CN209163176U - It cornices outside space structure ceiling system structure - Google Patents

It cornices outside space structure ceiling system structure Download PDF

Info

Publication number
CN209163176U
CN209163176U CN201821607269.6U CN201821607269U CN209163176U CN 209163176 U CN209163176 U CN 209163176U CN 201821607269 U CN201821607269 U CN 201821607269U CN 209163176 U CN209163176 U CN 209163176U
Authority
CN
China
Prior art keywords
ceiling system
main joist
support column
space structure
cornicing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201821607269.6U
Other languages
Chinese (zh)
Inventor
蓝建勋
李雄
陈贵强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Construction & Decoration Engineering Co ltd
Original Assignee
Guangdong Construction & Decoration Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Construction & Decoration Engineering Co ltd filed Critical Guangdong Construction & Decoration Engineering Co ltd
Priority to CN201821607269.6U priority Critical patent/CN209163176U/en
Application granted granted Critical
Publication of CN209163176U publication Critical patent/CN209163176U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pivots And Pivotal Connections (AREA)

Abstract

The utility model discloses cornicing outside space structure, the ceiling system structure structure includes support column, main joist, false keel, linkwork and Z-type connector;Wherein, one end of support column is fixed on the furred ceiling support of lower edge ball node, and the other end of support column is mutually fixedly mounted with main joist by bolt, and false keel is connect by being movably hinged one end of mechanism with main joist, to realize any turn up and down;False keel carries out a group frame by the other end and Z-type connector of secondary excessively movable linkwork, to realize that ceiling system three-dimensional is adjustable.This space structure flare eaves ceiling system replaces traditional sunpender to connect with rack lower edge ball-joint contact plate using support column, bears external wind load.Meanwhile this space structure flare eaves ceiling system uses " joint " movable connecting plate linkwork, realizes that furred ceiling three-dimensional is adjustable, to accommodate all movements caused by rack stress deformation, and meets furred ceiling hyperboloid moulding.

Description

It cornices outside space structure ceiling system structure
Technical field
The utility model relates to build mounting technology field, and in particular to cornice ceiling system knot outside a kind of space structure Structure.
Background technique
Currently, the furred ceiling that cornices outside the large span spatial structures such as large-scale terminal, stadiums, exhibition center is united and is answered extensively With.Large span spatial structure flare eaves ceiling system should can bear external wind load, accommodate rack stress (snow load, wind again Load, Forces, earthquake load etc.) deformation caused by all movements.Due to lacking corresponding flare eaves ceiling system skill Art standard, segment space structure is corniced using indoor ceiling furred ceiling technology outside, and the furred ceiling large area under windy conditions is caused to collapse It collapses and falls and the incident of injury.In this regard, studying space flare eaves structure ceiling system, there is engineering application value.
Utility model content
The purpose of the utility model is to overcome above-mentioned the deficiencies in the prior art, the furred ceiling that cornices outside a kind of space structure is provided System structure adapts to the functions such as rack deformation and receiving wind load to realize.
To achieve the above object, the technical solution of the utility model is:
It cornices outside space structure ceiling system structure, including support column, main joist, false keel, linkwork and Z-type connect Fitting;Wherein,
One end of the support column is fixed on the furred ceiling support of lower edge ball node, and the other end and main joist of support column are logical It crosses bolt to be mutually fixedly mounted, false keel is connect by being movably hinged mechanism with main joist, to realize turn up and down;False keel is also logical That crosses movable linkwork carries out a group frame with Z-type connector, to realize that ceiling system three-dimensional is adjustable.
The living hinge mechanism is rotation hinge connection part, and the movable hinged shaft of rotation hinge connection part is installed through master In keel, and the activity hinged shaft will rotate hinge connection part and be divided into two parts, and the upper half of rotation hinge connection part is sleeved on master In keel, the lower portion of hinge connection part is rotated except main joist, rotates the bottom end of hinge connection part lower half towards excurvation Folding forms mounting portion, and mounting portion is mutually installed by bolt with Z-type connector, and the bottom surface of Z-type connector is equipped with panel.
In the bottom end of the rotation hinge connection part lower half, bending place is provided with hinged movable hinged shaft outwardly, so that peace Dress portion can be rotated around hinged movable hinged shaft.
One end of the support column is bolted on the furred ceiling support of lower edge ball node.
The rotation hinge connection part is 3mm thickness stainless steel rotary blade connector.
The main joist and false keel are c-type shape.
The utility model compared with prior art, the beneficial effect is that:
Ceiling system structure of cornicing outside this space structure connects substitution with rack lower edge ball node crab bolt using support column Indoor tradition round steel sunpender, is connected with false keel using bolt and replaces indoor traditional c-type aluminium sheet and false keel clamping, held with this By external positive and negative wind load.Meanwhile ceiling system structure of cornicing outside this space structure is hinged using " joint " movable connecting plate Mechanism realizes that furred ceiling three-dimensional is adjustable, to accommodate rack stress (snow load, wind load, Forces, earthquake load etc.) deformation Caused by all movements, and meet the moulding of furred ceiling hyperboloid and fabricated construction.
Detailed description of the invention
Fig. 1 illustrates for the overall structure for ceiling system structure of cornicing outside space structure provided by the embodiment of the utility model Figure;
Fig. 2 is the scheme of installation for being movably hinged mechanism;
Fig. 3 is rotation hinge connection part bending place structural schematic diagram;
Fig. 4 is the schematic diagram of another state of ceiling system structure of cornicing outside space structure;
In figure: 1, support column;2, main joist;3, false keel;4, it is movably hinged mechanism;5, Z-type connector;6, panel;41, Movable hinged shaft;42, mounting portion;43, hinged movable hinged shaft;100, furred ceiling support.
Specific embodiment
The content of the utility model is described in further details with reference to the accompanying drawings and detailed description.
Embodiment:
As shown in fig.1, ceiling system structure of cornicing outside space structure provided in this embodiment includes support column 1, main dragon Bone 2, is movably hinged mechanism 4 and Z-type connector 5 at false keel 3.
Wherein, one end of the support column 1 is fixed on the furred ceiling support 100 of lower edge ball node, the other end of support column 1 and Main joist 2 is mutually fixedly mounted by bolt, and false keel 3 is any to realize by being movably hinged connecting with main joist 1 for mechanism 4 Upper and lower turn, false keel 3 also carries out a group frame by the other end and Z-type connector 5 that are movably hinged mechanism 4, to realize furred ceiling system System is three-dimensional adjustable.
It can thus be appreciated that ceiling system structure of cornicing outside this space structure replaces traditional sunpender and rack lower edge using support column External wind load is born in the connection of ball-joint contact plate.Meanwhile ceiling system structure of cornicing outside this space structure is movable using " joint " Connecting plate linkwork realizes that furred ceiling three-dimensional is adjustable, to accommodate rack stress (snow load, wind load, Forces, earthquake Load etc.) all movements caused by deformation, and meet furred ceiling hyperboloid moulding;Furthermore this simple and reliable for structure, installation effectiveness It is high, at low cost.
Specifically, as shown in Fig. 2, above-mentioned living hinge mechanism 4 is rotation hinge connection part, rotation hinge connection part Movable hinged shaft 41 is installed through in main joist 2, and the activity hinged shaft 41 will rotate hinge connection part and be divided into two parts, and rotation is closed The upper half of page connector is sleeved in main joist 2, rotates the lower portion of hinge connection part except main joist 2, rotation is closed The bottom end of page connector lower half is bent to form mounting portion 42 outwardly, and mounting portion is mutually installed by bolt with Z-type connector 5, Z-type The bottom surface of connector 5 is equipped with panel 6.That is, main joist 2, false keel 3 and the installation of panel 6 are using three-dimensional adjustable " pass Section " formula is movably hinged structure integrated connection on the support columns, reaches the external wind load of receiving, realizes that furred ceiling three-dimensional is adjustable (vertical Adjustment length is unrestricted, and plane X, Y-direction adjustment length are 110mm), it is ensured that the whole eaves reliability of structure that floats.
Preferably, as shown in figure 3, the bottom end bending place setting outwardly in above-mentioned rotation hinge connection part lower half is hinged Dynamic hinge of taking over a job 43, so that mounting portion 42 can be rotated around hinged movable hinged shaft 43, as shown in figure 4, can further increase Furred ceiling three-dimensional is schedulable.
Specifically, one end of above-mentioned support column 1 is bolted on the furred ceiling support 100 of lower edge ball node, with It convenient for assembly and disassembly installation, avoids welding, reduces pollution.
Above-mentioned rotation hinge connection part is 3mm thickness stainless steel rotary blade connector, to guarantee bearing capacity.Above-mentioned main dragon Bone 2 and false keel 3 are c-type shape, guarantee rigidity while saving material.
Correspondingly, the present embodiment additionally provides ceiling system construction method of cornicing outside space structure, this method comprises:
Unwrapping wire positioning:
By the arrangement requirement of drawing string ball ball node, string ball node is numbered one by one;
Using DHS 3 D laser scanning, collection site data simultaneously check BIM model orientation data, adjust model with this, obtain The actual coordinate of each string ball ball node is obtained, and is checked with theoretical string ball ball node coordinate, according to furred ceiling finished surface Actual height calculates the length of whole hanging piece, the usage quantity and position of whole hanging piece and triangular support bracket;
Using total station, according to rack status, a fixed reference line, then passes through reference line first on rack ball node The position of whole hanging piece is made, furred ceiling finished surface is 750mm apart from rack lower edge ball's dead center distance;
Support column installation:
According to field measurement, furred ceiling column base is positioned on string ball ball node, finished product support column is fixed with bolt, that is, is passed through Bolt is fixed on main roofing Elements of Space Grid Truss;
For receiving side position, at pillar, outer curtain wall, then special support is used as required, is mounted on lower boom.Furred ceiling Support must accurate positioning, firmly install
Ceiling joist lifting:
Main joist is installed: on the support columns by main joist installation, blending bolt fastening;
Installation rotation hinge connection part: movable hinged shaft bolt and main joist are fastened;
Installation keel: false keel is mounted on main joist, blending bolt fastening;Adjacent two c-type false keels are connected with Z-type Fitting connection, adjacent two rows keel interface position are staggered, and are adjusted to after installation horizontal straight.
Panel installation:
Panel is mounted in the bottom surface of Z-type connector according to corresponding order.
In-site installation welding, pollution-free it follows that this engineering method fabricated construction, when installation, is noiseless, ensure that green Color environmental protection construction.
Many large-scale public buildings, such as airport, conference centre, gymnasium have been built in succession in all parts of the country, this It cornices outside a little public building large spatial structures, mostly uses ceiling structure form of cornicing outside space structure.The achievement is to similar Engineering has reference function, there is higher application and popularization value.
For above-described embodiment simply to illustrate that the technical ideas and features of the present invention, its purpose is allows this field Interior those of ordinary skill can understand the content of the utility model and implement accordingly, can not limit the utility model with this Protection scope.The equivalent changes or modifications that all essence according to the content of the present invention is made, should all cover in this reality With in novel protection scope.

Claims (6)

1. ceiling system structure of cornicing outside space structure, which is characterized in that including support column, main joist, false keel, living hinge Mechanism and Z-type connector;Wherein,
One end of the support column is fixed on the furred ceiling support of lower edge ball node, and the other end and main joist of support column pass through spiral shell Bolt is mutually fixedly mounted, and false keel is connect by being movably hinged mechanism with main joist, and to realize turn up and down, false keel also passes through work Dynamic linkwork and Z-type connector carry out a group frame, to realize that ceiling system three-dimensional is adjustable.
2. ceiling system structure of cornicing outside space structure as described in claim 1, which is characterized in that the living hinge mechanism To rotate hinge connection part, the movable hinged shaft of rotation hinge connection part is installed through in main joist, and the activity hinged shaft will turn Dynamic circuit connector page connector is divided into two parts, and the upper half of rotation hinge connection part is sleeved in main joist, rotation hinge connection part Lower portion is except main joist, and the bottom end of rotation hinge connection part lower half is bent to form mounting portion outwardly, and mounting portion passes through Bolt is mutually installed with Z-type connector, and the bottom surface of Z-type connector is equipped with panel.
3. ceiling system structure of cornicing outside space structure as claimed in claim 2, which is characterized in that connect in the rotation hinge Bending place is provided with hinged movable hinged shaft outwardly for the bottom end of fitting lower half, so that mounting portion can turn around hinged movable hinged shaft It is dynamic.
4. ceiling system structure of cornicing outside space structure as described in claim 1, which is characterized in that one end of the support column It is bolted on the furred ceiling support of lower edge ball node.
5. ceiling system structure of cornicing outside space structure as claimed in claim 2 or claim 3, which is characterized in that the rotation hinge Connector is 3mm thickness stainless steel rotary blade connector.
6. ceiling system structure of cornicing outside space structure as described in claim 1, which is characterized in that the main joist and pair dragon Bone is c-type shape.
CN201821607269.6U 2018-09-29 2018-09-29 It cornices outside space structure ceiling system structure Withdrawn - After Issue CN209163176U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821607269.6U CN209163176U (en) 2018-09-29 2018-09-29 It cornices outside space structure ceiling system structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821607269.6U CN209163176U (en) 2018-09-29 2018-09-29 It cornices outside space structure ceiling system structure

Publications (1)

Publication Number Publication Date
CN209163176U true CN209163176U (en) 2019-07-26

Family

ID=67332752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821607269.6U Withdrawn - After Issue CN209163176U (en) 2018-09-29 2018-09-29 It cornices outside space structure ceiling system structure

Country Status (1)

Country Link
CN (1) CN209163176U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184061A (en) * 2018-09-29 2019-01-11 广东省建筑装饰工程有限公司 It cornices outside space structure ceiling system structure and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184061A (en) * 2018-09-29 2019-01-11 广东省建筑装饰工程有限公司 It cornices outside space structure ceiling system structure and construction method
CN109184061B (en) * 2018-09-29 2023-10-27 广东省建筑装饰工程有限公司 Space structure overhanging eave suspended ceiling system structure and construction method

Similar Documents

Publication Publication Date Title
CN109184061A (en) It cornices outside space structure ceiling system structure and construction method
CN104612307B (en) Ceiling system and its construction method
CN102220795A (en) Ceiling system applicable to large-span space steel structure and construction method thereof
CN202324340U (en) Combined type large steel-pipe truss
CN110656709B (en) Fireproof steel structure for green building
CN209163176U (en) It cornices outside space structure ceiling system structure
CN201050117Y (en) Detachable steel frame movable room
CN111945937A (en) Special-shaped space dislocation and distortion type curtain wall unit body
CN204418469U (en) ceiling system
CN109235740A (en) A kind of spherical net brace universal structure part
CN202099939U (en) Double-layer roof system
CN209538462U (en) A kind of removable lighting roof with ball shaped steel bearing
CN207664926U (en) A kind of residents photovoltaic bracket
CN201526180U (en) Tower mast with communication machine room
CN108661312A (en) A kind of laminated floor slab Construction Supporting System
CN211571968U (en) Beam column node unit of multi-story high-rise fabricated steel structure system
CN202945831U (en) Rapid construction type integrated assembling communication base station
CN207228708U (en) A kind of folding communication computer room
CN217711109U (en) Adjustable support node above net rack ball integrating horse way and ceiling keel
CN113216530B (en) Gutter structure of assembled steel construction roofing system
CN206034654U (en) Low roofing ridge and high node construction system of striding wall of striding
CN219910246U (en) Adjustable detachable pole holding structure
CN219528123U (en) Special-shaped grid suspended ceiling structure
CN220550779U (en) Big eaves mouth structure of two-way curve
CN218814423U (en) Steel construction industry factory building waterproof construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20190726

Effective date of abandoning: 20231027

AV01 Patent right actively abandoned

Granted publication date: 20190726

Effective date of abandoning: 20231027

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned