CN209384619U - A kind of hanging basket device that can be walked safely on foundation pit reinforced concrete - Google Patents

A kind of hanging basket device that can be walked safely on foundation pit reinforced concrete Download PDF

Info

Publication number
CN209384619U
CN209384619U CN201920062928.0U CN201920062928U CN209384619U CN 209384619 U CN209384619 U CN 209384619U CN 201920062928 U CN201920062928 U CN 201920062928U CN 209384619 U CN209384619 U CN 209384619U
Authority
CN
China
Prior art keywords
frame
reinforced concrete
foundation pit
top surface
pit reinforced
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920062928.0U
Other languages
Chinese (zh)
Inventor
俞南均
黄凯
秦亮
李刚柱
杨森
赵昕龙
代先斌
李晓儒
曹阳
屈学斌
李晓坤
黄崇星
毛燕超
高维杰
吴磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Three Bridge And Tunnel Engineering Co Ltd Group
China Railway No 3 Engineering Group Bridge and Tunnel Engineering Co Ltd
Original Assignee
Three Bridge And Tunnel Engineering Co Ltd Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Three Bridge And Tunnel Engineering Co Ltd Group filed Critical Three Bridge And Tunnel Engineering Co Ltd Group
Priority to CN201920062928.0U priority Critical patent/CN209384619U/en
Application granted granted Critical
Publication of CN209384619U publication Critical patent/CN209384619U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model provides a kind of hanging basket device that can be walked safely on foundation pit reinforced concrete, belongs to the technical field of Hanging Basket, including travelling platform and workbench;Travelling platform, which includes the first side, to frame and the second side to the top surface frame of frame and is arranged in orientation pulley of first side to frame, the second side on frame and top surface frame to frame and the second side to frame, the first side of connection;First side is located at the two sides of foundation pit reinforced concrete to frame and the second side to frame;Top surface frame is located at the top surface of foundation pit reinforced concrete;Orientation pulley is resisted against the top surface and two sides of foundation pit reinforced concrete;Workbench is arranged in the first side on frame.The hanging basket device provides workbench for staff, provides safety guarantee for staff.

Description

A kind of hanging basket device that can be walked safely on foundation pit reinforced concrete
Technical field
The utility model relates to the technical field of Hanging Basket, can walk safely on foundation pit reinforced concrete more particularly to a kind of Hanging basket device.
Background technique
In main structure and accessory structure work progress, staff needs to monitor precipitation well water on foundation pit reinforced concrete Position or the printing type face on reinforced concrete, since foundation pit reinforced concrete structural system hangs on fender post after pit earthwork excavation and encloses Between purlin, bottom and periphery are supporting the system that can not be leaned on when facade operation, are needing to prevent staff from falling without impetus It falls, guarantees the life security of staff.
Utility model content
The purpose of this utility model is to provide a kind of hanging basket devices that can be walked safely on foundation pit reinforced concrete, for work Personnel provide workbench, provide safety guarantee for staff.
To achieve the above object, the utility model provides a kind of hanging basket device that can be walked safely on foundation pit reinforced concrete, Including travelling platform and workbench;Travelling platform includes the first side to frame and the second side to frame, the first side of connection to frame Frame and top surface frame from the second side to frame and the first side be set determine to frame, the second side on frame and top surface frame To pulley;First side is located at the two sides of foundation pit reinforced concrete to frame and the second side to frame;Top surface frame is located at foundation pit steel The top surface of muscle concrete;Orientation pulley is resisted against the top surface and two sides of foundation pit reinforced concrete;Workbench is arranged in the first side on frame.
Further, the first side to frame include two the first vertical links for being parallel to foundation pit reinforced concrete side and company Connect the first transverse link of two the first vertical link bottom ends;Second side includes two to frame and is parallel to foundation pit reinforced concrete side The second vertical link and connect two the second vertical link bottom ends the second transverse link;Top surface frame includes being parallel to base It cheats two longitudinal rods of reinforced concrete top surface and connects the third transverse link of two longitudinal rod second ends;Longitudinal rod Second end to frame and is stretched out outside foundation pit reinforced concrete towards the second side, close to the body of rod of second end and the top of the second vertical link It is fixedly connected;Workbench include be fixed in the first vertical link bottom support, be vertically set on bottom support on it is more A vertical rail, the lateral guardrail of the multiple vertical rails of connection, the first vertical link of connection and the first of guardrail be tiltedly elevationally outward Support and the first diagonal brace of connection and the elevationally outward longitudinal bracing of guardrail.
Further, the first side to frame further include the first cross-brace being arranged between two the first vertical links.
Further, top surface frame further includes the second cross-brace being arranged between two longitudinal rods.
Further, top surface frame further includes the second diagonal brace for connecting the first vertical link and longitudinal rod.
Further, bottom support includes the 4th transverse link being oppositely arranged with the first transverse link, is arranged first Multiple shop fixtures connecting rods of transverse link and the 4th transverse link and the backing plate being laid on shop fixtures connecting rod.
The beneficial effects of the utility model are:
Hanging basket device provided by the utility model is mounted on foundation pit reinforced concrete, a staff is located at workbench Interior carry out operation, another staff are located at foundation pit reinforced concrete top surface and push away Hanging Basket along foundation pit reinforced concrete according to job scheduling Device.Above-mentioned hanging basket device provides workbench for staff, improves the monitoring precipitation Well Water Level on foundation pit reinforced concrete Or the problem of printing type face hardly possible, it has ensured the safety of staff, has improved work efficiency, reduced human and material resources and financial resources Waste, safety, efficiently, steadily.
Detailed description of the invention
Fig. 1 is the main view of the hanging basket device provided in this embodiment that can be walked safely on foundation pit reinforced concrete;
Fig. 2 is the right view of hanging basket device shown in Fig. 1;
Fig. 3 is the top view of hanging basket device shown in Fig. 1.
In figure: 1- orients pulley;The first vertical link of 2.1-;The first cross-brace of 2.2-;The second vertical link of 3.1-; 4.1- longitudinal rod;4.2- third transverse link;The second cross-brace of 4.3-;The second diagonal brace of 4.4-;5.1- vertical rail;5.2- Lateral guardrail;The first diagonal brace of 5.3-;5.4- longitudinal bracing;The 4th transverse link of 5.5-;5.6- shop fixtures connecting rod;5.7- backing plate; The foundation pit reinforced concrete of 100-.
Specific embodiment
The present embodiment provides a kind of hanging basket devices that can be walked safely on foundation pit reinforced concrete, including travelling platform and work Platform;Travelling platform includes the first side to frame and the second side to frame, the first side of connection to frame and the second side to frame Top surface frame and orientation pulley 1 of first side to frame, the second side on frame and top surface frame is set;First side is to frame Frame and the second side are located at the two sides of foundation pit reinforced concrete 100 to frame;Top surface frame is located at the top surface of foundation pit reinforced concrete 100; Orientation pulley 1 is resisted against the top surface and two sides of foundation pit reinforced concrete 100;Workbench is arranged in the first side on frame.
Above-mentioned hanging basket device is mounted on foundation pit reinforced concrete 100, a staff, which is located in workbench, to be made Industry, another staff are located at foundation pit reinforced concrete top surface, according to job scheduling, push away hanging basket device along foundation pit reinforced concrete 100. Above-mentioned hanging basket device provides workbench for staff, improve on foundation pit reinforced concrete 100 monitor precipitation Well Water Level or The problem of printing type face hardly possible, has ensured the safety of staff, has improved work efficiency, and reduces human and material resources and financial resources wave Take, safety, efficiently, steadily.
Further, the first side to frame include two the first vertical links 2.1 for being parallel to foundation pit reinforced 100 side of concrete And the first transverse link of two 2.1 bottom ends of the first vertical link of connection;Second side includes two to frame and is parallel to foundation pit Second vertical link 3.1 of 100 side of reinforced concrete and the second transverse link for connecting two 3.1 bottom ends of the second vertical link; Top surface frame includes two longitudinal rods 4.1 second of two longitudinal rods 4.1 and connection for being parallel to foundation pit reinforced concrete top surface The third transverse link 4.2 at end;The second end of longitudinal rod 4.1 to frame and is stretched out outside foundation pit reinforced concrete 100 towards the second side, The body of rod close to second end is fixedly connected with the top of the second vertical link 3.1;Workbench includes being fixed on first vertically to connect Bottom support on bar 2.1, multiple vertical rails 5.1 for being vertically set in the support of bottom, the multiple vertical rails 5.1 of connection Lateral guardrail 5.2, the first vertical link 2.1 of connection and guardrail 5.1(is the vertical rail 5.1 for being located at outside elevationally outward) the One diagonal brace 5.3 and the first diagonal brace 5.3 of connection and the elevationally outward longitudinal bracing 5.4 of guardrail 5.1.Above-mentioned hanging basket device structure letter It is single, it is easy to process, and can smoothly walk along foundation pit reinforced concrete 100.
Further, the first side further includes that first be arranged between two the first vertical links 2.1 laterally props up to frame Support 2.2, for enhancing structural strength of first side to frame.
Further, top surface frame further includes the second cross-brace 4.3 being arranged between two longitudinal rods 4.1, is used In the structural strength of enhancing top surface frame.
Further, top surface frame further includes the second diagonal brace 4.4 for connecting the first vertical link 2.1 and longitudinal rod 4.1, For enhancing the bonding strength of top surface frame and the first side to frame.
Further, bottom support includes the 4th transverse link 5.5 being oppositely arranged with the first transverse link, setting the Multiple shop fixtures connecting rods 5.6 of one transverse link and the 4th transverse link 5.5 and the backing plate 5.7 being laid on shop fixtures connecting rod 5.6. Bottom support mitigates the weight of workbench on the basis of guaranteeing workbench intensity using 5.7 structure of frame and backing plate.
Further, in above-mentioned hanging basket device, in addition to backing plate 5.7, remaining structure is square tube.
The above is only the embodiments of the present invention, and therefore it does not limit the scope of the patent of the utility model, all utilizations Equivalent structure or equivalent flow shift made by the utility model description is applied directly or indirectly in other relevant Technical field is also included in the patent protection scope of the utility model.

Claims (6)

1. a kind of hanging basket device that can be walked safely on foundation pit reinforced concrete, which is characterized in that flat including travelling platform and work Platform;
The travelling platform includes the first side to frame and the second side to frame, the first side of connection to frame and the second side to frame Top surface frame and orientation pulley of first side to frame, the second side on frame and top surface frame is set;
First side is located at the two sides of foundation pit reinforced concrete to frame and the second side to frame;
The top surface frame is located at the top surface of foundation pit reinforced concrete;
The orientation pulley is resisted against the top surface and two sides of foundation pit reinforced concrete;
The workbench is arranged in the first side on frame.
2. the hanging basket device according to claim 1 that can be walked safely on foundation pit reinforced concrete, which is characterized in that described One side to frame include two the first vertical links of two the first vertical links for being parallel to foundation pit reinforced concrete side and connection First transverse link of bottom end;
Second side to frame include two the second vertical links for being parallel to foundation pit reinforced concrete side and connection two the Second transverse link of two vertical link bottom ends;
The top surface frame includes two longitudinal rods of two longitudinal rods and connection for being parallel to foundation pit reinforced concrete top surface The third transverse link at two ends;
The second end of the longitudinal rod to frame and is stretched out outside foundation pit reinforced concrete towards the second side, close to second end the body of rod with The top of second vertical link is fixedly connected;
The workbench include be fixed in the first vertical link bottom support, be vertically set on bottom support on it is multiple Vertical rail, the lateral guardrail for connecting multiple vertical rails connect the first vertical link and elevationally outward the first diagonal brace of guardrail And connect the first diagonal brace and the elevationally outward longitudinal bracing of guardrail.
3. the hanging basket device according to claim 2 that can be walked safely on foundation pit reinforced concrete, which is characterized in that described One side to frame further include the first cross-brace being arranged between two the first vertical links.
4. the hanging basket device according to claim 2 that can be walked safely on foundation pit reinforced concrete, which is characterized in that the top Surface frame frame further includes the second cross-brace being arranged between two longitudinal rods.
5. the hanging basket device according to claim 4 that can be walked safely on foundation pit reinforced concrete, which is characterized in that the top Surface frame frame further includes the second diagonal brace for connecting the first vertical link and longitudinal rod.
6. the hanging basket device according to claim 2 that can be walked safely on foundation pit reinforced concrete, which is characterized in that the bottom Portion support include the 4th transverse link being oppositely arranged with the first transverse link, setting the first transverse link and the 4th laterally connect Multiple shop fixtures connecting rods of bar and the backing plate being laid on shop fixtures connecting rod.
CN201920062928.0U 2019-01-15 2019-01-15 A kind of hanging basket device that can be walked safely on foundation pit reinforced concrete Active CN209384619U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920062928.0U CN209384619U (en) 2019-01-15 2019-01-15 A kind of hanging basket device that can be walked safely on foundation pit reinforced concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920062928.0U CN209384619U (en) 2019-01-15 2019-01-15 A kind of hanging basket device that can be walked safely on foundation pit reinforced concrete

