CN209368697U - A kind of tensioning pylon - Google Patents

A kind of tensioning pylon Download PDF

Info

Publication number
CN209368697U
CN209368697U CN201821971636.0U CN201821971636U CN209368697U CN 209368697 U CN209368697 U CN 209368697U CN 201821971636 U CN201821971636 U CN 201821971636U CN 209368697 U CN209368697 U CN 209368697U
Authority
CN
China
Prior art keywords
pylon
tensioning
main body
steel
pylon structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821971636.0U
Other languages
Chinese (zh)
Inventor
陆有传
谯志
刘明友
黄新
姚松柏
赵大昭
陆国清
赵帅鹏
张琳
朱淑兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Civil Engineering Co Ltd of CREC
Fifth Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Original Assignee
Shanghai Civil Engineering Co Ltd of CREC
Fifth Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Civil Engineering Co Ltd of CREC, Fifth Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC filed Critical Shanghai Civil Engineering Co Ltd of CREC
Priority to CN201821971636.0U priority Critical patent/CN209368697U/en
Application granted granted Critical
Publication of CN209368697U publication Critical patent/CN209368697U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a kind of tensioning pylons, including pylon main body and tensioning system, the pylon main body includes the first pylon structure, the second pylon structure and third pylon structure surrounded by more root posts, first pylon structure and third pylon structure be it is arranged symmetrically, the second pylon structure setting is between the first pylon structure and third pylon structure;The pylon main body further includes more web members being connected between column and multiple cable saddles that pylon body top is arranged in.The utility model conducts steel girder front end component to rear by setting tower with suspended cable, using steel strand wires, steel girder bending-down is reduced, to guarantee steel nose girder smoothly upper pier.

Description

A kind of tensioning pylon
Technical field
The utility model relates to tower technique field more particularly to a kind of tensioning pylons.
Background technique
Currently, since pushing tow span is big, the length and weight of steel nose girder are difficult during Large-span Steel Box Beam incremental launching construction In meeting the requirements, thus how to guarantee that smoothly upper pier becomes a stubborn problem to steel nose girder.
Utility model content
The purpose of this utility model is to provide a kind of tensioning pylons to be passed by the way that tower with suspended cable is arranged using steel strand wires Steel girder front end component is led to rear, steel girder bending-down is reduced, guarantees steel nose girder smoothly upper pier.
To achieve the goals above, the technical solution adopted in the utility model is as follows:
A kind of tensioning pylon, including pylon main body and tensioning system, the pylon main body include being surrounded by more root posts The first pylon structure, the second pylon structure and third pylon structure, first pylon structure and third pylon structure are pair Claim setting, second pylon structure is arranged between the first pylon structure and third pylon structure;The pylon main body is also wrapped Include more web members being connected between column and multiple cable saddles that pylon body top is set.
Preferably, the tensioning system includes more tensioning ropes, one end of the tensioning rope is arranged in pylon main body Top.
Preferably, one end of the tensioning rope is arranged on cable saddle.
Preferably, the tensioning rope is 8, the tensioning rope is steel strand wires.
Preferably, the cable saddle is 8.
Preferably, the web member is made of φ 325mm steel pipe.
Preferably, the column is 8, it is made of φ 630mm steel pipe.
Preferably, the height of the pylon main body is 20-25m.
The utility model is by adopting the above-described technical solution, have the advantages that
The tensioning of the utility model is designed simply with pylon structure, and by the way that tensioning pylon is arranged, cable saddle is as steel strand wires The steering supporting point of tensioning conducts steel girder front end component to rear using steel strand wires, reduces steel girder bending-down, guarantee that steel is led Beam smoothly goes up pier;After first round steel box-girder pushing tow, by setting up pylon main body, cable saddle is arranged in top, installs steel strand wires, into Row tensioning adjusts Suo Li, reaches job specfication requirement, is carrying out subsequent passes steel box-girder pushing tow.
Detailed description of the invention
Fig. 1 is the cross-sectional configuration schematic diagram of the tensioning pylon of the utility model;
Fig. 2 is the longitudinal plane structure schematic diagram of the tensioning pylon of the utility model;
Fig. 3 is the usage state diagram of the tensioning pylon of the utility model.
In attached drawing, 1- pylon main body, 2- tensioning rope, 3- steel box-girder, 4- steel nose girder, the first pylon structure of 101-, 102- Second pylon structure, 103- third pylon structure, 104- column, 105- web member, the oblique web member of 105a-, 105b- transverse direction web member, 106- cable saddle.
Specific embodiment
For the purpose of this utility model, technical solution and advantage is more clearly understood, referring to the drawings and enumerate excellent Embodiment is selected, the utility model is further described.However, it is necessary to illustrate, many details listed in specification It is specific thin even without these just for the sake of making reader have a thorough explanation to one or more aspects of the present invention These aspects of the utility model also may be implemented in section.
Embodiment 1
As shown in Figure 1-3, a kind of tensioning pylon according to the present utility model, including pylon main body 1 and tensioning system, institute Stating pylon main body 1 includes the first pylon structure 101, the second pylon structure 102 and third pylon knot surrounded by more root posts 104 Structure 103, first pylon structure 101 are arranged symmetrically, the setting of the second pylon structure 102 with third pylon structure 103 Between the first pylon structure 101 and third pylon structure 103;The pylon main body 1 further includes being connected between column 104 More web members 105 and multiple cable saddles 106 that 1 top of pylon main body is arranged in, wherein web member includes oblique web member 105a and transverse direction Web member 105b;The tensioning system includes more tensioning ropes 2, and the top of pylon main body 1 is arranged in one end of the tensioning rope 2 Portion, more specifically, one end of the tensioning rope 2 is arranged on cable saddle 106;The tensioning rope 2 is 8, the tensioning rope Rope 2 is steel strand wires;The cable saddle 106 is 8.
Preferably, the web member 105 is made of φ 325mm steel pipe;The column 104 is 8, by φ 630mm steel pipe system At;The height of the pylon main body 1 is 20-25m.
The working process of the utility model is as follows:
Master operation:
1. pylon is set up
Main stress structural system of the pylon main body 1 as steel strand tension conductance, it is distinguished by 8 φ 630mm steel pipes It is welded in above steel box-girder web, structural system of the φ 325mm steel pipe as connection web member composition.
2. cable saddle is arranged in top
Cable saddle 106, the steering supporting point as steel strand tension are set at the top of pylon main body 1.
3. steel strand wires installation and tensioning
In the 1 front end position 40m of pylon main body, the rear end position 80m carries out hoist cable installation and tensioning;By steel strand wires in steel case 3 front end of beam is fixed, as fixing end;By cable saddle 106, fixed at 3 rear of steel box-girder, as stretching end, by very heavy Top carries out tensioning, adjusts Suo Li, so that 3 front end deflection of steel box-girder reaches construction prescribed requirement, to guarantee that steel nose girder 4 is smooth Upper pier.After 3 pushing tow of first round steel box-girder, pylon main body 1 is set up, cable saddle 106 is arranged in top, installs steel strand wires, is opened It draws, adjusts Suo Li, reach job specfication requirement, carrying out 3 pushing tow of subsequent passes steel box-girder.
The above is only the preferred embodiment of the utility model, it is noted that for the common skill of the art For art personnel, without departing from the principle of this utility model, can also make several improvements and retouch, these improve and Retouching also should be regarded as the protection scope of the utility model.

