher than lower water slot.
2. guarded drainage daylighting roof construction according to claim 1, it is characterised in that: the support portion is hollow chamber Body.
3. guarded drainage daylighting roof construction according to claim 1, it is characterised in that: the support steel structure is obliquely installed.
4. guarded drainage daylighting roof construction according to claim 1, it is characterised in that: the vertical portion of the munnion main body is perpendicular To strip hole is equipped with, zigzag alveolus is equipped in the outside side of vertical portion.
5. guarded drainage daylighting roof construction according to claim 4, it is characterised in that: the support steel structure is equipped with support Piece, support chip are equipped with circular hole, and fixing bolt is fixed supporting steel and munnion by circular hole and strip hole, are located at munnion in bolt The two sides of main body are equipped with grooved metal gasket, and the serrate slot matched with zigzag alveolus is equipped on grooved metal gasket.
CN201822155265.5U 2018-12-21 2018-12-21 A kind of guarded drainage daylighting roof construction Active CN209413162U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822155265.5U CN209413162U (en) 2018-12-21 2018-12-21 A kind of guarded drainage daylighting roof construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822155265.5U CN209413162U (en) 2018-12-21 2018-12-21 A kind of guarded drainage daylighting roof construction

Publications (1)

Publication Number Publication Date
CN209413162U true CN209413162U (en) 2019-09-20

Family

ID=67939515

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822155265.5U Active CN209413162U (en) 2018-12-21 2018-12-21 A kind of guarded drainage daylighting roof construction

Country Status (1)

Country Link
CN (1) CN209413162U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111980266A (en) * 2020-07-23 2020-11-24 中建深圳装饰有限公司 Semi-unit type daylighting roof glass curtain wall installation system and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111980266A (en) * 2020-07-23 2020-11-24 中建深圳装饰有限公司 Semi-unit type daylighting roof glass curtain wall installation system and construction method thereof

Similar Documents

Publication Publication Date Title
EP2752531B1 (en) A gutter-like flashing member and a roof structure including such a flashing member
CN209025335U (en) New waterproof Photovoltaic Building Integration device
CN209891586U (en) Waterproof external member
CN209413162U (en) A kind of guarded drainage daylighting roof construction
CN206289809U (en) A kind of lighting roof curtain wall
CN205100441U (en) Interior drainage daylighting top curtain system
CN208280472U (en) A kind of Photovoltaic Building Integration electricity generation system discharge structure
CN111173208A (en) Skylight system with built-in drainage structure
CN110439191A (en) A kind of new type roof waterproof construction
CN216196121U (en) Integrative roofing of photovoltaic building
JP2011099249A (en) Roof structure
CN211341455U (en) BIPV waterproof system
CN207944850U (en) Water-tight device based on steel building metal wall surface door and window
CN210780636U (en) Full-structure waterproof photovoltaic support
CN204626810U (en) Rain shade
CN208280480U (en) A kind of Photovoltaic Building Integration electricity generation system briquetting
CN210033189U (en) Door and window hidden drainage structure and hidden drainage adapter frame section bar
CN114362644A (en) Water guide supporting system for frameless photovoltaic assembly
CN203238825U (en) Daylighting plate flashing structure and flashing plate thereof
CN209308295U (en) Skylight
CN208363919U (en) Aluminium alloy windowsill apron flashing
JP2022087880A (en) Eaves structure
CN208571986U (en) A kind of photovoltaic generating system
CN216196120U (en) Support for photovoltaic building integrated roof
CN216196119U (en) Photovoltaic building integrated roof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant