- CN209088408U CN209088408U CN201821838286.0U CN201821838286U CN209088408U CN 209088408 U CN209088408 U CN 209088408U CN 201821838286 U CN201821838286 U CN 201821838286U CN 209088408 U CN209088408 U CN 209088408U
- Authority
- CN
- China
- Prior art keywords
- hanger
- adjustable
- livewire work
- insulation lath
- operating stick
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Electric Cable Installation (AREA)
Abstract
The utility model provides adjustable-angle operating stick hanger on a kind of livewire work column, including hanger and the ratchet-type tightener being mounted on hanger, the ratchet-type tightener is equipped with ratchet-type tightener fixed ring, the hanger is symmetrically installed with insulation lath with respect to its center, the insulation lath is rotatably mounted on hanger, and the insulation lath is equipped with multiple hanging holes.By the way that hanging hole is arranged on insulation lath, insulating bar can be suspended in hanging hole, and insulation lath is rotatably mounted on hanger, it during installation can be by adjusting the angle between insulation lath and hanger, it needs to carry out angle adjustment come the space according to practical operation, to obtain safer operating space, the insulating bar being suspended in hanging hole simultaneously is not easy to fall and take conveniently, labor intensity and the activity duration for greatly reducing operating personnel, improve the safety of operation.
Description
Technical field
The utility model relates to adjustable-angles on electric construction tool field more particularly to a kind of livewire work column to operate
Bar hanger.
Background technique
Earth potential working method refers to that human body is in ground potential, uses the operational method of insulating tool mediate contact equipment.
It is a kind of major way of livewire work work and the basis of other operational methods.The maximum feature of earth potential working method,
It is that operating personnel can operate in charging equipment surrounding.
Insulating bar working system in 10 KV hot-line works, there is that its is applied widely, investment is small and is not limited by geographical environment
Etc. advantages, be widely applied in power industry livewire work.But due to taking insulating bar indirect operating, complicated operation,
It is more demanding to personnel's physical strength and device.
When insulating bar indirect operating livewire work, No. 2 operating personnels step on bar to suitable position on No. 1 operating personnel and bar on bar
It sets, when preparing before livewire work starts on bar, insulating cord back with No. 2 operating personnels, is born on bar by No. 2 operating personnels on bar
The special-shaped wire clamp (or penetrating cable clamp) of 3 meters of fourth officer long insulating bars and anchor leg is hung to bar respectively using insulating cord by duty
On, because not having special isolation bar hanger, insulating bar is generally suspended from the core through screw rod of fixed branch line cross-arm after being hung on bar.
The insulating bar of suspension only has 10 centimeters or so with a distance from electric pole, No. 2 operating personnels' operations on No. 1 operating personnel and bar on bar
It is more troublesome when adjustment position, it is slightly careless to touch insulating bar, it causes insulating bar to be detached from hitch point and falls to
Ground, may cause insulating bar damage may also hit ground operation personnel.In addition insulating bar head metal portion
Disconnected device from the drop type being mounted on branch line cross-arm is ironed in position, and to charge upper pile crown safe distance smaller, also can be to the personnel of operation on bar
Safety has an impact.
Summary of the invention
The purpose of this utility model is to provide adjustable-angle operating sticks on a kind of good livewire work column of safety to hang
Frame.
In order to achieve the above object, the utility model adopts the following technical solution: angle adjustable on a kind of livewire work column
Formula operating stick hanger, including hanger and the ratchet-type tightener being mounted on hanger, the ratchet-type tightener is equipped with ratchet
Formula tightener fixed ring, the hanger are symmetrically installed with insulation lath with respect to its center, and the insulation lath is rotatably mounted to
On hanger, the insulation lath is equipped with multiple hanging holes.
Further, the lower end of the hanger is equipped with insulation coaster.
Further, the insulation lath is mounted on the both ends of hanger, and the length of hanger is 55-65cm.
Further, the insulation lath and 1 joining place of hanger are equipped with link.
Further, the internal diameter of the hanging hole is 20-24mm.
Further, spacing of the hanging hole on insulation lath length direction is 5-10cm.
Further, the opposite side of the hanging hole inner wall is mounted on mounting groove, the installation on insulation lath
Piston is mounted in slot, the piston is equipped with piston shaft far from the side of insulation lath, and the piston shaft is far from piston
Side is equipped with engagement plate, is equipped with limit hemisphere by bolt on the engagement plate.
Further, spring is installed, spring is socketed in the periphery of piston shaft between the piston and engagement plate.
Further, the opposite side of the limit hemisphere is mounted on elastic bumps.
After adopting the above technical scheme, the utility model has the advantages that
1, by the way that hanging hole is arranged on insulation lath, insulating bar can be suspended in hanging hole, and to insulate
Lath is rotatably mounted on hanger, during installation can be by adjusting the angle between insulation lath and hanger, according to reality
The space of operation needs to carry out angle adjustment, to obtain safer operating space, while being suspended on the insulation in hanging hole
Operating stick is not easy to fall and take conveniently, greatly reduces labor intensity and the activity duration of operating personnel, improves operation
Safety.
2, insulating bar and material can be transmitted above and below by ground operation personnel, is reduced by the coaster that insulate
The labor intensity of operating personnel on bar.
3, by making insulation lath be mounted on the both ends of hanger, and the length of hanger is 55-65cm, to ensure that suspension
Insulating bar on hanger and electric pole remain at least gap of 30cm, improve operating personnel's job position adjustment and
The safety of insulating bar position.
4, the closestool bag for putting material can be suspended on link by link, facilitates operation, improves work efficiency.
5, by making the internal diameter 20-22mm of hanging hole, the condition of insulating bar suspension is met, operation is improved
Efficiency, when the internal diameter of hanging hole is less than 20mm, it is inconvenient when insulating bar to cause to hang since internal diameter is too small, works as hanging hole
Internal diameter be greater than 22mm when, since the internal diameter of hanging hole is excessive, will lead to insulating bar suspension stability reduce, lead to operation
Safety reduces.
6, by making spacing 5-10cm of the hanging hole on insulation lath length direction, insulating bar suspension is met
The safe spacing requirement of suspension, ensure that the safety of operation, when spacing of the hanging hole on insulation lath length direction is small
When 5cm, insulating bar is suspended in hanging hole, and adjacent insulating bar is easy to interfere with each other, and leads to insulating bar
The safety for easily falling and reducing operation, when hanging hole is when the spacing on lath length direction that insulate is greater than 10cm, due to exhausted
The spacing for the hanging hole that listrium limited length system needs to meet the requirement of actual installation convenience, therefore is arranged on insulation lath
Setting should also should not be too large, and meet insulating bar and keep safe spacing suspension.
7, it by being respectively mounted mounting groove on insulation lath in the opposite side of hanging hole inner wall, and is installed in mounting groove
Piston and piston shaft are as buffer gear, and by installing limit hemisphere on engagement plate, and when hanging insulating bar, insulation is grasped
The suspended end for making bar can be limited hemisphere in hanging hole and be limited, and effectively increase the stability of insulating bar suspension,
Improve the safety of operation.
8, it by installing spring between piston and engagement plate, when insulating bar suspended end squeezes limit hemisphere, squeezes
Pressure causes piston shaft to stretch in piston, and realizes under the elastic force operation of spring to the reversed of insulating bar suspended end
Extruding force further improves the limit stability to insulating bar, improves the safety of operation.
9, it by being respectively mounted elastic bumps in the opposite side of limit hemisphere, further improves and insulating bar is hung
Stability, improve the safety of operation.
Detailed description of the invention
The utility model is described in further detail with reference to the accompanying drawing:
Fig. 1 is the knot of adjustable-angle operating stick hanger on a kind of livewire work column of the proposition of the utility model embodiment one
Structure schematic diagram;
Fig. 2 is exhausted in adjustable-angle operating stick hanger on a kind of livewire work column of the proposition of the utility model embodiment two
The cross-sectional view of listrium item.
Specific embodiment
The utility model is described in further detail in the following with reference to the drawings and specific embodiments.It is to be appreciated that following
The indicating positions such as "upper", "lower", "left", "right", " longitudinal direction ", " transverse direction ", "inner", "outside", "vertical", "horizontal", "top", "bottom"
Or the word of positional relationship is based only upon orientation or positional relationship shown in the drawings, only for the purposes of describing the utility model and simplification
Description, rather than device/element of indication or suggestion meaning must have a particular orientation or be constructed and be grasped with specific orientation
Make, therefore should not be understood as limiting the present invention.
Embodiment one
As shown in Figure 1, the utility model provides adjustable-angle operating stick hanger on a kind of livewire work column, including hanger
1 and the ratchet-type tightener 2 that is mounted on hanger 1, ratchet-type tightener 2 be equipped with ratchet-type tightener fixed ring 3, hanger 1
Its opposite center is symmetrically installed with insulation lath 6, and insulation lath 6 is rotatably mounted on hanger 1, and insulation lath 6 is equipped with more
A hanging hole 7.By the way that hanging hole 7 is arranged on insulation lath 6, insulating bar can be suspended in hanging hole 7, and make absolutely
Listrium item 6 is rotatably mounted on hanger 1, can carry out root during installation by adjusting the angle between insulation lath 6 and hanger 1
It needs to carry out angle adjustment according to the space of practical operation, to obtain safer operating space, while be suspended in hanging hole 7
Insulating bar be not easy to fall and take conveniently, greatly reduce labor intensity and the activity duration of operating personnel, improve
The safety of operation.
In the present embodiment, the lower end of hanger 1 is equipped with insulation coaster 5.By insulation coaster 5 can by insulating bar and
Material is transmitted above and below by ground operation personnel, reduces the labor intensity of operating personnel on bar.
In the present embodiment, insulation lath 6 is mounted on the both ends of hanger 1, and the length of hanger 1 is 55-65cm.By making
Insulation lath 6 is mounted on the both ends of hanger 1, and the length of hanger 1 is 55-65cm, thus ensure that be suspended on it is exhausted on hanger 1
Edge operating stick and electric pole remain at least gap of 30cm, improve adjustment and the insulating bar position of operating personnel's job position
The safety set.Specific in the present embodiment, the length of hanger 1 is 60cm.
It is understood that the length of hanger 1 can for 55cm, 56cm, 57cm, 58cm, 59cm, 60cm, 61cm,
62cm、63cm、64cm、65cm。
In the present embodiment, insulation lath 6 and 1 joining place of hanger are equipped with link 4.Material can will be put by link 4
Closestool bag be suspended on link 4, facilitate operation, improve work efficiency.
In the present embodiment, the internal diameter of hanging hole 7 is 20-24mm.By making the internal diameter 20-22mm of hanging hole 7, meet
The condition of insulating bar suspension, improves the efficiency of operation, when the internal diameter of hanging hole 7 is less than 20mm, due to internal diameter mistake
It is small cause to hang it is inconvenient when insulating bar, when the internal diameter of hanging hole 7 is greater than 22mm, since the internal diameter of hanging hole 7 is excessive,
Will lead to insulating bar suspension stability reduces, and operational security is caused to reduce.Specific in the present embodiment, hanging hole 7
Internal diameter is 22mm.
It is understood that the internal diameter of hanging hole 7 can be 20mm, 21mm, 22mm, 23mm, 24mm.
In the present embodiment, spacing of the hanging hole 7 on insulation 6 length direction of lath is 5-10cm.By making hanging hole 7
Spacing on insulation 6 length direction of lath is 5-10cm, meets the safe spacing requirement of insulating bar suspension suspension, protects
The safety for having demonstrate,proved operation, when hanging hole 7 is when the spacing on 6 length direction of lath that insulate is less than 5cm, insulating bar is outstanding
It hangs in hanging hole 7, adjacent insulating bar is easy to interfere with each other, and causes insulating bar easily to fall and reduces the peace of operation
Quan Xing, when hanging hole 7 insulate 6 length direction of lath on spacing be greater than 10cm when, due to insulate 6 limited length system of lath,
The spacing setting for the hanging hole 7 for needing to meet the requirement of actual installation convenience, therefore being arranged on insulation lath 6 also should should not mistake
Greatly, meet insulating bar and keep safe spacing suspension.Specific in the present embodiment, hanging hole 7 is in insulation 6 length of lath
Spacing on direction is 5cm.
It is understood that hanging hole 7 insulation 6 length direction of lath on spacing can for 5cm, 6cm, 7cm, 8cm,
9cm、10cm。
In the present embodiment, in actual installation process, one end of ratchet-type tightener 2 is passed through into Φ 10mm* first
The bolt of 60mm specification is connect with hanger 1, and No. 1 operating personnel puts the closestool bag rope sling of material on column 1 by suspension on bar
Back piggyback, is stepped on bar to electric pole after operation suitable position, hanger 1 is mounted on the position of 0.4m or so below electric pole branch line cross-arm
Place is set, the brocade wheel braid over braid that by the other end length of ratchet-type tightener 2 be 80cm, width is 5cm and band edge end hook hook jail
Ratchet-type tightener fixed ring 3 simultaneously tightens ratchet-type tightener 2, so that bar is hung 1 frame and is firmly fixed at the suitable position of electric pole,
Then insulation coaster 5 is hung in the link of hanger distal lower portion, insulating bar and material pass through coaster insulating cord by ground
Operating personnel is responsible for upper and lower transmitting, and the closestool bag for putting material that No. 2 operating personnels will be transmitted on bar on bar is suspended on hanger
In the rope sling of 1 lower section, the four pairs of insulating bars that will be transmitted on bar are suspended on mounting hung rack distal end top angle adjustable respectively
Insulation lath hanging hole 7 in, livewire work work after, remove column on adjustable-angle operating stick hanger sequence phase
Instead.
It is understood that hanger 1 is aluminium alloy or stainless steel material, insulation lath 6 is made of epoxide resin material, and
It is with a thickness of 1cm, width 6cm, length 70cm.
Embodiment two
As shown in Fig. 2, embodiment two and embodiment one the difference is that, the opposite side of 7 inner wall of hanging hole is exhausted
It is mounted on mounting groove 8 on listrium item 6, piston 9, side installation of the piston 9 far from insulation lath 6 are mounted in mounting groove 8
There is piston shaft 10, piston shaft 10 is equipped with engagement plate 12 far from the side of piston 9, installs on engagement plate 12 by bolt 13 limited
Position hemisphere 14.By being respectively mounted mounting groove 8 on insulation lath 6 in the opposite side of 7 inner wall of hanging hole, and in mounting groove 8
Piston 9 is installed and piston shaft 10 is used as buffer gear, and by installing limit hemisphere 14, suspension insulation operation on engagement plate 12
When bar, the suspended end of insulating bar can be limited hemisphere 14 in hanging hole 7 and be limited, and effectively increase insulating bar
The stability of suspension improves the safety of operation.
In the present embodiment, spring 11 is installed, spring 11 is socketed in the outer of piston shaft 10 between piston 9 and engagement plate 12
Week.By installing spring 11 between piston 9 and engagement plate 12, when insulating bar suspended end squeezes limit hemisphere 14, squeeze
Pressure causes piston shaft 10 to stretch in piston 9, and realizes under the elastic force operation of spring 11 to insulating bar suspended end
Reversed extruding force further improves the limit stability to insulating bar, improves the safety of operation.
In the present embodiment, the opposite side of limit hemisphere 14 is mounted on elastic bumps 15.By in limit hemisphere 14
Opposite side is respectively mounted elastic bumps 15, further improves the stability to insulating bar suspension, improves operation
Safety.
It should be noted that herein, relational terms such as first and second and the like are used merely to an entity
Or operation distinguished with another entity, without necessarily requiring or implying between these entities or operation there are it is any this
Perhaps sequence and the terms "include", "comprise" or its any other variant are intended to nonexcludability to the actual relationship of kind
Include so that include a series of elements process, method, article or equipment not only include which element, but also
Including other elements that are not explicitly listed, or further include for this process, method, article or equipment intrinsic want
Element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that in the case that do not depart from the utility model spirit and can make to these embodiments carry out it is a variety of variation, repair
Change, replace and deform, the scope of the utility model is limited by the following claims and their equivalents matter.
Claims (9)
1. adjustable-angle operating stick hanger on a kind of livewire work column, including hanger and the ratchet-type being mounted on hanger tightening
Device, the ratchet-type tightener are equipped with ratchet-type tightener fixed ring, which is characterized in that the hanger is with respect to its central symmetry
Insulation lath is installed, the insulation lath is rotatably mounted on hanger, and the insulation lath is equipped with multiple hanging holes.
2. adjustable-angle operating stick hanger on livewire work column according to claim 1, which is characterized in that the hanger
Lower end insulation coaster is installed.
3. adjustable-angle operating stick hanger on livewire work column according to claim 1, which is characterized in that the insulation
Lath is mounted on the both ends of hanger, and the length of hanger is 55-65cm.
4. adjustable-angle operating stick hanger on livewire work column according to claim 1, which is characterized in that the insulation
Lath and 1 joining place of hanger are equipped with link.
5. adjustable-angle operating stick hanger on livewire work column according to claim 1, which is characterized in that the suspension
The internal diameter in hole is 20-24mm.
6. adjustable-angle operating stick hanger on livewire work column according to claim 1, which is characterized in that the suspension
Spacing of the hole on insulation lath length direction is 5-10cm.
7. adjustable-angle operating stick hanger on livewire work column according to claim 1, which is characterized in that the suspension
Inner wall opposite side in hole is mounted on mounting groove on insulation lath, and piston, the piston are mounted in the mounting groove
Side far from insulation lath is equipped with piston shaft, and the piston shaft is equipped with engagement plate, the linking far from the side of piston
Limit hemisphere is equipped with by bolt on plate.
8. adjustable-angle operating stick hanger on livewire work column according to claim 7, which is characterized in that the piston
Spring is installed between engagement plate, spring is socketed in the periphery of piston shaft.
9. adjustable-angle operating stick hanger on livewire work column according to claim 7, which is characterized in that the limit
The opposite side of hemisphere is mounted on elastic bumps.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821838286.0U CN209088408U (en) | 2018-11-08 | 2018-11-08 | Adjustable-angle operating stick hanger on a kind of livewire work column |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821838286.0U CN209088408U (en) | 2018-11-08 | 2018-11-08 | Adjustable-angle operating stick hanger on a kind of livewire work column |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209088408U true CN209088408U (en) | 2019-07-09 |
Family
ID=67123116
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821838286.0U Active CN209088408U (en) | 2018-11-08 | 2018-11-08 | Adjustable-angle operating stick hanger on a kind of livewire work column |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209088408U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111244820A (en) * | 2020-03-13 | 2020-06-05 | 广东电网有限责任公司 | Iron tower tool hanging rack |
-
2018
- 2018-11-08 CN CN201821838286.0U patent/CN209088408U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111244820A (en) * | 2020-03-13 | 2020-06-05 | 广东电网有限责任公司 | Iron tower tool hanging rack |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104201614B (en) | Far-end operation changes the device of two division circuit two strings of strain insulators | |
CN209088408U (en) | Adjustable-angle operating stick hanger on a kind of livewire work column | |
CN105305317A (en) | Tool of suspending insulated flexible ladder on live wires | |
CN102496887B (en) | Folding live-working safety shelter | |
CN102185267B (en) | 66KV ground potential hot-line make-and-break bypassing method | |
CN207134726U (en) | A kind of electric operating hanger | |
CN201384805Y (en) | Steel cable fixation device for falling prevention used in electrical tower | |
CN101997281B (en) | Tower ground wire universal lifting mechanism | |
CN106532559B (en) | A kind of replacement tool of insulator | |
CN201663250U (en) | Turnable grounding wire hook | |
CN212337126U (en) | Special maintenance tool for power distribution network engineering | |
CN104269669A (en) | Ground lead | |
CN106300128B (en) | One kind changes double bundle conductor conductor spacer and puies forward the Line tool and application method | |
CN206710675U (en) | A kind of small Fracture Force optical cable pendant wire clip of small span | |
CN208865076U (en) | A kind of bushing shell for transformer operation safety belt system hanger | |
CN203150833U (en) | Universal hook for ground lead | |
CN207378065U (en) | A kind of steel wire clamp rigging | |
CN208272496U (en) | Hot line maintenance rope ladder lifting device | |
CN206471748U (en) | Universal 500kV straight lines wineglass tower line maintenance cross-arm hanging point device | |
CN105790158B (en) | Charged for replacement 35kV strain insulator string specific purpose tools | |
CN204131005U (en) | Double loop tangent tower steeple head cross-arm jig | |
CN204205171U (en) | A kind of novel grounded line structure | |
CN204947458U (en) | Work high above the ground Work tool rack | |
CN205960521U (en) | Overhead line overhauls and uses rope ladder | |
CN206023061U (en) | The powered positor of suspension clamp gyroaxis |