CN209223995U - A kind of double electric hammer turn hole devices - Google Patents

A kind of double electric hammer turn hole devices Download PDF

Info

Publication number
CN209223995U
CN209223995U CN201821872844.5U CN201821872844U CN209223995U CN 209223995 U CN209223995 U CN 209223995U CN 201821872844 U CN201821872844 U CN 201821872844U CN 209223995 U CN209223995 U CN 209223995U
Authority
CN
China
Prior art keywords
electric hammer
turn hole
adjusting
adjusting brackets
double electric
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821872844.5U
Other languages
Chinese (zh)
Inventor
刘海波
白素平
蔡美霞
孟秀芬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Second Metallurgy Group Co Ltd
Original Assignee
China Second Metallurgy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Second Metallurgy Group Co Ltd filed Critical China Second Metallurgy Group Co Ltd
Priority to CN201821872844.5U priority Critical patent/CN209223995U/en
Application granted granted Critical
Publication of CN209223995U publication Critical patent/CN209223995U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Drilling And Boring (AREA)

Abstract

The utility model provides a kind of double electric hammer turn hole devices, comprising: location position mechanism, two adjusting brackets and force application mechanism;Wherein, the lower section of two adjusting brackets is arranged in the location position mechanism, is demarcated and is locked for the position to two adjusting brackets;An electric hammer rotary head is separately installed on two adjusting brackets, also, two adjusting brackets are arranged in side by side in the location position mechanism, for adjusting the position for the electric hammer rotary head that respectively top is installed after location position;The force application mechanism is connected between two adjusting brackets, to apply active force so that the two moves synchronously to two adjusting brackets.In the utility model, human-body fatigue can be avoided to adverse effect caused by construction precision, while can once operate two electric hammers, not only can also greatly improve construction efficiency to avoid operation bring accumulated error twice.

Description

A kind of double electric hammer turn hole devices
Technical field
The utility model relates to hanger mounting technique fields, in particular to a kind of double electric hammer turn hole devices.
Background technique
The way manually to drill is usually taken in suspension and support work progress, operator needs to stand in scaffold in construction Upper both hands act holds electric hammer and looks up construction.Operator is held in act for a long time can generate fatigue, and hand-motion jitter displacement occurs, not can guarantee hole Position precision and vertical precision.
Summary of the invention
In consideration of it, the utility model proposes a kind of double electric hammer turn hole devices, it is intended to which solving existing manual turn hole can not protect Demonstrate,prove construction precision and the lower problem of construction efficiency.
On one side, the utility model proposes a kind of double electric hammer turn hole devices, comprising: location position mechanism, two tune Save frame and force application mechanism;Wherein, the lower section of two adjusting brackets is arranged in the location position mechanism, for described in two The position of adjusting bracket is demarcated and is locked;An electric hammer, also, two adjustings are separately installed on two adjusting brackets Frame is arranged in side by side in the location position mechanism, for adjusting the respectively rotary head of the electric hammer of top installation after location position Position;The force application mechanism is connected between two adjusting brackets, applying active forces to two adjusting brackets so that The two moves synchronously.
Further, in above-mentioned double electric hammer turn hole devices, the adjusting bracket includes: successively hinged lower support bar, control Bar, auxiliary rod and upper support bar;Wherein, the lower support bar, the control-rod, the auxiliary rod and the upper support bar are enclosed and are connect At a parallelogram lever;The lower support bar is arranged in the location position mechanism, is provided on the upper support bar Electric hammer mounting rack.
Further, in above-mentioned double electric hammer turn hole devices, one end of the control-rod is provided with electric hammer switch.
Further, in above-mentioned double electric hammer turn hole devices, the force application mechanism is link mechanism.
Further, it in above-mentioned double electric hammer turn hole devices, is rotatably arranged on the link mechanism there are two sliding sleeve, two A adjusting bracket passes through two sliding sleeves respectively and is rotatably connected with the force application mechanism.
Further, in above-mentioned double electric hammer turn hole devices, the link mechanism both ends are provided with to prevent the sliding sleeve From the gear part that the link mechanism slips.
Further, in above-mentioned double electric hammer turn hole devices, the location position mechanism includes: that scale fixed frame and two are vertical Column;Wherein, the card being fixed to the position to the adjusting bracket is provided on the scale fixed frame set channel;Two institutes The both ends that the scale fixed frame is arranged in column are stated, mutually to fix with adjustable shelf.
Further, in above-mentioned double electric hammer turn hole devices, the location position mechanism is two, and one of institute's rheme Calibrating device is set to be connected to above another described location position mechanism by column.
Further, in above-mentioned double electric hammer turn hole devices, if the scale fixed frame include: the horizontal ruler that is set side by side and Dry retaining mechanism;Wherein, each retaining mechanism is arranged in a one-to-one correspondence with the scale on the horizontal ruler, and the horizontal ruler and A channel for wearing the adjusting bracket is formed between the retaining mechanism.
Further, in above-mentioned double electric hammer turn hole devices, the retaining mechanism includes: screw arbor assembly and card slot;Wherein, institute The side that screw arbor assembly is connected to the card slot is stated, for locking the adjusting after the adjusting bracket is arranged in the card slot Frame.
In double electric hammer turn hole devices provided by the utility model, by the way that two adjustings are arranged above the calibrating device of position Force application mechanism is arranged between two adjusting brackets in frame, by the way that two electric hammers are separately mounted on two adjusting brackets, to operate When personnel apply pressure to force application mechanism, so that two adjusting brackets follow force application mechanism to rotate synchronously, to adjust two electric hammers Rotary head position, and then it is advantageously ensured that two turn holes precision, lift and hold on scaffold using artificial station with the prior art Electric hammer is looked up construction and is compared, and can be avoided human-body fatigue to adverse effect caused by construction precision, while can once operate two Platform electric hammer not only can also greatly improve construction efficiency to avoid operation bring accumulated error twice;Operator stands when operation Position is fixed, far from scaffold edge, can with maximum probability avoid the generation of fallen accident.
Detailed description of the invention
By reading the following detailed description of the preferred embodiment, various other advantages and benefits are common for this field Technical staff will become clear.The drawings are only for the purpose of illustrating a preferred embodiment, and is not considered as practical to this Novel limitation.And throughout the drawings, the same reference numbers will be used to refer to the same parts.In the accompanying drawings:
Fig. 1 is the structural schematic diagram of double electric hammer turn hole devices provided by the embodiment of the utility model;
Fig. 2 is the use state diagram of double electric hammer turn hole devices provided by the embodiment of the utility model.
Specific embodiment
Exemplary embodiments of the present disclosure are described in more detail below with reference to accompanying drawings.Although showing the disclosure in attached drawing Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure without should be by embodiments set forth here It is limited.On the contrary, these embodiments are provided to facilitate a more thoroughly understanding of the present invention, and can be by the scope of the present disclosure It is fully disclosed to those skilled in the art.It should be noted that in the absence of conflict, the implementation in the utility model Feature in example and embodiment can be combined with each other.It is below with reference to the accompanying drawings and in conjunction with the embodiments practical new this is described in detail Type.
Refering to fig. 1, double electric hammer turn hole devices of the utility model embodiment include: 1, two adjusting bracket of location position mechanism 2 and force application mechanism 3;Wherein, the lower section of two adjusting brackets 2 is arranged in the location position mechanism 1, for described in two The position of adjusting bracket 2 is demarcated and is locked;It is separately installed with an electric hammer 4 on two adjusting brackets 2, also, described in two Adjusting bracket 2 is arranged in side by side in the location position mechanism 1, for adjusting the electric hammer 4 that respectively top is installed after location position Rotary head position;The force application mechanism 3 is connected between two adjusting brackets 2, is made to apply to two adjusting brackets 2 Firmly so that the two moves synchronously.
Specifically, location position mechanism 1 can be set in bottom, two adjusting brackets 2 are connected to location position machine An electric hammer 4, installation site of two electric hammers 4 relative to adjusting bracket 2 are installed on the top of two adjusting brackets 2 in the both ends of structure 1 respectively It is consistent, also, the rotary head of two electric hammers 4 position of the direction to turn hole, in order to which subsequent displacement is adjusted and turn hole work Make.Force application mechanism 3 is connected between two adjusting brackets 2, when it is by applied external force, be will drive two adjusting brackets 2 and is moved To adjust the position of the rotary head of two electric hammers 4.Whole device is whole in use, location position mechanism 1 is fixed with 7 phase of adjustable shelf A turn hole device provides stable support;Meanwhile location position mechanism 1 can provide for two adjusting brackets 2 and wear channel, with After adjusting bracket 2 is worn wherein, it is positioned and is locked, to guarantee the verticality of two adjusting brackets 2, is further ensured Relative position between the verticality and two electric hammers 4 of two electric hammers 4.Force application mechanism 3 can be connected to two adjusting brackets 2 it Between driving member, it can be ensured that the movement of two adjusting brackets 2 is consistent.
It is above-mentioned obviously it can be concluded that, the double electric hammer turn hole devices provided in the present embodiment, by the calibrating device of position Two adjusting brackets of side's setting, are arranged force application mechanism between two adjusting brackets, by the way that two electric hammers are separately mounted to two tune It saves on frame, with when operator applies pressure to force application mechanism, so that two adjusting brackets follow force application mechanism to rotate synchronously, from And adjust two electric hammers rotary head position, and then it is advantageously ensured that two turn holes precision, with the prior art use artificial station It lifts to hold electric hammer and look up construction on scaffold and compare, can be avoided human-body fatigue to adverse effect caused by construction precision, simultaneously Two electric hammers can be once operated, not only can also greatly improve construction efficiency to avoid operation bring accumulated error twice; Operator's erect-position is fixed when operation, far from scaffold edge, can with maximum probability avoid the generation of fallen accident.
With continued reference to Fig. 1, adjusting bracket 2 includes: successively hinged lower support bar 21, control-rod 22, auxiliary rod 23 and upper branch Strut 24;Wherein, the lower support bar 21, the control-rod 22, the auxiliary rod 23 and the upper support bar 24 enclose and are connected into one Parallelogram lever;The lower support bar 21 is arranged in the location position mechanism 1, is provided on the upper support bar 24 Electric hammer mounting rack 5.
Specifically, lower support bar 21 and upper support bar 24 are arranged in parallel along the vertical direction, control-rod 22 and auxiliary rod 23 Edge is arranged in parallel with the inclined direction of vertical direction.Lower support bar 21, the control-rod 22, the auxiliary rod 23 and the upper branch Strut 24, which encloses, is connected into a parallelogram lever, also, is articulated and connected between any two, can guarantee entire adjusting bracket 2 in vertical side It moves up, to drive the rotary head of electric hammer 4 to the position feeding to turn hole, realizes the automation of turn hole, avoid artificial hand Hold error caused by electric hammer.When it is implemented, lower support bar 21 is arranged in location position mechanism 1, with realization and location position The locking of mechanism 1;Electric hammer mounting rack 5 is provided on upper support bar 24, for fixing electric hammer 4, to ensure electric hammer 4 and upper support bar 24 levelness, and skew does not occur in the construction process.Electric hammer mounting rack 5 can be any one structure in the prior art Mounting rack, the installation for being able to achieve electric hammer is fixed.
It, can be the one of control-rod 22 in order to increase the operation ease and safety of operator in above-described embodiment End is provided with electric hammer switch, specifically, can switch in control-rod 22 close to one end of force application mechanism 3 setting electric hammer.
For the uniformity of entire turn hole device operation, it is preferred that set a switch for two sets of electric hammers 4, and arrange On force application mechanism 3.
Preferably, force application mechanism 3 can be link mechanism.Specifically, link mechanism can be round tube part.Operation When, operator's both hands firmly press downwards link mechanism, adjusting bracket 2 can be driven to move upwards along the vertical direction, to adjust Electric hammer switch is opened extremely to turn hole position in the position of economize on electricity 4 rotary heads of hammer, until turn hole is completed;Lift link mechanism It drives adjusting bracket 2 to move vertically downwards, 4 rotary head of electric hammer can be withdrawn from from hole, close power supply, be moved to next It is operated to position of opening.As can be seen that link mechanism is simple, it is easy to accomplish.
When it is implemented, being rotatably arranged on the link mechanism there are two sliding sleeve 6, two adjusting brackets 2 are distinguished It is rotatably connected by two sliding sleeves 6 with force application mechanism 3.Sliding sleeve 6 can be Circular Rigid casing, and link mechanism is placed through two After sliding sleeve 6, for be uniformly controlled left and right two parts adjusting bracket 2 movement uniformity.
Preferably, the link mechanism both ends are provided with to anti-anti-skid sheath 6 from the gear part that the link mechanism slips a。
In the various embodiments described above, location position mechanism 1 includes: scale fixed frame 11 and two root posts 12;Wherein, scale is solid Determine to be provided with the card being fixed to the position to the adjusting bracket 2 on frame 11 and sets channel;Two settings of column 12 exist The both ends of the scale fixed frame 11, to be fixed with 7 phase of adjustable shelf.
Adjustable shelf 7 can be any one structure in the prior art, such as by four pillars and can be connected to four branch Roller structure, total easy to remove can be set in plate structure above column, four posts bottoms.Wherein, four pillars It can be hollow tubular structures, when installation site calibrating device 1, it is only necessary to be inserted into two root posts 12 in the pillar of adjustable shelf i.e. Entire double electric hammer turn hole devices can be fixed as one with adjustable shelf 7, ensure that the stability of whole device.
Location position mechanism 1 can be one or more;Preferably, location position mechanism 1 is two, and one of position It sets calibrating device 1 and another 1 top of location position mechanism is connected to by column 12.Liang Ge location position mechanism 1 can pass through The respective socket of column 12 connection is welded to connect, and specific connection type can be determined according to the actual situation.Two There is pre-determined distance along the vertical direction, so that the different portions of the lower support bar 21 of two adjusting brackets 2 between location position mechanism 1 Position locking advantageously ensures that the positioning accuracy of whole device in Liang Ge location position mechanism 1.
Specifically, the scale fixed frame 11 includes: the horizontal ruler 111 and several retaining mechanisms 112 being set side by side;Its In, each retaining mechanism 112 is arranged in a one-to-one correspondence with the scale on the horizontal ruler 111, and the horizontal ruler 111 and described A channel for wearing the adjusting bracket 2 is formed between retaining mechanism 112.Each retaining mechanism 112 is successively arranged, each locking machine Structure 112 is corresponding with the scale of each gear on horizontal ruler 111, forms the lower support bar 21 for placing adjusting bracket 2 therebetween Space, after the support rod 21 of two adjusting brackets 2 is placed in any two retaining mechanism 112, that is, can determine two support rods The fastening of two support rods 21 in relative position and realization between 21.
Two lower support bars 21 are inserted into preset retaining mechanism 112, that is, can determine the opposite position between two electric hammers 4 It sets, that is, can effectively avoid two electric hammers 4 and generate inclination in operation.
Preferably, the retaining mechanism 112 includes: screw arbor assembly 1121 and card slot 1122;Wherein, the screw arbor assembly 1121 are connected to the side of the card slot 1122, for locking the tune after the adjusting bracket 2 is arranged in the card slot 1122 Save frame 2.
Specifically, screw arbor assembly 1121 is connected after being arranged in connecting plate with card slot 1122, wherein connecting plate with Horizontal ruler 111 can be arranged in parallel.Card slot 1122 can be preferably semicircular arc-shaped structure, radian can under adjusting bracket 2 The outer wall radian of support rod 21 matches, and compresses lower support bar 21 with better occlusion.In actual use, when lower support bar 21 is worn If enter between horizontal ruler 111 and card slot 1122, it can be realized by tightening the nut on screw arbor assembly 1121 to lower support bar 21 locking, it can be seen that the retaining mechanism 112 has the advantages of simple structure and easy realization, and can conveniently lock and unclamp lower support Bar 21.
Referring to Fig.2, the course of work of the utility model embodiment is as follows: needing to fix in two scales according to concrete operations Suitable gear is selected on frame, two lower support bars are locked by locking member, to guarantee the relative position between two electric hammers;Lower branch For movable Scaffold to suitable position, whether examination operation control-rod observes turn hole position accurate after strut locking;It is adjusted after confirmation hole location Electric hammer hammer tip is resisted operating surface by section control-rod, opens electric hammer power switch.Link mechanism is firmly pressed downward by operator's both hands Under, until turn hole is completed.Lift link mechanism, electric hammer rotary head can be withdrawn from from hole, close power supply, be moved to it is next to Position of opening is operated.Double electric hammer turn hole devices provided in this embodiment, allow operator to operate two electric hammers simultaneously It is particularly suitable for the occasion that cable testing bridge sunpender and air hose sunpender etc. need to guarantee two sunpender spacing relative accuracys.
To sum up, in double electric hammer turn hole devices provided by the embodiment of the utility model, by being set above the calibrating device of position Two adjusting brackets are set, force application mechanism is set between two adjusting brackets, by the way that two electric hammers are separately mounted to two adjusting brackets On, with operator to force application mechanism apply pressure when so that two adjusting brackets follow force application mechanism to rotate synchronously, to adjust Save the position of the rotary head of two electric hammers, and then it is advantageously ensured that two turn holes precision, with the prior art using artificial station in foot It lifts to hold electric hammer and look up construction in hand cradle and compare, can be avoided human-body fatigue to adverse effect caused by construction precision, while is primary Two electric hammers can be operated, not only can also greatly improve construction efficiency to avoid operation bring accumulated error twice;Operation When operator's erect-position fix, far from scaffold edge, can with maximum probability avoid the generation of fallen accident.
Obviously, it is practical without departing from this can to carry out various modification and variations to the utility model by those skilled in the art Novel spirit and scope.If in this way, these modifications and variations of the present invention belong to the utility model claims and Within the scope of its equivalent technologies, then the utility model is also intended to include these modifications and variations.

Claims (10)

1. a kind of double electric hammer turn hole devices characterized by comprising location position mechanism (1), two adjusting brackets (2) and force Mechanism (3);Wherein,
Location position mechanism (1) setting is in the lower section of two adjusting brackets (2), for two adjusting brackets (2) Position demarcated and locked;
It is separately installed with an electric hammer (4) on two adjusting brackets (2), also, two adjusting brackets (2) are arranged in institute side by side Rheme is set in calibrating device (1), for adjusting the rotary head position for the electric hammer (4) that respectively top is installed after location position;
The force application mechanism (3) is connected between two adjusting brackets (2), makees to apply to two adjusting brackets (2) Firmly so that the two moves synchronously.
2. double electric hammer turn hole devices according to claim 1, which is characterized in that the adjusting bracket (2) includes: successively hinged Lower support bar (21), control-rod (22), auxiliary rod (23) and upper support bar (24);Wherein,
The lower support bar (21), the control-rod (22), the auxiliary rod (23) and the upper support bar (24) enclose and are connected into one Parallelogram lever;
The lower support bar (21) is arranged in the location position mechanism (1), is provided with electric hammer on the upper support bar (24) Mounting rack (5).
3. double electric hammer turn hole devices according to claim 2, which is characterized in that one end of the control-rod (22) is provided with Electric hammer switch.
4. double electric hammer turn hole devices according to any one of claim 1 to 3, which is characterized in that the force application mechanism (3) For link mechanism.
5. double electric hammer turn hole devices according to claim 4, which is characterized in that be rotatably arranged on the link mechanism There are two sliding sleeve (6), two adjusting brackets (2) can be rotated by two sliding sleeves (6) and the force application mechanism (3) respectively Connection.
6. double electric hammer turn hole devices according to claim 5, which is characterized in that the link mechanism both ends be provided with to Prevent the sliding sleeve (6) from the gear part (a) that the link mechanism slips.
7. double electric hammer turn hole devices according to any one of claim 1 to 3, which is characterized in that the location position machine Structure (1) includes: scale fixed frame (11) and two root posts (12);Wherein,
The card being fixed to the position to the adjusting bracket (2), which is provided with, on the scale fixed frame (11) sets channel;
Two columns (12) are arranged at the both ends of the scale fixed frame (11), mutually to fix with adjustable shelf (7).
8. double electric hammer turn hole devices according to claim 7, which is characterized in that the location position mechanism (1) is two, And one of them described location position mechanism (1) is connected to above another described location position mechanism (1) by column (12).
9. double electric hammer turn hole devices according to claim 7, which is characterized in that the scale fixed frame (11) includes: simultaneously Arrange the horizontal ruler (111) and several retaining mechanisms (112) of setting;Wherein,
Each retaining mechanism (112) is arranged in a one-to-one correspondence with the scale on the horizontal ruler (111), and the horizontal ruler (111) channel for wearing the adjusting bracket (2) is formed between the retaining mechanism (112).
10. double electric hammer turn hole devices according to claim 9, which is characterized in that the retaining mechanism (112) includes: spiral shell Bar assembly (1121) and card slot (1122);Wherein,
The screw arbor assembly (1121) is connected to the side of the card slot (1122), for being arranged in institute in the adjusting bracket (2) It states card slot (1122) and locks the adjusting bracket (2) afterwards.
CN201821872844.5U 2018-11-14 2018-11-14 A kind of double electric hammer turn hole devices Active CN209223995U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821872844.5U CN209223995U (en) 2018-11-14 2018-11-14 A kind of double electric hammer turn hole devices

