CN209128895U - A kind of support system for installing across river steel lid beam - Google Patents

A kind of support system for installing across river steel lid beam Download PDF

Info

Publication number
CN209128895U
CN209128895U CN201821825155.9U CN201821825155U CN209128895U CN 209128895 U CN209128895 U CN 209128895U CN 201821825155 U CN201821825155 U CN 201821825155U CN 209128895 U CN209128895 U CN 209128895U
Authority
CN
China
Prior art keywords
support column
cantilever beams
sandbox
boots
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821825155.9U
Other languages
Chinese (zh)
Inventor
逯平
赵昕
车青森
蔡连军
董昭
赵迪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing No2 Municipal Construction Engineering (ltd) Corp
Original Assignee
Beijing No2 Municipal Construction Engineering (ltd) Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing No2 Municipal Construction Engineering (ltd) Corp filed Critical Beijing No2 Municipal Construction Engineering (ltd) Corp
Priority to CN201821825155.9U priority Critical patent/CN209128895U/en
Application granted granted Critical
Publication of CN209128895U publication Critical patent/CN209128895U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of support systems for installing across river steel lid beam comprising inner support column, outer support column, spandrel girder, sandbox and Cantilever Beams;The inner support column is fixed on the ground, and inner support column is abutted with the support platform of steel bushing sole end four corners respectively;The outer support column is arranged on the outside of interior support column, and the length of outer support column is greater than inner support column, and outer support column lower end and ground consolidate, and upper surface is lower than steel lid top surface of the beam;The spandrel girder is arranged on outer support column, and the sandbox is arranged on spandrel girder, is used to support Cantilever Beams;The Cantilever Beams are installed on steel bushing boots, and Cantilever Beams position is corresponding with sandbox, and steel bushing boots are stretched out at the both ends of Cantilever Beams respectively, and the sandbox is supported on the position that Cantilever Beams stretch out steel bushing boots.The utility model has the effect of butt junction location and accurate adjustment steel lid depth of beam convenient for steel lid beam and pier stud.

Description

A kind of support system for installing across river steel lid beam
Technical field
The utility model relates to the technical fields of bridge construction, more particularly, to one kind for installing across river steel lid beam Support system.
Background technique
Bridge refers generally to be erected in rivers,lakes and seas, the structures for making traffic etc. that can smoothly pass through.It is modern to adapt to The transportation industry of high speed development, bridge be also extended to across mountain stream, unfavorable geology or meet other traffic need and set up make Current more convenient and fast building.Bridge mainly includes superstructure and substructure, and substructure includes that bridge pier and setting exist Bent cap on bridge pier.
Currently, certain engineering, when bridge is inclined cross river, in order to not influence the circulation in river, design has been adopted with overall steel bent cap Scheme.Referring to Fig. 5, such Steel Structure Installation method includes the pier stud 1 for being separately positioned on river two sides, is installed on pier stud 1 Steel bushing 2, the diameter of steel bushing 2 is identical with 1 diameter of pier stud and is installed in the steel lid beam 3 of 2 upper end of steel bushing.Steel lid beam 3 divides Section setting, including main cover beam section 31 and the steel bushing boots 32 for being respectively welded at 31 both ends of main cover beam section, steel bushing boots 32 are in inner hollow The horizontal cross-section of structure, steel bushing boots 32 is square, and the side length of steel bushing boots 32 is greater than the diameter of steel bushing 2, steel bushing boots 32 and steel bushing The quadrangle at the position of 2 contact of cylinder is extended with support platform 33.
Such 3 structure of steel lid beam is when being lifted, and since the span in river is big, the length and volume of steel lid beam 3 are larger, The height of steel bushing boots 32 is higher (6m), therefore, how safely and efficiently to install steel lid beam 3 and guarantees that installation accuracy is to need to solve The problem of.
Utility model content
The purpose of the utility model is to provide it is a kind of can it is safe and efficient and guarantee construction precision for installing across river The support system of road steel lid beam.
The above-mentioned purpose of utility model of the utility model has the technical scheme that
A kind of support system for installing across river steel lid beam comprising inner support column, outer support column, spandrel girder, Sandbox and Cantilever Beams;The inner support column is fixed on the ground, and inner support column is flat with the support of steel bushing sole end four corners respectively Platform abuts;The outer support column is arranged on the outside of interior support column, and the length of outer support column is greater than inner support column, outer support column lower end It is consolidated with ground, upper surface is lower than steel lid top surface of the beam;The spandrel girder is arranged on outer support column, and the sandbox is arranged in load-bearing Liang Shang is used to support Cantilever Beams;The Cantilever Beams are installed on steel bushing boots, and Cantilever Beams position is corresponding with sandbox, and the two of Cantilever Beams Steel bushing boots are stretched out at end respectively, and the sandbox is supported on the position that Cantilever Beams stretch out steel bushing boots.
Cantilever Beams are placed on the support columns using the supporting role of outer support column by using above-mentioned technical proposal On sandbox, steel lid beam is propped up and steel lid depth of beam is made to be higher than design height by outer support column, by the height for adjusting sandbox downwards Degree, makes steel lid beam reach design height.When avoiding steel lid beam integral hoisting, docking inaccuracy, height Adjustment precision is not achieved It is required that the problem of;It is arranged by the contraposition of outrigger and sandbox, controls the precision of steel lid beam horizontal direction.
The utility model is further arranged to: the sandbox is arranged right above outer support column center.
By using above-mentioned technical proposal, since steel lid beam weight is big, the gravity of steel lid beam is all acted on to be placed on and be held On the sandbox of weight beam, if sandbox is placed between adjacent outer support column, the problem of will lead to spandrel girder distorting sag, cause Steel lid depth of beam inaccuracy.Sandbox is placed on to the surface of support column, enhances the enabling capabilities to sandbox, prevents spandrel girder Deformation.
The utility model is further arranged to: two sandboxes of interval setting on spandrel girder correspond to sandbox on Cantilever Beams Position two Cantilever Beams are set, the sandbox is supported on Cantilever Beams.
By using above-mentioned technical proposal, the gravity of steel lid beam is shared to two sandboxes, makes outer support column support system It is more stable.
The utility model is further arranged to: strip footing, outer support column is arranged in outer support column and inner support column lower end It is consolidated respectively with strip footing with inner support column lower end.
By using above-mentioned technical proposal, since bridge construction is located at beside river, so the geology of construction area compares It is soft, it is easy to produce depression under the effect of the pressure, so that the precision of the mounting height of steel lid beam is influenced, in order to enhance holding for ground Beijing South Maxpower Technology Co. Ltd's power, prevents sinking of ground, is arranged with strip footing in outer support column and inner support column.
The utility model is further arranged to: Cantilever Beams include top flange plate, web and bottom wing listrium;The Cantilever Beams in Ribs is arranged in the part that steel bushing boots stretch out, and the ribs is arranged between top flange plate and bottom wing listrium;The ribs It is additionally arranged between top flange plate and steel bushing boots, the ribs is close to the position that steel bushing boots and bottom wing listrium dock.
By using above-mentioned technical proposal, since Cantilever Beams are when being placed on sandbox, the weight of all steel lid beams is undertaken, In order to increase the load-bearing capacity of Cantilever Beams, ribs is welded between the top flange plate and lower edge wing plate of Cantilever Beams.
The utility model is further arranged to: fixed hoisting ring on the Cantilever Beams.
By using above-mentioned technical proposal, for Cantilever Beams to be hung to lifting when rising to steel lid beam.
The utility model is further arranged to: the fixed Crossing brace between adjacent outer support column, the Crossing brace is along outer branch Dagger short transverse arranged for interval, Crossing brace include diagonal web member and horizontal support bar;Two diagonal web member arranged crosswises, the oblique abdomen The both ends of bar are installed in respectively on adjacent outer support column, and horizontal support bar is arranged in diagonal web member upper end, the horizontal support bar It is consolidated respectively with adjacent outer support column.
By using above-mentioned technical proposal, the stability between outer support column can be enhanced, prevent outer support column from becoming Shape.
The utility model is further arranged to: the fixed strengthening support between adjacent inner support column, the strengthening support are Z-shaped Structure, four ends of the strengthening support are consolidated with adjacent inner support column respectively.
By using above-mentioned technical proposal, enhances the stability between inner support column, prevent adjacent inner support column from becoming Shape.
The utility model is further arranged to: connecting rod is arranged between interior support column and outer support column.
By using above-mentioned technical proposal, inner support column and outer support column are connected into an entirety, make support system more Add firm.
In conclusion the advantageous effects of the utility model are as follows:
1. by the supporting role of outer support column, using the sandbox being arranged on outer support column, to steel lid depth of beam into The accurate adjustment of row, is arranged by the contraposition of outrigger and sandbox, controls the precision of steel lid beam horizontal direction;
2. increasing the bearing capacity of ground by the strip footing that outer support column and inner support column lower end is arranged in, place Ground sink, and influences height and adjusts;
3. increasing the load-bearing capacity of Cantilever Beams by the way that ribs is arranged between Cantilever Beams top flange plate and bottom wing listrium;
4. increasing outer support by the strengthening support being arranged between Crossing brace and inner support column between adjacent outer support column The stability of column and inner support column, prevents horizontal distortion.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the utility model;
Fig. 2 is the partial enlargement diagram of part A in Fig. 1;
Fig. 3 is the structural schematic diagram of the protrusion sandbox of the utility model;
Fig. 4 is the protrusion Crossing brace of the utility model and the structural schematic diagram of strengthening support;
Fig. 5 is the background technique structural schematic diagram of the utility model.
In figure, 1, pier stud;2, steel bushing;3, steel lid beam;31, main cover beam section;32, steel bushing boots;33, support platform;4, outer Support column;5, inner support column;6, spandrel girder;7, sandbox;71, outer case;711, casing bottom plate;712, into sand hole;713, it shakes out Hole;72, piston;8, Cantilever Beams;81, top flange plate;811, hoisting ring;82, web;83, bottom wing listrium;84, ribs;9, it cuts It supports;91, diagonal web member;92, horizontal support bar;10, strengthening support;11, connecting rod;12, strip footing.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
It referring to Fig.1, is a kind of support system for installing across river steel lid beam disclosed by the utility model, including outer Support column 4, inner support column 5, spandrel girder 6, sandbox 7 and Cantilever Beams 8.Inner support column 5 is four steel pipes, is respectively supported at steel bushing boots The support platform 33 of 32 bottom end four corners, 5 lower end of inner support column and ground consolidate, and upper end is supported with 32 support platform 33 of steel bushing boots It connects;The setting of outer support column 4 is correspondingly arranged six roots of sensation outer support column 4 in interior 5 outside of support column, each pier stud 1, and outer support column 4 is straight Diameter is greater than the steel pipe of 5 diameter of inner support column, and the length of outer support column 4 is greater than the length of inner support column 5, and outer support column 4 is set vertically It sets, lower end and ground consolidate, and the height of upper surface is lower than 3 top surface of steel lid beam;Spandrel girder 6 is I-steel, and spandrel girder 6 is arranged in pier On three outer support columns 4 of 1 side of column, outer support column 4 is stretched out at the both ends of spandrel girder 6 respectively, and sandbox 7 is arranged on spandrel girder 6; Two sandboxes 7 are set on each spandrel girder 6, and sandbox 7 is arranged right above outer 4 center of support column, and two sandboxes 7 are close to river Road side setting, convenient for adjusting height;Referring to Fig. 2, Cantilever Beams 8 are i-beam structure, and Cantilever Beams 8 include top flange plate 81, abdomen Plate 82 and bottom wing listrium 83, Cantilever Beams 8 are welded on 32 upper surface of steel bushing boots, the portion that Cantilever Beams 8 are contacted with 32 upper surface of steel bushing boots Position is not provided with bottom wing listrium 83, two Cantilever Beams 8 of each interval of steel bushing boots 32 setting, and position and 7 position of sandbox is arranged in Cantilever Beams 8 Corresponding up and down, steel bushing boots 32 are stretched out at the both ends of Cantilever Beams 8 respectively, support convenient for sandbox 7, fixed on 8 top flange plate 81 of Cantilever Beams There is hoisting ring 811, convenient for being welded and fixed in the lifting to steel bushing boots 32 of Cantilever Beams 8.
Referring to Figure 1 and Figure 3, sandbox 7 includes outer case 71 and piston 72.Outer case 71 is cylindrical, inner hollow arrangement, The fixed casing bottom plate 711 in the lower end of outer case 71, offers on the outer wall of outer case 71 into sand hole 712 and clearance hole 713, into Sand hole 712 and clearance hole 713 are located at close to one end of casing bottom plate 711, and 71 central axis two sides of outer case are respectively set;Piston 72 are adapted with outer case 71, are in hollow arrangement inside piston 72.When using sandbox 7, by into sand hole 712 to outer case 71 Fine sand is filled with inside piston 72, is placed on spandrel girder 6, according to the design height of steel lid beam 3, is carried out by clearance hole 713 It puts sand, reduces the height of steel lid beam 3 to design height.
When the height of sandbox 7 is arranged, since sandbox 7 is difficult to adjust upward height when supporting steel lid beam 3, so needing When meeting sandbox 7 and supporting steel lid beam 3, the height of 3 top surface of steel lid beam is higher than design height, so as to there are certain height, Adjust the height of steel lid beam 3 downwards convenient for sandbox 7.Sandbox 7 is when being adjusted to design position for 3 height of steel lid beam, inner support column 5 There is also certain gaps with 32 lower surface of steel bushing boots, in order to make inner support column 5 play a supporting role, in interior support column 5 and steel Washer or wedge block are arranged between gumshoe 32 makes inner support column 5 for the gap filling between inner support column 5 and steel bushing boots 32 Support steel lid beam 3.
It is arranged between adjacent support column and shears to guarantee the stability between outer support column 4 with Fig. 4 referring to Fig.1 Support 9, Crossing brace 9 is fixed multiple along 4 short transverse interval of outer support column, and Crossing brace 9 includes the diagonal web member 91 of two arranged crosswises, The both ends of diagonal web member 91 are welded and fixed with the outer support column 4 of two sides respectively, arrange fixed level in the upper and lower ends of diagonal web member 91 Support rod 92,92 both ends of horizontal support bar are welded and fixed respectively at adjacent outer support column 4, ensure that by the way that Crossing brace 9 is arranged The stability in the horizontal and vertical direction of outer support column 4.Since inner support column 5 can undertake steel after the height for having adjusted steel lid beam 3 The main pressure of bent cap 3, in order to guarantee the stability of inner support column 5, the fixed strengthening support 10 between adjacent inner support column 5, Four ends of the Z-shaped structure of strengthening support 10, strengthening support 10 are welded and fixed with adjacent inner support column 5 respectively.In order to further Enhancing inner support column 5 and outer support column 4 stability, the fixed connecting rod 11 between interior support column 5 and outer support column 4, will Inner support column 5 and outer support column 4 connect integral, keep inner support column 5 and outer support column 4 more stable.
The weight of all steel lid beams 3 is undertaken since Cantilever Beams 8 are when being placed on sandbox 7 referring to Fig. 2, it is outstanding in order to increase The load-bearing capacity of outrigger 8, welds ribs 84 between the top flange plate 81 and lower edge wing plate of Cantilever Beams 8, and ribs 84 is spaced Arrange multiple tracks, ribs 84 is separately positioned on 82 two sides of web, and ribs 84 is installed in the portion that Cantilever Beams 8 stretch out steel bushing boots 32 Position.Since the position load-bearing capacity that the bottom wing listrium 83 of Cantilever Beams 8 is docked with steel bushing boots 32 is poor, in the upper table of steel bushing boots 32 Ribs 84 is welded and fixed between face and top flange plate 81, ribs 84 is close to the position of 8 bottom wing listrium 83 of Cantilever Beams, Ke Yizeng The load-bearing capacity of strong Cantilever Beams 8 and 32 docking site of steel bushing boots, while keeping the connection between Cantilever Beams 8 and steel bushing boots 32 more steady Gu.
Referring to Fig.1, since the present embodiment bridge construction is located at beside river, so the geology of construction area is relatively soft, Depression is easy to produce under the action of pressure, so that the precision of the mounting height of steel lid beam 3 is influenced, in order to enhance the load-bearing energy on ground Power prevents sinking of ground, is arranged with strip footing 12 in outer support column 4 and inner support column 5, strip footing 12 is poured for concrete It builds to be formed, outer support column 4 and inner support column 5 are fixed by bolt and strip footing 12.
Work progress is as follows:
It is calculated first according to bridge coordinate before construction each for installing the position coordinates of 3 structure of steel lid beam, utilization Pay-off equipment releases the position of Cantilever Beams 8 in 32 upper surface of steel bushing boots first.Cantilever Beams 8 are welded and fixed.According to calculating Coordinate data out releases the position coordinates of outer support column 4 and inner support column 5 respectively, and outer support column 4 and inner support column 5 are consolidated It is fixed to complete, spandrel girder 6 is set on outer support column 4, places sandbox 7 right above 4 center of outer support column on spandrel girder 6.Steel 3 integral hoisting of bent cap is supported steel lid beam 3 using the Cantilever Beams 8 on 7 supporting steel bent cap 3 of sandbox, while steel lid beam 3 Height is higher than setting height and the height of sandbox 7 is gradually decreased, until steel lid beam 3 reaches according to the height of measurement 32 top surface of steel bushing boots To design height.When reaching the design height of steel lid beam 3, pads and pad at the gap that interior support column 5 and steel bushing boots 32 contact Circle, makes inner support column 5 support steel lid beam 3;The height for continuing downward sandbox 7, separates sandbox 7 with Cantilever Beams 8.To steel lid beam Casting concrete in 3 is removed outstanding on outer support column 4, inner support column 5 and steel bushing boots 32 after concrete reaches intensity requirement Outrigger 8.
The embodiment of present embodiment is the preferred embodiment of the utility model, and not limitation is originally practical new according to this The protection scope of type, therefore: the equivalence changes that all structures, shape, principle according to the utility model are done should all be covered by practical Within novel protection scope.

