CN209333344U - A kind of construction site sewage-treatment plant - Google Patents

A kind of construction site sewage-treatment plant Download PDF

Info

Publication number
CN209333344U
CN209333344U CN201821420498.7U CN201821420498U CN209333344U CN 209333344 U CN209333344 U CN 209333344U CN 201821420498 U CN201821420498 U CN 201821420498U CN 209333344 U CN209333344 U CN 209333344U
Authority
CN
China
Prior art keywords
fixedly installed
cartridge filter
end outer
process chamber
motor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821420498.7U
Other languages
Chinese (zh)
Inventor
张凤江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Shengshi Xintong Environmental Protection Equipment Co Ltd
Original Assignee
Tianjin Shengshi Xintong Environmental Protection Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Shengshi Xintong Environmental Protection Equipment Co Ltd filed Critical Tianjin Shengshi Xintong Environmental Protection Equipment Co Ltd
Priority to CN201821420498.7U priority Critical patent/CN209333344U/en
Application granted granted Critical
Publication of CN209333344U publication Critical patent/CN209333344U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of construction site sewage-treatment plants, including process chamber, funnel and bracket, the inside of the process chamber is equipped with rotating cabin close to intermediate position, and the bosom position of rotating cabin is fixedly installed with concentrator bowl, the two sides position of the concentrator bowl is fixedly installed with apopore, and the two sides position of concentrator bowl is equipped with the first cartridge filter, one side of first cartridge filter is equipped with the second cartridge filter, the inside of first cartridge filter is fixedly installed with absorption sponge plate, and the two sides position of first cartridge filter is equipped with clamping item.A kind of construction site sewage-treatment plant is by being provided with scraper plate, concentrator bowl and shake motor, scraper plate can all wipe the soil being sticked on inner wall of hopper off, avoid the phenomenon that generating blocking, the quality of filtering can be improved by the rotation of concentrator bowl and the filtering of the first cartridge filter and the second cartridge filter simultaneously, the rate for improving filtering, enhances practicability.

Description

A kind of construction site sewage-treatment plant
Technical field
The utility model relates to technical field of sewage, specially a kind of construction site sewage-treatment plant.
Background technique
Sewage treatment is discharged into the mistake that a certain water body or the water quality requirement reused purify it to reach sewage Journey.It is each that sewage treatment is widely used in building, agricultural, traffic, the energy, petrochemical industry, environmental protection, urban landscape, medical treatment, food and drink etc. The daily life of common people is also come into field more and more.
Now sewage-treatment plant on-site is when in use because the silt in sewage is excessive, under will appear The phenomenon that hopper blocks, and not thorough enough, device complicated integral structure is handled, inconvenience operation.
Utility model content
The purpose of this utility model is to provide a kind of construction site sewage-treatment plants, to solve above-mentioned background technique The problem of middle proposition is easy to happen blocking, and processing is not thorough enough, and structure is complicated, inconvenience operation.
To achieve the above object, the utility model provides the following technical solutions: a kind of construction site sewage-treatment plant, Including process chamber, funnel and bracket, the inside of the process chamber is equipped with rotating cabin close to intermediate position, and in the inside of rotating cabin Between position be fixedly installed with concentrator bowl, the two sides position of the concentrator bowl is fixedly installed with apopore, and the both sides of concentrator bowl Position is equipped with the first cartridge filter, and a side of first cartridge filter is equipped with the second cartridge filter, the inside of first cartridge filter It is fixedly installed with absorption sponge plate, the two sides position of first cartridge filter is equipped with clamping item, and the absorption sponge plate passes through card Narrow bars are connect with the first cartridge filter, and first cartridge filter is identical as the second cartridge filter internal structure, second cartridge filter Lower end outer surface is fixedly installed with water pipe, and the top and bottom outer surface of the rotating cabin is fixedly installed with fixed block, and solid Block is determined equipped with track, and the two sides position of the fixed block is equipped with runner, is fixedly installed on the upper end inner wall of the process chamber Connecting tube, and filter screen is fixedly installed in connecting tube, the lower portion of the rotating cabin is equipped with first motor, the process chamber Lower end outer surface be fixedly installed with fixed frame, and shake motor is fixedly installed on fixed frame, it is fixed on the shake motor Traction rope is installed, the funnel is fixedly mounted on the upper end outer surface of process chamber, and the fixed peace in upper end outer surface of process chamber Equipped with water inlet, a side of the water inlet is fixedly installed with the second motor, and the lower end outer surface of the second motor is fixed Swingle is installed, two side external surfaces of the swingle are fixedly installed with connecting rod, and scraper plate is fixedly installed in connecting rod, The bracket is fixedly mounted on the lower end outer surface of process chamber, and the intermediate position of the bracket is fixedly installed with filter frame, and mistake The inside of filter frame is fixedly installed with web plate, and the lower end outer surface of the filter frame is fixedly installed with water outlet.
Preferably, a side external surface of the process chamber is fixedly installed with conducting wire, and the end of conducting wire is fixedly installed with plug.
Preferably, the lower end outer surface of the funnel is fixedly installed with cavity, and cavity is fixedly connected with connecting tube.
Preferably, the upper end outer surface of the first motor is fixedly installed with shaft, and rotating cabin passes through shaft and first Motor is fixedly connected.
Preferably, link block is fixedly installed on the web plate, the lower end outer surface of the web plate is fixedly installed with spring, And web plate is fixedly connected by link block with traction rope.
Preferably, valve is fixedly installed on the water outlet.
Compared with prior art, the utility model has the beneficial effects that a kind of construction site sewage-treatment plant, leads to It crosses and is provided with scraper plate, concentrator bowl and shake motor, scraper plate can all wipe the soil being sticked on inner wall of hopper off, avoid generating stifled The phenomenon that plug, while the matter of filtering can be improved by the rotation of concentrator bowl and the filtering of the first cartridge filter and the second cartridge filter Amount, improves the rate of filtering, enhances practicability;
(1) it is provided with scraper plate, drives swingle to be rotated by the second motor, so that swingle drives scraper plate in funnel Inside rotated, scraper plate rotation can by inner wall of hopper soil and impurity clear up, guarantee funnel inside cleaning With the generation for preventing clogging;
(2) it is provided with swivelling chute, drives rotating cabin to be rotated by first motor, sewage can carry out height in concentrator bowl The rotation of speed, and sewage can be flowed in the first cartridge filter and the second cartridge filter by apopore, the first cartridge filter and the second filtering Absorption sponge plate inside cylinder can absorb the impurity in sewage, carry out cleaning treatment to sewage, improve the speed of processing Degree and quality;
(3) it is provided with shake motor, drives traction rope to be shaken by shake motor, traction rope will drive web plate progress Shake, can efficiently handle sewage by the shake of web plate, be filtered sewage repeatedly adequately on web plate, Improve the quality of processing.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the structural schematic diagram of funnel in the utility model;
Fig. 3 is the structural schematic diagram of rotating cabin in the utility model;
Fig. 4 is the structural schematic diagram of the first cartridge filter in the utility model.
In figure: 1, process chamber;2, funnel;3, bracket;4, rotating cabin;5, fixed block;6, track;7, runner;8, concentrator bowl; 9, apopore;10, the first cartridge filter;11, the second cartridge filter;12, first motor;13, connecting tube;14, filter screen;15, water pipe; 16, water inlet;17, the second motor;18, swingle;19, connecting rod;20, scraper plate;21, fixed frame;22, motor is shaken;23, it leads Messenger;24, filter frame;25, web plate;26, water outlet;27, shaft;28, sponge plate is adsorbed;29, it is clamped item.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-4 is please referred to, a kind of embodiment provided by the utility model:
A kind of construction site sewage-treatment plant, including process chamber 1, funnel 2 and bracket 3, the inside of process chamber 1 are close Intermediate position is equipped with rotating cabin 4, and the bosom position of rotating cabin 4 is fixedly installed with concentrator bowl 8, the both sides of concentrator bowl 8 Position is fixedly installed with apopore 9, and the two sides position of concentrator bowl 8 is equipped with the first cartridge filter 10, a side of the first cartridge filter 10 Equipped with the second cartridge filter 11, the inside of the first cartridge filter 10 is fixedly installed with absorption sponge plate 28, the two sides of the first cartridge filter 10 Position is equipped with clamping item 29, and absorption sponge plate 28 is connect by being clamped item 29 with the first cartridge filter 10, the first cartridge filter 10 and the Two cartridge filters, 11 internal structure is identical, and the lower end outer surface of the second cartridge filter 11 is fixedly installed with water pipe 15, the upper end of rotating cabin 4 It is fixedly installed with fixed block 5 with lower end outer surface, and fixed block 5 is equipped with track 6, the two sides position of fixed block 5, which is equipped with, to be turned 7 are taken turns, is fixedly installed with connecting tube 13 on the upper end inner wall of process chamber 1, and be fixedly installed with filter screen 14 in connecting tube 13, is rotated The lower portion in storehouse 4 is equipped with first motor 12, and the upper end outer surface of first motor 12 is fixedly installed with shaft 27, and rotating cabin 4 It is fixedly connected by shaft 27 with first motor 12.
Preferably, sewage can flow in concentrator bowl 8 when sewage is poured into rotating cabin 4, first motor is opened 12, first motor 12 drives rotating cabin 4 to be rotated by shaft 27, sewage can in concentrator bowl 8 high speed rotation, and sewage It can be flowed in the first cartridge filter 10 and the second cartridge filter 11 from apopore 9, by the first cartridge filter 10 and the second cartridge filter 11 The absorption sponge plate 28 in portion can fall the impurity absorption in sewage, and make sewage repeatedly and absorption sponge under the action of rotation Plate 28 contacts, and makes sewage by repeatedly processing, improves the quality of processing, the sewage after processing can flow to filtering by water pipe 15 Inside frame 24.
The lower end outer surface of process chamber 1 is fixedly installed with fixed frame 21, and shake motor is fixedly installed on fixed frame 21 22, it shakes and is fixedly installed with traction rope 23 on motor 22, traction rope 23 can be driven to be shaken by shaking motor 22, handled One side external surface of room 1 is fixedly installed with conducting wire, and the end of conducting wire is fixedly installed with plug, can will be filled by conducting wire and plug Set energization.
Funnel 2 is fixedly mounted on the upper end outer surface of process chamber 1, and the lower end outer surface of funnel 2 is fixedly installed with cavity, empty Chamber is fixedly connected with connecting tube 13, and the upper end outer surface of process chamber 1 is fixedly installed with water inlet 16, a side of water inlet 16 Position is fixedly installed with the second motor 17, and the lower end outer surface of the second motor 17 is fixedly installed with swingle 18, swingle 18 Two side external surfaces are fixedly installed with connecting rod 19, and scraper plate 20 is fixedly installed in connecting rod 19.
Preferably, sewage is poured into funnel 2 from water inlet 16, the second motor 17, the second motor are opened simultaneously 17 drive swingles 18 are rotated, and swingle 18 drives connecting rod 19 to be rotated, while connecting rod 19 drives scraper plate 20 to exist It is rotated, and then can be struck off remaining silt on the inner wall to funnel 2 in funnel 2, to be carried out clearly to funnel 2 Clean, avoiding funnel 2, there is a phenomenon where block.
Bracket 3 is fixedly mounted on the lower end outer surface of process chamber 1, and the intermediate position of bracket 3 is fixedly installed with filter frame 24, And the inside of filter frame 24 is fixedly installed with web plate 25, the active carbon inside web plate 25 can inhale the impurity inside sewage It is attached, link block is fixedly installed on web plate 25, the lower end outer surface of web plate 25 is fixedly installed with spring, and web plate 25 passes through connection Block is fixedly connected with traction rope 23, and the lower end outer surface of filter frame 24 is fixedly installed with water outlet 26, fixed peace on water outlet 26 Equipped with valve.
Preferably, opening shake motor 22 when sewage flows in filter frame 24 from water pipe 15, shaking 22 band of motor Dynamic traction rope 23 is shaken, and traction rope 23 will drive web plate 25 and be shaken, by the shake of web plate 25 can to sewage into The efficient processing of row, is filtered sewage repeatedly adequately on web plate 25, improves the quality of processing.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this is practical new in other specific forms Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this is practical new The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing for the equivalent requirements of the claims will be fallen in All changes in justice and range are embraced therein.It should not treat any reference in the claims as limiting Related claim.

Claims (6)

1. a kind of construction site sewage-treatment plant, including process chamber (1), funnel (2) and bracket (3), it is characterised in that: institute The inside for stating process chamber (1) is equipped with rotating cabin (4) close to intermediate position, and the bosom position of rotating cabin (4) is fixedly mounted Have concentrator bowl (8), the two sides position of the concentrator bowl (8) is fixedly installed with apopore (9), and the two sides position of concentrator bowl (8) Equipped with the first cartridge filter (10), a side of first cartridge filter (10) is equipped with the second cartridge filter (11), first mistake The inside of filter cylinder (10) is fixedly installed with absorption sponge plate (28), and the two sides position of first cartridge filter (10) is equipped with clamping item (29), the absorption sponge plate (28) is connect by being clamped item (29) with the first cartridge filter (10), first cartridge filter (10) Identical as the second cartridge filter (11) internal structure, the lower end outer surface of second cartridge filter (11) is fixedly installed with water pipe (15), the top and bottom outer surface of the rotating cabin (4) is fixedly installed with fixed block (5), and fixed block (5) is equipped with rail The two sides position in road (6), the fixed block (5) is equipped with runner (7), is fixedly installed on the upper end inner wall of the process chamber (1) Connecting tube (13), and be fixedly installed with filter screen (14) in connecting tube (13), the lower portion of the rotating cabin (4) is equipped with first The lower end outer surface of motor (12), the process chamber (1) is fixedly installed with fixed frame (21), and is fixedly mounted on fixed frame (21) Have shake motor (22), be fixedly installed with traction rope (23) on the shake motor (22), the funnel (2) is fixedly mounted on place The upper end outer surface of room (1) is managed, and the upper end outer surface of process chamber (1) is fixedly installed with water inlet (16), the water inlet (16) a side is fixedly installed with the second motor (17), and the lower end outer surface of the second motor (17) is fixedly installed with rotation Two side external surfaces of bar (18), the swingle (18) are fixedly installed with connecting rod (19), and are fixedly mounted in connecting rod (19) Have scraper plate (20), the bracket (3) is fixedly mounted on the lower end outer surface of process chamber (1), and the intermediate position of the bracket (3) is solid Dingan County is equipped with filter frame (24), and the inside of filter frame (24) is fixedly installed with web plate (25), the lower end of the filter frame (24) Outer surface is fixedly installed with water outlet (26).
2. a kind of construction site sewage-treatment plant according to claim 1, it is characterised in that: the process chamber (1) A side external surface be fixedly installed with conducting wire, the end of conducting wire is fixedly installed with plug.
3. a kind of construction site sewage-treatment plant according to claim 1, it is characterised in that: the funnel (2) Lower end outer surface is fixedly installed with cavity, and cavity is fixedly connected with connecting tube (13).
4. a kind of construction site sewage-treatment plant according to claim 1, it is characterised in that: the first motor (12) upper end outer surface is fixedly installed with shaft (27), and rotating cabin (4) is fixed by shaft (27) and first motor (12) Connection.
5. a kind of construction site sewage-treatment plant according to claim 1, it is characterised in that: on the web plate (25) It is fixedly installed with link block, the lower end outer surface of the web plate (25) is fixedly installed with spring, and web plate (25) passes through link block It is fixedly connected with traction rope (23).
6. a kind of construction site sewage-treatment plant according to claim 1, it is characterised in that: the water outlet (26) On be fixedly installed with valve.
CN201821420498.7U 2018-08-31 2018-08-31 A kind of construction site sewage-treatment plant Expired - Fee Related CN209333344U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821420498.7U CN209333344U (en) 2018-08-31 2018-08-31 A kind of construction site sewage-treatment plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821420498.7U CN209333344U (en) 2018-08-31 2018-08-31 A kind of construction site sewage-treatment plant

Publications (1)

Publication Number Publication Date
CN209333344U true CN209333344U (en) 2019-09-03

Family

ID=67743823

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821420498.7U Expired - Fee Related CN209333344U (en) 2018-08-31 2018-08-31 A kind of construction site sewage-treatment plant

Country Status (1)

Country Link
CN (1) CN209333344U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113499631A (en) * 2021-07-29 2021-10-15 合肥志诚邦远家居有限责任公司 Be used for panel mill to use sewage treatment device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113499631A (en) * 2021-07-29 2021-10-15 合肥志诚邦远家居有限责任公司 Be used for panel mill to use sewage treatment device

Similar Documents

Publication Publication Date Title
CN208829405U (en) A kind of sandfiltration pot
CN109292880A (en) A kind of sewage-treatment plant with anti-blockage function
CN107700587A (en) A kind of rain collector
CN208839110U (en) A kind of quartz filter
CN208244814U (en) A kind of discarded concrete crushing device
CN108786268A (en) A kind of sewage-treatment plant
CN209333344U (en) A kind of construction site sewage-treatment plant
CN202026707U (en) Water-dirt separator
CN207856469U (en) A kind of anticlogging sewage-treatment plant
CN204395583U (en) Self-cleaning brush type filter
CN207108726U (en) Possesses the activated carbon filter for being stirred function
CN209576175U (en) A kind of environmental project removing dust and clearing ash device
CN102144605A (en) Water sewage separator
CN207276412U (en) A kind of high-efficiency fibre filter
CN207722467U (en) A kind of novel rotary type sewage grid maker
CN106731209A (en) A kind of environmental protection building material production sewage disposal device
CN214735062U (en) River water purifying equipment
CN209098355U (en) A kind of sewage disposal device purified with microfiltration membranes
CN209740867U (en) Sewage treatment equipment
CN209997267U (en) conveniently-assembled sewage treatment device
CN208429889U (en) A kind of Novel domestic sewage treatment device
CN208586136U (en) A kind of water correction plant
CN208599247U (en) A kind of low-pressure micro-resistance quartz sand filter
CN207680151U (en) A kind of cloth envelop collector
CN202690108U (en) Coal mine dust-removing equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190903

Termination date: 20210831

CF01 Termination of patent right due to non-payment of annual fee