CN209368865U CN201822214989.2U CN201822214989U CN209368865U CN 209368865 U CN209368865 U CN 209368865U CN 201822214989 U CN201822214989 U CN 201822214989U CN 209368865 U CN209368865 U CN 209368865U
Authority
CN
China
Prior art keywords
mixed mud
steel pipe
foundation
pier
foundation pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822214989.2U
Other languages
Chinese (zh)
Inventor
谢威
徐加波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Suge Architectural Technology Co Ltd
Original Assignee
Hangzhou Suge Architectural Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Suge Architectural Technology Co Ltd filed Critical Hangzhou Suge Architectural Technology Co Ltd
Priority to CN201822214989.2U priority Critical patent/CN209368865U/en
Application granted granted Critical
Publication of CN209368865U publication Critical patent/CN209368865U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to bearing pile technical field, specifically a kind of quick foundation pile, including mixed mud foundation pier and steel pipe;The mixed mud foundation pier is integrally poured, and steel pipe inclination is inserted in the through-hole being arranged on the mixed mud foundation pier and fixed with through-hole, and there are four the steel pipe settings and is evenly distributed on mixed mud foundation pier.The utility model is novel in design, the utility model is to soil environment close friend, construction and use process do not generate building waste, soil constituent is not destroyed and does not destroy surface vegetation, belong to the green technology product of environmentally protective, recyclable recycling, the angle-inserting type steel pipe that working efficiency can be effectively improved, be worthy to be popularized, while being used effectively increases the stability of foundation pile.

Description

A kind of quick foundation pile
Technical field
The utility model relates to bearing pile technical field, specifically a kind of quick foundation pile.
Background technique
Pile foundation is the top of several piles to be coupled by cushion cap a kind of integral, the common deep base for bearing sound load Plinth, and stake is the vertical or inclined basic component being set in soil, its role is to pass through weak high-compressibility soil layer or Water, the load that stake is born are transmitted on harder, the lesser soil supporting layer of more closely knit or compressibility, we are usually by pile foundation Stake in plinth is known as foundation pile.
Various buildings are high for foundation bearing force request, generally use foundation pile.Foundation pile is a kind of common basic shape Formula has been widely adopted at present.It is poor often caused by shallow layer foundation mechanical index using foundation pile, and deep layer is satisfactory Ground is embedding and relatively deep, is a kind of cost-effective base form using foundation pile, being capable of safe and effective transmitting load.It is right In providing the foundation pile of main foundation bearing capacity by the frictional force of the soil body and pile body, pile body and soil around pile how are effectively improved Frictional force, so that the bearing capacity for improving foundation pile is particularly significant for foundation pile.
Summary of the invention
The purpose of this utility model is to provide a kind of quick foundation piles, to solve mentioned above in the background art ask Topic.
To achieve the above object, the utility model provides the following technical solutions:
A kind of quick foundation pile, including mixed mud foundation pier and steel pipe;The mixed mud foundation pier is integrally poured, steel Pipe inclination is inserted in the through-hole being arranged on the mixed mud foundation pier and is fixed with through-hole, and there are four the steel pipe settings and uniform It is distributed on mixed mud foundation pier.
As a further solution of the present invention: the interlude outer diameter of the mixed mud foundation pier is greater than mixed mud basis The outer diameter of pier upper and lower side.
The steel pipe uses square tube or round tube as a further solution of the present invention,.
The outside of the mixed mud foundation pier is multilateral shape as a further solution of the present invention,.
It as a further solution of the present invention, further include the bolt being embedded on mixed mud foundation pier.
The position for connecting bolt on the mixed mud foundation pier as a further solution of the present invention, is higher than steel pipe Insert position.
The bolt is provided with multiple and is fixed with steel plate by nut as a further solution of the present invention, The mounting post for connecting receiver is fixed on steel plate.
The mounting post and the fixed form of steel plate are that stud is fixed or welded as a further solution of the present invention, It connects.
Compared with prior art, the utility model has the beneficial effects that the utility model is novel in design, the utility model pair Soil environment is friendly, and construction and use process do not generate building waste, does not destroy soil constituent and does not destroy surface vegetation, belongs to The green technology product of environmentally protective, recyclable recycling, the oblique cutting that working efficiency can be effectively improved, be worthy to be popularized, while being used Formula steel pipe effectively increases the stability of foundation pile.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of quick foundation pile.
Fig. 2 is the left view of quick foundation pile.
Fig. 3 is the top view of quick foundation pile.
In figure: 1- steel pipe, 2- mixed mud foundation pier, 3- iron plate, 4- bolt, 5- mounting post.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Please refer to Fig. 1 ~ 3, in the utility model embodiment, a kind of quick foundation pile, including mixed mud foundation pier 2 and steel pipe 1;The mixed mud foundation pier 2 is integrally poured, and the inclination of steel pipe 1 is inserted in the through-hole being arranged on the mixed mud foundation pier 2 And fixed with through-hole, it is preferred that there are four the settings of steel pipe 1 and is evenly distributed on mixed mud foundation pier 2, is being embodied It is easy for installation in the process, and building waste will not be generated, work efficiency is high, while the angle-inserting type steel pipe 1 used effectively increases base The stability of plinth stake.
Preferably, the interlude outer diameter of the mixed mud foundation pier 2 is greater than the outer diameter of 2 upper and lower side of mixed mud foundation pier, from And the stability after foundation pile installation can be effectively increased.
Preferably, square tube or round tube can be used in the steel pipe 1, and the application is not construed as limiting this.
Embodiment two
Please refer to Fig. 1 ~ 3, in the utility model embodiment, a kind of quick foundation pile, including mixed mud foundation pier 2 and steel pipe 1;The mixed mud foundation pier 2 is integrally poured, and the inclination of steel pipe 1 is inserted in the through-hole being arranged on the mixed mud foundation pier 2 And fixed with through-hole, it is preferred that there are four the settings of steel pipe 1 and is evenly distributed on mixed mud foundation pier 2.
Preferably, the interlude outer diameter of the mixed mud foundation pier 2 is greater than the outer diameter of 2 upper and lower side of mixed mud foundation pier, from And the stability after foundation pile installation can be effectively increased.
The outside of the mixed mud foundation pier 2 is multilateral shape, can be effectively increased between mixed mud foundation pier 2 and soil Frictional force.
Preferably, square tube or round tube can be used in the steel pipe 1, and the application is not construed as limiting this.
In order to facilitate the property easy to use of the utility model, additionally provided in the utility model specific implementation process another Embodiment is planted to improve the application, further includes the bolt 4 being embedded on mixed mud foundation pier 2, connects on the mixed mud foundation pier 2 The position of connecting bolt 4 is higher than steel pipe 1 and inserts position.
Preferably, the bolt 4 is provided with multiple and is fixed with steel plate 3 by nut, is fixed on steel plate 3 for connecting The fixed form of the mounting post 5 of receiver, the mounting post 5 and steel plate 3 includes but is not limited to that stud is fixed or welded.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this is practical new in other specific forms Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this is practical new The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing for the equivalent requirements of the claims will be fallen in All changes in justice and range are embraced therein.It should not treat any reference in the claims as limiting Related claim.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (8)

1. a kind of quick foundation pile, including mixed mud foundation pier (2) and steel pipe (1);It is characterized in that, the mixed mud foundation pier (2) it being integrally poured, steel pipe (1) inclination is inserted in the through-hole being arranged on the mixed mud foundation pier (2) and is fixed with through-hole, There are four steel pipe (1) settings and is evenly distributed on mixed mud foundation pier (2).
2. a kind of quick foundation pile according to claim 1, which is characterized in that the centre of the mixed mud foundation pier (2) Section outer diameter is greater than the outer diameter of mixed mud foundation pier (2) upper and lower side.
3. a kind of quick foundation pile according to claim 1, which is characterized in that the steel pipe (1) uses square tube or round tube.
4. a kind of quick foundation pile according to claim 1, which is characterized in that the outside of the mixed mud foundation pier (2) For multilateral shape.
5. a kind of quick foundation pile according to claim 1, which is characterized in that further include being embedded in mixed mud foundation pier (2) bolt (4) on.
6. a kind of quick foundation pile according to claim 5, which is characterized in that connected on the mixed mud foundation pier (2) The position of bolt (4) is higher than steel pipe (1) and inserts position.
7. a kind of quick foundation pile according to claim 6, which is characterized in that the bolt (4) is provided with multiple and logical It crosses nut to be fixed with steel plate (3), the mounting post (5) for connecting receiver is fixed on steel plate (3).
8. a kind of quick foundation pile according to claim 7, which is characterized in that the mounting post (5) is consolidated with steel plate (3) Determining mode is that stud is fixed or welded.
CN201822214989.2U 2018-12-27 2018-12-27 A kind of quick foundation pile Active CN209368865U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822214989.2U CN209368865U (en) 2018-12-27 2018-12-27 A kind of quick foundation pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822214989.2U CN209368865U (en) 2018-12-27 2018-12-27 A kind of quick foundation pile

Publications (1)

Publication Number Publication Date
CN209368865U true CN209368865U (en) 2019-09-10

Family

ID=67827747

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822214989.2U Active CN209368865U (en) 2018-12-27 2018-12-27 A kind of quick foundation pile

Country Status (1)

Country Link
CN (1) CN209368865U (en)

Similar Documents

Publication Publication Date Title
CN201722776U (en) Beam column nodal point suitable for square steel pipe column
CN209368865U (en) A kind of quick foundation pile
CN205776311U (en) A kind of offshore wind farm embedding rock single-pile foundation
CN102011408A (en) Wire pole base embedded in pit
CN209429159U (en) Offshore wind farm single-pile foundation
CN205276234U (en) Structure that opens ice of high pile platform
CN207436110U (en) A kind of Anti-quaking foundation structure
CN206267169U (en) A kind of split blade type prestressing force anchor slab
CN202298613U (en) Opening pile toe
CN202369993U (en) Oppositely pulled type filling pile base pit supporting structure
CN205077392U (en) Improvement type power consumption subtracting isolation bearing
CN209854711U (en) Tubular pile shoe suitable for deep loose aeolian sand geology
CN204112765U (en) A kind of earthen ruins bracing means
CN206986879U (en) A kind of compression-resistant type embedded rock pile
CN207453621U (en) A kind of shock absorbing apparatus for communication tower
CN205617365U (en) Novel stake of reinforced concrete spiral
CN202298614U (en) Reinforced pile toe
CN205475237U (en) Steel protects a section of thick bamboo and adds outer guard shield structure
CN208702084U (en) A kind of permeable terrace convenient for splicing
CN206591539U (en) A kind of foundation pile of civil engineering
CN207714323U (en) Super large still-pressure dynamic replacement is hammered into shape
CN208056048U (en) A kind of anchor rod static pressure steel pipe body pilework
CN108179738A (en) A kind of novel quick foundation pile
CN206859724U (en) FRP networks for reinforcing wall
CN203160256U (en) Novel open sea deep foundation pit supporting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant