CN209053164U - Diversion tunnel water inlet layered water drawing structure - Google Patents

Diversion tunnel water inlet layered water drawing structure Download PDF

Info

Publication number
CN209053164U
CN209053164U CN201821775107.3U CN201821775107U CN209053164U CN 209053164 U CN209053164 U CN 209053164U CN 201821775107 U CN201821775107 U CN 201821775107U CN 209053164 U CN209053164 U CN 209053164U
Authority
CN
China
Prior art keywords
intake
water
elevation
diversion tunnel
gate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821775107.3U
Other languages
Chinese (zh)
Inventor
苟芳蓉
刘跃
谷玲
赵明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201821775107.3U priority Critical patent/CN209053164U/en
Application granted granted Critical
Publication of CN209053164U publication Critical patent/CN209053164U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of diversion tunnel water inlet layered water drawing structures, are related to hydraulic and hydroelectric engineering field, solve the problems, such as to be to provide that a kind of operation is convenient, reduces investment outlay and the diversion tunnel water inlet layered water drawing structure of easy access.The technical solution adopted in the utility model is: diversion tunnel water inlet layered water drawing structure, including intake tower, intake chamber is set in the tower body of intake tower, the intake that the upstream side of intake chamber is not waited in reservoir operation scheme at least two elevation arranged below, water gate is respectively set in each intake, and the floor elevation of the minimum intake of elevation is higher than reservoir sedimentation elevation and is lower than dead water level elevation;The downstream side of intake chamber is arranged bulkhead gate, connects diversion tunnel by changeover portion at the downstream of bulkhead gate.The utility model uses fixed type steel reinforced concrete breast wall structure, and operation is convenient, reduces investment outlay;It can guarantee that high-quality raw water can be quoted when reservoir difference water level according to water demand stratified pumping, be also convenient for overhauling.

Description

Diversion tunnel water inlet layered water drawing structure
Technical field
The utility model relates to hydraulic and hydroelectric engineering field, the layering of specifically a kind of power station diversion tunnel water inlet is taken Water-bound.
Background technique
In hydraulic and hydroelectric engineering, intake tower is the important building of generating system by piloting water, is related to generating system by piloting water, life The operation of state water intaking and the pith of implementation and environmental protection.The water inlet of diversion tunnel is set in intake tower, due to Large, medium and small type power station reference flow is larger, and it is a variety of that diversion tunnel has both sand washing, water supply, irrigation etc. before power generation, emptying, dam Function, traditional diversion tunnel water inlet only designs one, positioned at the level of dead water of reservoir, does not fully consider the purposes of water intaking, There are temperature of irrigation waters it is too low, silt sundries deposit is more the problems such as.
Currently, the intake tower of domestic power station stratified pumping uses steel construction more piece gate flap stoplog door, steel construction is folded Liangmen is that more piece gate flap is composed, and the operation of steel construction Stoplog gate is complicated, and a section one is needed to save land lifting in the operation of different water levels, Rolled steel dosage is more, and investment is high.
In addition, diversion tunnel reference flow is big, diversion tunnel is long, and pressure-bearing is high, in order to ensure generating system by piloting water is persistently pacified Row for the national games, needs periodic inspection, so diversion tunnel also needs to take into account the needs of maintenance.
Utility model content
That the technical problem to be solved by the utility model is to provide a kind of operations is convenient, reduce investment outlay and easy access is drawn Water tunnel water inlet layered water drawing structure.
The technical scheme adopted by the utility model to solve the technical problem is as follows: diversion tunnel water inlet stratified pumping knot Structure, including intake tower, the tower body of intake tower is interior to be arranged intake chamber, and the upstream side of intake chamber is arranged below in reservoir operation scheme Water gate, the upstream side setting of each water gate is not respectively set in equal intake, each intake at least two elevations Trash rack, wherein the floor elevation of the minimum intake of elevation is higher than reservoir sedimentation elevation and is lower than dead water level elevation;Into Bulkhead gate is arranged in the downstream side of sink, and bulkhead gate downstream side is equipped with venthole, passes through changeover portion at the downstream of bulkhead gate Connect diversion tunnel.
Further, the intake at least three, intake chamber is in up-small and down-big shape, and intake is ladder-like arranged.
Specifically, the intake is three, respectively upper layer intake, middle layer water withdrawal mouth and lower layer's intake, upper layer Height difference between intake and the bottom elevation of middle layer water withdrawal mouth is not less than 15m.
Specifically, the water gate is steel construction bulkhgead gate.
The beneficial effects of the utility model are: diversion tunnel water inlet layered water drawing structure uses fixed type steel reinforced concrete Breast wall structure cancels steel construction Stoplog gate, and operation is convenient, reduces investment outlay.In different elevations, intake is set, it can be according to water need It asks stratified pumping, such as irrigation water that shallow superficial water, town dweller's water supply is taken to take mid-water, improves and use water quality, guarantee reservoir High-quality raw water can be quoted when different water levels.Bulkhead gate is arranged in the downstream side of intake chamber, convenient for the maintenance of diversion tunnel, thus Guarantee the safe operation of generating system by piloting water.
Detailed description of the invention
Fig. 1 is the sectional side elevation of the utility model diversion tunnel water inlet layered water drawing structure embodiment.
Fig. 2 is 1-1 cross-sectional view in Fig. 1.
Components, position and number in figure: intake chamber 1, water gate 2, trash rack 3, bulkhead gate 4, venthole 5, mistake Cross section 6, diversion tunnel 7;Massif 8, access bridge 9, original place upper thread 10;Level of dead water A, it normal pool level B, design flood level C, checks Flood level D.
Specific embodiment
The utility model is described in further detail with reference to the accompanying drawing.
As shown in Figure 1, the utility model diversion tunnel water inlet layered water drawing structure, including intake tower, the tower of intake tower Setting intake chamber 1 in vivo, the upstream side of intake chamber 1, i.e. intake chamber 1 are arranged what at least two elevations did not waited close to the side of storage capacity Water gate 2 is respectively set in intake, each intake, and trash rack 3 is arranged in the upstream side of each water gate 2.Intake is equal Positioned in reservoir operation scheme B hereinafter, the elevation of each intake differs, to realize stratified pumping.Wherein, elevation is minimum The floor elevation of intake is higher than reservoir sedimentation elevation and is lower than dead water level A elevation, the bottom plate of the minimum intake of elevation Elevation also needs to reserve certain safe margin with water guarantee for the special time, and is determined according to the orographic condition of intake, makes to take Mouth of a river floor elevation is lower than dead water level A elevation and has certain depth of the water submerging.
The downstream side of intake chamber 1 is arranged bulkhead gate 4, and 4 downstream side of bulkhead gate is equipped with venthole 5, under bulkhead gate 4 Diversion tunnel 7 is connected by changeover portion 6 at trip.Bulkhead gate 4 is used for the maintenance of diversion tunnel 7, to guarantee generating system by piloting water Safe operation.The top of intake tower is connected with access bridge 9.
The quantity of intake, the i.e. number of plies of stratified pumping are determined according to reservoir scale.For example, intake is three, Respectively upper layer intake, middle layer water withdrawal mouth and lower layer's intake, are ladder-like arranged.Upper layer intake and middle layer water withdrawal mouth Floor elevation determines that height difference is not less than 15m between every layer of intake floor elevation, corresponding intake according to reservoir scale Water gate 2 is steel construction bulkhgead gate, and the upstream of water gate 2 is trash rack 3.Intake chamber 1 is to be set in intake tower Cavity, the intake of the upstream side setting stepped arrangement of cavity, downstream is vertical metope, therefore cavity is integrally in up-small and down-big Shape, as shown in Figure 1.

Claims (4)

1. diversion tunnel water inlet layered water drawing structure, including intake tower, it is characterised in that: setting water inlet in the tower body of intake tower Slot (1), the intake that the upstream side of intake chamber (1) is not waited in reservoir operation scheme (B) at least two elevation arranged below, respectively A intake is respectively set water gate (2), and trash rack (3) are arranged in the upstream side of each water gate (2), and wherein elevation is minimum Intake floor elevation be higher than reservoir sedimentation elevation and be lower than dead water level (A) elevation;The downstream side of intake chamber (1) is set It sets bulkhead gate (4), bulkhead gate (4) downstream side is equipped with venthole (5), passes through changeover portion (6) at the downstream of bulkhead gate (4) It connects diversion tunnel (7).
2. diversion tunnel water inlet layered water drawing structure as described in claim 1, it is characterised in that: the intake at least three A, intake chamber (1) is in up-small and down-big shape, and intake is ladder-like arranged.
3. diversion tunnel water inlet layered water drawing structure as claimed in claim 1 or 2, it is characterised in that: the intake is The bottom elevation of three, respectively upper layer intake, middle layer water withdrawal mouth and lower layer's intake, upper layer intake and middle layer water withdrawal mouth it Between height difference be not less than 15m.
4. diversion tunnel water inlet layered water drawing structure as claimed in claim 3, it is characterised in that: the water gate (2) For steel construction bulkhgead gate.
CN201821775107.3U 2018-10-30 2018-10-30 Diversion tunnel water inlet layered water drawing structure Active CN209053164U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821775107.3U CN209053164U (en) 2018-10-30 2018-10-30 Diversion tunnel water inlet layered water drawing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821775107.3U CN209053164U (en) 2018-10-30 2018-10-30 Diversion tunnel water inlet layered water drawing structure

Publications (1)

Publication Number Publication Date
CN209053164U true CN209053164U (en) 2019-07-02

Family

ID=67052008

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821775107.3U Active CN209053164U (en) 2018-10-30 2018-10-30 Diversion tunnel water inlet layered water drawing structure

Country Status (1)

Country Link
CN (1) CN209053164U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110468810A (en) * 2019-08-02 2019-11-19 昆明理工大学 A kind of more water inlet diversion tunnel devices and construction method
CN110805007A (en) * 2019-10-16 2020-02-18 中国电建集团华东勘测设计研究院有限公司 Safe and reliable factory-wide public water supply method and system
CN112878280A (en) * 2021-01-15 2021-06-01 中国电建集团成都勘测设计研究院有限公司 Laminated water taking stoplog door system
CN113882466A (en) * 2021-09-10 2022-01-04 贵阳筑水水利产业发展有限公司 Reservoir layering water intaking structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110468810A (en) * 2019-08-02 2019-11-19 昆明理工大学 A kind of more water inlet diversion tunnel devices and construction method
CN110805007A (en) * 2019-10-16 2020-02-18 中国电建集团华东勘测设计研究院有限公司 Safe and reliable factory-wide public water supply method and system
CN110805007B (en) * 2019-10-16 2022-04-08 中国电建集团华东勘测设计研究院有限公司 Whole-plant public water supply method and system
CN112878280A (en) * 2021-01-15 2021-06-01 中国电建集团成都勘测设计研究院有限公司 Laminated water taking stoplog door system
CN113882466A (en) * 2021-09-10 2022-01-04 贵阳筑水水利产业发展有限公司 Reservoir layering water intaking structure

Similar Documents

Publication Publication Date Title
CN209053164U (en) Diversion tunnel water inlet layered water drawing structure
CN104294803A (en) Winding type fishway
CN104179159B (en) Power station bright flowing full tail water system
CN104452666A (en) Lifting submerged dam
CN109778800B (en) Gradual change falls sill type stilling basin
CN208857807U (en) It is a kind of to fill sluicing and water charging system for large scale ship
CN107740389A (en) A kind of diversion tunnel structure and its plugging construction method
CN213571838U (en) Multi-layer water intake tower structure of water diversion building
CN204715305U (en) A kind of two-way stratification water gate
CN202865812U (en) Flow-isolating structure of ship-lock approach channels
CN211571646U (en) Air supply ridge structure for drainage energy dissipation hole
CN203113359U (en) Earth rock cofferdam structure
CN104074174A (en) Method for relieving low-temperature water environment influence of reservoir project and dam structure
CN202989895U (en) Mountain ship lock
CN210482455U (en) Pump station diversion and drainage combined overpass culvert gate
CN111809579B (en) Self-aeration ternary hydraulic jump stilling basin
CN210262966U (en) Reconstruction ecological water drainage hole structure combined with permanent plug
CN210459143U (en) Utilize integrated configuration of river levee and lock to realize crossing fish function
CN101063305A (en) Dam for flood discharger
CN210086195U (en) Shaft type tail canal of hydropower station
CN206529831U (en) A kind of intake structure faced forever with vertical shaft cofferdam with reference to arrangement
CN219260936U (en) Double-layer water inlet structure with construction period diversion and running period draining functions
CN211849300U (en) Flood discharge building structure
CN209584992U (en) A kind of dam flood control system
CN106836145A (en) High-tech zones cut-pff wall slides flexible connecting structure with gallery

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant