CN209311537U CN201821865559.0U CN201821865559U CN209311537U CN 209311537 U CN209311537 U CN 209311537U CN 201821865559 U CN201821865559 U CN 201821865559U CN 209311537 U CN209311537 U CN 209311537U
Authority
CN
China
Prior art keywords
several
test
connector
electrical apparatus
power transformer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821865559.0U
Other languages
Chinese (zh)
Inventor
赵铁羽
张犟
付克勤
陆毅娜
唐书窗
陈法锦
钟尚东
黄展
朱栋
奉永鹏
王勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Binshan Power Supply Co of State Grid Chongqing Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Binshan Power Supply Co of State Grid Chongqing Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Binshan Power Supply Co of State Grid Chongqing Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201821865559.0U priority Critical patent/CN209311537U/en
Application granted granted Critical
Publication of CN209311537U publication Critical patent/CN209311537U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Relating To Insulation (AREA)

Abstract

The utility model provides power transformer electrical apparatus test auxiliary connection device, includes shell, several connector links, several test joints and controller;Several connector link both ends are connected on two lead receptacles that shell is equipped with;Several test joints are set on each connector link;Several test joints are connect with each transformer phase connector;And trigger switch is connected separately between each test joint;The trigger switch control terminal is connect with controller;The controller includes driving unit and sequence switch unit;The output end of the sequence switch unit is connect with driving unit control terminal.The utility model proposes power transformer electrical apparatus test auxiliary connection device, test transformer phase connector is automatically switched by sequence switch unit, manpower is saved, and ensure that the safety of operator.

Description

Power transformer electrical apparatus test auxiliary connection device
Technical field
The utility model relates to maintenance of electrical equipment technical fields, and in particular to power transformer electrical apparatus test auxiliary connection Device.
Background technique
In the power system, a kind of most important power equipment is power transformer.Ensure the master of transformer safety operation Wanting method is to carry out electrical test to power transformer.At the scene during actual tests, due to the transformer of 35kV or more Height is mostly 1.5 meters or more, climbs up transformer after needing testing crew to fasten seat belts again and carries out test connection.During test Due to pilot project and the difference of experiment position, frequent reconfiguration line is needed, first is that causing setting up time much larger than test period The case where, second is that wiring personnel need to wait on the transformer for a long time, there are some potential safety problemss.In addition it is examined for safety Consider, also needs testing crew to climb down transformer waiting when carrying out certain high-voltage tests, climb up transformer again after to be tested Reconfiguration line further reduced the efficiency of test.Since current junction box is when testing the D.C. resistance of each test splice, Need the modes of connection, the working efficiencies such as the independent wiring of manual switching transformer, short circuit, ground connection low.Also, a transformer needs Multiple junction box's connections are corresponded to, are taken up space big, it is complicated for operation.Therefore, how to promote power transformer test efficiency, reduce Empirical risk, which becomes one, is worth the problem of thinking deeply.
Utility model content
Problem to be solved in the utility model is to provide power transformer for the above-mentioned deficiency in the presence of the prior art Device electrical apparatus test auxiliary connection device realizes automatic switchover transformer testing by sequence switch unit and driving unit Terminals improve test efficiency, reduce personnel's operational risk;And connector link is set as U-shaped, multiple examinations can be installed Connector is tested, multiple junction boxes are integrated into the same junction box, save installation space.
A part to achieve the above object, the utility model use the following technical solution:
Power transformer electrical apparatus test auxiliary connection device includes shell, several connector links, several test joints and control Device processed;Several connector link both ends are connected on two lead receptacles that shell is equipped with;If the dry test connects Head is set on each connector link;Several test joints are connect with each transformer phase connector;And between each test joint respectively It is connected with trigger switch;The trigger switch control terminal is connect with controller;The controller includes driving unit and sequence Switch unit;The output end of the sequence switch unit is connect with driving unit control terminal.
Further, the sequence switch unit includes low frequency/pulse-pattern generator, counter and analog switch;Institute The output of low frequency/pulse-pattern generator is stated to be connected with the input of counter;The output of the counter and the ground of analog switch Location control terminal is connected;The output of the analog switch and the control terminal of each trigger switch are separately connected.
Further, several connector links are U-shaped;It is same that two free end of each connector link is connected to shell On two lead receptacles of side;The test joint of each connector link connection includes at least two.
Further, several connector links include several high pressure connection connecting rods, several middle crimp head connecting rods and several Low-pressure connector connecting rod;Several high pressure connection connecting rods, several middle crimp head connecting rods and several low-pressure connector connecting rods are separately connected On shell not the same side.
Further, the address control terminal of the analog switch is connected with manual switch;The manual switch Output end connect with driving unit input terminal.
Further, the driving unit includes driving motor and insulating barrier;The insulating barrier is set to each test and connects Between head;The driving motor for control insulating barrier into and out.
The working principle and beneficial effect of the utility model are as follows: switching signal control driving is issued by sequence switch unit Unit, driving unit issues driving signal and controls connecting or disconnecting for each trigger switch, to complete each lead receptacle and transformer The sequential testing of phase connector;It realizes that the switching to different tests connector connects by sequence switch unit, is surveyed by outer connecting resistance Measuring appratus tests the insulation resistance or D.C. resistance between different tests case;Connector link is set as U-shaped, makes the examination in test box It tests connector quantity to increase, improves the integrated level of the test joint of chamber;By high pressure connection connecting rod, several middle crimp head connecting rods It is respectively provided at shell not the same side with several low-pressure connector connecting rods, convenient for distinguishing connector link and corresponding transformer phase connector phase Even.
The further advantage, target and feature of the utility model will be partially reflected by the following instructions, and part will also pass through Research and practice to the utility model and be understood by the person skilled in the art.
Detailed description of the invention
Fig. 1 is that embodiment power transformer electrical apparatus test auxiliary connection device uses schematic diagram;
Fig. 2 is embodiment power transformer electrical apparatus test auxiliary connection schematic diagram of device.
The utility model is marked comprising the following drawings: transformer 1, phase connector 2, wire clamp 3, insulator pin 4, shell 5, connector Connecting rod 6, test joint 7, insulating barrier 8, lead receptacle 9.
Specific embodiment
In order to make technological means of the utility model, creation characteristic, reach purpose and effect is more clear and is easy to Understand, the utility model be further elaborated with reference to the accompanying drawings and detailed description:
As shown in Figure 1,1 electrical apparatus test auxiliary connection case of power transformer, comprising shell 5, several connector links 6, several Test joint 7 and controller;6 both ends of several connector links are connected to two lead receptacles 9 that shell 5 is equipped with On;Several test joints 7 are set on each connector link 6;Several test joints 7 connect with each 1 phase connector 2 of transformer It connects;And trigger switch is connected separately between each test joint 7;The trigger switch control terminal is connect with controller;The control Device processed includes driving unit and sequence switch unit;The output end and driving unit control terminal of the sequence switch unit connect It connects.
As shown in Fig. 2, 1 electrical apparatus test auxiliary connection case schematic diagram of power transformer, the sequence switch unit includes low Frequently/pulse-pattern generator, counter and analog switch;The output of the low frequency/pulse-pattern generator and counter it is defeated Enter connected;The output of the counter is connected with the address control terminal of analog switch;The output of the analog switch and each triggering The control terminal of switch is separately connected.
Several connector links 6 are U-shaped;6 liang of free ends of each connector link are connected to 5 the same side of shell On two lead receptacles 9;The test joint 7 that each connector link 6 connects includes at least two.
Several connector links 6 include that several high pressure connection connecting rods 6, several middle crimp head connecting rods 6 and several low pressure connect Head connecting rod 6;Several high pressure connection connecting rods 6, several middle crimp head connecting rods 6 and several low-pressure connector connecting rods 6 are connected to Shell 5 is not on the same side.
The address control terminal of the analog switch is connected with manual switch;The output end of the manual switch with The connection of driving unit input terminal.
The driving unit includes driving motor and insulating barrier 8;The insulating barrier 8 is set between each test joint 7; The driving motor for control insulating barrier 8 into and out.Insulating barrier 8 is equipped with the bar shaped that may pass through connector link 6 Through-hole, connector link 6 are movable in strip through-hole.
The working principle of this programme are as follows: insulator pin 4 is connected on test joint 7, insulator pin 4 stretches out lead receptacle 9 One end is connected with wire clamp 3,1 power supply of transformer is closed, by the high pressure connection connecting rod 6 of wire clamp 3, middle crimp head connecting rod 6 and low pressure After connector link 6 is connect with each phase connector 2 of 1 senior middle school's low-pressure side of transformer one by one respectively, 1 power supply of transformer is opened, and connect The controller power source of line case.Low frequency/pulse-pattern generator of sequence switch unit, will after the voltage pulse of transformer 1 It is counted according to the output of impulse waveform, and controls analog switch and switch over, realize the effect of short circuit, to realize each Analog switch between test joint 7 disconnects or connection, tests the combined D.C. resistance of different 1 phase connectors 2 of transformer to facilitate, When test, external resistance apparatus is needed.And by being only connected to high pressure, middle pressure or 6 any one of them of low-pressure connector connecting rod, It can insulation resistance under the different pressure of test transformer 1.At this point, driving motor by the insulation between the test joint 7 of connection every Plate 8 is put down, and promotes the dielectric strength between two test joints 7, reduces electromagnetic field shadow of each test joint 7 by surge voltage It rings.Specified analog switch, which can be connected to, by manual switch carries out single-phase test.
Finally, it is stated that above embodiments are merely intended for describing the technical solutions of the present application, but not for limiting the present application, it can be right The technical solution of the utility model is modified or replaced equivalently, without departing from the objective and model of technical solutions of the utility model It encloses, should all cover in the scope of the claims of the utility model.

Claims (6)

1. power transformer electrical apparatus test auxiliary connection device, which is characterized in that include shell, several connector links, Ruo Ganshi Test connector and controller;Several connector link both ends are connected on two lead receptacles that shell is equipped with;It is described Several test joints are set on each connector link;Several test joints are connect with each transformer phase connector;And each test connects Trigger switch is connected separately between head;The trigger switch control terminal is connect with controller;The controller includes driving Unit and sequence switch unit;The output end of the sequence switch unit is connect with driving unit control terminal.
2. power transformer electrical apparatus test auxiliary connection device according to claim 1, which is characterized in that the sequence is cut Changing unit includes low frequency/pulse-pattern generator, counter and analog switch;The output of the low frequency/pulse-pattern generator It is connected with the input of counter;The output of the counter is connected with the address control terminal of analog switch;The analog switch It exports and is separately connected with the control terminal of each trigger switch.
3. power transformer electrical apparatus test auxiliary connection device according to claim 1, which is characterized in that if the stem grafting Head connecting rod is U-shaped;Two free end of each connector link is connected on two lead receptacles of shell the same side;It is described each The test joint of connector link connection includes at least two.
4. power transformer electrical apparatus test auxiliary connection device according to claim 3, which is characterized in that if the stem grafting Head connecting rod includes several high pressure connection connecting rods, several middle crimp head connecting rods and several low-pressure connector connecting rods;Several high-voltage connectings Head connecting rod, several middle crimp head connecting rods and several low-pressure connector connecting rods are connected to shell not on the same side.
5. power transformer electrical apparatus test auxiliary connection device according to claim 2, which is characterized in that the simulation is opened The address control terminal of pass is connected with manual switch;The output end and driving unit input terminal of the manual switch connect It connects.
6. power transformer electrical apparatus test auxiliary connection device according to claim 1-5, which is characterized in that institute Stating driving unit includes driving motor and insulating barrier;The insulating barrier is set between each test joint;The driving motor For control insulating barrier into and out.
CN201821865559.0U 2018-11-13 2018-11-13 Power transformer electrical apparatus test auxiliary connection device Active CN209311537U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821865559.0U CN209311537U (en) 2018-11-13 2018-11-13 Power transformer electrical apparatus test auxiliary connection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821865559.0U CN209311537U (en) 2018-11-13 2018-11-13 Power transformer electrical apparatus test auxiliary connection device

Publications (1)

Publication Number Publication Date
CN209311537U true CN209311537U (en) 2019-08-27

Family

ID=67673164

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821865559.0U Active CN209311537U (en) 2018-11-13 2018-11-13 Power transformer electrical apparatus test auxiliary connection device

Country Status (1)

Country Link
CN (1) CN209311537U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109374934A (en) * 2018-11-13 2019-02-22 国网重庆市电力公司璧山供电分公司 A kind of power transformer electrical test auxiliary connection case

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109374934A (en) * 2018-11-13 2019-02-22 国网重庆市电力公司璧山供电分公司 A kind of power transformer electrical test auxiliary connection case

Similar Documents

Publication Publication Date Title
CN107544001B (en) The insulating test set of spacecraft thermal test cable
CN107271899B (en) A kind of test method of more specification voltage generating sets
CN112051491A (en) Full-automatic high-voltage transformer insulation and voltage resistance testing device
CN209311537U (en) Power transformer electrical apparatus test auxiliary connection device
CN109254243A (en) A kind of high-voltage circuitbreaker test short jumper device
CN105319466A (en) Medium voltage generating equipment simulated on-line detection test method
CN209728100U (en) DC break down voltage tests electric discharge device
CN202330518U (en) Anti-induction electric operation cabinet for parameter test of overhead power transmission lines
CN208316268U (en) A kind of cable broken skin earth leakage protective device
CN109374934A (en) A kind of power transformer electrical test auxiliary connection case
CN206788308U (en) Full-automatic multiloop secondary cable Insulation test servicing unit
CN111239643A (en) Single-phase grounding test device and method for power distribution network
CN213337883U (en) Insulation inspection device of closed bus duct
CN209979771U (en) Alternating current transmission line tree obstacle test device
CN104426088A (en) Voltage transformer handcart
CN113960400A (en) High-voltage testing system of new energy automobile
CN209148844U (en) A kind of high-voltage circuitbreaker test short jumper device
CN207542135U (en) A kind of remote control disconnecting switch
CN207601193U (en) It is a kind of from mutual nuclear phase display device
CN203224526U (en) A high-voltage wire connector used for AC withstanding voltage
CN205210272U (en) Direct current contactor switch -on breaking capacity test device under ambient condition of plateau
CN207380168U (en) A kind of device for checking cable connection
CN213715373U (en) Artificial intelligence multi-station distribution network high-voltage transformer insulation test diagnosis system
CN215678556U (en) Whole cabinet return circuit resistance testing arrangement of cubical switchboard
CN209016437U (en) A kind of 10kV switchgear distribution system

Legal Events

Date Code Title Description
GR01 Patent grant