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821872844.5U CN209223995U (en) 2018-11-14 2018-11-14 A kind of double electric hammer turn hole devices

Publications (1)

Publication Number Publication Date
CN209223995U true CN209223995U (en) 2019-08-09

Family

ID=67502926

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821872844.5U Active CN209223995U (en) 2018-11-14 2018-11-14 A kind of double electric hammer turn hole devices

Country Status (1)

Country Link
CN (1) CN209223995U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111188573A (en) * 2020-03-03 2020-05-22 郑州机械研究所有限公司 Tunnel top drilling device
CN112482818A (en) * 2020-12-08 2021-03-12 浙江上嘉建设有限公司 Construction method for building external wall reconstruction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111188573A (en) * 2020-03-03 2020-05-22 郑州机械研究所有限公司 Tunnel top drilling device
CN112482818A (en) * 2020-12-08 2021-03-12 浙江上嘉建设有限公司 Construction method for building external wall reconstruction

Similar Documents

Publication Publication Date Title
CN209223995U (en) A kind of double electric hammer turn hole devices
CN207776396U (en) For building strengthening, the operating platform of protection
CN208578355U (en) A kind of construction support device that classification is adjusted
CN111644857A (en) Height-adjustable high-altitude machining equipment
CN208563954U (en) Scaffold pedestal
CN201738819U (en) Drilling moving frame
CN109366028B (en) Automatic welding device for box-shaped beam and using method
CN107086474A (en) A kind of electricity box install power assisting device
CN214815087U (en) Adjustable drilling tool
CN215407592U (en) Be used for civil engineering construction strutting arrangement convenient to remove
CN209992752U (en) Astronomical telescope support frame with height of being convenient for is adjusted to astronomical table
CN112267675B (en) High-precision control building construction strut auxiliary mechanism and control method thereof
CN107297596B (en) Cultural relic orthopedic instrument
CN103774694A (en) Adjustable locating jig frame for reinforcement cage
CN208505775U (en) A kind of bracket for building wall board load experimental rig
CN113638588A (en) Large cornice scaffold for high-rise building
CN206931906U (en) Electricity box install power assisting device
CN220580462U (en) Support frame
CN210489332U (en) Flange alignment locking device for producing extra-high voltage composite strut
CN215368598U (en) Multifunctional construction support
CN215928999U (en) Survey and use total powerstation bearing structure
CN214702757U (en) Fixing device for assisting steam turbine maintenance
CN216516759U (en) Steel construction stable support frame based on engineering construction
CN216921499U (en) Top bracing device for controlling crack of super-long reinforced concrete structure
CN219616762U (en) Impact drill booster

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant