Prior art keywords
detecting device
electric energy
resistance detecting
rack
pallet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821737120.XU
Other languages
Chinese (zh)
Inventor
冯彦元
张楠
陈少忠
林军
陈长基
吴清耀
江旭
朱斌
姚民
吴小军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HAINAN STATE GRID Co Ltd
Shenzhen Clou Electronics Co Ltd
Original Assignee
HAINAN STATE GRID Co Ltd
Shenzhen Clou Electronics Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HAINAN STATE GRID Co Ltd, Shenzhen Clou Electronics Co Ltd filed Critical HAINAN STATE GRID Co Ltd
Priority to CN201821737120.XU priority Critical patent/CN209247950U/en
Application granted granted Critical
Publication of CN209247950U publication Critical patent/CN209247950U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Measurement Of Resistance Or Impedance (AREA)

Abstract

The utility model belongs to the automation resistance test field of metering automation terminal and three-phase electric energy meter, disclose a kind of overpressure resistance detecting device, including rack, the bottom of the rack is equipped with power supply and overpressure resistance detecting device, top is equipped with workbench, the side of the workbench be spaced laterally apart it is multiple can workbench sliding relatively connecting device, elevating mechanism is equipped in the rack, elevating mechanism can drive correspondingly part to be detected rise to unit of correspondingly plugging into, both the calibrating of three-phase electric energy meter can have been carried out, the calibrating of metering automation terminal can be carried out again, a variety of detection demands can be met, save place, improve device utilization rate.

Description

A kind of overpressure resistance detecting device
Technical field
The invention belongs to metering automation terminal and the automation resistance test fields of three-phase electric energy meter, more particularly to one kind Overpressure resistance detecting device.
Background technique
Southern Power Grid Company has unified the surface structure of three-phase electric energy meter and metering automation terminal, size model number, calibrating Index and standard, this is created condition for the high-volume automatic detection of three-phase electric energy meter and metering automation terminal.
However south electric network standard is inconsistent for the formal Specification of three-phase electric energy meter and metering automation terminal at present, needs It separately designs corresponding overpressure resistance detecting device to detect, the detection time of three-phase electric energy meter and metering automation terminal is longer, inspection Inefficiency is surveyed, also waste place, device utilization efficiency are low.Therefore, it is necessary to provide a kind of compatible three-phase electric energy meter and meter Measure the overpressure resistance detecting device of automatization terminal.
Summary of the invention
The present invention provides a kind of overpressure resistance detecting device, compatible detection three-phase electric energy meter and metering automation terminal, increases Utilization ratio of device, efficiently solves the problems, such as that device occupied ground is more.
The present invention is to solve a kind of technical solution that its technical problem provides to be:
The bottom of a kind of overpressure resistance detecting device, including rack, the rack is equipped with power supply and overpressure resistance detecting device, and top is set Have a workbench, the side of the workbench be spaced laterally apart it is multiple can the relatively described workbench sliding connecting device, institute It states and is equipped with elevating mechanism in rack, and the top of the elevating mechanism is equipped with the pallet for placing part to be detected, through the support After identification device identification in disk, the elevating mechanism drives the pallet to rise to the connecting device and carries out resistance test.
As an improvement of the above technical solution, the part to be detected be three-phase electric energy meter or metering automation terminal, it is described Connecting device includes that the first metering automation terminal plugs into and unit and plugs on unit set on the first metering automation terminal The three-phase electric energy meter of side is plugged into unit;The support for placing the pallet is additionally provided between the elevating mechanism and the pallet Plate, the rack are equipped with the upper layer locating slot and lower layer's locating slot being caught in for the supporting plate.
As a further improvement of the above technical scheme, the elevating mechanism includes mounting plate, is securable to the rack On fixed plate, on the upside of the fixed plate and the first cylinder for being fixed on the mounting plate and be set under the fixed plate Second cylinder of side, the power output end connection of the power output end and the second cylinder of first cylinder, the mounting plate are consolidated The guide post for making mounting plate stablize lifting is additionally provided between fixed board.
As a further improvement of the above technical scheme, it plugs on the workbench with the first metering automation terminal The side of unit face, which is also spaced, to be equipped with the second metering automation terminal and plugs into unit;The elevating mechanism and the pallet it Between be equipped with rotating mechanism, the pallet through the rotating mechanism rotate 180 degree after be delivered to the second metering automation terminal Unit of plugging into carries out resistance test.
As a further improvement of the above technical scheme, three-phase electric energy meter unit of plugging into includes that direct access is plugged into Mechanism and mutual inductor access type connecting mechanism.
As an improvement of the above technical solution, the bottom of the connecting device is equipped with sliding block, along the longitudinal direction of the workbench Equipped with sliding rail, the third cylinder for driving the connecting device to slide along the sliding rail is further fixed on the workbench.
As an improvement of the above technical solution, the identification device is whole for receiving three-phase electric energy meter/metering automation The RFID of the data information at end carries code device.
As an improvement of the above technical solution, the compatible three-phase electric energy meter of the pallet and metering automation terminal, and can put Set two pieces of three-phase electric energy meters or metering automation terminal.
As an improvement of the above technical solution, the bottom end four corners of the rack are mounted on universal wheel, and stablize institute State the retractable supports column of rack.
The method have the benefit that: rack is equipped with and three-phase electric energy meter and metering automation terminal is corresponding connects Device is refuted, elevating mechanism drives part to be detected to rise to unit of correspondingly plugging into, can not only carry out the calibrating of three-phase electric energy meter, but also can The calibrating for carrying out metering automation terminal, can meet a variety of detection demands, save place, improve device utilization rate.
Detailed description of the invention
For the clearer technical solution illustrated in the embodiment of the present invention, will make below to required in embodiment description Attached drawing briefly describes.
Fig. 1 is the structural schematic diagram of the overpressure resistance detecting device of one embodiment of the invention;
Fig. 2 is the side view of the overpressure resistance detecting device of one embodiment of the invention;
Fig. 3 is the structural schematic diagram of elevating mechanism in the overpressure resistance detecting device of one embodiment of the invention.
Specific embodiment
Carried out with reference to embodiments with technical effect of the attached drawing to design of the invention, specific structure and generation it is clear, It is fully described by, to fully understand the purpose of the present invention, scheme and effect.It should be noted that in the absence of conflict originally The feature in embodiment and embodiment in application can be combined with each other.Furthermore the upper and lower, left and right etc. used in the present invention It describes in only opposite figure for each component part mutual alignment relation of the present invention.
For Fig. 1 to Fig. 2 shows a kind of overpressure resistance detecting device, including rack 100, the bottom of rack 100 is equipped with power supply and resistance to Detection device is pressed, top is equipped with workbench 200, and the side of workbench 200 has been spaced laterally apart multiple dresses of slidably plugging into 500 are set, elevating mechanism 300 is equipped in rack 100, and the top of elevating mechanism 300 is equipped with the pallet for placing part to be detected 400。
Part to be detected can be three-phase electric energy meter, or metering automation terminal.Pallet 400 in the present embodiment is simultaneous Hold three-phase electric energy meter and metering automation terminal, two pieces of three-phase electric energy meters or two pieces of metering automation terminals can be placed.Southern electricity Net three-phase electric energy meter and metering automation terminal include multiple types, for example, three-phase electric energy meter be divided into direct access three-phase electricity and Mutual inductor access type three-phase meter, direct access three-phase meter can be divided into two kinds according to electric current difference again, metering automation terminal Two kinds can be divided by size of current, then the terminal structure of plugging into when detecting on connecting device is also not quite similar.If therefore individually For various three-phase electric energy meters or metering automation terminal installation setting calibrating detection line, more site area can be occupied, and fill It is not high to set utilization rate.
Therefore, it is equipped in the compatibility three-phase electric energy meter of the present embodiment and the overpressure resistance detecting device of metering automation terminal available In the connecting device of detection three-phase electric energy meter and metering automation terminal, and detectable calibrating has the metering of different terminals of plugging into Automatization terminal and three-phase electric energy meter.
Specifically, connecting device 500 includes that the first metering automation terminal is plugged into unit 510 and to be set to the first metering automatic Change the plug into three-phase electric energy meter of the top of unit 510 of terminal to plug into unit 520, pallet 400 is specifically placed on set on elevating mechanism 300 On the supporting plate 310 on top, rack 100 is equipped with the upper layer locating slot 110 and lower layer's locating slot 120 being caught in for supporting plate 310.It plugs into The bottom of device 500 is equipped with sliding block 530, the sliding rail 210 that slides for sliding block 530 is equipped with along the longitudinal direction of workbench 200, on workbench It is fixed with the third cylinder 220 that driving connecting device 500 is slided along sliding rail 210.When supporting plate 310 rises to and upper layer locating slot 110 or lower layer's locating slot 120 height when, third cylinder 220 drive connecting device 500 towards workbench intermediary movements, plug into In plug into terminal insertion three-phase electric energy meter or metering automation terminal on device 500.
As shown in figure 3, elevating mechanism 300 includes mounting plate 320, the fixed plate 330 being securable in rack, is set to and fixes 330 upside of plate and the first cylinder 340 being fixed on mounting plate 320 and the second cylinder 350 set on 330 downside of fixed plate, the The power output end 341 of one cylinder 340 is connected with defeated 351 outlet of the power of the second cylinder 350 by floating junction, mounting plate The guide post 360 for guaranteeing that mounting plate 320 stablizes lifting is additionally provided between 320 and fixed plate 330.
Two column connecting devices can be laterally set on workbench, and elevating mechanism is arranged between two connecting devices.Such as Fig. 1 and figure Shown in 2, in the present embodiment, the side of face connecting device 500 is also equipped with connecting device on workbench 200, but this is plugged into Device only has plug into the second metering automation terminal of unit 510 of face the first metering automation terminal to plug into unit 540;Lifting It is provided with rotating mechanism in mechanism 300, if the metering automation terminal needs placed in pallet were sent to the second metering automation end Termination refute unit detection, then pallet through rotating mechanism rotate 180 degree after be delivered to the second metering automation terminal plug into unit into Row resistance test.
Elevating mechanism cooperation switch carry out connection detection circuit so that the calibrating line can examine and determine three-phase electric energy meter and Metering automation terminal is examined and determine, a variety of calibrating detection demands can be met.
In order to move the overpressure resistance detecting device of the compatibility three-phase electric energy meter and metering automation terminal, frame bottom four corners It is mounted on universal wheel, and stablizes the retractable supports column of rack.
Metering automation terminal/three-phase electric energy meter is placed by compatible pallet, and automatization terminal/tri- are measured in pallet The data information of phase electric energy meter is judged through the RFID data carrier of RFID reader write-in pallet, is then driven through elevating mechanism The three-phase electric energy meter unit of plugging into for rising to upper layer is examined and determine, and if metering automation terminal, elevating mechanism then drives pallet Metering automation terminal unit of plugging into lower layer is examined and determine.
If desired it is delivered to the second metering automation terminal unit of plugging into be examined and determine, then pallet is rotated by rotating mechanism The second metering automation terminal is delivered to after 180 degree to plug into unit.
Specifically, it is 200mm if it is three-phase electric energy meter top lifting height, is if it is metering automation terminal top lifting height 15mm。
Metering automation terminal/three-phase electric energy meter carries out voltage-withstand test according to JJG596-2012, and test data is stored in work It stands.
It is the acquisition of Southern Power Grid Company standard power information with metering automatization terminal and three-phase electric energy meter in the present embodiment Terminal and three-phase electric energy meter, automatic calibration detection line be have transmission Southern Power Grid Company standard power information acquisition terminal and Intelligent electric energy meter automation detecting detection line.
Three-phase electric energy meter/metering automation terminal carries out resistance test, Ke Yi on automatic calibration detection assembly line The overpressure resistance detecting device of compatible metering automation terminal and three-phase electric energy meter carries out after detecting automatically, uploads experimental data, passes through Software systems are passed to Production investigtion, complete resistance test overall process.By building compatible metering automation terminal The service efficiency that equipment can be improved with the overpressure resistance detecting device of three-phase electric energy meter improves the place service efficiency of equipment.
Although specifically showing and describing the present invention in conjunction with preferred embodiment, those skilled in the art should be bright It is white, it is not departing from the spirit and scope of the present invention defined by described claims, it in the form and details can be right The present invention makes a variety of changes, and is protection scope of the present invention.

Claims (9)

1. the bottom of a kind of overpressure resistance detecting device, including rack, the rack is equipped with power supply and overpressure resistance detecting device, top is equipped with Workbench, which is characterized in that the side of the workbench is spaced laterally apart and multiple workbench sliding can connect relatively Device is refuted, elevating mechanism is equipped in the rack, and the top of the elevating mechanism is equipped with the pallet for placing part to be detected, After the identification device identification in the pallet, it is resistance to that the elevating mechanism drives the pallet to rise to the connecting device progress Pressure detection.
2. overpressure resistance detecting device according to claim 1, which is characterized in that the part to be detected is three-phase electric energy meter or meter Measure automatization terminal, the connecting device includes that the first metering automation terminal is plugged into unit and to be set to first metering automatic Change the three-phase electric energy meter that terminal is plugged into above unit to plug into unit;It is additionally provided between the elevating mechanism and the pallet for putting The supporting plate of the pallet is set, the rack is equipped with the upper layer locating slot and lower layer's locating slot being caught in for the supporting plate.
3. overpressure resistance detecting device according to claim 2, which is characterized in that the elevating mechanism includes mounting plate, can consolidate Due in the rack fixed plate, on the upside of the fixed plate and the first cylinder for being fixed on the mounting plate and be set to The second cylinder on the downside of the fixed plate, the power output end connection of the power output end and the second cylinder of first cylinder, The guide post for making mounting plate stablize lifting is additionally provided between the mounting plate, fixed plate.
4. overpressure resistance detecting device according to claim 2, which is characterized in that on the workbench certainly with first metering The plug into side of unit face of dynamicization terminal is also spaced and is equipped with the second metering automation terminal and plugs into unit;The elevating mechanism Rotating mechanism is equipped between the pallet, the pallet is delivered to second meter after the rotating mechanism rotates 180 degree Amount automatization terminal plug into unit carry out resistance test.
5. overpressure resistance detecting device according to claim 2 or 4, which is characterized in that the three-phase electric energy meter is plugged into unit packet Include direct access connecting mechanism and mutual inductor access type connecting mechanism.
6. overpressure resistance detecting device according to claim 1, which is characterized in that the bottom of the connecting device is equipped with sliding block, It is equipped with sliding rail along the longitudinal direction of the workbench, the driving connecting device is further fixed on the workbench and is slided along the sliding rail Third cylinder.
7. overpressure resistance detecting device according to claim 1, which is characterized in that the identification device is for receiving three-phase electricity The RFID of energy table/metering automation terminal data information carries code device.
8. overpressure resistance detecting device according to claim 1, which is characterized in that the compatible three-phase electric energy meter of the pallet and metering Automatization terminal, and two pieces of three-phase electric energy meters or metering automation terminal can be placed.
9. overpressure resistance detecting device according to claim 1, which is characterized in that the bottom end four corners of the rack are mounted on Universal wheel and the retractable supports column for stablizing the rack.
CN201821737120.XU 2018-10-25 2018-10-25 A kind of overpressure resistance detecting device Active CN209247950U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821737120.XU CN209247950U (en) 2018-10-25 2018-10-25 A kind of overpressure resistance detecting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821737120.XU CN209247950U (en) 2018-10-25 2018-10-25 A kind of overpressure resistance detecting device

Publications (1)

Publication Number Publication Date
CN209247950U true CN209247950U (en) 2019-08-13

Family

ID=67525930

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821737120.XU Active CN209247950U (en) 2018-10-25 2018-10-25 A kind of overpressure resistance detecting device

Country Status (1)

Country Link
CN (1) CN209247950U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109342894A (en) * 2018-10-25 2019-02-15 海南电网有限责任公司 A kind of overpressure resistance detecting device and method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109342894A (en) * 2018-10-25 2019-02-15 海南电网有限责任公司 A kind of overpressure resistance detecting device and method

Similar Documents

Publication Publication Date Title
CN201909843U (en) Wiring device for automatic verification of three-phase electric energy meter
CN102998643B (en) Power utilization information acquisition terminal detecting system
CN109342894A (en) A kind of overpressure resistance detecting device and method
CN208091349U (en) A kind of test measuring device of electric wire
CN209247950U (en) A kind of overpressure resistance detecting device
CN201732472U (en) Automatic testing device of concentrated electric energy meter reading equipment
CN202854326U (en) Automatic positioning and crimping device for intelligent electric energy meter connection terminals
CN203849330U (en) DC (direct current) resistance measuring instrument for AC (alternating current) loop
CN206594266U (en) SIM card test device
CN210839614U (en) Handheld terminal supporting detection of communication protocols of multiple types of ammeter modules
CN204177838U (en) Multichannel AC ammeter
CN207232363U (en) The device of three-phase direct 1 type working plate of concentrator compatible with mutual inductance type electric energy meter
CN204314866U (en) A kind of computer main board automatic test machine
CN201438204U (en) Automation measurement system of electronic component
CN204882850U (en) A 0. 02 grade of miniature standard electric energy meter that is used for single -phase intelligent ammeter verification system repeatability experimental
CN204925339U (en) Intelligent driving control PCBA's quick detection device of automation
CN204855778U (en) A 0. 02 grade of miniature standard electric energy meter for examineing and determine check during directly going into formula three -phase intelligent ammeter verification system
CN103698560A (en) High-frequency electromagnetic field anti-interference testing tool
CN209198543U (en) A kind of FPC Wireless charging coil characteristic resistance value test macro
CN108802460B (en) Compatible electric energy meter base and method for realizing compatibility
CN203350282U (en) Electric energy meter detection wiring device
CN202948100U (en) Voltage-withstanding testing apparatus for three-phase electric energy meter
CN208156477U (en) A kind of data concentrator of installation and repairing quality intelligent control platform
CN201903565U (en) Terminal combined type automatic wiring and disconnecting device for electric energy meter
CN203232149U (en) Automated detection system tray compatible with three-phase electric energy meter and an III-type collection terminal of a dedicated transformer