CN209389769U CN201821983948.3U CN201821983948U CN209389769U CN 209389769 U CN209389769 U CN 209389769U CN 201821983948 U CN201821983948 U CN 201821983948U CN 209389769 U CN209389769 U CN 209389769U
Authority
CN
China
Prior art keywords
power supply
battery
power
main working
energy storage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821983948.3U
Other languages
Chinese (zh)
Inventor
李增楠
马自国
赵喆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guoneng Longyuan Environmental Protection Co Ltd
Original Assignee
Beijing Guodian Longyuan Environmental Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Guodian Longyuan Environmental Engineering Co Ltd filed Critical Beijing Guodian Longyuan Environmental Engineering Co Ltd
Priority to CN201821983948.3U priority Critical patent/CN209389769U/en
Application granted granted Critical
Publication of CN209389769U publication Critical patent/CN209389769U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Stand-By Power Supply Arrangements (AREA)

Abstract

The utility model discloses a kind of complete high-voltage energy storage power supply units, including high-tension switch cabinet, main working power and emergency standby power;Main working power is to be connected with long bus out of the electric main of external access high-tension switch cabinet, high-tension switch cabinet, and main working power is connected to long bus;The branch line that multichannel is each power supply for electrical equipment is drawn at long bus;Emergency standby power is battery; battery is mounted in high-tension switch cabinet, and the direct current of battery output is connected to long bus after inverter, output transformer, static switch, output switch, step-up transformer and the first protective switch are transformed into High Level AC Voltage;When normal condition, main working power is power supply for electrical equipment;When having emergency situation, main working power is cut off, battery is automatically engaged, continued as electrical equipment and high-voltage ac power is provided.

Description

Complete high-voltage energy storage power supply unit
Technical field
The utility model belongs to that thermal power plant, substation, height pushes back in workshop and civilian commercial power supply place Road power supply system is specifically related to a kind of complete high-voltage energy storage power supply unit.
Background technique
In thermal power plant, substation, workshop and civilian commercial power supply system, the power supply of Chang Peibei ac high-voltage Equipment draws from generator outlet or at power grid and connects power supply and voltage conversion, is high pressure illumination, communication, electric operator etc. The power supply of Smaller load equipment.Configure Emergent diesel generator, UPS(exchange not power-off device) etc. emergency services equipment, it is disconnected in burst To necessary load equipment power supply when electric situation.
But in practical application, there are still many deficiencies for emergency service equipment, if equipment cost is excessively high, diesel-driven generator starting Overlong time exchanges not power-off device operation and maintenance complexity etc..
Utility model content
The purpose of this utility model is that the current high pressure emergency service equipment cost of solution is excessively high, and diesel-driven generator starts the time It is too long, exchange the technical problem of not power-off device operation and maintenance complexity.
To realize the above purpose of utility model, the utility model provides a kind of complete high-voltage energy storage power supply unit, including height Compress switch cabinet, main working power and emergency standby power;
The main working power is to be connected with length out of the external electric main for accessing the high-tension switch cabinet, high-tension switch cabinet Bus, the main working power are connected to the long bus;Point that multichannel is each power supply for electrical equipment is drawn at the long bus Branch line;
The emergency standby power is battery, and the battery is mounted in the high-tension switch cabinet, the battery The direct current of output turns through inverter, output transformer, static switch, output switch, step-up transformer and the first protective switch The long bus is connected to after becoming High Level AC Voltage;
When normal condition, the main working power is power supply for electrical equipment;When having emergency situation, the master is cut off Working power automatically engages the battery, continues as electrical equipment and provides high-voltage ac power.
Further, battery pack maintenance switch is connected between the battery and the inverter.
Further, the cabinet body of the high-tension switch cabinet is formed by carbon steel, forward and backward to be separately installed with manual maintenance door, Inside is equipped with illuminator and temperature regulating device.
Further, ammeter and/or voltmeter are installed on the long bus and/or each branch line, for supervising Survey power supply operating status.
Further, the battery is connected with battery-detecting instrument, issues alarm signal when the battery exception, Convenient for patrol officer's supervision.
Compared with prior art, the utility model has the beneficial effects that
The utility model operation is simple and convenient, and cost is substantially reduced compared with UPS device, diesel-driven generator, occupied area It significantly reduces, and can quickly put into backup power source, reduce operation and maintenance amount, improve safety and stability grade, and be convenient for group It ships defeated.
Detailed description of the invention
Fig. 1 is the schematic diagram of the utility model one embodiment.
Specific embodiment
Preferred descriptions are made to the utility model in the following with reference to the drawings and specific embodiments.
As shown in Figure 1, the complete high-voltage energy storage power supply unit of the utility model, including high-tension switch cabinet, main working power And emergency standby power;
Main working power is to be connected with long bus out of the electric main of external access high-tension switch cabinet, high-tension switch cabinet, main Working power is connected to long bus;At long bus draw multichannel be each power supply for electrical equipment branch line, u1 as shown in Figure 1, U2 etc., for connecting various practical electrical equipments;
Emergency standby power is battery, and battery is mounted in high-tension switch cabinet, and the direct current of battery output is through inverse Become device, output transformer, static switch, output switch, step-up transformer and the first protective switch (being located in Fig. 1 by upper right side) Long bus is connected to after being transformed into High Level AC Voltage;
When normal condition, main working power is power supply for electrical equipment, and to charge the battery;Emergency situation to be had When, main working power is cut off, battery is automatically engaged, electrical equipment is continued as and high-voltage ac power is provided.
Preferably, battery pack maintenance switch is connected between battery and inverter.
Preferably, the cabinet body of high-tension switch cabinet is formed by carbon steel, forward and backward to be separately installed with manual maintenance door, inside peace Equipped with illuminator and temperature regulating device.
Preferably, ammeter and/or voltmeter are installed on long bus and/or each branch line, for monitoring power supply operation State.
Preferably, battery is connected with battery-detecting instrument, issues alarm signal when battery exception, is convenient for inspection people Member's supervision.
It is always each electricity consumption by main working power in the normal situation of external ac power source when utility model works Equipment power supply, and simultaneously to charge the battery.Main working power by the second protective switch (be located at Fig. 1 in bottom) directly with Bus connection, gives bussed supply.When external communication electricity occurs tripping or when other abnormal emergency cases, by having voltage signal The automatic power-supply switch of detection function, bus is automatically switched to by storage battery power supply.When main working power restores normal When, after patrol officer's safety verification, manual switching is powered to main working power again.
It is enlightenment, through the above description, related work people with the above-mentioned desirable embodiment according to the utility model Member can carry out various changes and amendments in the range of without departing from this item utility model technical idea completely.This item is real It is not limited to the contents of the specification with novel technical scope, it is necessary to its technology is determined according to scope of the claims Property range.

Claims (5)

1. complete high-voltage energy storage power supply unit, which is characterized in that including high-tension switch cabinet, main working power and emergency power electricity Source;
The main working power is to be connected with long bus out of the external alternating current for accessing the high-tension switch cabinet, high-tension switch cabinet, The main working power is connected to the long bus;The branch line that multichannel is each power supply for electrical equipment is drawn at the long bus;
The emergency standby power is battery, and the battery is mounted in the high-tension switch cabinet, the battery output Direct current be transformed into through inverter, output transformer, static switch, output switch, step-up transformer and the first protective switch The long bus is connected to after High Level AC Voltage;
When normal condition, the main working power is power supply for electrical equipment;When having emergency situation, the main work is cut off Power supply automatically engages the battery, continues as electrical equipment and provides high-voltage ac power.
2. complete high-voltage energy storage power supply unit as described in claim 1, which is characterized in that the battery and the inverter Between be connected with battery pack maintenance switch.
3. complete high-voltage energy storage power supply unit as described in claim 1, which is characterized in that the cabinet body of the high-tension switch cabinet by Carbon steel molding, forward and backward to be separately installed with manual maintenance door, inside is equipped with illuminator and temperature regulating device.
4. complete high-voltage energy storage power supply unit as described in claim 1, which is characterized in that the long bus and/or each described Ammeter and/or voltmeter are installed, for monitoring power supply operating status on branch line.
5. complete high-voltage energy storage power supply unit as described in claim 1, which is characterized in that the battery is connected with battery Detector issues alarm signal when the battery exception, supervises convenient for patrol officer.
CN201821983948.3U 2018-11-29 2018-11-29 Complete high-voltage energy storage power supply unit Active CN209389769U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821983948.3U CN209389769U (en) 2018-11-29 2018-11-29 Complete high-voltage energy storage power supply unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821983948.3U CN209389769U (en) 2018-11-29 2018-11-29 Complete high-voltage energy storage power supply unit

Publications (1)

Publication Number Publication Date
CN209389769U true CN209389769U (en) 2019-09-13

Family

ID=67865941

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821983948.3U Active CN209389769U (en) 2018-11-29 2018-11-29 Complete high-voltage energy storage power supply unit

Country Status (1)

Country Link
CN (1) CN209389769U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109309405A (en) * 2018-11-29 2019-02-05 北京国电龙源环保工程有限公司 Complete high-voltage energy storage power supply unit

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109309405A (en) * 2018-11-29 2019-02-05 北京国电龙源环保工程有限公司 Complete high-voltage energy storage power supply unit

Similar Documents

Publication Publication Date Title
CN109455106B (en) Intelligent charging station for electric automobile
CN102035249B (en) Direct current power supply emergency system of transformer substation based on lithium iron battery
CN201109373Y (en) Auxiliary power unit of slow run magnetic suspension train
CN111717052A (en) Common-bus multifunctional mobile energy storage vehicle and control strategy
CN102447298B (en) Mobile intelligent direct current power supply device
CN103204080A (en) Temporary locomotive-drive power supply method and system for electric locomotive during outage
CN103441567A (en) Emergency electrical power supply system and power supply method related to nuclear power station passive system
CN201309445Y (en) Emergency electric power supply vehicle
CN109552096B (en) Charging terminal of intelligent charging station for electric automobile
CN103516045B (en) A kind of booting-self controller method of portable electric power system
CN109367434A (en) A kind of moving type marine integration off-network energy storage for power supply system
CN209389769U (en) Complete high-voltage energy storage power supply unit
CN110932252A (en) Electrical system of direct-current distribution board of pure electric ship and control method
CN209088616U (en) Complete low pressure energy-storage power supplying apparatus
CN201887528U (en) Direct-current power supply emergency system of substation on basis of ion-lithium battery
CN208874350U (en) A kind of standby power supply device and its marine tidal-current energy generator group of marine tidal-current energy generator group
CN109309405A (en) Complete high-voltage energy storage power supply unit
CN109327075A (en) Complete low pressure energy-storage power supplying apparatus
CN109149762A (en) A kind of novel spare emergent power source
CN206023353U (en) A kind of transforming plant DC bus emergency bypass supply unit
CN211405579U (en) Intelligent standby power system of integrated cabinet
CN103904776A (en) Intelligent power distribution room power system
CN209134120U (en) Integrated capacitor charging module
CN206041629U (en) Distribution transformer load record appearance with external electric power storage energy storage equipment
CN105186675A (en) Emergency power source system for electric locomotive

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 100039 room 901, 9 / F, building 1, yard 16, West Fourth Ring Middle Road, Haidian District, Beijing

Patentee after: Guoneng Longyuan environmental protection Co.,Ltd.

Address before: 100039 room 911, 1 building, 16 West Fourth Ring Road, Haidian District, Beijing.

Patentee before: BEIJING GUODIAN LONGYUAN ENVIRONMENTAL ENGINEERING Co.,Ltd.