Publications (1)

Publication Number Publication Date
CN209384619U true CN209384619U (en) 2019-09-13

Family

ID=67853399

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920062928.0U Active CN209384619U (en) 2019-01-15 2019-01-15 A kind of hanging basket device that can be walked safely on foundation pit reinforced concrete

Country Status (1)

Country Link
CN (1) CN209384619U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820753A (en) * 2019-11-12 2020-02-21 顾青林 Hydraulic engineering construction excavation anti-collapse device
WO2021103024A1 (en) * 2019-11-30 2021-06-03 中铁五局集团有限公司 Sidewalk construction scaffold for railway bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110820753A (en) * 2019-11-12 2020-02-21 顾青林 Hydraulic engineering construction excavation anti-collapse device
CN110820753B (en) * 2019-11-12 2021-02-09 顾青林 Hydraulic engineering construction excavation anti-collapse device
WO2021103024A1 (en) * 2019-11-30 2021-06-03 中铁五局集团有限公司 Sidewalk construction scaffold for railway bridge

Similar Documents

Publication Publication Date Title
CN209384619U (en) A kind of hanging basket device that can be walked safely on foundation pit reinforced concrete
CN206034880U (en) Attached type lifting scaffold
CN210976543U (en) Cage platform for tensioning construction
CN209975993U (en) Suspension cage
CN207277192U (en) Portable overhanging lifting platform for crash barrier template construction
CN211173007U (en) Novel tripod of encorbelmenting
CN210316599U (en) A curtain ring rail for roofing truss beam position
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN206971693U (en) Adjustable type welds hanging basket
CN108824214A (en) A kind of fast-type high-speed rail Bridge Pier Construction hanging basket mounting platform and application method
CN212296237U (en) Side slope drilling trolley
CN211499700U (en) Construction protection handling frame
CN213572927U (en) Movable steel platform with adjustable size and capable of being circulated
CN214573768U (en) Self-climbing sliding formwork pouring system for second-stage concrete pouring of gate slot
CN208732480U (en) Prefabricated girder tensioning auxiliary hoisting device
CN201339311Y (en) Turning plate device of hanging rack
CN210858055U (en) Convenient type construction platform of unloading
CN210289068U (en) Elevator shaft lifting platform
CN207739605U (en) Elevator shaft three-dimensional construction protection system
CN110606429A (en) Elevator shaft discharging device and using method thereof
CN206308627U (en) A kind of portable beam body side operation frame
CN212316698U (en) Concrete bridge guardrail construction platform device
CN208685448U (en) A kind of safety scaffold of bridge construction
CN212024482U (en) Novel construction elevator platform
CN208456092U (en) Skyscraper main body construction hoistway operation platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant