CN209243486U - A kind of steep slope region underloading road structure - Google Patents
A kind of steep slope region underloading road structure Download PDFInfo
- Publication number
- CN209243486U CN209243486U CN201821760511.3U CN201821760511U CN209243486U CN 209243486 U CN209243486 U CN 209243486U CN 201821760511 U CN201821760511 U CN 201821760511U CN 209243486 U CN209243486 U CN 209243486U
- Authority
- CN
- China
- Prior art keywords
- road
- cantilever beams
- anchor
- slopes
- steep slope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
The utility model relates to abrupt slope road fields, disclose a kind of steep slope region underloading road structure, comprising: be used to support the overhanging girder construction of road;The overhanging girder construction includes Cantilever Beams and support construction;Multiple Cantilever Beams are arranged along the length direction interval of road, and the Cantilever Beams are horizontally disposed and one end is fixedly connected with slopes, and the bottom of the Cantilever Beams is provided with support construction, is laid with road surface structare layer on the Cantilever Beams.A kind of steep slope region provided by the utility model is lightly loaded road structure, and setting overhanging girder construction is supported road, can save road supporting and retaining system measure, reduce bridge accounting, the cubic metre of earth and stone, gear shield quantity of masonry and sign land scale can be reduced, project amount, investment reduction are reduced.
Description
Technical field
The utility model relates to abrupt slope road fields, are lightly loaded road structure more particularly to a kind of steep slope region.
Background technique
Existing steep slope region, roadway travel are substantially divided to two kinds of the forms of road cross section: one is parallel contour two-way streets
Road form of fracture, one is not contour two-way framing road section forms parallel.The former will appear inside cut slope height, excavation
Situation big and that amount of fill big side slope of embankment in outside is high is measured to occur.
High Cut Slope traditional at present often uses the structure types such as high gravity retaining wall, pile plate wall, but limited
In its supporting and retaining system ability, often retaining wall highest does not exceed 8m, and pile plate wall does not exceed 10m, even Prestressing generally yet
In the case where anchor cable, pile plate wall is not more than 15m, and lower block is generally not more than 10m using balance weight retaining wall.It is high again
If need staking base beam or cushion cap, or use pile plate wall, or even need to change type of bridge into, expropriation of land can be greatly increased and torn open
The area and expense moved increases the degree of soil erosion and generates landslide and slip the geological disaster risk collapsed.
If land area can be effectively reduced using the latter, the risk of soil erosion and Landslide Hazards is reduced, still
Need to increase the retaining between upper and lower framing road, though have significantly than parallel contour road section form on the whole
Advantage, but construction investment scale may not be reduced or be reduced not enough obviously.
Often civil engineering is larger for existing steep slope region underloading road structure at present, causes project amount larger and invests
It is higher.
Utility model content
(1) technical problems to be solved
The purpose of the utility model is to provide a kind of steep slope regions to be lightly loaded road structure, solves for solution or part current
The problem of often civil engineering is larger for existing steep slope region underloading road structure, causes project amount larger and high investment.
(2) technical solution
In order to solve the above-mentioned technical problem, the utility model provides a kind of steep slope region underloading road structure, comprising: is used for
Support the overhanging girder construction of road;The overhanging girder construction includes Cantilever Beams and support construction;Multiple Cantilever Beams are along road
The setting of length direction interval, the Cantilever Beams are horizontally disposed and one end is fixedly connected with slopes, and the bottom of the Cantilever Beams is set
It is equipped with support construction, is laid with road surface structare layer on the Cantilever Beams.
On the basis of above scheme, the support construction includes: diagonal brace;One end of the diagonal brace and the Cantilever Beams are another
The bottom of one end is connected, and the other end and the slopes of the diagonal brace are fixedly connected.
On the basis of above scheme, the support construction includes: pier stud;The pier stud be vertically arranged and top with it is described
The bottom of the Cantilever Beams other end is connected, and in the bottom insertion slopes of the pier stud and is fixed in good ground.
On the basis of above scheme, one end of the Cantilever Beams is connected with the first anchor pier, and first anchor pier is by extremely
Few first anchor cable is fixed on slope surface, and the first anchor cable hole in one end insertion slopes of first anchor cable is simultaneously fixed on
In the rock mass stability of slopes, the other end of first anchor cable passes through first anchor pier and is connected with the first anchor pier.