Claims (8)

1. a kind of tensioning pylon, it is characterised in that: including pylon main body and tensioning system, the pylon main body includes by more The first pylon structure, the second pylon structure and the third pylon structure that column surrounds, first pylon structure and third pylon Structure be it is arranged symmetrically, second pylon structure is arranged between the first pylon structure and third pylon structure;The pylon Main body further includes more web members being connected between column and multiple cable saddles that pylon body top is arranged in.
2. a kind of tensioning pylon according to claim 1, it is characterised in that: the tensioning system includes more tensioning ropes The top of pylon main body is arranged in one end of rope, the tensioning rope.
3. a kind of tensioning pylon according to claim 2, it is characterised in that: one end of the tensioning rope is arranged in rope On saddle.
4. a kind of tensioning pylon according to claim 3, it is characterised in that: the tensioning rope is 8, the tensioning Rope is steel strand wires.
5. a kind of tensioning pylon according to claim 3, it is characterised in that: the cable saddle is 8.
6. a kind of tensioning pylon according to claim 1, it is characterised in that: the web member is made of φ 325mm steel pipe.
7. a kind of tensioning pylon according to claim 1, it is characterised in that: the column is 8, by φ 630mm steel Pipe is made.
8. a kind of tensioning pylon according to claim 1, it is characterised in that: the height of the pylon main body is 20- 25m。
CN201821971636.0U 2018-11-28 2018-11-28 A kind of tensioning pylon Expired - Fee Related CN209368697U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821971636.0U CN209368697U (en) 2018-11-28 2018-11-28 A kind of tensioning pylon

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821971636.0U CN209368697U (en) 2018-11-28 2018-11-28 A kind of tensioning pylon

Publications (1)

Publication Number Publication Date
CN209368697U true CN209368697U (en) 2019-09-10

Family

ID=67834033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821971636.0U Expired - Fee Related CN209368697U (en) 2018-11-28 2018-11-28 A kind of tensioning pylon

Country Status (1)

Country Link
CN (1) CN209368697U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110904860A (en) * 2019-11-07 2020-03-24 中铁大桥局集团第一工程有限公司 Large-span flexible steel beam pushing construction method based on stay cable assistance

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110904860A (en) * 2019-11-07 2020-03-24 中铁大桥局集团第一工程有限公司 Large-span flexible steel beam pushing construction method based on stay cable assistance
CN110904860B (en) * 2019-11-07 2022-02-01 中铁大桥局集团第一工程有限公司 Large-span flexible steel beam pushing construction method based on stay cable assistance

Similar Documents

Publication Publication Date Title
CN101476293B (en) Non-stand construction method for large bridge arch rib
CN105863145B (en) Beam-string structure, beam string and building
CN102444086A (en) Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge
CN105401714A (en) Attached lifting scaffold and lifting method
CN104110086A (en) Suspended dome and plane prestress combined structure, tensioning tool and construction method
CN206071141U (en) Transformer substation framework beam
CN202012047U (en) Steel strand inclined pulling and buckling system of tower
WO2021143647A1 (en) Ultra-long steel strand threading construction method for continuous beam
CN105256728B (en) A kind of cantilever erection method of the Chinese human relations formula steel truss girder of cable-stayed bridge
CN109853393A (en) A kind of the hanging cable construction system and its construction method of king-tower vertical transfer cable-stayed bridge
CN209368697U (en) A kind of tensioning pylon
CN106498837A (en) A kind of novel bridge and its construction method
CN106087759B (en) A kind of threading method of prestressed strand threader and prestressed strand
CN108505623A (en) A kind of overhead cable construction method suitable for flexible double rope net system
CN107476195A (en) A kind of suspension bridge transports the fortune beam tackle system of stiff girder
CN106049881A (en) Method for ultralong-distance penetration of prestressed anchor cable
CN203200665U (en) Prestressing steel strand threading device for bridge construction
CN205857670U (en) A kind of external wall construction hanging basket is encorbelmented device
CN210714046U (en) Device for lifting inverted chimney steel inner cylinder by using steel twisted rope hydraulic pressure
CN204644869U (en) Drag-line bridge tower anchoring structure
CN209779465U (en) main tower erects cable-stay bridge's string cable construction system that changes
CN209128888U (en) Anchor head traction device after a kind of suspension bridge dorsal funciculus
CN207597851U (en) Wall-attached supporting seat drawknot device
CN101210417B (en) Fastener and anchor cable system bidirectional simple supported non-torsion tower top tension anchoring method
CN110541599A (en) Device for lifting inverted chimney steel inner cylinder by using steel twisted rope hydraulic pressure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant