CN209369041U - Tensile force regulating structure and pneumatic membrane building basis for pneumatic membrane building construction - Google Patents

Tensile force regulating structure and pneumatic membrane building basis for pneumatic membrane building construction Download PDF

Info

Publication number
CN209369041U
CN209369041U CN201821907013.7U CN201821907013U CN209369041U CN 209369041 U CN209369041 U CN 209369041U CN 201821907013 U CN201821907013 U CN 201821907013U CN 209369041 U CN209369041 U CN 209369041U
Authority
CN
China
Prior art keywords
lever arm
pneumatic membrane
membrane building
tensile force
flexible connecting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201821907013.7U
Other languages
Chinese (zh)
Inventor
韩文冬
肖龙
王秦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Braodwell Environment Protection Technology Co Ltd
Original Assignee
Shenzhen Braodwell Environment Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Braodwell Environment Protection Technology Co Ltd filed Critical Shenzhen Braodwell Environment Protection Technology Co Ltd
Priority to CN201821907013.7U priority Critical patent/CN209369041U/en
Application granted granted Critical
Publication of CN209369041U publication Critical patent/CN209369041U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Tents Or Canopies (AREA)

Abstract

The utility model embodiment disclose it is a kind of for pneumatic membrane building construction tensile force regulating structure and pneumatic membrane building basis.A kind of tensile force regulating structure for pneumatic membrane building construction, including pedestal, supporting element and lever arm, supporting element are fixed on pedestal, and one end of lever arm with the first flexible connecting member for connecting, and the other end of lever arm with the second flexible connecting member for connecting;The first flexible connecting member is adjusted by using tightening equipment, may make the second flexible connecting member to form slope or substantially concordant with the top surface on pneumatic membrane building basis on the ground, and be in tensioning state;Air film main body can be smoothly transported to the top surface on pneumatic membrane building basis by the slope or plane that are formed by more second flexible connecting members, be can be avoided air film main body and be destroyed in the construction process, improve installation quality and installation effectiveness.

Description

Tensile force regulating structure and pneumatic membrane building basis for pneumatic membrane building construction
Technical field
The utility model embodiment is related to technical field of buildings, more particularly to a kind of pulling force for pneumatic membrane building construction Adjust structure and pneumatic membrane building basis.
Background technique
Pneumatic membrane building is supported " shell " by internal and external pressure difference as building " shell " using special building tunica fibrosa Get up, form building main body, interior is supported without any frame or beam column, is suitable as stadiums, warehouse, logistics center And interim indoor spaces etc..
In the installation of pneumatic membrane building, especially for the pneumatic membrane building of industry storage class, frequently encounters air film and build It is excessively high to build basis, needs the case where membrane material is pulled to basic top surface from ground.Size due to membrane material in width direction is fixed, It is pulled in work progress extremely difficult, it usually needs scaffolding, but scaffold is due to having splicing and point convex, in work progress In be easy scratch membrane material.
Summary of the invention
The utility model embodiment is mainly solving the technical problems that provide a kind of pulling force tune for pneumatic membrane building construction Whole structure and pneumatic membrane building basis, can be avoided air film main body and are destroyed in the construction process, improve installation quality and installation Efficiency.
The technical solution adopted in the utility model is: in a first aspect, the utility model embodiment provides one kind for air film The tensile force regulating structure of construction, the tensile force regulating structure include pedestal, supporting element and lever arm, and the supporting element is fixed On the base, the upper end of the supporting element offers inner via hole, and the lever arm includes left lever arm and right activity for setting Arm, the left lever arm and the right lever arm are symmetrically arranged at the two sides of the supporting element, and the left lever arm and The lower end of the right lever arm offers accessibke porosity corresponding with the inner via hole, the left lever arm and the right lever arm It is pivotally connected respectively by the connecting shaft being located in the inner via hole and the accessibke porosity and the supporting element;
Wherein, the both ends of the left lever arm and the right lever arm are provided with the first pin hole and the second pin hole, described The first fastener is equipped in first pin hole of the first pin hole of left lever arm and the right lever arm, first fastener is used It connect in the first flexible connecting member, is equipped in the second pin hole of the second pin hole of the left lever arm and the right lever arm Second fastener, second fastener with the second flexible connecting member for connecting.
Optionally, the left lever arm and the right lever arm are inverted triangular structure, the side of the up-side down triangle with It is connected between side using arc-shaped transition;
The accessibke porosity, first pin hole and second pin hole are located at three apex angles of the up-side down triangle.
Optionally, it is detachably fixed between first fastener and the left lever arm and the right lever arm;It is described It is detachably fixed between second fastener and the left lever arm and the right lever arm.
In one embodiment, first fastener is pin or is bolt, nut;
Second fastener is pin or is bolt, nut.
Optionally, the supporting element is fixed with the tube chamber welds with base.
Second aspect, the utility model embodiment provide a kind of pneumatic membrane building basis, the top surface on the pneumatic membrane building basis Interval pre-determined distance is fixedly installed tensile force regulating structure as described above.
Optionally, the pedestal of the tensile force regulating structure is rectangular configuration, and quadrangle offers mounting hole, the pedestal and institute Pneumatic membrane building basis is stated to fix by the expansion bolt being located in the mounting hole.
Optionally, the pneumatic membrane building basis is further fixedly arranged on hook on the opposite of the tensile force regulating structure.
The beneficial effect of the utility model embodiment is: it is in contrast to the prior art, the utility model embodiment Pneumatic membrane building includes pneumatic membrane building basis and air film main body, in the construction process, the top surface interval on pneumatic membrane building basis it is default away from From tensile force regulating structure is fixedly installed, tensile force regulating structure includes pedestal, supporting element and lever arm, and supporting element is fixed at On pedestal, for connecting with the first flexible connecting member, the other end of lever arm is used for and the second flexible connection for one end of lever arm Part connection adjusts the pulling force of the first flexible connecting member and the angle of lever arm by using tightening equipment, may make that second is soft Property connector forms slope or substantially concordant with the top surface on pneumatic membrane building basis on the ground;It is flexibly connected by more second Air film main body can be smoothly transported to the top surface on pneumatic membrane building basis by slope or plane that part is formed, can be avoided air film master Body is destroyed in the construction process, improves installation quality and installation effectiveness.
Detailed description of the invention
Fig. 1 is the schematic diagram of the pneumatic membrane building of the utility model embodiment;
Fig. 2 is the schematic top plan view on the pneumatic membrane building basis of the utility model embodiment;
Fig. 3 is the schematic front view of the tensile force regulating structure of the utility model embodiment;
Fig. 4 is the schematic top plan view of the tensile force regulating structure of the utility model embodiment;
Fig. 5 is the schematic front view of the pneumatic membrane building basis of the utility model embodiment in the construction process;
Fig. 6 is schematic front view one of the pneumatic membrane building basis of the utility model embodiment in another work progress;
Fig. 7 is the schematic front view in the work progress shown in Fig. 6 of the pneumatic membrane building basis of the utility model embodiment Two;
Fig. 8 is the schematic top plan view in the work progress shown in Fig. 6 of the pneumatic membrane building basis of the utility model embodiment;
Fig. 9 is schematic front view of the pneumatic membrane building basis of the utility model embodiment in another work progress;
Figure 10 is the vertical view signal in the work progress shown in Fig. 9 of the pneumatic membrane building basis of the utility model embodiment Figure.
Specific embodiment
For the ease of understanding the utility model, in the following with reference to the drawings and specific embodiments, the utility model is carried out more detailed Thin explanation.It should be noted that it can be directly in another element when element is expressed " being fixed on " another element Upper or placed in the middle there may be one or more therebetween elements.When an element is expressed " connection " another element, it can To be directly to another element or elements placed in the middle there may be one or more therebetween.This specification is used Term "vertical", "horizontal", "left" and "right" and similar statement for illustrative purposes only.
Unless otherwise defined, technical and scientific term all used in this specification and the skill for belonging to the utility model The normally understood meaning of the technical staff in art field is identical.Art used in the description of the utility model in this specification Language, which is only for the purpose of describing specific embodiments, is not intended to limitation the utility model.
Embodiment 1
Fig. 1 and Fig. 2 are please referred to, pneumatic membrane building provided by the embodiment of the utility model includes pneumatic membrane building basis 10 and air film Main body 20, before the inflation of 20 main body of air film main body, the top surface interval pre-determined distance on pneumatic membrane building basis 10 is fixedly installed drawing Power adjusts structure 100.
Also referring to Fig. 3 and Fig. 4, tensile force regulating structure 100 includes pedestal 110, supporting element 120 and lever arm 130, branch Support member 120 is fixed on pedestal 110.Preferably scheme, the setting of supporting element 120 is hit exactly in pedestal 110, with pedestal 110 are welded and fixed;Pedestal 110 is rectangular configuration, and quadrangle offers mounting hole, and pedestal 110 and pneumatic membrane building basis 10 pass through position Fixed in the expansion bolt in mounting hole, by the above-mentioned means, realize pneumatic membrane building basis 10, pedestal 110 and supporting element 120 it Between firm installation.
The upper end of supporting element 120 offers inner via hole, and lever arm 130 includes left lever arm 131 and right lever arm 132, a left side Lever arm 131 and right lever arm 132 are symmetrically arranged at the two sides of supporting element 120, and left lever arm 131 and right lever arm 132 lower end offers accessibke porosity corresponding with inner via hole, left lever arm and right lever arm respectively by be located at inner via hole and Connecting shaft 140 and supporting element 120 in accessibke porosity are pivotally connected.
Wherein, the both ends of left lever arm 131 and right lever arm 132 are provided with the first pin hole and the second pin hole, left activity The first fastener 150 is equipped in first pin hole of arm 131 and the first pin hole of right lever arm 132, the first fastener 150 is used for It is connect with the first flexible connecting member 30, is equipped in the second pin hole of left lever arm 131 and the second pin hole of right lever arm 132 Two fasteners 160, the second fastener 160 with the second flexible connecting member 40 for connecting.
When it is implemented, the other end of the first flexible connecting member 30 extends to the outside on pneumatic membrane building basis 10, and with receipts Clamping apparatus connection, the other end of the second flexible connecting member 40 and ground are fixed or are fixed with the tensile force regulating structure 100 on opposite, And tentatively tighten, the other end of the tensile force regulating structure 100 on opposite is also connected with another first flexible connecting member 30 and another receipts Clamping apparatus.It can adjust the pulling force of the first flexible connecting member 30 and the angle of lever arm connected to it 130 by tightening equipment, So that the second flexible connecting member 40 forms slope or substantially concordant with the top surface on pneumatic membrane building basis 10 on the ground, and it is in Tensioning state.
In other embodiments, pneumatic membrane building basis 10 is further fixedly arranged on extension on the opposite of tensile force regulating structure 100 Hook passes through the first flexible connection of adjustment of tightening equipment when the other end of the second flexible connecting member 40 and the fixed hook on opposite The angle of the pulling force of part 30 and lever arm connected to it 130 similarly may make the second flexible connecting member 40 to build with air film The top surface for building basis 10 is substantially concordant, and is in tensioning state.
When more second flexible connecting members 40 are in tensioning state, formed by more second flexible connecting members 40 oblique Air film main body 20 can be smoothly transported to the top surface on pneumatic membrane building basis 10 by slope or plane, the mode pulled with scaffolding It compares, can be avoided air film main body 20 and be destroyed, improve installation quality, and in the construction process without installing instrument or auxiliary Assistant engineer's tool, reduces manpower and material resources, improves installation effectiveness.
First flexible connecting member 30 and the second flexible connecting member 40 are cable, such as various safety ropes, wirerope, in air film In the work progress of building, can endurance according to actual needs, select the cable of unlike material, different size.
Optionally, left lever arm 131 and right lever arm 132 are inverted triangular structure, up-side down triangle while while between It is connected using arc-shaped transition, the edge of left lever arm 131 and right lever arm 132 is avoided to scratch air film main body 20, accessibke porosity, first Pin hole and the second pin hole are located at three apex angles of up-side down triangle.
In one embodiment, up-side down triangle be fall isosceles triangle, also that is, the distance between the first pin hole and accessibke porosity with Second pin hole is equal with the distance between accessibke porosity.In other embodiments, left lever arm 131 and right lever arm 132 can also be Irregular inverted triangular structure, so that the distance between the first pin hole and accessibke porosity are more than or less than the second pin hole and outside The distance between through-hole.
Left lever arm 131 and right lever arm 132 can be also other structures, such as T-shaped structure or linear type structure, equally Ground is, it can be achieved that adjust the purpose of the pulling force of cable.
In the above-described embodiments, it is detachably fixed between the first fastener 150 and left lever arm 131 and right lever arm 132, It is also detachably fixed between second fastener 160 and left lever arm 131 and right lever arm 132.In practical applications, to prevent rope The end of cable overbending and abrasion, cable is looped around on capel, by cable and the first fastener 150 or the second fastener Before 160 connections, first the first fastener 150 or the second fastener 160 are removed from left lever arm 131 and right lever arm 132, It is fixed with left lever arm 131 and right lever arm 132 again after capel, realize that cable and the first fastener 150 or second are tight Connection between firmware 160.
First fastener 150 is that pin is perhaps that bolt, the second fastener of nut 160 are pin or are bolt, spiral shell It is female.Illustratively, the first fastener 150 and the second fastener 160 are screw bolt and nut, and bolt passes through left 131 He of lever arm By nut check after right lever arm 132.
The pneumatic membrane building of the present embodiment includes pneumatic membrane building basis 10 and air film main body 20, is inflated in 20 main body of air film main body Before, the top surface interval pre-determined distance on pneumatic membrane building basis 10 is fixedly installed tensile force regulating structure 100, tensile force regulating structure 100 include pedestal 110, supporting element 120 and lever arm 130, and supporting element 120 is fixed on pedestal 110, lever arm 130 For connecting with the first flexible connecting member 30, the other end of lever arm 130 leads to for connecting with the second flexible connecting member 40 for one end It crosses and the pulling force of the first flexible connecting member 30 and the angle of lever arm connected to it 130 is adjusted using tightening equipment, may make Second flexible connecting member 40 forms slope or substantially concordant with the top surface on pneumatic membrane building basis 10 on the ground, and in tensioning State;Air film main body 20 can be smoothly transported to air film by the slope or plane formed by more second flexible connecting members 40 The top surface of building foundation 10 can be avoided air film main body 20 and be destroyed in the construction process, improve installation quality and installation effect Rate.
Embodiment 2
The utility model embodiment also provides a kind of construction method of the pneumatic membrane building, comprising:
Step 11: one end of more first flexible connecting members 30 is respectively sleeved at the of multiple tensile force regulating structures 100 On one fastener 150, the other end of the first flexible connecting member 30 extends to the outside on pneumatic membrane building basis 10, and with tightening equipment Connection;
Step 12: one end of more second flexible connecting members 40 is respectively sleeved at the of multiple tensile force regulating structures 100 On two fasteners 160, the other end of the second flexible connecting member 40 extends to the inside on pneumatic membrane building basis 10, and is fixed on ground On, by the second tentatively tightening of flexible connecting member 40 when fixed, so that the second flexible connecting member 40 forms a slope on the ground, As shown in Figure 5;
Step 13: the pulling force and lever arm connected to it 130 of the first flexible connecting member 30 are adjusted by tightening equipment Angle, to adjust the pulling force of the second flexible connecting member 40, until more second flexible connecting members 40 are in tensioning state;
Step 14: air film main body 20 is pulled to pneumatic membrane building basis along the slope that more second flexible connecting members 40 are formed 20 top.
In above-mentioned steps, the end of the first flexible connecting member 30 can be fixed by cord clip, by the first flexible connecting member 30 One end be set on the first fastener 150 after, one tightening equipment of the other end of every one first flexible connecting member 30 connection, tightening Equipment can be hoist engine, flower basket bolt or jack.
Similarly, the end of the second flexible connecting member 40 can be fixed by cord clip, by one end of the second flexible connecting member 40 After being set on the second fastener 160, the other end of the second flexible connecting member 40 passes through earth anchorage on the ground.Specific implementation When, each second flexible connecting member 40 can respectively by different earth anchorages on the ground or adjacent two or more the Two flexible connecting members 40 share an earth anchor or two opposite second flexible connecting members 40 share an earth anchor, this implementation Example comparison is not construed as limiting.
After more second flexible connecting members 40 form slope on ground, drawing that can be gentle along slope by air film main body 20 It is multiple by what is fixed on pneumatic membrane building basis 10 then before the inflation of air film main body 20 to the top surface on pneumatic membrane building basis 10 Tensile force regulating structure 100 is removed.Aforesaid way can be avoided air film main body 20 and broken compared with the mode that scaffolding pulls It is bad, installation quality is improved, and reduce manpower and material resources without installing instrument or auxiliary tool in the construction process, improve Installation effectiveness.
Embodiment 3
The utility model embodiment also provides another construction method of the pneumatic membrane building, comprising:
Step 21: one end of more first flexible connecting members 30 is respectively sleeved at the of multiple tensile force regulating structures 100 On one fastener 150, the other end of the first flexible connecting member 30 extends to the outside on pneumatic membrane building basis 10, and tightens with first Equipment connection;
Step 22: one end of more second flexible connecting members 40 is respectively sleeved at above-mentioned multiple tensile force regulating structures 100 The second fastener 160 on, the other end of the second flexible connecting member 40 extends to the inside on pneumatic membrane building basis 10, is fixed on pair On second fastener 160 of the tensile force regulating structure 100 in face, and the second flexible connecting member 40 is made to be in preliminary tightening state, As shown in Figure 6;
Step 23: one end of more third flexible connecting members 50 is respectively sleeved to multiple tensile force regulating structures on opposite On 100 the first fastener 150, the other end of third flexible connecting member 50 extends to the outside on pneumatic membrane building basis 10, and with Second tightening equipment connection, as shown in Figure 7;
Step 24: the pulling force and lever arm connected to it of the first flexible connecting member 30 are adjusted by the first tightening equipment Angle, by second tightening equipment adjust third flexible connecting member 50 pulling force and lever arm connected to it angle, To adjust the pulling force of the second flexible connecting member 40, until more second flexible connecting members 40 are in tensioning state;
Step 25: air film main body 20 is laid in the top of more second flexible connecting members 40.
It will be appreciated by those skilled in the art that the effect of third flexible connecting member 50 and the effect 30 of the first flexible connecting member Be it is the same, can first pass through in step 24 the first tightening equipment adjust the first flexible connecting member 30 pulling force, can also be first The pulling force of third flexible connecting member 50 is adjusted by the second tightening equipment, or adjusts first simultaneously by the tightening equipment of two sides The pulling force of flexible connecting member 30 and third flexible connecting member 50, so that the second flexible connecting member 40 is in tensioning state.
In the form of construction work, as shown in figure 8, more second flexible connecting members 40 are under tensioning state, more second The plane and the top surface on pneumatic membrane building basis 10 that flexible connecting member 40 is formed are substantially concordant.It will be packaged in rolls using crane After air film main body 20 lifts on more second flexible connecting members 40, the expansion of air film main body 20 is laid in more second flexibilities even The top of fitting 40, air film main body 20 are used also with the top surface on pneumatic membrane building basis 10 almost on a horizontal plane without additional Power pulls up again, further improves installation effectiveness.
Embodiment 4
The utility model embodiment also provides another construction method of the pneumatic membrane building, and pneumatic membrane building basis is in pulling force tune The opposite of whole structure 100 is further fixedly arranged on hook, and method includes:
Step 31: one end of more first flexible connecting members 30 is respectively sleeved at the of multiple tensile force regulating structures 100 On one fastener 150, the other end of the first flexible connecting member 30 extends to the outside on pneumatic membrane building basis 10, and with tightening equipment Connection;
Step 32: one end of more second flexible connecting members 40 is respectively sleeved at above-mentioned multiple tensile force regulating structures 100 The second fastener 160 on, the other end of the second flexible connecting member 40 extends to the inside on pneumatic membrane building basis 10, is fixed on pair On the hook in face, and the second flexible connecting member 40 is made to be in preliminary tightening state, as shown in Figure 9;
Step 33: the pulling force of the first flexible connecting member 30 and the angle of lever arm connected to it are adjusted by tightening equipment Degree, to adjust the pulling force of the second flexible connecting member 40, until more second flexible connecting members 40 are in tensioning state;
Step 34: air film main body 20 is laid in the top of more second flexible connecting members 40.
Using the form of construction work, because hook is set to the top on pneumatic membrane building basis 10, therefore the second flexible connecting member 40 The plane of formation is also substantially concordant with the top surface on pneumatic membrane building basis 10, as shown in Figure 10, air film main body 20 is laid in more Behind the top of second flexible connecting member 40, air film main body 20 is also with the top surface on pneumatic membrane building basis 10 almost in a horizontal plane On, without additionally firmly pulling up again.
Wherein, multiple tensile force regulating structures 100 shown in Figure 10 are arranged at the side on pneumatic membrane building basis 10, multiple extensions Hook is arranged at the other side on pneumatic membrane building basis 10;In other embodiments, multiple tensile force regulating structures 100 and multiple hooks Also it can be set in the two sides on pneumatic membrane building basis 10, i.e., multiple tensile force regulating structures 100 and the setting of multiple hooks interval.
It should be noted that giving the preferable implementation of the utility model in the specification and its attached drawing of the utility model Example, still, the utility model can be realized by many different forms, however it is not limited to which this specification is described to be implemented Example, not as the additional limitation to the content of the present invention, purpose of providing these embodiments is makes to this reality these embodiments Understanding with novel disclosure is more thorough and comprehensive.Also, above-mentioned each technical characteristic continues to be combined with each other, and is formed not upper The various embodiments that face is enumerated are accordingly to be regarded as the range of the utility model specification record;Further, to ordinary skill For personnel, it can be modified or changed according to the above description, and all to should belong to this practical new for all these modifications and variations The protection scope of type appended claims.

Claims (8)

1. it is a kind of for pneumatic membrane building construction tensile force regulating structure, which is characterized in that the tensile force regulating structure include pedestal, Supporting element and lever arm, on the base, the upper end of the supporting element offers inner via hole, institute for the supporting element fixed setting Stating lever arm includes left lever arm and right lever arm, and the left lever arm and the right lever arm are symmetrically arranged at the branch The two sides of support member, and the lower end of the left lever arm and the right lever arm offer it is corresponding with the inner via hole outer logical Hole, the left lever arm and the right lever arm pass through the connecting shaft being located in the inner via hole and the accessibke porosity and institute respectively State supporting element pivot joint;
Wherein, the both ends of the left lever arm and the right lever arm are provided with the first pin hole and the second pin hole, the left work Be equipped with the first fastener in first pin hole of the first pin hole of swing arm and the right lever arm, first fastener be used for Second is equipped in second pin hole of the connection of the first flexible connecting member, the second pin hole of the left lever arm and the right lever arm Fastener, second fastener with the second flexible connecting member for connecting.
2. tensile force regulating structure according to claim 1, which is characterized in that
The left lever arm and the right lever arm are inverted triangular structure, the up-side down triangle while while between use arc Shape transition connection;
The accessibke porosity, first pin hole and second pin hole are located at three apex angles of the up-side down triangle.
3. tensile force regulating structure according to claim 1, which is characterized in that
It is detachably fixed between first fastener and the left lever arm and the right lever arm;
It is detachably fixed between second fastener and the left lever arm and the right lever arm.
4. tensile force regulating structure according to claim 3, which is characterized in that
First fastener is pin or is bolt, nut;
Second fastener is pin or is bolt, nut.
5. tensile force regulating structure according to claim 1, which is characterized in that
The supporting element is fixed with the tube chamber welds with base.
6. a kind of pneumatic membrane building basis, which is characterized in that the top surface interval pre-determined distance on the pneumatic membrane building basis is fixedly installed There is tensile force regulating structure as described in any one in claim 1-5.
7. pneumatic membrane building basis according to claim 6, which is characterized in that
The pedestal of the tensile force regulating structure is rectangular configuration, and quadrangle offers mounting hole, the pedestal and the pneumatic membrane building Basis is fixed by the expansion bolt being located in the mounting hole.
8. pneumatic membrane building basis according to claim 7, which is characterized in that
The pneumatic membrane building basis is further fixedly arranged on hook on the opposite of the tensile force regulating structure.
CN201821907013.7U 2018-11-19 2018-11-19 Tensile force regulating structure and pneumatic membrane building basis for pneumatic membrane building construction Withdrawn - After Issue CN209369041U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821907013.7U CN209369041U (en) 2018-11-19 2018-11-19 Tensile force regulating structure and pneumatic membrane building basis for pneumatic membrane building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821907013.7U CN209369041U (en) 2018-11-19 2018-11-19 Tensile force regulating structure and pneumatic membrane building basis for pneumatic membrane building construction

Publications (1)

Publication Number Publication Date
CN209369041U true CN209369041U (en) 2019-09-10

Family

ID=67836836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821907013.7U Withdrawn - After Issue CN209369041U (en) 2018-11-19 2018-11-19 Tensile force regulating structure and pneumatic membrane building basis for pneumatic membrane building construction

Country Status (1)

Country Link
CN (1) CN209369041U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109457807A (en) * 2018-11-19 2019-03-12 深圳市博德维环境技术股份有限公司 The construction method of pneumatic membrane building and the tensile force regulating structure for the construction method, pneumatic membrane building basis
CN111395522A (en) * 2020-03-21 2020-07-10 深圳市佛兰空间膜结构有限公司 Adjustable connecting structure for steel cable and diaphragm foundation in air-supported diaphragm structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109457807A (en) * 2018-11-19 2019-03-12 深圳市博德维环境技术股份有限公司 The construction method of pneumatic membrane building and the tensile force regulating structure for the construction method, pneumatic membrane building basis
CN109457807B (en) * 2018-11-19 2024-01-16 深圳市博德维环境技术股份有限公司 Construction method of air film building and tension adjusting structure and air film building foundation for construction method
CN111395522A (en) * 2020-03-21 2020-07-10 深圳市佛兰空间膜结构有限公司 Adjustable connecting structure for steel cable and diaphragm foundation in air-supported diaphragm structure

Similar Documents

Publication Publication Date Title
CN105443871B (en) A kind of new suspension and support and construction technology for the connection of horizontal multi-pipeline counterpart
CN113454306B (en) Integral lifting construction method and device for arch structure
CN209369041U (en) Tensile force regulating structure and pneumatic membrane building basis for pneumatic membrane building construction
CN110230262B (en) Half-integral hoisting structure and butt joint method for main arch rib of basket type steel pipe arch bridge
WO2021052142A1 (en) Cable-supported large-span structure and construction method therefor
CN110907152B (en) Rotary cable clamp test device and test method
KR200383712Y1 (en) A tower crane wall bracing frame or guy rope frame
WO2019128291A1 (en) Double-layer stepped suspended ceiling and mounting method
KR101102904B1 (en) Angle control curtain plate
US5388376A (en) Portable roof and tower system and method for construction
CN109457807A (en) The construction method of pneumatic membrane building and the tensile force regulating structure for the construction method, pneumatic membrane building basis
CN113047438B (en) Cable net assembly, building and building construction method
CN102057108A (en) Rigging deck module
CN114180456A (en) Hoisting posture adjusting method for giant laterally inclined truss structure
CN112523414B (en) Bucket screen installation design method applied to large-span rigid roof cable dome structure
CN105019557B (en) Construction method for flying-wing-type formwork space truss structure
CN205975969U (en) Combination framework and connecting piece of rack and truss antarafacial
JP2007145509A (en) Simple boom device
CN214462405U (en) Simple construction platform for industrial steel structure installation
CN114348852A (en) H-shaped steel beam erection hoisting device
JP2008007943A (en) Stretching device and stretching method for tent sheet
CN204079226U (en) A kind of movable beam string hanging apparatus that can increase rigidity when tubular truss lifts
JP3576338B2 (en) Fixing device for cable end and method of using the same
KR102362409B1 (en) A Scaffoling Unit For Ceiling-Installation Of Stage Devices
CN219198375U (en) Double-deck crane span structure installation gallows

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 518000 b1-603, building B, Kexing Science Park, 15 Keyuan Road, Science Park community, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: BROADWELL (SHENZHEN) TECHNOLOGY Co.,Ltd.

Address before: 518057 No.3, 12 / F, unit 2, building B, Kexing Science Park, No.15 Keyuan Road, Central District, Nanshan District, Shenzhen City, Guangdong Province

Patentee before: BROADWELL (SHENZHEN) TECHNOLOGY Co.,Ltd.

CP02 Change in the address of a patent holder
AV01 Patent right actively abandoned

Granted publication date: 20190910

Effective date of abandoning: 20240116

AV01 Patent right actively abandoned

Granted publication date: 20190910

Effective date of abandoning: 20240116

AV01 Patent right actively abandoned