CN209227563U - High steep weathering seriously with the rock side slope supporting construction of joints development - Google Patents

High steep weathering seriously with the rock side slope supporting construction of joints development Download PDF

Info

Publication number
CN209227563U
CN209227563U CN201821889830.4U CN201821889830U CN209227563U CN 209227563 U CN209227563 U CN 209227563U CN 201821889830 U CN201821889830 U CN 201821889830U CN 209227563 U CN209227563 U CN 209227563U
Authority
CN
China
Prior art keywords
slope
rib
transverse ribs
rock
rock mass
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821889830.4U
Other languages
Chinese (zh)
Inventor
张延年
朱鑫泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nuclear Industry East China 268 Basic Engineering Co
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201821889830.4U priority Critical patent/CN209227563U/en
Application granted granted Critical
Publication of CN209227563U publication Critical patent/CN209227563U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The high steep weathering of the utility model belongs to slope retaining technical field seriously with the rock side slope supporting construction of joints development.The hierarchical arrangement longitudinal rib on slope rock mass, longitudinally upper rib are connect by connecting reinforcing bar with cushion cap;Transverse ribs are connect with longitudinally upper rib;Transverse ribs are connect with cushion cap;Prestress anchorage cable passes through the anchor cable hole being reserved in transverse ribs and transverse ribs is fixed on slope rock mass;Prestressed anchor passes through reinforcing bar protective net and is fixed on slope rock mass, carries out Seal treatment to reinforcing bar protective net spray furnace.The beneficial effects of the utility model and advantage are that setting concrete rib carries out integer support to rock mass, and spray furnace closing side slope country rock prevents country rock from further weakening;The structural strength and resistance to deformation rigidity that rock side slope can be improved using bolt-spary supports mode improve the overall stability of rock side slope, and stratum deformation is adaptable, can prevent rock side slope weathering.

Description

High steep weathering seriously with the rock side slope supporting construction of joints development
Technical field
The utility model belongs to slope retaining technical field, more particularly to a kind of high steep weathering seriously with joints development Rock side slope supporting construction.
Background technique
Rock side slope refers to guarantee rock matter subgrade stability, on the slope with certain slope that rock matter roadbed two sides are made into Face.The general joint of rock side slope compared with development, slope surface without vegetation, slope height is big, weathering is more serious, wind effect and long-term rain Under water souring, collapse rock-fall phenomenon can often occur.But existing slope retaining not only cannot be guaranteed the stabilization of rock side slope With prevent the further weathering of rock side slope, and construction cost is higher.Make rock side slope by special slope treatment mode There is apparent superiority for resisting the destruction of natural cause and improving highway environment.
Utility model content
In order to solve above-mentioned technical problem, the utility model provide a kind of high steep weathering seriously with joints development Rock side slope supporting construction, mainly for developing, a kind of side slope good integrity, stratum deformation is adaptable, can prevent rock side slope The slope retaining structure of weathering, can be effectively solved that high steep weathering is serious, joints development rock side slope weathering is serious and The problem of stability is difficult to ensure.
The technical solution adopted in the utility model is as follows:
High steep weathering is seriously with the rock side slope supporting construction of joints development, the hierarchical arrangement longitudinal rib on slope rock mass Item, every 10 meters of two column longitudinal rib spacing;Longitudinal rib include longitudinally upper rib, cushion cap and longitudinally lower rib, cushion cap and Longitudinally lower rib is prefabricated integral structure, and longitudinally upper rib is connect by connecting reinforcing bar with cushion cap;Transverse ribs are by wearing The U bolt for crossing U bolt slot is connect with longitudinally upper rib;Transverse ribs by pass through plain bolt slot expansion bolt with Cushion cap connection;Prestress anchorage cable passes through the anchor cable hole being reserved in transverse ribs and transverse ribs is fixed on slope rock mass;It is vertical The prefabricated slide resistant pile of one side contacted to upper rib and longitudinally lower rib with slope rock mass, by slide resistant pile by longitudinally upper rib Item and longitudinally lower rib are fixed on slope rock mass;Institute is exposed in the fenestral fabric that transverse ribs and longitudinal rib surround Reinforcing bar protective net is laid on slope rock mass out, prestressed anchor passes through reinforcing bar protective net and is fixed on slope rock mass, The equidistant arrangement of prestressed anchor, arrangement spacing are 1 meter × 1 meter;Seal treatment is carried out to reinforcing bar protective net spray furnace.
Further, the prestress anchorage cable includes bearing plate, anchor head and rope body;Bearing plate passes through rope body, and anchor head is consolidated It is scheduled on bearing plate, rope body passes through reserved anchor cable hole in transverse ribs and transverse ribs are fixed on slope rock mass.
Further, the slide resistant pile is connect with longitudinally upper rib and longitudinally lower rib using wet method, is contacted The reserved connection reinforcing bar in face, scene is spliced, depending on slide resistant pile actual number can be according to the length of side slope.
The utility model has the beneficial effects that
The beneficial effects of the utility model and advantage are that setting concrete rib carries out integer support, spray furnace to rock mass Closing side slope country rock prevents country rock from further weakening;The structural strength of rock side slope can be improved using bolt-spary supports mode and resist Deformation rigidity improves the overall stability of rock side slope, and stratum deformation is adaptable, can prevent rock side slope weathering.
Detailed description of the invention
Fig. 1 is the high steep weathering seriously diagrammatic cross-section with the rock side slope supporting construction of joints development.
Fig. 2 is the high steep weathering seriously front view with the rock side slope supporting construction of joints development.
Fig. 3 is the structural schematic diagram that transverse ribs are connected with longitudinal rib in the utility model.
Fig. 4 is the structural schematic diagram of prestress anchorage cable monomer in the utility model.
Fig. 5 is slide resistant pile safeguard structure schematic diagram in the utility model.
Fig. 6 is cushion cap front view in the utility model.
Fig. 7 is cushion cap side view in the utility model.
In figure, 1 is slope rock mass;2 be prestressed anchor;3 be prestress anchorage cable;3-1 is bearing plate;3-2 is anchor head;3- 3 be rope body;4 be transverse ribs;5 be longitudinal rib;5-1 is longitudinally upper rib;5-2 is longitudinally lower rib;6 be cushion cap;7 For slide resistant pile;8 be reinforcing bar protective net;9 be connection reinforcing bar;10 be U bolt slot;11 be plain bolt slot.
Specific embodiment
The utility model is described in detail with reference to the accompanying drawings and examples.
Embodiment
As shown in Fig. 1-Fig. 7, a kind of high steep weathering seriously with the rock side slope supporting construction of joints development, in slope rock mass Hierarchical arrangement longitudinal rib 5 on 1, every 10 meters of two column longitudinal rib, 5 spacing;Longitudinal rib 5 includes longitudinally upper rib 5-1, holds Platform 6 and longitudinally lower rib 5-2, cushion cap 6 and longitudinally lower rib 5-2 are prefabricated integral structure, and longitudinally upper rib 5-1 passes through Connection reinforcing bar 9 is connect with cushion cap 6;Transverse ribs 4 are connected by the U bolt and longitudinally upper rib 5-1 for passing through U bolt slot 10 It connects;Transverse ribs 4 are connect by passing through the expansion bolt of plain bolt slot 11 with cushion cap 6;Prestress anchorage cable 3 passes through and is reserved in cross Transverse ribs 4 are fixed on slope rock mass 1 by the anchor cable hole on rib 4;Longitudinally upper rib 5-1 and longitudinally lower rib 5- The 2 prefabricated slide resistant piles 7 of one side contacted with slope rock mass 1, by slide resistant pile 7 by longitudinally upper rib 5-1 and longitudinally lower rib 5-2 is fixed on slope rock mass 1;The exposed side slope of institute in the fenestral fabric that transverse ribs 4 and longitudinal rib 5 surround Reinforcing bar protective net 8 is laid on rock mass 1, prestressed anchor 2 passes through reinforcing bar protective net 8 and is fixed on slope rock mass 1, prestressing force The equidistant arrangement of anchor pole 2, arrangement spacing are 1 meter × 1 meter;Seal treatment is carried out to 8 spray furnace of reinforcing bar protective net.
As shown in figure 4, the prestress anchorage cable 3 includes bearing plate 3-1, anchor head 3-2 and rope body;Bearing plate 3-1 passes through rope Anchor head 3-2 is fixed on bearing plate 3-1 by body 3-3, and rope body 3-3, which is passed through, reserves anchor cable hole for transverse ribs 4 in transverse ribs 4 It is fixed on slope rock mass 1.
As shown in figure 5, the slide resistant pile 7 and longitudinally upper rib 5-1 and longitudinally lower rib 5-2 is connected using wet method It connects, the reserved connection reinforcing bar 9 of contact surface, scene is spliced, depending on 7 actual number of slide resistant pile can be according to the length of side slope.
The above is only the preferred embodiment of the utility model, it is noted that for the common skill of the art For art personnel, without departing from the principle of this utility model, several improvements and modifications can also be made, these improve and Retouching also should be regarded as the protection scope of the utility model.

Claims (3)

1. high steep weathering seriously with the rock side slope supporting construction of joints development, it is characterised in that: be classified on slope rock mass (1) It arranges longitudinal rib (5), 10 meters of spacing of every two column longitudinal rib (5);Longitudinal rib (5) includes longitudinally upper rib (5-1), holds Platform (6) and longitudinally lower rib (5-2), cushion cap (6) and longitudinally lower rib (5-2) are prefabricated integral structure, longitudinally upper rib Item (5-1) is connect by connecting reinforcing bar (9) with cushion cap (6);Transverse ribs (4) pass through the U bolt across U bolt slot (10) It is connect with longitudinally upper rib (5-1);Transverse ribs (4) by pass through plain bolt slot (11) expansion bolt and cushion cap (6) Connection;Prestress anchorage cable (3) passes through the anchor cable hole being reserved on transverse ribs (4) and transverse ribs (4) is fixed on slope rock mass (1) on;The prefabricated slide resistant pile of one side that longitudinally upper rib (5-1) and longitudinally lower rib (5-2) are contacted with slope rock mass (1) (7), longitudinally upper rib (5-1) and longitudinally lower rib (5-2) are fixed on slope rock mass (1) by slide resistant pile (7);? It is anti-that reinforcing bar is laid on the exposed slope rock mass (1) of institute in the fenestral fabric that transverse ribs (4) and longitudinal rib (5) surround Protective net (8), prestressed anchor (2) pass through reinforcing bar protective net (8) and are fixed on slope rock mass (1), prestressed anchor (2) etc. Distance arrangement, arrangement spacing are 1 meter × 1 meter;Seal treatment is carried out to reinforcing bar protective net (8) spray furnace.
2. according to claim 1 high steep weathering seriously with the rock side slope supporting construction of joints development, it is characterised in that: institute Stating prestress anchorage cable (3) includes bearing plate (3-1), anchor head (3-2) He Suoshen;Bearing plate (3-1) passes through rope body (3-3), by anchor Head (3-2) is fixed on bearing plate (3-1), and rope body (3-3), which passes through, reserves anchor cable hole for transverse ribs (4) on transverse ribs (4) It is fixed on slope rock mass (1).
3. according to claim 1 high steep weathering seriously with the rock side slope supporting construction of joints development, it is characterised in that: institute It states slide resistant pile (7) and is connect with longitudinally upper rib (5-1) and longitudinally lower rib (5-2) using wet method, contact surface is reserved It connects reinforcing bar (9), scene is spliced.
CN201821889830.4U 2018-11-16 2018-11-16 High steep weathering seriously with the rock side slope supporting construction of joints development Expired - Fee Related CN209227563U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821889830.4U CN209227563U (en) 2018-11-16 2018-11-16 High steep weathering seriously with the rock side slope supporting construction of joints development

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821889830.4U CN209227563U (en) 2018-11-16 2018-11-16 High steep weathering seriously with the rock side slope supporting construction of joints development

Publications (1)

Publication Number Publication Date
CN209227563U true CN209227563U (en) 2019-08-09

Family

ID=67503308

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821889830.4U Expired - Fee Related CN209227563U (en) 2018-11-16 2018-11-16 High steep weathering seriously with the rock side slope supporting construction of joints development

Country Status (1)

Country Link
CN (1) CN209227563U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501795A (en) * 2020-04-29 2020-08-07 中铁二院工程集团有限责任公司 Anchor net device for reinforcing and protecting high and steep slope and construction method thereof
CN111501794A (en) * 2020-04-29 2020-08-07 中铁二院工程集团有限责任公司 Anchoring device, anchoring system and construction method for reinforcing and protecting high and steep slope
CN113279416A (en) * 2021-04-23 2021-08-20 游永华 Highway side slope reinforcing apparatus

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501795A (en) * 2020-04-29 2020-08-07 中铁二院工程集团有限责任公司 Anchor net device for reinforcing and protecting high and steep slope and construction method thereof
CN111501794A (en) * 2020-04-29 2020-08-07 中铁二院工程集团有限责任公司 Anchoring device, anchoring system and construction method for reinforcing and protecting high and steep slope
CN113279416A (en) * 2021-04-23 2021-08-20 游永华 Highway side slope reinforcing apparatus

Similar Documents

Publication Publication Date Title
CN209227563U (en) High steep weathering seriously with the rock side slope supporting construction of joints development
CN106400813B (en) A kind of foundation pit support system and its construction method
CN108589514A (en) Load-bearing and earth-quake resistant mechanism separate type precast assembly bridge pier system
WO2016192320A1 (en) Continuous beam type anti-floating structure of shield tunnel
CN105178206B (en) Spliced-type shed tunnel
CN203452092U (en) T-shaped pile retaining wall
CN203307817U (en) Double-row pile structure provided with steel tube prestressed concrete for connection between front-row piles and rear-row piles
CN209194544U (en) Combined type foundation pit supporting construction
CN108342982A (en) A kind of hybrid combining girder stayed-cable bridge cable crane track cable beam-ends is from anchor structure
CN206090275U (en) Assembled rectangular concrete -filled steel tube makes up truss bridge
CN206538676U (en) A kind of utilization split column technology exempts from seismic Damage high-speed railway bridge pier
CN103306295A (en) Rigid frame pile supporting and blocking structure
CN204780568U (en) High water level, fast velocity of flow arched bridge binder buttress system
CN204530425U (en) Prestressed steel truss bridge
CN209669718U (en) A kind of existing hangar tunnel combination stone cut off wall structure of rockfall protection
CN206828906U (en) A kind of temporary pavement bedding structure for Metro Deep Excavation
CN209082285U (en) A kind of pavement structure having fiber mixture
CN103669976A (en) Ancient pagoda correction
CN109295989A (en) High steep weathering seriously with the rock side slope supporting construction of joints development
CN102877413B (en) Construction technology for large-size cableway bridge engineering
CN202081383U (en) Temporary support used in construction striding over existing line bridge
CN105155377A (en) Roadbed structure close to expressway pier
CN204401462U (en) For the support of pier prestressed cap beam with extra length Construction Supporting System in water
CN208395854U (en) A kind of modified truss-like retaining wall structure
CN206902528U (en) Overpass structure-improved

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200409

Address after: 334000 Fenghuang mountain, Yushan County, Shangrao City, Jiangxi Province

Patentee after: Nuclear industry east China 268 basic engineering Co.

Address before: Hunnan Hunnan Road Shenyang city Liaoning province 110168 No. 9

Patentee before: SHENYANG JIANZHU University

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190809

Termination date: 20211116