CN209308057U - Civil engineering built pile - Google Patents

Civil engineering built pile Download PDF

Info

Publication number
CN209308057U
CN209308057U CN201821783345.9U CN201821783345U CN209308057U CN 209308057 U CN209308057 U CN 209308057U CN 201821783345 U CN201821783345 U CN 201821783345U CN 209308057 U CN209308057 U CN 209308057U
Authority
CN
China
Prior art keywords
several
stake
long
bed course
retaining wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821783345.9U
Other languages
Chinese (zh)
Inventor
薛勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821783345.9U priority Critical patent/CN209308057U/en
Application granted granted Critical
Publication of CN209308057U publication Critical patent/CN209308057U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

Civil engineering built pile, it is related to technical field of civil engineering;It includes soil horizon, stub, long stake, bed course and armoured concrete slab;Several stubs and several long stakes, stub and long stake interlaced arrangement are inserted in the soil horizon;The upper surface of several stubs, several long stakes and soil horizon is equipped with bed course, and the upper surface of bed course has poured armoured concrete slab;The stub and long stake are made of several main reinforcements, spiral bar, reinforcing rib, retaining wall, pile cover, concrete;The outer wall of the spiral bar is welded with several main reinforcements of circumference uniform distribution, reinforcing rib is welded between main reinforcement, the periphery of several main reinforcements is provided with retaining wall, has poured concrete in retaining wall, pours the pile cover of concrete in the upper end of several main reinforcements, spiral bar and retaining wall.The utility model freezing tolerance is strong, reduces destruction of the Frozen-thawed cycled to pile foundation and stake, and the high-speed rail stake for adapting to paramos area uses, and long service life reduces maintenance, repair cost.

Description

Civil engineering built pile
Technical field
The utility model relates to technical field of civil engineering, and in particular to civil engineering built pile.
Background technique
Civil engineering is to build the general designation of the science and technology of all kinds of job facilities.The purpose of civil engineering is to form mankind's life Produce or life required for, function is good and the space and channel of Comfortable attractive.It is both the needs in terms of substance, also there is symbol The demand of spiritual aspect.With the development of society, engineering structure is more and more large-scale, complicates, super high-rise building, large-scale bridges Beam, huge dam, complicated subway system continue to bring out, and meet people's lives demand, while also developing into social strength Symbol.It is the safety of engineering that civil engineering, which needs the root problem solved, and structure is enable to resist various natural or artificial works Firmly.
Built pile is to be inserted into prestressed-concrete pile in mixing pile and formed, and is mentioned including the big specific surface area of inner body Upper load is undertaken using internal high-intensitive concrete-pile core for frictional resistance, while again, this has high vertical bearing capacity, And low cost.
In high-speed railway civil engineering, in the bad section of the geology such as decayed rock, Frozen-thawed cycled damages pile foundation, The appearance repeatedly of Frozen-thawed cycled, causes the serious destruction of architectural construction, and Frozen-thawed cycled can cause serious inside architectural construction Weathering loses durability.Existing high-speed rail stake is limited by bearing capacity, settling amount, paramos area service life compared with Short, maintenance, maintenance cost are high.
Summary of the invention
The purpose of this utility model is that in view of the drawbacks of the prior art and insufficient, provide that a kind of structure is simple, design is closed Reason, civil engineering built pile easy to use.
In order to achieve the above purposes, the technical solution adopted by the utility model is:, and it includes soil horizon, stub, long stake, bed course And armoured concrete slab;Several stubs and several long stakes, stub and long stake interlaced arrangement are inserted in the soil horizon;It is described Several stubs, several long stakes and soil horizon upper surface be equipped with bed course, the upper surface of bed course has poured armored concrete Plate;The stub and long stake are made of several main reinforcements, spiral bar, reinforcing rib, retaining wall, pile cover, concrete;The spiral shell The outer wall of rotation muscle is welded with several main reinforcements of circumference uniform distribution, is welded with reinforcing rib between main reinforcement, the periphery of several main reinforcements is set It is equipped with retaining wall, has poured concrete in retaining wall, pours the stake of concrete in the upper end of several main reinforcements, spiral bar and retaining wall Cap.
Preferably, the length of the length stake is at least twice of stub.
Preferably, the bed course is coarse sand and natural soft-clay.
Preferably, the diameter of the main reinforcement and reinforcing rib is 14 ~ 20mm of φ, the diameter of spiral bar is φ 8mm.
Preferably, the bed course with a thickness of be greater than 150mm.
The working principle of the utility model are as follows: the stub of interlaced arrangement and long stake, and cooperate bed course and armoured concrete slab, The water stability and frost heaving resistant ability of lower soil, and diffusible load are improved, to reduce the deformation of soil horizon, while playing raising Bearing capacity, the effect for reducing settling amount and combining closely with soil layer;Spiral bar improves the compression strength of concrete, prevents from mixing Local failure occurs under the action of tension stress for solidifying soil, improves the service life of stub and long stake.
After adopting the above structure, the utility model is the beneficial effects are as follows: civil engineering described in the utility model is used Built pile, freezing tolerance is strong, reduces destruction of the Frozen-thawed cycled to pile foundation and stake, and the high-speed rail stake for adapting to paramos area uses, and makes It is long with the service life, maintenance, repair cost is reduced, the utility model has many advantages, such as that structure is simple, setting is reasonable, low manufacture cost.
Detailed description of the invention
Fig. 1 is the structure chart of the utility model;
Fig. 2 is the structure chart of the utility model stub or long stake;
Fig. 3 is the top view of Fig. 2.
Description of symbols:
Soil horizon 1, stub 2, long stake 3, bed course 4, armoured concrete slab 5, main reinforcement 6, spiral bar 7, reinforcing rib 8, retaining wall 9, Pile cover 10, concrete 11.
Specific embodiment
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, before not making the creative labor property It puts, is also possible to obtain other drawings based on these drawings.
Referring to such as Fig. 1 --- shown in Fig. 3, present embodiment adopts the following technical scheme that it includes soil horizon 1, short Stake 2, long stake 3, bed course 4 and armoured concrete slab 5;Several stubs 2 and several long stakes 3, stub are inserted in the soil horizon 1 2 with long 3 interlaced arrangement of stake;The upper surface of several stubs 2, several long stakes 3 and soil horizon 1 is equipped with bed course 4, bed course 4 upper surface has poured armoured concrete slab 5;The length of the length stake 3 is at least twice of stub 2, increases level, diffusion Load improves bearing capacity, reduces settling amount, combine closely with soil layer to reduce the deformation of soil horizon 1.
The stub 2 and long stake 3 is by several main reinforcements 6, spiral bar 7, reinforcing rib 8, retaining wall 9, pile cover 10, concrete 11 are constituted;The outer wall of the spiral bar 7 is welded with several main reinforcements 6 of circumference uniform distribution, is welded with reinforcing rib 8 between main reinforcement 6, The periphery of several main reinforcements 6 is provided with retaining wall 9, and concrete 11 has been poured in retaining wall 9, in several main reinforcements 6, spiral bar 7 and shield The upper end of wall 9 pours the pile cover 10 of concrete.Spiral bar 7 improves the compression strength of concrete 11, prevents concrete 11 from opening Local failure occurs under the action of tensile stress, improves the service life of stub 2 and long stake 3.
The bed course 4 is coarse sand and natural soft-clay, bed course 4 with a thickness of 150mm is greater than, the water for improving lower soil is steady Property and frost heaving resistant ability.
The diameter of the main reinforcement 6 and reinforcing rib 8 is 14 ~ 20mm of φ, and the diameter of spiral bar 7 is φ 8mm, improves carrying energy Power.
After adopting the above structure, present embodiment is the beneficial effects are as follows: soil described in present embodiment Wood engineering built pile, freezing tolerance is strong, reduces destruction of the Frozen-thawed cycled to pile foundation and stake, adapts to the high-speed rail stake in paramos area Use, long service life reduce maintenance, repair cost, and present embodiment is simple with structure, setting is reasonable, is fabricated to This low advantage.
The advantages of basic principles and main features and the utility model of the utility model have been shown and described above.This The technical staff of industry is retouched in above embodiments and description it should be appreciated that the present utility model is not limited to the above embodiments That states only illustrates the principles of the present invention, on the premise of not departing from the spirit and scope of the utility model, the utility model It will also have various changes and improvements, these various changes and improvements fall within the scope of the claimed invention.This is practical new Type is claimed range and is defined by the appending claims and its equivalent thereof.

Claims (5)

1. civil engineering built pile, it is characterised in that: it includes soil horizon, stub, long stake, bed course and armoured concrete slab; Several stubs and several long stakes, stub and long stake interlaced arrangement are inserted in the soil horizon;It is several stubs, several The upper surface of long stake and soil horizon is equipped with bed course, and the upper surface of bed course has poured armoured concrete slab;The stub and Long stake is made of several main reinforcements, spiral bar, reinforcing rib, retaining wall, pile cover, concrete;The outer wall of the spiral bar welds There are several main reinforcements of circumference uniform distribution, be welded with reinforcing rib between main reinforcement, the periphery of several main reinforcements is provided with retaining wall, in retaining wall Concrete has been poured, has poured the pile cover of concrete in the upper end of several main reinforcements, spiral bar and retaining wall.
2. civil engineering built pile according to claim 1, it is characterised in that: the length of the length stake is at least short Twice of stake.
3. civil engineering built pile according to claim 1, it is characterised in that: the bed course is coarse sand and natural sand Gravel.
4. civil engineering built pile according to claim 1, it is characterised in that: the diameter of the main reinforcement and reinforcing rib For 14 ~ 20mm of φ, the diameter of spiral bar is φ 8mm.
5. civil engineering built pile according to claim 1, it is characterised in that: the bed course with a thickness of being greater than 150mm。
CN201821783345.9U 2018-10-31 2018-10-31 Civil engineering built pile Expired - Fee Related CN209308057U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821783345.9U CN209308057U (en) 2018-10-31 2018-10-31 Civil engineering built pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821783345.9U CN209308057U (en) 2018-10-31 2018-10-31 Civil engineering built pile

Publications (1)

Publication Number Publication Date
CN209308057U true CN209308057U (en) 2019-08-27

Family

ID=67670195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821783345.9U Expired - Fee Related CN209308057U (en) 2018-10-31 2018-10-31 Civil engineering built pile

Country Status (1)

Country Link
CN (1) CN209308057U (en)

Similar Documents

Publication Publication Date Title
CN106592585B (en) A kind of expansion body compaction pile and construction method for eliminating pile foundation negative friction force
CN206581145U (en) A kind of concrete-bridge end deck installation structure for exempting from expansion joint
CN104120686B (en) A kind of high-elastic die-cushion A seating compound dam
CN206512588U (en) A kind of T-shaped steel tube confinement reinforced concrete bridge pier beam-column connection of assembled
CN201459716U (en) Retard-bonded or unbonded post-tensioned prestressing filling pile
CN102383420A (en) High-strength concrete prefabricated pile doped with fiber-reinforced plastic bar
CN103015414B (en) A kind of precast concrete post grouting pile and grouting process
CN202208916U (en) High-strength concrete prefabricated pile
CN201771514U (en) Concealed tunneling structure with pile foundation
CN204491649U (en) A kind of blower fan pile pier basis
CN209308057U (en) Civil engineering built pile
CN205934862U (en) Local high -modulus enrockment concrete -faced rockfill dam structure
CN207672344U (en) Railway bed karez location pin-connected panel foundation stabilization construction
CN202989911U (en) Post-grouting pile of precast concrete
CN203603525U (en) Reinforcing structure with clamp plate girder and clamp plate column externally arranged for stone structure
CN110042749A (en) UHPC steel tube concrete overlap-type lattice column structure and its construction method
CN206127866U (en) Retailing backwall capable of preventing high filling earthwork subgrade from bridge bump
CN2673944Y (en) Prestressed pipe pile with large end filled with sand
CN206457838U (en) A kind of assembling type base for power transmission tower
CN204919568U (en) Compound supporting construction of shallow foundation ditch
CN213476772U (en) Novel river bank protection structure
CN204898944U (en) Steel plate concrete that cracks combination power consumption shear force wall
CN211850370U (en) Sea sand fiber recycled concrete combined column with built-in FRP framework, hollow interlayer and stainless steel tube
CN210315261U (en) Utilize anti bridge tilting device of building rubbish
CN207619919U (en) A kind of assembled eco-embankment structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190827

Termination date: 20211031