Claims (9)

1. a kind of support system for installing across river steel lid beam, it is characterised in that: including inner support column (5), outer support Column (4), spandrel girder (6), sandbox (7) and Cantilever Beams (8);The inner support column (5) is fixed on the ground, inner support column (5) point It is not abutted with the support platform (33) of steel bushing boots (32) bottom end four corners;The outer support column (4) setting interior support column (5) outside The length of side, outer support column (4) is greater than inner support column (5), and outer support column (4) lower end and ground consolidate, and upper surface is lower than steel lid Beam (3) top surface;The spandrel girder (6) is arranged on outer support column (4), and the sandbox (7) is arranged on spandrel girder (6), is used for It supports Cantilever Beams (8);The Cantilever Beams (8) are installed on steel bushing boots (32), and Cantilever Beams (8) position is corresponding with sandbox (7), overhanging The both ends of beam (8) are stretched out steel bushing boots (32) respectively, and the sandbox (7) is supported on the position that Cantilever Beams (8) stretch out steel bushing boots (32).
2. according to claim 1 for installing the support system across river steel lid beam, it is characterised in that: the sandbox (7) setting is right above outer support column (4) center.
3. according to claim 1 for installing the support system across river steel lid beam, it is characterised in that: in spandrel girder (6) setting two sandboxes (7) in interval on, two Cantilever Beams (8) are arranged in the position that sandbox (7) is corresponded on Cantilever Beams (8), described Sandbox (7) is supported on Cantilever Beams (8).
4. according to claim 1 for installing the support system across river steel lid beam, it is characterised in that: in outer support Column (4) and inner support column (5) lower end are arranged strip footing, outer support column (4) and inner support column (5) lower end respectively with strip footing (12) it consolidates.
5. according to claim 1 for installing the support system across river steel lid beam, it is characterised in that: Cantilever Beams It (8) include top flange plate (81), web (82) and bottom wing listrium (83);The Cantilever Beams (8) are in the portion that steel bushing boots (32) stretch out Set up separately and set ribs (84), the ribs (84) is arranged between top flange plate (81) and bottom wing listrium (83);The reinforcement Rib (84) is additionally arranged between top flange plate (81) and steel bushing boots (32), and the ribs (84) is close to steel bushing boots (32) and bottom wing The position of listrium (83) docking.
6. according to claim 1 for installing the support system across river steel lid beam, it is characterised in that: the overhanging Fixed hoisting ring (811) on beam (8).
7. according to claim 1 for installing the support system across river steel lid beam, it is characterised in that: adjacent outer Fixed Crossing brace (9) between support column (4), the Crossing brace (9) is along outer support column (4) short transverse arranged for interval, Crossing brace It (9) include diagonal web member (91) and horizontal support bar (92);Two diagonal web member (91) arranged crosswises, the both ends of the diagonal web member (91) It is installed on adjacent outer support column (4) respectively, horizontal support bar (92) setting is described horizontally-supported in diagonal web member (91) upper end Bar (92) is consolidated with adjacent outer support column (4) respectively.
8. according to claim 1 for installing the support system across river steel lid beam, it is characterised in that: adjacent Fixed strengthening support (10) between inner support column (5), the Z-shaped structure of the strengthening support (10), (10) four ends of the strengthening support It is consolidated respectively with adjacent inner support column (5).
9. according to claim 1 for installing the support system across river steel lid beam, it is characterised in that: in inner support Connecting rod (11) are set between column (5) and outer support column (4).
CN201821825155.9U 2018-11-06 2018-11-06 A kind of support system for installing across river steel lid beam Active CN209128895U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821825155.9U CN209128895U (en) 2018-11-06 2018-11-06 A kind of support system for installing across river steel lid beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821825155.9U CN209128895U (en) 2018-11-06 2018-11-06 A kind of support system for installing across river steel lid beam

Publications (1)

Publication Number Publication Date
CN209128895U true CN209128895U (en) 2019-07-19

Family

ID=67244007

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821825155.9U Active CN209128895U (en) 2018-11-06 2018-11-06 A kind of support system for installing across river steel lid beam

Country Status (1)

Country Link
CN (1) CN209128895U (en)

Similar Documents

Publication Publication Date Title
CN106012864B (en) A kind of method of the overall erection & lift of bridge arch rib
CN104389313B (en) The positioning and plumbing device of Two bors d's oeuveres type i iron lattice column and positioning and plumbing method thereof
CN102828469B (en) Positioning mounting construction method for triangular steel constructed pillar of inclined-leg steel box
CN106087744B (en) Cable-stayed bridge beams of concrete cable guide pipe supporting and positioning device and method
CN106088120B (en) A kind of cofferdam decentralization construction method
CN103866693A (en) Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge
CN102535353A (en) Construction method for box beam swinging body striding on expressways and railways in rail transit
CN102733307B (en) Method for constructing cast-in-place beam falsework
CN109267493A (en) A kind of construction method installed across river steel lid beam
CN205917601U (en) Integrally lift up device of bridge arch rib
CN215580291U (en) Large-span ultrahigh-voltage power pipe trench suspension device in foundation pit
CN204385629U (en) A kind of support for the construction of suspension bridge king-tower top rail
CN209128895U (en) A kind of support system for installing across river steel lid beam
CN216040719U (en) Template support cantilever bearing structure
CN203531002U (en) Steel platform tower crane foundation
CN208167484U (en) The steel construction overline bridge being easily installed
CN214656386U (en) Leg rail structure before piece together wide bridge frame bridge crane
CN114369996A (en) Method for mounting steel pipe column of pier in bridge water
CN205742125U (en) A kind of work platform for boring
CN204715362U (en) A kind of deep foundation ditch embedded column base bracing frame
CN209194354U (en) High-altitude long-span binder base-supporting shellfish thunder support construction
CN211849438U (en) Device for pile connection and perpendicularity adjustment
CN103938877B (en) The installation method of crab-bolt stock
CN204343294U (en) The positioning and plumbing device of Two bors d's oeuveres type i iron lattice column