CN209230971U - A kind of test equipment for STDR-G type melting snow on turnout junction equipment - Google Patents

A kind of test equipment for STDR-G type melting snow on turnout junction equipment Download PDF

Info

Publication number
CN209230971U
CN209230971U CN201822225287.4U CN201822225287U CN209230971U CN 209230971 U CN209230971 U CN 209230971U CN 201822225287 U CN201822225287 U CN 201822225287U CN 209230971 U CN209230971 U CN 209230971U
Authority
CN
China
Prior art keywords
cabinet
equipment
stdr
snow
turnout junction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822225287.4U
Other languages
Chinese (zh)
Inventor
徐霆钧
刘大明
刘智伟
戴健
唐浩然
贾姣
余嘉贤
张华�
江守智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Railway Communication Co Ltd
Original Assignee
Shanghai Railway Communication Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Railway Communication Co Ltd filed Critical Shanghai Railway Communication Co Ltd
Priority to CN201822225287.4U priority Critical patent/CN209230971U/en
Application granted granted Critical
Publication of CN209230971U publication Critical patent/CN209230971U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of test equipments for STDR-G type melting snow on turnout junction equipment, including cabinet and the power module being placed in cabinet, cabinet is equipped with the power input interface for extraneous alternating current 220V input, and it is respectively used to 12 the first output interfaces of connection 12 tunnel of snow melting equipment outdoor cabinet input and is respectively used to 2 the second output interfaces of connection snow melting equipment outdoor cabinet uplink throat and downlink throat, power module includes regulated power supply and step-down rectifier module, regulated power supply and the input terminal of step-down rectifier module are connected to power input interface, output end is respectively connected to the second output interface and the first output interface.Compared with prior art, the utility model is by cabinet and the integration testing power module in cabinet, and the low pressure with 12 tunnels exports, 2 road High voltage outputs, can the perfect test realized for melting snow on turnout junction equipment, improve testing efficiency.

Description

A kind of test equipment for STDR-G type melting snow on turnout junction equipment
Technical field
The utility model relates to a kind of test equipments, more particularly, to a kind of survey for STDR-G type melting snow on turnout junction equipment Try equipment.
Background technique
STDR-G type electric heating melting snow on turnout junction equipment is a kind of using Electric heating, passes through the electric heating being mounted on track switch Element heats track switch to reach the purpose equipment of snow removing, has the characteristics that fire-bar and heating module are used in combination, road Branch off after electric heating snow removing device installation, efficiently solve the problems, such as track switch cleaning snow in winter, ensure that the normal work of track switch in winter, Ensure the safe, unimpeded of railway transportation.Its principle is the high-power output in 12 tunnels by electrical control cabinet, makes to be mounted on rail Other electric heating original part temperature increases rapidly, melts the accumulated snow being deposited near point machine, enables the normal work of goat Make, so being usually used in the more station of track switch.
Outdoor control cabinet is to assign signal by the simulation softward on the industrial personal computer in controlling terminal, is sent out by the port DB9 The pulse signal for sending a string of specific baud rates, to the CPU element of PLC, CPU can receive letter according to the program being written in advance, analysis Number pulse and baud rate, provide the voltage of 24V for specified port, the A.C. contactor being connected with the port PLC can pick up, break Road device closure, output port can export 220V voltage, if 12 tunnels can work normally, wiring is correct.PLC can be real The independent power supply on 1 tunnel of incumbent meaning or multichannel are powered simultaneously, and in order to which user facilitates operation, PLC can also be by intermediate relay, together When make the A.C. contactor of 6 uplink throats or 6 downlink throats while picking up, without being operated one by one.
It being operated by then passing through the software installed on the industrial personal computer in another cabinet, software itself is simultaneously unstable, Often there is phenomena such as Caton, sudden strain of a muscle are moved back, and signal is transmitted by signal wire, signal cable is again long, in multiple devices When being tested, often there is a situation where interfering with each other, causes signal to be delayed, or even failure, need to make repeated attempts, be desirable Restart industrial personal computer, more even misleads tester and be thought as that wiring mistake leads to equipment failure, need to check, can not find often again Reason, but cannot proper testing, influence to produce.
Utility model content
The purpose of this utility model is exactly to provide a kind of for STDR- to overcome the problems of the above-mentioned prior art The test equipment of G type melting snow on turnout junction equipment.
The purpose of this utility model can be achieved through the following technical solutions:
A kind of test equipment for STDR-G type melting snow on turnout junction equipment, including cabinet and the power supply mould being placed in cabinet Block, the cabinet is equipped with the power input interface for extraneous alternating current 220V input, and is respectively used to connection snow melting equipment 12 the first output interfaces and be respectively used to connection snow melting equipment outdoor cabinet uplink throat and downlink pharynx that 12 tunnel of outdoor cabinet inputs 2 the second output interfaces of larynx, the power module include regulated power supply and step-down rectifier module, the regulated power supply and decompression The input terminal of rectification module is connected to power input interface, and output end is respectively connected to the second output interface and the first output connects Mouthful.
The step-down rectifier module includes sequentially connected transformer, rectifier and filter, and the transformer is connected to Power input interface, the filter are connected to all first output interfaces.
The test equipment further includes that 12 first switches for being used to control the first output interface on-off and 2 are used to control The second switch of the second output interface on-off is controlled, 12 first switches are respectively arranged on step-down rectifier module and 12 first outputs Between interface, 2 second switches are respectively arranged between regulated power supply and 2 the second output interfaces.
Upper compartment and lower compartment are divided into the cabinet, the power module is placed in lower compartment, the first switch Upper compartment surface is placed in second switch.
The bottom of box is equipped with universal wheel.
Telescopic bar is additionally provided on the cabinet.
Compared with prior art, the utility model has the following beneficial effects:
1) by cabinet and the integration testing power module in cabinet, the low pressure with 12 tunnels is exported, and 2 tunnel high pressures are defeated Out, can the perfect test realized for melting snow on turnout junction equipment, improve testing efficiency.
2) on-off control can be carried out to a interface by first switch and the second switch, thus in test without carrying out The plug of plug carries out on-off control, while compared to the mode of software control, reliability is higher.
3) internal to be divided into two compartments, and power module is set in lower compartment, switch is set in upper compartment, convenient for operation While safety it is higher.
4) cabinet is equipped with universal wheel and pull rod, this test equipment easy to remove improves portable degree.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the structural schematic diagram of power module;
Fig. 3 is equipment front schematic view;
Fig. 4 is equipment back side schematic diagram;
Fig. 5 is test philosophy schematic diagram;
Fig. 6 is test process schematic diagram;
Fig. 7 is the cabinet schematic diagram with universal wheel and pull rod;
Fig. 8 is the structural schematic diagram of pull rod;
Wherein: 1, cabinet, 2, power module, 3, first switch, 4, second switch, 11, power input interface, 12, first Output interface, the 13, second output interface, 14, upper compartment, 15, lower compartment, 16, universal wheel, 17, telescopic bar, 21, pressure stabilizing Power supply, 22, transformer, 23, rectifier, 24, filter.
Specific embodiment
The utility model is described in detail in the following with reference to the drawings and specific embodiments.The present embodiment is with the utility model Implemented premised on technical solution, the detailed implementation method and specific operation process are given, but the guarantor of the utility model Shield range is not limited to the following embodiments.
A kind of test equipment for STDR-G type melting snow on turnout junction equipment as shown in Fig. 1,3,4, including cabinet 1 and is placed in Power module 2 in cabinet, cabinet 1 is equipped with the power input interface 11 for extraneous alternating current 220V input, and uses respectively In 12 the first output interfaces 12 for connecting the input of 12 tunnel of snow melting equipment outdoor cabinet and it is respectively used to connection snow melting equipment outdoor cabinet 2 the second output interfaces 13 of uplink throat and downlink throat, power module 2 include regulated power supply 21 and step-down rectifier module, Regulated power supply 21 and the input terminal of step-down rectifier module are connected to power input interface 11, and it is defeated that output end is respectively connected to second Outgoing interface 13 and the first output interface 12.
As shown in Fig. 2, step-down rectifier module includes sequentially connected transformer 22, rectifier 23 and filter 24, transformation Device 22 is connected to power input interface 11, and filter 24 is connected to all first output interfaces 12.
Regulated power supply 21 in the application is the 220V regulated power supply of disposable type, in order to by general lighting 220V circuit provides accurately 220V and powers, and step-down rectifier module is the module that alternating current 220V turns direct current 24V, can be used The models such as HA24N10-2539.
Test equipment further includes 12 first switches 3 and 2 for controlling 12 on-off of the first output interface for controlling 4,12 first switches of second switch for controlling 13 on-off of the second output interface are respectively arranged on step-down rectifier module and 12 first Between output interface 12,2 second switches 4 are respectively arranged between the second output interface of regulated power supply 21 and 2 13.
Upper compartment 14 and lower compartment 15 are divided into cabinet 1, power module 2 is placed in lower compartment 15, first switch 3 and Two switches 4 are placed in 14 surface of upper compartment.
As shown in fig. 7,1 bottom of cabinet is equipped with universal wheel 16, it is additionally provided with telescopic bar 17 on cabinet 1, as shown in figure 8, Telescopic bar 17 is realized by flexible rod principle to be stretched, and limit buckle can be set on bar, matched by limiting groove and limit buckle It closes and realizes limit.
First switch 3 and second switch 4 can choose using breaker, upper and lower part have outlet hole because matching Line is more, will not seem in disorder.
The pulse signal of BUG and specific baud rate when in order to avoid software test are easy to receive the interference of other signal sources The problem of, this test equipment makes the state switching for being powered and powering off by physical switch.Schematic diagram is as shown in Figure 5.Figure In power module be capable of providing 12 road 24V DC power supplies and 2 road 220V AC power sources, with the 1st road 24V DC power supply act Example, when 24V exports 1 when closing the switch, 14 contact points of contactor 1 are powered, at the same 13 contact points by electrical control cabinet inside The voltage of 24V+ is provided, induction coil is activated, and contactor closure, terminal 1 and 2,3 and 4,5 and 6 are connected, the three-phase electricity of 380V A phase power supply in source and the 220V alternating current between zero curve can reach output end, when output end has load by contactor When, so that it may output voltage, output electric current and output power at this time are shown by the synthesis voltameter in cabinet, operate phase It is intuitive when facilitating, and not will receive the interference of other equipment signal source.Similarly, the 2nd road to the 12nd tunnel all uses identical side Method is tested, and per that can work independently all the way, can also be worked at the same time,
For 220V AC power source, when 220V exports 1 when closing the switch, the contact point A1 of contactor 1,2,3,4,5,6 It is powered, meanwhile, the contact point A2 of all contactors is all by providing the alternating voltage of 220V- inside electric control cabinet, in contactor The induction coil in portion is activated, and contactor 1,2,3,4,5,6 is all closed, and simulates live uplink throat emergency button closure When, all fire-bars for being mounted on uplink throat can power in electrical control cabinet situation.Similarly, when 220V output 2 The case where when closing the switch, contactor 7,8,9,10,11,12 is all closed, and is simulated when live downlink throat emergency button is closed.
Specific testing process is as shown in Figure 6.Two above function is for electric control cabinet remote operation, automation control For system than more comprehensively test, other test contents are that the emergency of electric control cabinet is tested, and pass through the circuit of interior of equipment cabinet itself Design is to complete.

Claims (6)

1. a kind of test equipment for STDR-G type melting snow on turnout junction equipment, which is characterized in that including cabinet (1) and be placed in cabinet In power module (2), the cabinet (1) is equipped with the power input interface (11) for extraneous alternating current 220V input, and It is respectively used to connect 12 the first output interfaces (12) of 12 tunnel of snow melting equipment outdoor cabinet input and be respectively used to connection snow melt to set 2 the second output interfaces (13) of standby outdoor cabinet uplink throat and downlink throat, the power module (2) includes regulated power supply (21) and step-down rectifier module, the input terminal of the regulated power supply (21) and step-down rectifier module is connected to power input interface (11), output end is respectively connected to the second output interface (13) and the first output interface (12).
2. a kind of test equipment for STDR-G type melting snow on turnout junction equipment according to claim 1, which is characterized in that institute Stating step-down rectifier module includes sequentially connected transformer (22), rectifier (23) and filter (24), the transformer (22) It is connected to power input interface (11), the filter (24) is connected to all first output interfaces (12).
3. a kind of test equipment for STDR-G type melting snow on turnout junction equipment according to claim 1, which is characterized in that institute Stating test equipment further includes that 12 first switches (3) for being used to control the first output interface (12) on-off and 2 are controlled for controlling Make the second switch (4) of the second output interface (13) on-off, 12 first switches are respectively arranged on step-down rectifier module and 12 the Between one output interface (12), 2 second switches (4) be respectively arranged on regulated power supply (21) and 2 the second output interfaces (13) it Between.
4. a kind of test equipment for STDR-G type melting snow on turnout junction equipment according to claim 3, which is characterized in that institute It states in cabinet (1) and is divided into upper compartment (14) and lower compartment (15), the power module (2) is placed in lower compartment (15), described First switch (3) and second switch (4) are placed in upper compartment (14) surface.
5. a kind of test equipment for STDR-G type melting snow on turnout junction equipment according to claim 1, which is characterized in that institute Cabinet (1) bottom is stated equipped with universal wheel (16).
6. a kind of test equipment for STDR-G type melting snow on turnout junction equipment according to claim 1, which is characterized in that institute It states and is additionally provided with telescopic bar (17) on cabinet (1).
CN201822225287.4U 2018-12-28 2018-12-28 A kind of test equipment for STDR-G type melting snow on turnout junction equipment Expired - Fee Related CN209230971U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822225287.4U CN209230971U (en) 2018-12-28 2018-12-28 A kind of test equipment for STDR-G type melting snow on turnout junction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822225287.4U CN209230971U (en) 2018-12-28 2018-12-28 A kind of test equipment for STDR-G type melting snow on turnout junction equipment

Publications (1)

Publication Number Publication Date
CN209230971U true CN209230971U (en) 2019-08-09

Family

ID=67509543

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822225287.4U Expired - Fee Related CN209230971U (en) 2018-12-28 2018-12-28 A kind of test equipment for STDR-G type melting snow on turnout junction equipment

Country Status (1)

Country Link
CN (1) CN209230971U (en)

Similar Documents

Publication Publication Date Title
CN102435899B (en) Locomotive traction converter test apparatus and method thereof
CN104518569B (en) A kind of Auto-Test System supplies power distribution equipment
CN209230971U (en) A kind of test equipment for STDR-G type melting snow on turnout junction equipment
CN107833510B (en) 110kV power transformation interval somatosensory practical training equipment and practical training method
CN204681157U (en) A kind of intelligent double-power control system
CN207199529U (en) A kind of automatic electric switch
CN203039437U (en) Power distribution box provided with PLC intelligent controller
CN206992014U (en) Safety relay
CN108614176A (en) A kind of Current Voltage adjusting instruction carriage
CN207072716U (en) A kind of online synchronous manipulation device of tensioner multimachine
CN208506157U (en) A kind of Current Voltage adjusting instruction carriage
CN203720597U (en) Intelligent high voltage switch cabinet compartment measurement and control apparatus
CN204989315U (en) Threephase cable phase place checking apparatus
CN209168979U (en) A kind of constructional device of rack ATS
CN207457443U (en) The test system and its control device of a kind of high-tension switch gear
CN203397961U (en) Special mobile power supply switch for maintenance and debugging
CN105021892B (en) A kind of intelligent cable phase checking device
CN207232333U (en) The mechanical operating operation test device of one kind switch
CN206023597U (en) Finger-print type classroom power control
CN203812034U (en) Comprehensive training device for ship/vessel-used lighting system
CN207425185U (en) A kind of multifunctional intelligent Ship Power Station actual training device
CN208284123U (en) A kind of simulation unit discharge system
CN207134987U (en) Voltage dropping silicon chain with reserved interface
CN209327545U (en) A kind of DC experiment power supply
CN208819480U (en) A kind of one-and-half breaker bus grid switching operation experimental provision

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190809

CF01 Termination of patent right due to non-payment of annual fee