On the basis of above scheme, the other end of the diagonal brace is connected with the second anchor pier, and second anchor pier is by extremely
Few second anchor cable is fixed on slope surface, and the second anchor cable hole in one end insertion slopes of second anchor cable is simultaneously fixed on
In the rock mass stability of slopes, the other end of second anchor cable passes through second anchor pier and is connected with the second anchor pier.
On the basis of above scheme, it is laid with prefabricated board in the top of the Cantilever Beams, is spread in the top of the prefabricated board
If road surface structare layer, setting structure is stitched between the road surface structare layer adjacent two layers.
On the basis of above scheme, crossbeam, the crossbeam and institute are laid between the Cantilever Beams and the prefabricated board
The length direction for stating Cantilever Beams is vertically arranged and the both ends of the crossbeam are located at the tops of two neighboring Cantilever Beams, along described
Multiple crossbeams are arranged in the length direction interval of Cantilever Beams.
On the basis of above scheme, road is parallel not contour framing road structure, is arranged in the bottom of lower width road
The overhanging girder construction.
(3) beneficial effect
A kind of steep slope region provided by the utility model is lightly loaded road structure, and setting overhanging girder construction props up road
Support can save road supporting and retaining system measure, reduce bridge accounting, can reduce the cubic metre of earth and stone, gear shield quantity of masonry and sign land scale, reduce
Project amount, investment reduction.
Detailed description of the invention
Fig. 1 is the schematic diagram that a kind of steep slope region of the utility model is lightly loaded one embodiment of road structure;
Fig. 2 is the schematic diagram that a kind of steep slope region of the utility model is lightly loaded another embodiment of road structure.
Description of symbols:
1-Cantilever Beams;21-diagonal braces;22-pier studs;
3-slopes;4-the first anchor pier;5-the first anchor cable;
6-the second anchor pier;7-the second anchor cable;8-prefabricated boards;
9-crossbeams.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiment of the present utility model is described in further detail.Below
Example is not intended to limit the scope of the present invention for illustrating the utility model.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " is pacified
Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally
Connection;It can be mechanical connection, be also possible to be electrically connected;Can be directly connected, can also indirectly connected through an intermediary,
It can be the connection inside two elements.For the ordinary skill in the art, above-mentioned art can be understood with concrete condition
The concrete meaning of language in the present invention.
A kind of steep slope region underloading road structure is provided according to the utility model embodiment, with reference to Fig. 1, the road structure packet
It includes: being used to support the overhanging girder construction of road;Overhanging girder construction includes Cantilever Beams 1 and support construction;Multiple Cantilever Beams 1 are along road
The setting of length direction interval, Cantilever Beams 1 are horizontally disposed and one end is fixedly connected with slopes 3, and the bottom of Cantilever Beams 1 is provided with branch
Support structure is laid with road surface structare layer on Cantilever Beams 1.
A kind of steep slope region provided in this embodiment is lightly loaded road structure, and setting overhanging girder construction is supported road,
Road retaining structure even bridge structure form can be reduced, project amount is reduced.Overhanging girder construction mainly includes Cantilever Beams 1 and support
Structure.
Cantilever Beams 1 are arranged along the length direction interval of road in the side of slopes 3 on abrupt slope.Each Cantilever Beams 1 are horizontal hanging
It is placed in the side of abrupt slope slopes 3.1 one end of Cantilever Beams is fixedly connected with slopes 3, and bottom is fixed by support construction.It can incite somebody to action
Road pavement is in the top of Cantilever Beams 1.Cantilever Beams 1 and the road surface structare layer load of upper part, pedestrian's load and non-motor vehicle
Load etc. is passed in good ground by bottom bracing structure.
A kind of steep slope region provided in this embodiment is lightly loaded road structure, and setting overhanging girder construction is supported road,
Road supporting and retaining system measure can be saved, bridge accounting is reduced, the cubic metre of earth and stone, gear shield quantity of masonry and sign land scale can be reduced, reduce work
Cheng Liang, investment reduction.
On the basis of the above embodiments, further, with reference to Fig. 1, support construction includes: diagonal brace 21;The one of diagonal brace 21
End is connected with the bottom of 1 other end of Cantilever Beams, and the other end and the slopes 3 of diagonal brace 21 are fixedly connected.
On the basis of the above embodiments, further, with reference to Fig. 2, support construction includes: pier stud 22;Pier stud 22 is vertical
It is arranged and top is connected with the bottom of 1 other end of Cantilever Beams, in the bottom insertion slopes 3 of pier stud 22 and is fixed on good ground
In.
The support construction of 1 bottom of Cantilever Beams can be diagonal brace 21.21 one end of diagonal brace can be riveted with the bottom of 1 other end of Cantilever Beams
Connection.The other end of diagonal brace 21 is fixedly connected with slopes 3.Support construction can also be pier stud 22.Support construction can also be other knots
Structure is not limited this for the purpose of it can realize stable support to Cantilever Beams 1.
On the basis of the above embodiments, further, one end of Cantilever Beams 1 is connected with the first anchor pier 4, the first anchor pier 4
It is fixed on 3 surface of slopes by least one first anchor cable 5, the first anchor cable hole in one end insertion slopes 3 of the first anchor cable 5 is simultaneously
It is fixed in the rock mass stability of slopes 3, the other end of the first anchor cable 5 passes through the first anchor pier 4 and is connected with the first anchor pier 4.
In the junction of Cantilever Beams 1 and slopes 3, anchor cable structure is set, to realize the secured connection of Cantilever Beams 1 Yu slopes 3,
Guarantee the overall stability of road structure.At least one first anchor cable 5 is set.Setting and the first anchor cable 5 one are a pair of in slopes 3
The first anchor cable hole answered.In first anchor cable hole of the corresponding insertion in one end of first anchor cable 5, it is connect with slopes 3 by pouring.
First anchor cable hole bottom should be located in the rock mass stability of slopes 3, make one end of the first anchor cable 5 and the stabilization of slopes 3
Rock mass is fixedly connected.The other end of first anchor cable 5 is pierced by the first anchor cable hole, and passes through the first anchor pier 4, securely by the first anchor pier 4
It is fixed on the surface of slopes 3.One end of Cantilever Beams 1 can be fixedly connected with the first anchor pier 4, can be riveting.
First anchor pier 4 can be fixed in the rock mass stability in slopes 3 with the first anchor cable 5, it is ensured that road structure form
Overall stability.
On the basis of the above embodiments, further, the other end of diagonal brace 21 is connected with the second anchor pier 6, the second anchor pier 6
It is fixed on 3 surface of slopes by least one second anchor cable 7, the second anchor cable hole in one end insertion slopes 3 of the second anchor cable 7 is simultaneously
It is fixed in the rock mass stability of slopes 3, one end of the second anchor cable 7 passes through the second anchor pier 6 and is connected with the second anchor pier 6.
When support construction is diagonal brace 21, diagonal brace 21 is same as the junction of slopes 3 to be arranged anchor cable structure, to realize diagonal brace
21 with the secured connections of slopes 3, guarantee to support stablizing for Cantilever Beams 1.At least one second anchor cable 7 is set.It is set in slopes 3
It sets and one-to-one second anchor cable hole of the second anchor cable 7.In second anchor cable hole of the corresponding insertion in one end of second anchor cable 7, with slopes 3
By pouring connection.
Second anchor cable hole bottom should equally be located in the rock mass stability of slopes 3, make one end of the second anchor cable 7 and slopes 3
Rock mass stability is fixedly connected.The other end of second anchor cable 7 is pierced by the second anchor cable hole, and passes through the second anchor pier 6, by the second anchor pier 6
It is fixedly secured on the surface of slopes 3.The other end of diagonal brace 21 can be fixedly connected with the second anchor pier 6, can be riveting.
Further, between 1 other end bottom of 21 one end of diagonal brace and Cantilever Beams, 21 other end of diagonal brace and the second anchor pier 6 it
Between and 1 one end of Cantilever Beams and the first anchor pier 4 between other connection types can also be used, by be able to achieve securely connection for the purpose of,
It does not limit this.
Further, the first anchor cable 5 and the second anchor cable 7 are prestress anchorage cable.
On the basis of the above embodiments, further, it is laid with prefabricated board 8 in the top of Cantilever Beams 1, in prefabricated board 8
Top is laid with road surface structare layer, setting structure seam between road surface structare layer adjacent two layers.Cantilever Beams 1 are along the length direction of road
It is spaced, it can be laid with prefabricated board 8 on Cantilever Beams 1, apply road surface structare layer on prefabricated board 8.The layer of road surface structare layer
Between reserve structural joint.
On the basis of the above embodiments, further, between Cantilever Beams 1 and prefabricated board 8 be laid with crossbeam 9, crossbeam 9 with
The length direction of Cantilever Beams 1 is vertically arranged and the both ends of crossbeam 9 are located at the tops of two neighboring Cantilever Beams 1, along Cantilever Beams 1
Length direction interval multiple crossbeams 9 are set.
For the stability for guaranteeing the laying of prefabricated board 8, crossbeam 9 can be set in the top of Cantilever Beams 1, the lower section of prefabricated board 8.It is horizontal
Beam 9 is horizontal between two neighboring Cantilever Beams 1.Can along the length direction of Cantilever Beams 1, above two adjacent Cantilever Beams 1 between
Every horizontal multiple crossbeams 9.The length direction of Cantilever Beams 1, that is, each Cantilever Beams 1 length direction, the i.e. width direction of road.
, can be horizontal on the gap of two neighboring Cantilever Beams 1 in the horizontal crossbeam 9 in the top of Cantilever Beams 1, to prefabricated board 8 into
Row preferably support guarantees the stability of entire road structure to guarantee that road pavement structure sheaf realizes the support of firm stable.
On the basis of the above embodiments, further, road is parallel not contour framing road structure, in lower width road
Bottom setting overhanging girder construction.
Half moat, half dike cross-sectional form is produced under conditions of parallel contour not framing for the road of steep slope region,
According to existing upper gear and lower block measure, it is most likely that cause gear shield ability inadequate, or even need the shape using midway half-bridge
Formula just can solve, and bring that filled soil quality is big, upper lower block scale is big, and what land expropriation cost and retaining expense were substantially increased asks
Topic is easy to cause large area vegetation deterioration and causes large area soil erosion or even landslide etc. no simultaneously because the brush slope gradient is excessively high
The consequence of good geological disaster.
To solve the problems, such as that above-mentioned parallel contour not framing road is brought, excavation is filled out in reduction, can be by steep slope region road knot
Structure is set as parallel not contour framing the forms of road cross section.And in order to reduce the lower gear of lower width road or even avoid the occurrence of bridge
Girder construction form, in the bottom of lower width road setting overhanging girder construction.
It is laid with prefabricated board 8 on Cantilever Beams 1, applies road surface structure layer on plate, the plate load of Cantilever Beams 1 and upper part,
Pedestrian's load, non-motor vehicle load by the support construction of its underpart by being passed in good ground.
On the basis of the above embodiments, further, a kind of steep slope region is lightly loaded road structure construction method, feature
It is, comprising: apply the first anchor pier 4 and the first anchor cable 5: the first anchor cable that will be reserved in one end insertion slopes 3 of the first anchor cable 5
Anchored end is applied in hole;The free end of first anchor cable 5 is pierced by the first anchor cable hole, is stretched to default pulling capacity step by step;Envelope
Anchor cable is closed, the first anchor pier 4 is applied;It applies support construction: including applying the second anchor pier 6 and the second anchor when support construction is diagonal brace 21
Rope 7 binds the reinforcing bar of diagonal brace 21, formwork erection and casting concrete;Support construction includes machine drilling when being pier stud 22, binds pier stud
22 reinforcing bar, casting concrete;Apply Cantilever Beams 1: the reinforcing bar of binding Cantilever Beams 1, formwork erection and casting concrete;Apply road surface knot
Structure layer: crossbeam 9 is applied by casting concrete in the top of Cantilever Beams 1 or is directly laid with prefabricated crossbeam 9;In crossbeam 9
Top piecemeal is laid with prefabricated board 8, and setting overlaps and stay seam between contiguous prefabricated plate 8;Implement road surface above prefabricated board 8.
On the basis of the above embodiments, further, the free end of the first anchor cable 5 is pierced by the first anchor cable hole, carried out
It is stretched to before default pulling capacity step by step further include:
0.1-0.2 times of anchor cable axial tension value is taken, to anchor cable pre- tensioning 1-2 times;
1.10-1.20 times of prestress value of ultra stretching is designed to anchor cable.
On the basis of the above embodiments, further, a kind of concrete construction method of steep slope region underloading road structure
Include:
Apply the first anchor pier 4 and the first anchor cable of prestressing force 5: first by the first anchor in one end insertion slopes 3 of the first anchor cable 5
Suo Kongzhong applies anchoring section, and one end of the first anchor cable 5 is fixedly connected with the rock mass stability inside slopes 3;Then by the first anchor
The free end of rope 5 is pierced by the first anchor cable hole, starts to carry out tensioning step by step, it is to be achieved it is default needed for after pulling capacity, anchor cable is carried out
Locking applies the first anchor pier 4, after finally solidifying, wipes out remaining anchor cable part.
The first anchor cable hole deviations are not preferably greater than 20.0mm when the first anchor cable of prestressing force 5 is constructed, and anchor hole degree of skewness is not answered
Greater than 2%, drilling depth is more than that anchorage cable design length is no less than 0.5m.Ying Qingkong before prestress anchorage cable is in the milk, in discharge orifice
Ponding, Grouting Pipe are preferably put into hole with anchor cable simultaneously.Into lateral aperture or the hole that has a down dip when slip casting, Grouting Pipe outlet should be inserted into away from hole
At the 100-300mm of bottom, slurries continuous pouring from bottom to top;In acclivitous drilling when slip casting, sealing dress should be set in aperture
It sets.When aperture overflows slurries or exhaust pipe stopping exhaust and meets slip casting requirement, slip casting can be stopped.
Strength standard value of first anchor cable, 5 control stress for prestressing no more than 0.65 times of steel strand wires.Carrying out formal tensioning
Before, 0.1-0.2 times of anchor cable axial tension value should be taken, to the pre- tensioning of anchor cable 1 time -2 times, keeps the contact at its each position close and bar
Body is totally straight.With the appropriate to the occasion ultra stretching for carrying out 1.10-1.20 times of anchorage cable design prestress value, prestressing force retention, which should meet, to be set
Meter requires.
To stratum and the engineering more demanding by anchor structure Bit andits control, the lock value of prestress anchorage cable is preferably anchor cable axis
To pulling force characteristic value;To the engineering allowing stratum and centainly being deformed by anchor structure generation, the lock value of prestress anchorage cable is preferably
Anchorage cable design prestress value obtains 0.75 times -0.90 times.
Apply support construction.Because support construction can be diagonal brace 21 or pier stud 22, in two kinds of situation.It is tied in support
When structure is diagonal brace 21, the second anchor cable 7 and the second anchor first should be applied according to the method that applies of above-mentioned first anchor cable 5 and the first anchor pier 4
Pier 6;Then the reinforcing bar of diagonal brace 21 is bound, formwork erection, casting concrete can be riveting between diagonal brace 21 and the second anchor pier 6.
Apply Cantilever Beams 1.The reinforcing bar of Cantilever Beams 1 is bound, formwork erection, casting concrete can between Cantilever Beams 1 and support construction
For riveting, also it is considered as riveting between the first anchor pier 4.
Apply crossbeam 9.Crossbeam 9 can be prefabricated, and prefabricated 9 finished product of crossbeam is mounted on Cantilever Beams 1;It can also show
It pours, binds the reinforcing bar of crossbeam 9, formwork erection, casting concrete according to 9 design requirement of crossbeam on Cantilever Beams 1.
Apply roadbed base plate and supercrust.Piecemeal installs 8 pieces of prefabricated board, carries out overlap joint and stays seam, real on roadbed base plate
Supercrust is applied, has stayed deformation joint in seam crossing correspondence.
Steep slope region provided in this embodiment is lightly loaded road structure form, compared with existing steep slope region road structure form
Advantage is significant: compared with steep slope region parallel contour road structure form, can significantly drop and reduce lower block scale and difficulty, reduces bridge
Beam accounting, advantage is significant in terms of the cubic metre of earth and stone, gear shield quantity of masonry, sign land scale.
Compared with not contour double lower block road structure forms parallel, lower width road supporting and retaining system measure can be saved, bridge is reduced and accounts for
Than advantage is significant in terms of the cubic metre of earth and stone, gear shield quantity of masonry, sign land scale;Compared with midway half-bridge road structure form, advantage
It is more obvious, bridge accounting is directly reduced, investment cost is significantly reduced.
Cantilever Beams 1, prestress anchorage cable and diagonal brace 21 or pier stud 22 are combined together by the road structure, and structure is simple, energy
The enough structure type for adapting to high gradient slope location very well is a kind of novel Steep Slope Embankment landscape road structure form.The road
Structure solves situations such as existing steep slope region can not add landscape road, ride, go slowly, and is a kind of novel framing underloading road
Line structure form.
Compared with traditional retaining structure, the structure type is of less demanding to basic condition, especially has to Steep Slope Embankment
Better adaptability, lightweight are its sharpest edges;Large area earth excavation and the destruction to vegetation are reduced simultaneously, can significantly be saved
Save bricklaying and investment cost.
The road structure closing slope effect is good, can save land used transverse width 1-4m, shortens bridge length 1-2 across comprehensive to survey
It calculates, reduces investment cost at least 10% or more, society and remarkable in economical benefits.In recent years, with highway, the hair of railway engineering
Exhibition dynamics, so that Steep Slope Embankment engineering is significantly increased, which is exactly to be Steep Slope Embankment and research and develop, and has wide application
Prospect.
Mountain area steep slope region creates landscape road, rides, goes slowly, and has that land area is big, cutting brush slope is high, road
Dike bankets the predicament of high, upper lower block measure weight, is limited the limitation of existing supporting and retaining system measure closing slope ability, it is difficult to well solve above-mentioned
Difficulty, and the new road structure type can be perfectly suitable for steep slope region, overcome above-mentioned difficulties, have and use well
Prospect.It reducing construction land simultaneously, reducing the geological disasters sides such as construction investment, reduction soil erosion, reduction landslide
Face effect is obvious.
In conclusion the road structure formal technique is advanced, applied widely, society and remarkable in economical benefits have good
Good popularization and application foreground and social economic value.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this
Within the spirit and principle of utility model, any modification, equivalent replacement, improvement and so on should be included in the utility model
Protection scope within.
Claims (8)
1. a kind of steep slope region is lightly loaded road structure characterized by comprising be used to support the overhanging girder construction of road;It is described
Overhanging girder construction includes Cantilever Beams and support construction;Multiple Cantilever Beams are arranged along the length direction interval of road, described outstanding
Outrigger is horizontally disposed and one end is fixedly connected with slopes, and the bottom of the Cantilever Beams is provided with support construction, in the Cantilever Beams
Upper laying road surface structare layer.
2. steep slope region according to claim 1 is lightly loaded road structure, which is characterized in that the support construction includes: oblique
Support;One end of the diagonal brace is connected with the bottom of the Cantilever Beams other end, and the other end and the slopes of the diagonal brace are fixedly connected.
3. steep slope region according to claim 1 is lightly loaded road structure, which is characterized in that the support construction includes: pier
Column;The pier stud is vertically arranged and top is connected with the bottom of the Cantilever Beams other end, and slopes are inserted into the bottom of the pier stud
In and be fixed in good ground.
4. steep slope region according to any one of claims 1 to 3 is lightly loaded road structure, which is characterized in that the Cantilever Beams
One end is connected with the first anchor pier, and first anchor pier is fixed on slope surface, first anchor by least one first anchor cable
Rope one end insertion slopes on the first anchor cable hole and be fixed in the rock mass stability of slopes, the other end of first anchor cable is worn
First anchor pier is crossed to be connected with the first anchor pier.
5. steep slope region according to claim 2 is lightly loaded road structure, which is characterized in that the other end of the diagonal brace and the
Two anchor piers are connected, and second anchor pier is fixed on slope surface, one end of second anchor cable by least one second anchor cable
The second anchor cable hole in insertion slopes is simultaneously fixed in the rock mass stability of slopes, and the other end of second anchor cable passes through described the
Two anchor piers are connected with the second anchor pier.
6. steep slope region according to claim 1 is lightly loaded road structure, which is characterized in that spread in the top of the Cantilever Beams
If prefabricated board, road surface structare layer, setting structure between the road surface structare layer adjacent two layers are laid in the top of the prefabricated board
Seam.
7. steep slope region according to claim 6 is lightly loaded road structure, which is characterized in that in Cantilever Beams and described pre-
It is laid with crossbeam between making sheet, the length direction of the crossbeam and the Cantilever Beams is vertically arranged and the both ends of crossbeam difference position
In the top of two neighboring Cantilever Beams, multiple crossbeams are set along the length direction interval of the Cantilever Beams.
8. steep slope region according to claim 1 is lightly loaded road structure, which is characterized in that road is parallel not contour framing
The overhanging girder construction is arranged in the bottom of lower width road in road structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821760511.3U CN209243486U (en) | 2018-10-29 | 2018-10-29 | A kind of steep slope region underloading road structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821760511.3U CN209243486U (en) | 2018-10-29 | 2018-10-29 | A kind of steep slope region underloading road structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209243486U true CN209243486U (en) | 2019-08-13 |
Family
ID=67526235
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821760511.3U Active CN209243486U (en) | 2018-10-29 | 2018-10-29 | A kind of steep slope region underloading road structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209243486U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109403180A (en) * | 2018-10-29 | 2019-03-01 | 中铁四院集团西南勘察设计有限公司 | A kind of steep slope region underloading road structure and construction method |
-
2018
- 2018-10-29 CN CN201821760511.3U patent/CN209243486U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109403180A (en) * | 2018-10-29 | 2019-03-01 | 中铁四院集团西南勘察设计有限公司 | A kind of steep slope region underloading road structure and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106012797A (en) | All-ground-anchor type single-tower double-span cable-stayed bridge structure and construction method thereof | |
CN102425117B (en) | Construction method for non-cantilever sections of sidespans of multiplex continuous beam or steel-constructed beam | |
CN109403371A (en) | A kind of Steep Slope Embankment retaining structure and construction method | |
CN106223183B (en) | Assembled concrete-filled rectangular steel tube combines truss bridge and construction method | |
CN109371989B (en) | A kind of combined type retaining structure and its construction method suitable for stability of slope supporting | |
CN108343077A (en) | A kind of Miniature anti-slide pile composite structure and its construction method | |
CN209368867U (en) | A kind of Steep Slope Embankment retaining structure | |
CN108005094A (en) | Pier and pier top beam section construction method in naked rock river bed water | |
CN105672144B (en) | A kind of medium-small span bridges are reinforced with spelling wide structure and its construction method | |
CN105133484B (en) | A kind of part earth anchor higher-lower tower cable-stayed bridge structure | |
CN109403372A (en) | Abrupt slope road structure and its construction method | |
CN206090275U (en) | Assembled rectangular concrete -filled steel tube makes up truss bridge | |
CN109403180A (en) | A kind of steep slope region underloading road structure and construction method | |
CN110629770B (en) | Reservoir side slope hydro-fluctuation belt seepage-proofing slope protection structure and construction method thereof | |
CN102146676A (en) | High-steep side slope subgrade structure for mountain area | |
CN209243486U (en) | A kind of steep slope region underloading road structure | |
CN105804101B (en) | Reduce off-loading supporting and retaining system system and construction method and the application of retaining structure stress | |
CN110042770A (en) | A method of using the original bridge of external prestressing steel Shu Tuokuan in length and breadth | |
CN208152057U (en) | A kind of Miniature anti-slide pile composite structure | |
CN106917358B (en) | A kind of cable-stayed bridge main-beam combination constructing method thereof and its counter weight construction system | |
CN207862744U (en) | A kind of composite construction of bridge, tunnel, embankment | |
CN208293630U (en) | A kind of structural system of the antiseismic liquefaction uplifting in subway station | |
CN109750567A (en) | Expressway extension structure and expressway extension method | |
CN108505547A (en) | A kind of structural system and method for the antiseismic liquefaction uplifting in subway station | |
CN209368866U (en) | Abrupt slope road structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |