Prior art keywords
pipeline
cutting pipeline
chute
push pipe
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821781566.2U
Other languages
Chinese (zh)
Inventor
王升龙
李靖
程宝康
李强强
胡奋智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Civil Engineering Co Ltd
Original Assignee
China Construction Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Civil Engineering Co Ltd filed Critical China Construction Civil Engineering Co Ltd
Priority to CN201821781566.2U priority Critical patent/CN209243769U/en
Application granted granted Critical
Publication of CN209243769U publication Critical patent/CN209243769U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Branch Pipes, Bends, And The Like (AREA)

Abstract

The utility model discloses a kind of push pipe intermediate wells chutes, well and cutting pipeline are poured including prefabricated, prefabricated pour offers U-type groove in the middle part of well, the bottom of the U-type groove is fixedly connected with the bottom of cutting pipeline, the bottom of the cutting pipeline is fixedly connected with reinforcing rib, the inner surface of the cutting pipeline is equipped with hardness and strengthens arc panel, the hardness strengthens the both ends at the top of arc panel and is located at the top of cutting pipeline equipped with fixed baffle, the bottom of the fixed baffle is fixedly connected with the top of cutting pipeline by fixing bolt, the reinforcing rib is in long strip, and reinforcing rib is made by manganese steel, blackening process is passed through on the surface of the fixing bolt, the utility model relates to technical field of pipeline construction.The push pipe intermediate wells chute, the method now used are excision pipelines, and inspection shaft and chute pour simultaneously, reduce process, shorten the time, substantially increase labor efficiency, want demolition and maintenance more convenient later.

Description

A kind of push pipe intermediate wells chute
Technical field
The utility model relates to technical field of pipeline construction, specially a kind of push pipe intermediate wells chute.
Background technique
Inspection shaft be the power supply for Urban Underground infrastructure, water supply, draining, blowdown, communication, cable television, gas pipe, The maintenance such as public lighting circuit, it is easy for installation and setting.Be generally located at pipeline intersection, turning, caliber or gradient change, with And locate at a certain distance on straight line pipeline section, it is easy for inspecting periodically auxiliary construction, inspection shaft is used in one residential range Interior buried plastics pipe road outer diameter is not more than 800mm, and the depth of burying is not more than 6m, is generally located in drainage pipeline intersection, turns At crook, caliber or gradient change, at drop etc., for the ease of inspecting periodically, cleaning and dredge or down-hole operation inspection Plastics integrated injection molding form or it is brick at well shape structures.
According to the requirement of 06MS201 atlas and design drawing, chute uses C30 concreting, for generally constructing After at least needing formerly to abolish pipeline, poured inspection shaft again, chute formwork, then carry out chute and pour, but this mode The structural instability for wasting time, and pouring.
Utility model content
In view of the deficiencies of the prior art, the utility model provides a kind of push pipe intermediate wells chute, solves inspection shaft and slips Inconvenient when slot is constructed, process is many and diverse, wastes time, the problem that pouring structure is unstable.
In order to achieve the above object, the utility model is achieved by the following technical programs: a kind of push pipe intermediate wells chute, Pour well and cutting pipeline including prefabricated, prefabricated pour offer U-type groove in the middle part of well, the bottom of the U-type groove with cut The bottom in pipe cutting road is fixedly connected, and the bottom of the cutting pipeline is fixedly connected with reinforcing rib, the inner surface of the cutting pipeline Strengthen arc panel equipped with hardness, the hardness strengthens the both ends at the top of arc panel and is located at the top of cutting pipeline equipped with fixed gear The bottom of plate, the fixed baffle is fixedly connected with the top of cutting pipeline by fixing bolt.
Preferably, the reinforcing rib is in long strip, and reinforcing rib is made by manganese steel.
Preferably, blackening process is passed through on the surface of the fixing bolt.
Preferably, the hardness strengthens the bottom of arc panel and the inner surface of cutting pipeline fits closely.
Preferably, antirust treatment is passed through on the surface that the hardness strengthens arc panel.
Beneficial effect
The utility model provides a kind of push pipe intermediate wells chute.Have compared with prior art it is following the utility model has the advantages that
(1), the push pipe intermediate wells chute, by offering U-type groove in the middle part of well in prefabricated pour, the bottom of U-type groove with The bottom of cutting pipeline is fixedly connected, and the bottom for cutting pipeline is fixedly connected with reinforcing rib, and the inner surface for cutting pipeline is equipped with firmly Degree strengthens arc panel, and hardness strengthens the both ends at the top of arc panel and is equipped with fixed baffle, fixed gear positioned at the top of cutting pipeline The bottom of plate with cutting pipeline top be fixedly connected by fixing bolt, the method now used be excision pipeline, inspection shaft and Chute pours simultaneously, reduces process, shortens the time, substantially increases labor efficiency, improve the globality of inspection shaft and chute, It safeguards later more convenient.
(2), the push pipe intermediate wells chute strengthens arc panel by being equipped with hardness in the inner surface of cutting pipeline, and hardness is strong Change the both ends at the top of arc panel and the top for being located at cutting pipeline is equipped with fixed baffle, bottom and the cutting pipeline of fixed baffle Top is fixedly connected by fixing bolt, and equipment mechanism is simple, easy to use, can be fast implemented pouring for mating type, be saved Manpower has saved cost.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the side view that the utility model cuts pipeline;
Fig. 3 is the main view that the utility model cuts pipeline;
Fig. 4 is the partial enlarged view in the utility model Fig. 3 at A.
In figure: prefabricated well, 2- cutting pipeline, 3-U type groove, 4- reinforcing rib, 5- hardness reinforcing arc panel, the 6- of pouring of 1- is fixed Baffle, 7- fixing bolt.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-4 is please referred to, the utility model provides a kind of technical solution: a kind of push pipe intermediate wells chute, including prefabricated pour Well 1 and cutting pipeline 2 are built, the prefabricated middle part for pouring well 1 offers U-type groove 3, the bottom of U-type groove 3 and the bottom of cutting pipeline 2 It is fixedly connected, the bottom of cutting pipeline 2 is fixedly connected with reinforcing rib 4, and the inner surface of cutting pipeline 2 is equipped with hardness and strengthens arc panel 5, hardness strengthens the both ends at 5 top of arc panel and is located at the top of cutting pipeline 2 equipped with fixed baffle 6, the bottom of fixed baffle 6 It is fixedly connected with the top of cutting pipeline 2 by fixing bolt 7, the method now used is excision pipeline, and inspection shaft and chute are same When pour, reduce process, shorten the time, substantially increase labor efficiency, want demolition and maintenance more convenient later, reinforcing rib 4 is in Strip, and reinforcing rib 4 is made by manganese steel, blackening process is passed through on the surface of fixing bolt 7, and nigrescence is chemical surface treatment A kind of conventional means, principle is to make metal surface generate layer oxide film to reach antirust purpose to completely cut off air, so that fixed Bolt 7 can be with antirust, and equipment mechanism is simple, easy to use, can fast implement pouring for mating type, saves manpower, saves Cost, hardness strengthens the bottom of arc panel 5 and the inner surface of cutting pipeline 2 fits closely, and hardness strengthens the surface warp of arc panel 5 Cross antirust treatment.
Before use, the prefabricated well 1 that pours will first be needed to pour in advance, a ditch is dug out on the ground planned in advance, Fixed plate will be poured to fix, in pipeline in the upper size for marking out inspection shaft chute, cut semicircle along pipeline vertical direction And it is vertical with horizontal line, it cuts, pipeline top half is abolished, completely further along horizontal direction, pipeline center's line position Reservation pipeline lower half portion, using the lower half portion for retaining pipeline as template, disposably poured with wall in inspection shaft formwork Build, after waiting for a period of time later, to concrete cohesion after, by hardness reinforcing arc panel 5 be placed into cutting pipeline 2 it It is interior, two fixed baffles 6 are then placed into cutting pipeline 2 and hardness strengthens the top of 5 two sides of arc panel, pass through fixing bolt 7 are fixedly connected with fixed baffle 6 with the top of cutting pipeline 2.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (5)

1. a kind of push pipe intermediate wells chute, including it is prefabricated pour well (1) and cutting pipeline (2), it is described prefabricated to pour in well (1) Portion offers U-type groove (3), and the bottom of the U-type groove (3) is fixedly connected with the bottom of cutting pipeline (2), it is characterised in that: institute The bottom for stating cutting pipeline (2) is fixedly connected with reinforcing rib (4), and the inner surface of cutting pipeline (2) is equipped with hardness and strengthens arc Shape plate (5), the hardness strengthen the both ends at the top of arc panel (5) and are located at the top of cutting pipeline (2) equipped with fixed baffle (6), the bottom of the fixed baffle (6) is fixedly connected with the top of cutting pipeline (2) by fixing bolt (7).
2. a kind of push pipe intermediate wells chute according to claim 1, it is characterised in that: the reinforcing rib (4) is in long strip, And reinforcing rib (4) is made by manganese steel.
3. a kind of push pipe intermediate wells chute according to claim 1, it is characterised in that: the surface of the fixing bolt (7) By blackening process.
4. a kind of push pipe intermediate wells chute according to claim 1, it is characterised in that: the hardness strengthens arc panel (5) Bottom and cut pipeline (2) inner surface fit closely.
5. a kind of push pipe intermediate wells chute according to claim 1, it is characterised in that: the hardness strengthens arc panel (5) Surface pass through antirust treatment.
CN201821781566.2U 2018-10-31 2018-10-31 A kind of push pipe intermediate wells chute Active CN209243769U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821781566.2U CN209243769U (en) 2018-10-31 2018-10-31 A kind of push pipe intermediate wells chute

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821781566.2U CN209243769U (en) 2018-10-31 2018-10-31 A kind of push pipe intermediate wells chute

Publications (1)

Publication Number Publication Date
CN209243769U true CN209243769U (en) 2019-08-13

Family

ID=67526637

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821781566.2U Active CN209243769U (en) 2018-10-31 2018-10-31 A kind of push pipe intermediate wells chute

Country Status (1)

Country Link
CN (1) CN209243769U (en)

Similar Documents

Publication Publication Date Title
CN210031914U (en) Assembled inspection shaft
CN103015719B (en) Preliminary work for spudding steel concrete wastewater disposal basin monobloc cast technique
CN103821219A (en) Top pipe construction modification inspection well construction method
CN110158656A (en) A kind of integrated template piping lane and its method of construction
CN103343503B (en) Bridge-type prefabricated reinforced concrete trough slab wear resistant road surface structural system and construction method
CN105065040B (en) A kind of prefabricated underground space tunneling construction method of top plate
CN102619521B (en) Construction method for vertical shaft bedrock section wall structure
CN204626453U (en) The supporting device of pipeline in Urban Underground pipe gallery
CN107268675A (en) The laying method and structure of a kind of many storehouse underground pipe galleries of combined type
CN207268009U (en) A kind of underground pipe gallery drainage system based on existing blowdown canal
CN209243769U (en) A kind of push pipe intermediate wells chute
CN103334534A (en) Special building block for anti-seismic energy-saving reinforced masonry of well-off building and new construction technology
CN110671547A (en) Concrete-plastic composite pipe
CN109137984A (en) Assembled integral mixes prefabricated pipe gallery
CN206090623U (en) Prefabricated inspection shaft of construction efficient
CN205530345U (en) Modular many storehouses utility tunnel structure
CN108930323A (en) A kind of pipe jacking construction method
CN108179677A (en) Sponge urban water-through pavement
CN104908150B (en) A kind of piping shaft making template and the method based on factorial praluction piping shaft
CN209350486U (en) A kind of constructional column reinforcing prefabricated section through walls and mold
CN203729323U (en) Precast concrete pipeline foundation
CN201883422U (en) Fabricated steel guide wall for underground continuous wall
CN216553095U (en) Reverse construction method frame post secondary pouring device
CN217517653U (en) Prefabricated inspection well structure based on non-excavation directional drilling trombone slide construction
CN207941913U (en) A kind of production RC pipejacking reinforcing steel bar cage manufacture support mould

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant