CN209399384U - A kind of boiler that heat utilization rate is high - Google Patents

A kind of boiler that heat utilization rate is high Download PDF

Info

Publication number
CN209399384U
CN209399384U CN201822121555.8U CN201822121555U CN209399384U CN 209399384 U CN209399384 U CN 209399384U CN 201822121555 U CN201822121555 U CN 201822121555U CN 209399384 U CN209399384 U CN 209399384U
Authority
CN
China
Prior art keywords
flue
heater box
boiler
fixed
utilization rate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822121555.8U
Other languages
Chinese (zh)
Inventor
王文骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Anmai Industrial Automation Technology Co Ltd
Original Assignee
Xian Anmai Industrial Automation Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Anmai Industrial Automation Technology Co Ltd filed Critical Xian Anmai Industrial Automation Technology Co Ltd
Priority to CN201822121555.8U priority Critical patent/CN209399384U/en
Application granted granted Critical
Publication of CN209399384U publication Critical patent/CN209399384U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Processing Of Solid Wastes (AREA)
  • Gasification And Melting Of Waste (AREA)
  • Incineration Of Waste (AREA)

Abstract

The utility model is a kind of boiler that heat utilization rate is high, including pedestal, heater box, feed inlet, ash handling equipment, sieve grey net and ash cleaning slot, heater box is fixedly installed with above the pedestal, the heater box outer left side is fixed with feed inlet, the heater box bottom is fixedly installed with ash handling equipment, it is fixed with combustion-supporting at the top of the heater box, is fixed with lateral flue above the heater box.The high boiler of this heat utilization rate passes through the ash handling equipment being equipped with, it can use the grey net of sieve to be effectively treated with the dust after ash cleaning slot material combusting, pass through the left flue and right flue being equipped with, the heat of flue gas is absorbed using heat-sink shell and insulating layer, reduce thermal loss, the temperature of steam chest is detected by the temperature sensor being equipped with, when too high or too low for temperature, it is transferred data on temperature display by the control device being equipped with, to which operator is adjusted, keep the temperature of furnace interior constant.

Description

A kind of boiler that heat utilization rate is high
Technical field
The utility model relates to boiler plant technical field, specially a kind of boiler that heat utilization rate is high.
Background technique
Boiler is the mechanical equipment for water being heated as using the thermal energy of fuel or other energy hot water or steam.Boiler is A kind of energy conversion, the energy inputted to boiler have the forms such as the thermal energy of chemical energy in fuel, electric energy, high-temperature flue gas, And pass through boiler and convert, output has steam, high-temperature water or the organic heat carrier of certain thermal energy outward.
The utilization of the energy at present and the protection of environment, Main Natural Gas, coal gas, device in Gas, biogas are main fuel;But Biomass fuel, the boiler utilization of the New-type fuels such as semi-coke is also more and more extensive, in the past, proposition have be configured to comprising shell and It is configured at multiple water pipes of the inside of the shell and supply is heated and generated the boiler of steam to the water of multiple water pipes. As such boiler, heat utilization ratio is not high, causes energy waste, and encourages to be inconvenient to control when in use, is not easy to grasp Make, therefore, these problems are urgently to be resolved.
Utility model content
In view of the deficienciess of the prior art, the utility model aim is to provide a kind of pot that heat utilization rate is high Furnace, to improve the problems mentioned above in the background art, design is scientific and reasonable for the utility model, and heat utilization ratio is high, Er Qiefang Just it controls, it is easy to operate.
In order to improve the above problem, the utility model is to embody by the following technical solutions: a kind of heat benefit With the high boiler of rate, including the grey net of pedestal, heater box, feed inlet, ash handling equipment, sieve, ash cleaning slot, combustion-supporting and lateral cigarette Road, the pedestal top are fixedly installed with heater box, and the heater box outer left side is fixed with feed inlet, the heater box bottom Portion is fixedly installed with ash handling equipment, and combustion-supporting is fixed at the top of the heater box, is fixed with transverse direction above the heater box Flue, the transverse direction flue left end are fixedly connected with left flue, and the transverse direction flue right end is fixedly connected with right flue, the cross To being fixed with heating water tank above flue, the heating water tank upper inside is provided with several ventholes, in the heating water tank Side is fixed with steam chest, and temperature sensor is fixedly installed with above the steam chest, and fixation is set above the temperature sensor There is control device, is fixedly installed with temperature display inside the control device.
As a kind of preferred embodiment of the utility model, the ash handling equipment includes sieving grey net and ash cleaning slot, described Grey net is sieved to be fixedly mounted on above ash cleaning slot.
As a kind of preferred embodiment of the utility model, the heating water tank lower left side fixation is provided with water inlet, Fixation is provided with water outlet on the right side of the water inlet.
It is solid close to water tank side inside the left flue and right flue as a kind of preferred embodiment of the utility model Surely it is equipped with heat-sink shell, is fixedly installed with insulating layer on the inside of the heat-sink shell.
As a kind of preferred embodiment of the utility model, PLC controller is equipped with inside the control device.
The utility model has the beneficial effects that a kind of boiler that heat utilization rate is high of the utility model, including pedestal, Heater box, feed inlet, ash handling equipment, sieve grey net, ash cleaning slot, combustion-supporting, lateral flue, left flue, right flue, heating water tank, Venthole, steam chest, heat-sink shell, temperature sensor, control device, temperature display, insulating layer, water inlet, water outlet.
1. the high boiler of this heat utilization rate passes through the ash handling equipment being equipped with, it can use the grey net of sieve and ash cleaning slot be former Dust after material burning is effectively treated, by the left flue and right flue being equipped with, using heat-sink shell and insulating layer to flue gas Heat absorbed, reduce thermal loss.
The temperature of steam chest is detected 2. the high boiler of this heat utilization rate passes through the temperature sensor being equipped with, It when too high or too low for temperature, is transferred data on temperature display by the control device being equipped with, so that operator adds To adjust, keep the temperature of furnace interior constant.
The utility model compensates for the shortcoming in background technique to a certain extent.
Detailed description of the invention
Fig. 1 is a kind of overall structure diagram for the boiler that heat utilization rate is high of the utility model;
Fig. 2 is a kind of partial structure diagram for the boiler that heat utilization rate is high of the utility model;
In figure: 1, pedestal, 2, heater box, 3, feed inlet, 4, ash handling equipment, 401, sieve grey net, 402, ash cleaning slot, 5, combustion-supporting Device, 6, lateral flue, 7, left flue, 8, right flue, 9, heating water tank, 10, venthole, 11, steam chest, 12, heat-sink shell, 13, Temperature sensor, 14, control device, 15, temperature display, 16, insulating layer, 17, water inlet, 18, water outlet.
Specific embodiment
To be easy to understand the technical means, creative features, achievement of purpose, and effectiveness of the utility model, below In conjunction with specific embodiment, the utility model is further described.
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment, based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1 to Fig. 2 is please referred to, the utility model provides a kind of technical solution: a kind of boiler that heat utilization rate is high, Including pedestal 1, heater box 2, feed inlet 3, ash handling equipment 4, grey net 401, ash cleaning slot 402, combustion-supporting 5 and lateral flue 6 are sieved, Heater box 2 is fixedly installed with above the pedestal 1,2 outer left side of heater box is fixed with feed inlet 3, the heater box 2 Bottom is fixedly installed with ash handling equipment 4, and combustion-supporting 5 is fixed at the top of the heater box 2, and fixation is set above the heater box 2 There is lateral flue 6,6 left end of the transverse direction flue is fixedly connected with left flue 7, and transverse direction 7 right end of flue is fixedly connected with the right side Flue 8, it is described transverse direction flue 7 above be fixed with heating water tank 9,9 upper inside of heating water tank is provided with several ventholes 10, steam chest 11 is fixed with above the heating water tank 9, is fixedly installed with temperature sensor 13 above the steam chest 11, It is fixed with control device 14 above the temperature sensor 13, is fixedly installed with temperature display inside the control device 14 15。
Working principle: the high boiler of heat utilization rate when in use, by the ash handling equipment 4 being equipped with, can use Grey net 401 is sieved to be effectively treated with the dust after 402 material combusting of ash cleaning slot, by the left flue 7 and right flue 8 being equipped with, It is absorbed using heat-sink shell 12 and heat of the insulating layer 12 to flue gas, reduces thermal loss, pass through the temperature sensor being equipped with The temperature of 13 pairs of steam chests 11 detects, and when too high or too low for temperature, is transmitted data by the control device 14 being equipped with Onto temperature display 15, so that operator is adjusted, keep the temperature of furnace interior constant.
As a kind of preferred embodiment of the utility model, the ash handling equipment 4 includes sieving grey net 401 and ash cleaning slot 402, the grey net 401 of the sieve is fixedly mounted on 402 top of ash cleaning slot.
As a kind of preferred embodiment of the utility model, 9 lower left side of the heating water tank fixation is provided with water inlet 17, fixation is provided with water outlet 18 on the right side of the water inlet 17.
As a kind of preferred embodiment of the utility model, close to water tank side inside the left flue 7 and right flue 8 It is fixed with heat-sink shell 12, is fixedly installed with insulating layer 16 on the inside of the heat-sink shell 12.
As a kind of preferred embodiment of the utility model, PLC controller is equipped with inside the control device 14.
The utility model main feature: the high boiler of this heat utilization rate passes through the ash handling equipment 4, Ke Yili being equipped with It is effectively treated with grey net 401 is sieved with the dust after 402 material combusting of ash cleaning slot, passes through the left flue 7 and right flue being equipped with 8, it is absorbed using heat-sink shell 12 and heat of the insulating layer 12 to flue gas, reduces thermal loss.
The high boiler of this heat utilization rate passes through the temperature sensor 13 being equipped with and examines to the temperature of steam chest 11 It surveys, when too high or too low for temperature, is transferred data on temperature display 15 by the control device 14 being equipped with, to operate Personnel are adjusted, and keep the temperature of furnace interior constant.
The basic principles and main features of the present invention and the advantages of the present invention have been shown and described above, for For those skilled in the art, it is clear that the present invention is not limited to the details of the above exemplary embodiments, and without departing substantially from this In the case where the spirit or essential attributes of utility model, the utility model can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the utility model is by institute Attached claim rather than above description limit, it is intended that will fall within the meaning and scope of the equivalent elements of the claims All changes are embraced therein.It should not treat any reference in the claims as limiting related right It is required that.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (5)

1. a kind of boiler that heat utilization rate is high, including pedestal (1), heater box (2), feed inlet (3), ash handling equipment (4), Sieve grey net (401), ash cleaning slot (402), combustion-supporting (5) and lateral flue (6), it is characterised in that: solid above the pedestal (1) Dingan County is equipped with heater box (2), and heater box (2) outer left side is fixed with feed inlet (3), and heater box (2) bottom is solid Dingan County is equipped with ash handling equipment (4), is fixed with combustion-supporting (5) at the top of the heater box (2), fixed above the heater box (2) Equipped with lateral flue (6), described transverse direction flue (6) left end is fixedly connected with left flue (7), and described transverse direction flue (6) right end is solid Surely it is connected with right flue (8), is fixed with heating water tank (9) above the transverse direction flue (6), the heating water tank (9) is internal Upside is provided with several ventholes (10), is fixed with steam chest (11) above the heating water tank (9), on the steam chest (11) Side is fixedly installed with temperature sensor (13), is fixed with control device (14), the control above the temperature sensor (13) Temperature display (15) are fixedly installed with inside device (14) processed.
2. a kind of boiler that heat utilization rate is high according to claim 1, which is characterized in that the ash handling equipment It (4) include sieving grey net (401) and ash cleaning slot (402), the grey net (401) of the sieve is fixedly mounted on above ash cleaning slot (402).
3. a kind of boiler that heat utilization rate is high according to claim 1, which is characterized in that the heating water tank (9) lower left side fixation is provided with water inlet (17), and fixation is provided with water outlet (18) on the right side of the water inlet (17).
4. a kind of boiler that heat utilization rate is high according to claim 1, which is characterized in that the left flue (7) It is fixed with heat-sink shell (12) with right flue (8) inside close to water tank side, is fixedly installed with guarantor on the inside of the heat-sink shell (12) Warm layer (16).
5. a kind of boiler that heat utilization rate is high according to claim 1, which is characterized in that the control device (14) internal to be equipped with PLC controller.
CN201822121555.8U 2018-12-18 2018-12-18 A kind of boiler that heat utilization rate is high Expired - Fee Related CN209399384U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822121555.8U CN209399384U (en) 2018-12-18 2018-12-18 A kind of boiler that heat utilization rate is high

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822121555.8U CN209399384U (en) 2018-12-18 2018-12-18 A kind of boiler that heat utilization rate is high

Publications (1)

Publication Number Publication Date
CN209399384U true CN209399384U (en) 2019-09-17

Family

ID=67895111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822121555.8U Expired - Fee Related CN209399384U (en) 2018-12-18 2018-12-18 A kind of boiler that heat utilization rate is high

Country Status (1)

Country Link
CN (1) CN209399384U (en)

Similar Documents

Publication Publication Date Title
CN104830377B (en) The combustion and segmented inverting biological charcoal/steam co-producing technology of biomass pyrogenation gasification
CN201885203U (en) Horizontal type internal combustion three-return shell boiler capable of burning biomass, fuel oil or gas
CN103486566A (en) Waste heat utilization system capable of guaranteeing lignite boiler dry output and SCR safe flue gas temperature
CN204648215U (en) Hydrogen Energy is produced and is applied boiler
CN209399384U (en) A kind of boiler that heat utilization rate is high
CN202581245U (en) Gas-fired steam generator
CN108087897A (en) A kind of coal mine light concentration mash gas gas catalytic combustion heat-energy utilizing device
CN207702726U (en) A kind of abundant combustion environmental-friendly energy-saving boiler
CN208275179U (en) A kind of tail gas treatment device of boiler
CN106287669A (en) Hydrogen Energy is produced and applies boiler
CN210831924U (en) Half-boiling combustion rice husk steam boiler
CN108102674A (en) Carbonized by means of superheated steam stove
CN209101550U (en) Biological particles combustion environmental-friendly furnace
CN207186511U (en) A kind of seafood steam cabinet
CN204032282U (en) Energy-conserving and environment-protective retort
CN203744213U (en) Low-heat radiation boiler
CN209706015U (en) A kind of energy-saving steam generating system
CN201599781U (en) Waste-heat boiler for a four-in-one or two-in-one heating furnace of a large continuous reforming device
ITBO20080168A1 (en) SOLAR-THERMAL SYSTEM INTEGRATED WITH A FLUID BED
CN201858631U (en) Combustion boiler of combustible gas containing corrosive material
CN205002102U (en) Boiler with automatically, device packs
CN204923425U (en) High -efficient anti - enamelware pot stove
CN216244366U (en) Natural gas combustion device
CN204648209U (en) Living beings and coal boiler for dual purpose
CN206449618U (en) A kind of efficient waste-heat boiler

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190917