CN209369307U CN201821931765.7U CN201821931765U CN209369307U CN 209369307 U CN209369307 U CN 209369307U CN 201821931765 U CN201821931765 U CN 201821931765U CN 209369307 U CN209369307 U CN 209369307U
Authority
CN
China
Prior art keywords
angle bar
scaffold
wall
screw rod
connecting piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821931765.7U
Other languages
Chinese (zh)
Inventor
刘海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Huide Construction Engineering Co Ltd
Original Assignee
Anhui Huide Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Huide Construction Engineering Co Ltd filed Critical Anhui Huide Construction Engineering Co Ltd
Priority to CN201821931765.7U priority Critical patent/CN209369307U/en
Application granted granted Critical
Publication of CN209369307U publication Critical patent/CN209369307U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model belongs to safety techniques for construction field, and in particular to a kind of exterior wall scaffold wall-connecting piece, including the first and second screw rod, sleeve, sleeve both ends are threadedly coupled the first and second screw rod respectively, and sleeve, the first screw pre-buried are in concrete structure;Second screw rod right end is welded to connect on the first angle bar;Several first connecting holes are equipped on one side of the first angle bar from left to right;By fastener fixing steel pipe on scaffold, steel pipe left end is fixedly connected on the second angle bar, is equipped with several second connecting holes on a side of the second angle bar from left to right;First connecting hole on first angle bar is corresponding with second connecting hole on the second angle bar, bolt is set in hole and is fixed by nut.The utility model is formed using conventional building material by simple combination, is filled, is torn open conveniently, high recycling rate, by the way that bolt is arranged in the different corresponding aperture of two angle bar and is fixed by nut, convenient verticality between adjustment exterior wall and scaffold in time.

Description

A kind of exterior wall scaffold wall-connecting piece
Technical field
The utility model relates to a kind of exterior wall scaffold wall-connecting pieces for building engineering construction, belong to safety techniques for construction Field.
Background technique
At present in architectural engineering exterior wall scaffold wall-connecting piece in use, mostly using welding round steel on steel pipe or steel pipe directly pre- It is embedded in concrete, this method: 1. increasing cost, increase labor intensity;2. wall-connecting piece needs preformed hole at the position of building wall Hole, the position wall needs secondary masonry after cutting off embedded steel tube (round steel), easily causes outer wall body leak;3. cutting pre-buried Part, misoperation easily cause the safety accidents such as fire;When exterior wall scaffold frame body perpendicularity deviation is larger, it is difficult to entangle immediately Partially, misoperation easily causes scaffold frame body cave-in accident.
Utility model content
The purpose of this utility model is just to provide a kind of exterior wall scaffold wall-connecting piece, using conventional building material, by letter It is singly composed, makes, installs simply, fill, tear open conveniently, high recycling rate, by being set in the different corresponding aperture of two angle bar It sets bolt and is fixed by nut, and then adjust the verticality between exterior wall and scaffold.
The purpose of this utility model is achieved through the following technical solutions, a kind of exterior wall scaffold wall-connecting piece, including the One screw rod, the second screw rod, sleeve, sleeve both ends are threadedly coupled the first screw rod, the second screw rod, sleeve, the first screw pre-buried respectively In concrete structure;Second screw rod right end is welded to connect on the first angle bar;It is equipped with from left to right on one side of the first angle bar Several first connecting holes;
By fastener fixing steel pipe on scaffold, steel pipe left end is fixedly connected on the second angle bar, and one of the second angle bar Several second connecting holes are equipped on side from left to right;
, the hole corresponding with second connecting hole on the second angle bar by one of them first connecting hole on the first angle bar Middle setting bolt is simultaneously fixed by nut.
Preferably, first connecting hole, the second connecting hole are slotted hole.
Preferably, the concrete structure includes concrete structural wall, beam and/or column.
Preferably, first angle bar, the second angle bar size be L200mm*50mm*4mm,
Preferably, the scaffold includes cross bar, vertical bar and upright bar composition.
Compared with prior art, the utility model has the following beneficial effects: the utility model structure is simple, at low cost It is honest and clean, easy for construction, and high recycling rate, bolt, nut, the second screw rod and the first angle bar sub-assembly, steel pipe after dismounting with Second angle bar sub-assembly can reuse, while again can be different by two angle bar according to the actual needs of construction site Bolt is set in corresponding aperture and is fixed by nut, adjusts the verticality of exterior wall scaffold frame body in time, to guarantee outer foundation The overall stability and safety of hand cradle.
Detailed description of the invention:
Fig. 1 is the using state structure diagram of the utility model exterior wall scaffold wall-connecting piece.
Fig. 2 is the attachment structure schematic diagram of the first and second angle bar of the utility model exterior wall scaffold wall-connecting piece.
Specific embodiment
As Figure 1-Figure 2, a kind of exterior wall scaffold wall-connecting piece, including the first screw rod 11, the second screw rod 12, sleeve 2, set 2 both ends of cylinder are threadedly coupled the first screw rod 11, the second screw rod 12 respectively, and sleeve 2, the first screw rod 11 are embedded in concrete structure.First 11 end of screw rod is bending section, and raising sockets power.
Second screw rod, 12 right end is welded to connect on the first angle bar 3.
Several first connecting holes 31 are equipped on one side of the first angle bar 3 from left to right.
By the fixed steel pipe 5 of fastener 6 on scaffold, 5 left end of steel pipe is fixedly connected on the second angle bar 4, the second angle bar 4 Several second connecting holes 41 are equipped on one side from left to right.
By one of them first connecting hole 31 on the first angle bar 3 and 41 phase of the second connecting hole on the second angle bar 4 It is corresponding, bolt 10 is set in hole and is fixed by nut.
First connecting hole 31, the second connecting hole 41 are slotted hole, facilitate alignment and the insertion of bolt.
Concrete structure includes concrete structural wall, beam and/or column.
First angle bar 3, the second angle bar 4 size be L200mm*50mm*4mm,
Scaffold includes that cross bar 9, vertical bar 8 and upright bar 7 form.
Second screw rod is welded on to the corner of the first angle bar, the two side walls company of welding of two screw rods and the first angle bar It connects, guarantees the stability of component.
By steel-pipe welding in the corner of the second angle bar, the two side walls of steel pipe and the second angle bar are welded to connect, and are guaranteed The stability of component.
The utility model is of simple structure and low cost, easy for construction, and high recycling rate, bolt, spiral shell after dismounting Female, the second screw rod can be reused with the first angle bar sub-assembly, steel pipe and the second angle bar sub-assembly, while again can be according to construction The actual needs at scene adjusts exterior wall by the way that bolt is arranged in the different corresponding aperture of two angle bar and fixes by nut in time The verticality of scaffold frame body, to guarantee the overall stability and safety of exterior wall scaffold.

Claims (5)

1. a kind of exterior wall scaffold wall-connecting piece, characterized in that the wall-connecting piece include the first screw rod (11), the second screw rod (12), Sleeve (2), sleeve (2) both ends are threadedly coupled the first screw rod (11), the second screw rod (12), sleeve (2), the first screw rod (11) respectively It is embedded in concrete structure;Second screw rod (12) right end is welded to connect on the first angle bar (3);One side of the first angle bar (3) On from left to right be equipped with several first connecting holes (31);
Fixed steel pipe (5) by fastener (6) on scaffold, steel pipe (5) left end is fixedly connected on the second angle bar (4), and second jiao Several second connecting holes (41) are equipped on one side of iron (4) from left to right;
By one of them first connecting hole (31) on the first angle bar (3) and second connecting hole on the second angle bar (4) (41) corresponding, bolt (10) are set in hole and are fixed by nut.
2. a kind of exterior wall scaffold wall-connecting piece according to claim 1, characterized in that first connecting hole (31), Two connecting holes (41) are slotted hole.
3. a kind of exterior wall scaffold wall-connecting piece according to claim 1, characterized in that the concrete structure includes concrete structure Wall, beam and/or column.
4. a kind of exterior wall scaffold wall-connecting piece according to claim 1, characterized in that first angle bar (3), second jiao The size of iron (4) is L200mm*50mm*4mm.
5. a kind of exterior wall scaffold wall-connecting piece according to claim 1, characterized in that the scaffold include cross bar (9), Vertical bar (8) and upright bar (7) composition.
CN201821931765.7U 2018-11-22 2018-11-22 A kind of exterior wall scaffold wall-connecting piece Expired - Fee Related CN209369307U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821931765.7U CN209369307U (en) 2018-11-22 2018-11-22 A kind of exterior wall scaffold wall-connecting piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821931765.7U CN209369307U (en) 2018-11-22 2018-11-22 A kind of exterior wall scaffold wall-connecting piece

Publications (1)

Publication Number Publication Date
CN209369307U true CN209369307U (en) 2019-09-10

Family

ID=67833489

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821931765.7U Expired - Fee Related CN209369307U (en) 2018-11-22 2018-11-22 A kind of exterior wall scaffold wall-connecting piece

Country Status (1)

Country Link
CN (1) CN209369307U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012469A (en) * 2020-08-17 2020-12-01 海宁市宏顺设备租赁有限公司 Automatic sag deviation adjusting mechanism for scaffold

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012469A (en) * 2020-08-17 2020-12-01 海宁市宏顺设备租赁有限公司 Automatic sag deviation adjusting mechanism for scaffold
CN112012469B (en) * 2020-08-17 2022-03-18 海宁市宏顺设备租赁有限公司 Automatic sag deviation adjusting mechanism for scaffold

Similar Documents

Publication Publication Date Title
CN208202530U (en) A kind of new type scaffold wall-connecting piece
CN103452304B (en) Exempt from foot trick plug-in type outrigger L-type steel wall-connecting piece structure and construction method thereof
CN209369307U (en) A kind of exterior wall scaffold wall-connecting piece
CN203867158U (en) Cantilever type scaffold structure with positioning plug for fixation
CN203654710U (en) Instrumental connecting tube for external wall scaffold shearing wall portion
CN212224604U (en) Wall connecting assembly for connecting outer wall scaffold and wall structure
CN104120874A (en) Assembly type scaffold and wall connecting piece
CN206091264U (en) Outer wall scaffold frame is wall spare even
CN204001665U (en) A kind of scaffold assembling wall-connecting piece
CN203080510U (en) Pin-sleeved type pile joint
CN210562223U (en) Slope protection template with arch framework
CN202209046U (en) Wall connecting rod for external scaffold
CN206707255U (en) Combined type wall attaching parts for external scaffolding
CN208122270U (en) A kind of scaffold wall connecting piece mounting structure
CN204266572U (en) Scaffold wall connecting piece
CN206385794U (en) A kind of wall-connecting piece and its connection system
CN206829589U (en) A kind of recyclable scaffold wall connecting piece
CN106567538B (en) A kind of positioning mold of toilet concrete flanging
CN205296807U (en) Novel fastener -style steel pipe scaffold U type is wall spare even
CN209457418U (en) A kind of quick positioning connection structure of assembled architecture light plate shear wall
CN209053419U (en) Pre-buried, assembling type outer wall scaffold wall connecting piece
CN204081087U (en) A kind of reinforced concrete column and reinforcing steel bar connecting device
CN209989702U (en) Novel bracket
CN204418696U (en) Vertical reinforcement spreading lifting assistor
CN205025079U (en) Fastener -style steel pipe scaffold is wall drawknot spare even

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190910