CN209053120U - Bolt Bolted angle connection assembled counterfort retaining wall - Google Patents

Bolt Bolted angle connection assembled counterfort retaining wall Download PDF

Info

Publication number
CN209053120U
CN209053120U CN201821608066.9U CN201821608066U CN209053120U CN 209053120 U CN209053120 U CN 209053120U CN 201821608066 U CN201821608066 U CN 201821608066U CN 209053120 U CN209053120 U CN 209053120U
Authority
CN
China
Prior art keywords
bottom plate
vertical plate
bolt
retaining wall
counterfort
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821608066.9U
Other languages
Chinese (zh)
Inventor
方勇刚
徐健
陈建荣
余茂科
吕俊平
徐志敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Shuzhijiaoyuan Technology Co Ltd
Original Assignee
Zhejiang Provincial Institute of Communications Planning Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Provincial Institute of Communications Planning Design and Research Co Ltd filed Critical Zhejiang Provincial Institute of Communications Planning Design and Research Co Ltd
Priority to CN201821608066.9U priority Critical patent/CN209053120U/en
Application granted granted Critical
Publication of CN209053120U publication Critical patent/CN209053120U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Retaining Walls (AREA)

Abstract

本实用新型公开了一种螺栓角钢连接装配式扶壁挡土墙,包括多个并排设置的挡土墙单元,所述的挡土墙单元均包括底板、立板和扶壁,立板和扶壁垂直于底板设置在底板上,扶壁垂直于立板,扶壁的支撑面与立板的背面接触;立板底部与底板之间、扶壁底部与底板之间及扶壁与立板背面之间采用角钢和螺栓连接。本实用新型的底板、立板和扶壁为钢筋混凝土结构,能够在现场进行装配施工,具具有构件单元质量可靠、现场施工简单、施工效率高的优点;在底板和立板两侧设有相邻单元搭接结构,保证相邻底板整体沉降和加强相邻立板抗倾覆稳定性。

The utility model discloses an assembled buttress retaining wall connected with bolt angle steel, which comprises a plurality of retaining wall units arranged side by side. The wall is arranged on the bottom plate perpendicular to the bottom plate, the buttress is perpendicular to the vertical plate, and the supporting surface of the buttress is in contact with the back of the vertical plate; Angle steel and bolt connection are used between them. The bottom plate, the vertical plate and the buttress of the utility model are reinforced concrete structures, which can be assembled and constructed on site, and have the advantages of reliable quality of component units, simple on-site construction and high construction efficiency; The adjacent unit lap joint structure ensures the overall settlement of the adjacent bottom plate and strengthens the anti-overturning stability of the adjacent vertical plate.

Description

螺栓角钢连接装配式扶壁挡土墙Bolted Angle Steel Connection Prefabricated Buttress Retaining Wall

技术领域technical field

本实用新型涉及土木工程中的挡土墙,特别涉及一种采用螺栓角钢连接的装配式扶壁挡土墙。The utility model relates to a retaining wall in civil engineering, in particular to an assembled buttress retaining wall connected by bolt angle steel.

背景技术Background technique

挡土墙是保证边坡土体稳定性的主要工程措施之一,在铁道、公路、市政、水利、矿山、房建以及地质灾害处治工程中得到大量使用。目前挡土墙的结构形式比较多,如重力式挡土墙、悬臂式挡土墙、扶臂式挡土墙等,其中重力式挡土墙应用最为广泛,其具有结构简单、取材方便、施工工艺简单等优点,但重力式挡土工人劳动强度高、机械化程度低、受施工场地周围材料限制大、工程质量难以得到保证;另外,工程中悬臂式和扶臂式挡土墙的面板采用钢筋混凝土结构,一般为现场浇注制作,施工条件差,挡墙面板质量参差不齐,施工完之后不能立即承受相应荷载,从而影响工程进度,并且施工后还要定期养护。Retaining wall is one of the main engineering measures to ensure the stability of slope soil. It is widely used in railway, highway, municipal, water conservancy, mine, housing construction and geological disaster treatment projects. At present, there are many structural forms of retaining walls, such as gravity retaining wall, cantilever retaining wall, arm retaining wall, etc. Among them, the gravity retaining wall is the most widely used, which has the advantages of simple structure, convenient material selection and construction. It has the advantages of simple process, etc., but the labor intensity of gravity retaining workers is high, the degree of mechanization is low, it is greatly restricted by the materials around the construction site, and the quality of the project is difficult to guarantee; in addition, the panels of the cantilever and arm retaining walls in the project are made of steel bars. Concrete structures are generally made by on-site casting. The construction conditions are poor, and the quality of the retaining wall panels is uneven. After the construction is completed, it cannot bear the corresponding load immediately, thus affecting the progress of the project, and regular maintenance is required after construction.

发明内容SUMMARY OF THE INVENTION

为了解决上述技术问题,本实用新型提供一种结构简单、质量可靠、施工方便的螺栓角钢连接装配式扶壁挡土墙。In order to solve the above technical problems, the utility model provides a bolted angle steel connection assembled buttress retaining wall with simple structure, reliable quality and convenient construction.

本实用新型解决上述问题的技术方案是:一种螺栓角钢连接装配式扶壁挡土墙,包括多个并排设置的挡土墙单元,所述的挡土墙单元均包括底板、立板和扶壁,立板和扶壁垂直于底板设置在底板上,扶壁垂直于立板,扶壁的支撑面与立板的背面接触;立板底部与底板之间、扶壁底部与底板之间及扶壁与立板背面之间采用角钢和螺栓连接。The technical solution of the present invention to solve the above problems is: a bolted angle steel connection assembled buttress retaining wall, which includes a plurality of retaining wall units arranged side by side, and the retaining wall units all include a bottom plate, a vertical plate and a supporting wall. The wall, the vertical plate and the buttress are arranged on the bottom plate perpendicular to the bottom plate, the buttress is perpendicular to the vertical plate, and the supporting surface of the buttress is in contact with the back of the vertical plate; between the bottom of the vertical plate and the bottom plate, between the bottom of the buttress and the bottom plate, and Angle steel and bolts are used to connect the buttress and the back of the vertical plate.

上述的螺栓角钢连接装配式扶壁挡土墙中,所述的底板上立板和扶壁的安装处设有凹槽;底板、立板和扶壁均为钢筋混凝土结构。In the above-mentioned bolt-angle-steel-connected assembled buttress retaining wall, grooves are provided at the installation positions of the vertical plate and the buttress on the bottom plate; the bottom plate, the vertical plate and the buttress are all reinforced concrete structures.

上述的螺栓角钢连接装配式扶壁挡土墙中,相邻的两挡土墙单元的底板之间采用卯榫结构连接,或相邻的两挡土墙单元的底板的相对的面为相互配合的L形结构,两底板的L形结构搭接后采用螺栓连接。In the above-mentioned bolted angle steel connection assembled buttress retaining wall, the bottom plates of two adjacent retaining wall units are connected by a mortise and tenon structure, or the opposite surfaces of the bottom plates of the two adjacent retaining wall units are matched with each other. The L-shaped structure of the two bottom plates is connected by bolts after overlapping.

上述的螺栓角钢连接装配式扶壁挡土墙中,所述底板上靠近凹槽处设有螺栓,螺栓与底板中钢筋焊接在一起,所述立板底部设有横向螺栓孔或螺栓,螺栓孔或螺栓的位置与立板和底板连接的角钢上的螺栓孔的位置相对应,所述扶壁底部与靠近立板侧设有螺栓孔,螺栓孔与立板和扶壁连接的角钢上的螺栓孔的位置相对应。In the above-mentioned bolted angle steel connection assembled buttress retaining wall, the bottom plate is provided with bolts near the grooves, and the bolts are welded with the steel bars in the bottom plate, and the bottom of the vertical plate is provided with transverse bolt holes or bolts, and the bolt holes are provided with bolts. Or the position of the bolt corresponds to the position of the bolt hole on the angle steel connecting the vertical plate and the bottom plate, the bottom of the buttress and the side close to the vertical plate are provided with bolt holes, and the bolt holes are connected with the vertical plate and the buttress. The positions of the holes correspond.

上述的螺栓角钢连接装配式扶壁挡土墙中,所述底板、立板上的螺栓采用双头螺栓或单头螺栓,双头螺栓呈一字型,垂直于底板或立板穿过底板或立板,双头螺栓两端的螺纹均始于底板或立板的表面,单头螺栓呈L型,带螺纹的杆部垂直于底板或立板,螺纹露在底板或立板外。In the above-mentioned bolted angle steel connection assembled buttress retaining wall, the bolts on the bottom plate and the vertical plate are stud bolts or single-head bolts, and the stud bolts are in a shape, perpendicular to the bottom plate or the vertical plate and pass through the bottom plate or the vertical plate. For vertical plates, the threads at both ends of the stud bolts start from the surface of the bottom plate or vertical plate. The single-ended bolts are L-shaped, the threaded rod is perpendicular to the bottom plate or vertical plate, and the threads are exposed outside the bottom plate or vertical plate.

上述的螺栓角钢连接装配式扶壁挡土墙中,所述底板、立板螺栓和扶壁上的螺栓孔等距布置,相互之间呈交错状。In the above-mentioned bolted angle steel connection assembled buttress retaining wall, the bottom plate, the upright plate bolts and the bolt holes on the buttress are arranged at equal distances, and are staggered with each other.

上述的螺栓角钢连接装配式扶壁挡土墙中,所述底板凹槽内通过灌入纯水泥浆将立板与扶壁固定在凹槽内。In the above-mentioned bolted angle steel connection assembled buttress retaining wall, the vertical plate and the buttress are fixed in the groove by pouring pure cement slurry into the groove of the bottom plate.

上述的螺栓角钢连接装配式扶壁挡土墙中,所述角钢两侧壁上设有螺栓孔,角钢两侧壁之间等距布置有多个肋板,肋板垂直于角钢两侧壁设置。In the above-mentioned bolted angle steel connection assembled buttress retaining wall, bolt holes are arranged on the two side walls of the angle steel, and a plurality of ribs are arranged equidistantly between the two side walls of the angle steel, and the ribs are arranged perpendicular to the two side walls of the angle steel. .

与现有技术相比,本实用新型的有益效果在于:Compared with the prior art, the beneficial effects of the present utility model are:

1、本实用新型的底板、立板和扶壁均为钢筋混凝土结构,能够在现场进行装配施工,具有施工质量高、现场施工简单、环境污染低的优点。1. The bottom plate, vertical plate and buttress of the present invention are all reinforced concrete structures, which can be assembled and constructed on site, and have the advantages of high construction quality, simple on-site construction and low environmental pollution.

2、本实用新型在底板上与扶壁和立板相接位置留有两条凹槽,凹槽内通过纯水泥浆固定立板和扶壁,进一步加强挡墙安全系数,增加工程安全性。2. The utility model has two grooves on the bottom plate where the buttress and the vertical plate are connected, and the vertical plate and the buttress are fixed by pure cement slurry in the groove, which further strengthens the safety factor of the retaining wall and increases the safety of the project.

3、本实用新型施工时可在挡墙外侧面进行平面图案制作,营造工程景观。3. During the construction of the utility model, a plane pattern can be made on the outer side of the retaining wall to create a project landscape.

附图说明Description of drawings

图1为本实用新型的结构示意图。Figure 1 is a schematic structural diagram of the utility model.

图2为本实用新型的俯视图。FIG. 2 is a top view of the utility model.

图3为本实用新型的底板的结构示意图。FIG. 3 is a schematic structural diagram of the bottom plate of the present invention.

图4为本实用新型的立板的结构示意图。4 is a schematic structural diagram of a vertical plate of the present invention.

图5为本实用新型的扶壁的结构示意图。FIG. 5 is a schematic view of the structure of the buttress of the present invention.

图6为本实用新型的角钢的结构示意图。6 is a schematic structural diagram of the angle steel of the present invention.

图7为本实用新型的相邻挡土墙单元底板之间的搭接结构实施例1的结构示意图。7 is a schematic structural diagram of Embodiment 1 of the lap joint structure between the base plates of adjacent retaining wall units of the present invention.

图8为本实用新型的相邻挡土墙单元底板之间的搭接结构实施例2的结构示意图8 is a schematic structural diagram of Embodiment 2 of the lap joint structure between the base plates of adjacent retaining wall units of the present invention

图9为本实用新型现场装配施工图。Figure 9 is a construction drawing of the utility model on-site assembly.

具体实施方式Detailed ways

下面结合附图对本实用新型作进一步的说明。The utility model will be further described below in conjunction with the accompanying drawings.

如图1-图8所示,本实用新型包括多个并排设置的挡土墙单元,所述的挡土墙单元均包括底板1、立板2和扶壁3,底板1、立板2和扶壁3均为钢筋混凝土结构,所述底板1平放在地基9上,底板1顶面上立板2和扶壁3的安装处预留凹槽6,凹槽6呈T形。在凹槽6边缘处设有多个竖向单头螺栓7,单头螺栓7呈L形,单头螺栓7与底板1内的钢筋焊接在一起,其带螺纹的杆部垂直于底板1,螺纹露在底板1外,螺纹始于底板1顶面。如图7、8所示,相邻的两挡土墙单元的底板1之间采用卯榫结构连接,或者两底板1相对的面采用L形结构搭接后采用螺栓连接的方式连接,以增加挡墙工程的整体性。所述的立板2和扶壁3垂直于底板1置于底板上的凹槽6内,并在凹槽6内灌入纯水泥浆将立板2与扶壁4固定在凹槽6内。扶壁3垂直于立板2,扶壁3的支撑面与立板2的背面接触。As shown in Figures 1-8, the present invention includes a plurality of retaining wall units arranged side by side, and the retaining wall units all include a bottom plate 1, a vertical plate 2 and a buttress 3, the bottom plate 1, the vertical plate 2 and The buttresses 3 are all reinforced concrete structures, the bottom plate 1 is placed flat on the foundation 9, and a groove 6 is reserved at the installation place of the vertical plate 2 and the buttress 3 on the top surface of the bottom plate 1, and the groove 6 is T-shaped. A plurality of vertical single-headed bolts 7 are arranged at the edge of the groove 6, and the single-headed bolts 7 are L-shaped. The threads are exposed outside the base plate 1, and the threads start from the top surface of the base plate 1. As shown in Figures 7 and 8, the bottom plates 1 of two adjacent retaining wall units are connected by a mortise and tenon structure, or the opposite surfaces of the two bottom plates 1 are connected by an L-shaped structure and then connected by bolts, so as to increase the The integrity of the retaining wall project. The vertical plate 2 and the buttress 3 are placed in the groove 6 on the bottom plate perpendicular to the bottom plate 1 , and pure cement slurry is poured into the groove 6 to fix the vertical plate 2 and the buttress 4 in the groove 6 . The buttress 3 is perpendicular to the vertical plate 2 , and the supporting surface of the buttress 3 is in contact with the back of the vertical plate 2 .

立板2底部及靠近扶壁3支撑面处设有多个横向单头螺栓7以及多个横向双头螺栓8。所述底板1、立板2上的螺栓和扶壁3上的螺栓孔等距布置,相互之间呈交错状。扶壁3底部及朝向立板2一端设有多个横向螺栓孔,立板2底部与底板1之间、扶壁3底部与底板1之间及扶壁3与立板2背面之间采用角钢连接。将立板2和扶壁3放入底板凹槽6中,接触面缝隙用纯水泥浆进行填充,然后将角钢10的螺栓孔对准单头螺栓7和双头螺栓8,螺栓伸入孔中并用螺母固定。双头螺栓8双头螺栓呈一字型,垂直于底板或立板穿过底板或立板,双头螺栓两端的螺纹均始于底板或立板的表面。如图6所示,所述角钢10两侧壁上设有螺栓孔,角钢两侧壁之间等距布置有多个肋板,肋板垂直于角钢两侧壁设置。底板1、立板2和扶壁3安装完成,利用混凝土对拼接部位处角钢10和两种螺栓7、8进行覆盖形成二次浇筑部位4,成型之后拆模并养护。A plurality of transverse single-headed bolts 7 and a plurality of transverse double-headed bolts 8 are provided at the bottom of the vertical plate 2 and near the supporting surface of the buttress 3 . The bolts on the bottom plate 1 and the vertical plate 2 and the bolt holes on the buttress 3 are arranged at equal distances, and are staggered with each other. The bottom of the buttress 3 and one end facing the vertical plate 2 are provided with a plurality of transverse bolt holes, and angle steel is used between the bottom of the vertical plate 2 and the bottom plate 1, between the bottom of the buttress 3 and the bottom plate 1, and between the buttress 3 and the back of the vertical plate 2. connect. Put the vertical plate 2 and the buttress 3 into the groove 6 of the bottom plate, fill the contact surface gap with pure cement slurry, and then align the bolt holes of the angle steel 10 with the single-head bolts 7 and stud bolts 8, and the bolts extend into the holes. and fasten with nuts. Stud bolts 8 The stud bolts are in a straight line shape and pass through the bottom plate or vertical plate perpendicular to the bottom plate or vertical plate. The threads at both ends of the stud bolt start from the surface of the bottom plate or vertical plate. As shown in FIG. 6 , the two side walls of the angle steel 10 are provided with bolt holes, a plurality of rib plates are arranged equidistantly between the two side walls of the angle steel, and the rib plates are arranged perpendicular to the two side walls of the angle steel. The bottom plate 1, the vertical plate 2 and the buttress 3 are installed. The angle steel 10 and the two types of bolts 7 and 8 at the splicing part are covered with concrete to form the secondary pouring part 4. After forming, the mold is removed and cured.

本实用新型的实施过程如下:如图9所示,首先按设计图纸在预制场用组合钢模预制底板1、立板2和扶壁3,并按钢筋混凝土结构规范要求进行养护,堆放,待挡土墙的施工现场地基9达到要求后将底板1、立板2和扶壁3运送到现场。然后用汽车起重机将底板1吊装到位,并进行相邻底板拼接;然后再吊装立板2,使立板2垂直放于底板1上,并用螺母进行固定。然后在立板2上预先安装角钢10。然后将角钢10安装在扶壁3上,用汽车起重机将扶壁3吊装至底板凹槽6中,并用螺母固定。最后,在角钢10连接处浇筑混凝土,形成保护层,待强度符合规范要求之后回填墙后填土,压实填土5形成挡土墙。The implementation process of the present utility model is as follows: as shown in Figure 9, firstly use composite steel formwork prefabricated bottom plate 1, vertical plate 2 and buttress 3 in the prefabrication field according to the design drawing, and carry out maintenance according to the requirements of the reinforced concrete structure specification, stack, wait for After the construction site foundation 9 of the retaining wall meets the requirements, the bottom plate 1, the vertical plate 2 and the buttress 3 are transported to the site. Then use a truck crane to hoist the bottom plate 1 in place, and splicing adjacent bottom plates; then hoist the vertical plate 2 so that the vertical plate 2 is placed vertically on the bottom plate 1 and fixed with nuts. Then the angle steel 10 is pre-installed on the vertical plate 2 . Then, the angle steel 10 is installed on the buttress 3, and the buttress 3 is hoisted into the groove 6 of the bottom plate by a truck crane, and fixed with nuts. Finally, pour concrete at the connection of angle steel 10 to form a protective layer, backfill the wall after the strength meets the requirements of the specification, and compact the fill 5 to form a retaining wall.

Claims (8)

1. a kind of bolt Bolted angle connection assembled counterfort retaining wall, it is characterised in that: including multiple retaining wall lists arranged side by side Member, the retaining wall unit include bottom plate, vertical plate and counterfort, and vertical plate and counterfort are arranged on bottom plate perpendicular to bottom plate, help Wall is perpendicular to vertical plate, the supporting surface of counterfort and the rear-face contact of vertical plate;Between vertical plate bottom and bottom plate, counterfort bottom and bottom plate it Between and counterfort and the vertical plate back side between using angle steel and being bolted.
2. bolt Bolted angle connection assembled counterfort retaining wall according to claim 1, it is characterised in that: on the bottom plate The installation place of vertical plate and counterfort is equipped with groove;Bottom plate, vertical plate and counterfort are reinforced concrete structure.
3. bolt Bolted angle connection assembled counterfort retaining wall according to claim 2, it is characterised in that: two adjacent earth-retainings It is connected between the bottom plate of wall unit using tenon structure or the opposite face of the bottom plate of two adjacent retaining wall units is phase interworking The L-shaped structure of conjunction, the L-shaped structure of two bottom plates are connected by screw bolts after overlapping.
4. bolt Bolted angle connection assembled counterfort retaining wall according to claim 2, it is characterised in that: leaned on the bottom plate Nearly groove is equipped with bolt, and for bolt together with reinforcement welding in bottom plate, the vertical plate bottom is equipped with cross bolts hole or bolt, The position of bolt hole on angle steel that the position of bolt hole or bolt and vertical plate and bottom plate connect is corresponding, the counterfort bottom with It is equipped with bolt hole close to vertical plate side, bolt hole is corresponding with the position of bolt hole on the angle steel that vertical plate and counterfort connect.
5. bolt Bolted angle connection assembled counterfort retaining wall according to claim 4, it is characterised in that: the bottom plate is stood Bolt on plate uses stud or single ended bolt, and stud is in "-" type, perpendicular to bottom plate or vertical plate pass through bottom plate or Vertical plate, the screw thread at stud both ends start from the surface of bottom plate or vertical plate, and single ended bolt is L-shaped, and threaded bar portion is vertical In bottom plate or vertical plate, screw thread is exposed at outside bottom plate or vertical plate.
6. bolt Bolted angle connection assembled counterfort retaining wall according to claim 4, it is characterised in that: the bottom plate is stood Bolt hole equidistant placement on crab bolt and counterfort, it is cross-shaped between each other.
7. bolt Bolted angle connection assembled counterfort retaining wall according to claim 4, it is characterised in that: the bottom plate groove It is interior that vertical plate and counterfort are fixed in groove by pouring into neat slurry.
8. bolt Bolted angle connection assembled counterfort retaining wall according to claim 4, it is characterised in that: the angle steel two sides Wall is equipped with bolt hole, and equidistant placement has multiple floors between angle steel two sidewalls, and floor is arranged perpendicular to angle steel two sidewalls.
CN201821608066.9U 2018-09-30 2018-09-30 Bolt Bolted angle connection assembled counterfort retaining wall Active CN209053120U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821608066.9U CN209053120U (en) 2018-09-30 2018-09-30 Bolt Bolted angle connection assembled counterfort retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821608066.9U CN209053120U (en) 2018-09-30 2018-09-30 Bolt Bolted angle connection assembled counterfort retaining wall

Publications (1)

Publication Number Publication Date
CN209053120U true CN209053120U (en) 2019-07-02

Family

ID=67049858

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821608066.9U Active CN209053120U (en) 2018-09-30 2018-09-30 Bolt Bolted angle connection assembled counterfort retaining wall

Country Status (1)

Country Link
CN (1) CN209053120U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453724A (en) * 2019-09-18 2019-11-15 安徽工程大学 A new type of prefabricated anti-seismic buttress retaining wall
CN110777925A (en) * 2019-11-28 2020-02-11 中冶京诚工程技术有限公司 An open pool structure
CN110820795A (en) * 2019-10-16 2020-02-21 同济大学 Double-deck corrugated steel plate concrete combination retaining wall
CN111648399A (en) * 2020-06-11 2020-09-11 中铁十四局集团大盾构工程有限公司 Protection and reinforcement method for retaining wall structure
CN113309137A (en) * 2021-05-08 2021-08-27 浙大城市学院 Construction method of counterfort assembled retaining wall
CN114108692A (en) * 2021-12-16 2022-03-01 哈尔滨工业大学 Fabricated buttress retaining wall with uplift pile and construction method thereof
CN114215105A (en) * 2021-12-31 2022-03-22 山东高速岩土科技有限公司 Abutment back backfill pouring method and novel assembly type retaining wall

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453724A (en) * 2019-09-18 2019-11-15 安徽工程大学 A new type of prefabricated anti-seismic buttress retaining wall
CN110820795A (en) * 2019-10-16 2020-02-21 同济大学 Double-deck corrugated steel plate concrete combination retaining wall
CN110820795B (en) * 2019-10-16 2021-03-26 同济大学 A double-layer corrugated steel plate concrete composite retaining wall
CN110777925A (en) * 2019-11-28 2020-02-11 中冶京诚工程技术有限公司 An open pool structure
CN111648399A (en) * 2020-06-11 2020-09-11 中铁十四局集团大盾构工程有限公司 Protection and reinforcement method for retaining wall structure
CN111648399B (en) * 2020-06-11 2021-11-30 中铁十四局集团大盾构工程有限公司 Protection and reinforcement method for retaining wall structure
CN113309137A (en) * 2021-05-08 2021-08-27 浙大城市学院 Construction method of counterfort assembled retaining wall
CN114108692A (en) * 2021-12-16 2022-03-01 哈尔滨工业大学 Fabricated buttress retaining wall with uplift pile and construction method thereof
CN114215105A (en) * 2021-12-31 2022-03-22 山东高速岩土科技有限公司 Abutment back backfill pouring method and novel assembly type retaining wall

Similar Documents

Publication Publication Date Title
CN209053120U (en) Bolt Bolted angle connection assembled counterfort retaining wall
CN104746422B (en) A kind of hollow pier stud delay-pour joint structure of bridge prefabrication and construction method
CN104652671B (en) Prefabricated assembly-type concrete outer-hanging wallboard fixing device and installation method
CN108385512A (en) One kind being based on bolted modular assembly formula Hollow High Pier splicing structure and its practice
CN110670770A (en) Combined structure and construction method of solid shear wall and laminated plate edge member
CN113653235A (en) Laminated slab, connecting structure of laminated slab and combination beam and construction method
CN115653160A (en) Buckle connecting piece, single-side detachable formwork superposed shear wall and construction method
CN212534738U (en) Truss Floor Slab
CN113356405A (en) Prefabricated composite wall structure based on embedded profile steel and construction method thereof
CN204097864U (en) A kind of bridge prefabrication hollow pier stud delay-pour joint structure
CN208023601U (en) A kind of prefabricated pile foundation support table side form of mutual buckle type
CN108547311A (en) Isolated footing under a kind of prefabricated assembled profile steel concrete column
CN116290075B (en) Back wall of jacking pipe capable of being used in turnover mode and construction process of back wall
CN103015453A (en) Dual-connection type tower crane foundation
CN110512776B (en) Construction method of assembled steel structure multi-cavity steel plate composite shear wall
CN111749364A (en) A prefabricated composite wall based on C-shaped steel and its construction method
CN212866842U (en) Frame structure type building scaffold
CN210482352U (en) Assembled main basis that becomes of high voltage mortise-tenon joint structure
CN109235482B (en) Tower Crane Foundation Based on Bonded Prestressed Concrete and Its Construction Method
CN114000631B (en) Rotary detachable steel frame and laminated plate connecting structure
CN208009729U (en) Assembled horse tooth trough overlap edge-punching sheet metal floorslab with bars
CN100485137C (en) Combined foundation of backstay type machinery apparatus
CN204849733U (en) High performance concrete wave form sheet pile and forming die
CN117090334A (en) Detachable steel bar truss floor support plate and combined cast-in-situ floor construction method thereof
CN116145721A (en) A rapid construction method of semi-prefabricated buttress retaining wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: No. 89, Huancheng West Road, Xihu District, Hangzhou City, Zhejiang Province

Patentee after: Zhejiang shuzhijiaoyuan Technology Co.,Ltd.

Address before: No. 89, Huancheng West Road, Xihu District, Hangzhou City, Zhejiang Province

Patentee before: ZHEJIANG PROVINCIAL INSTITUTE OF COMMUNICATIONS PLANNING DESIGN & RESEARCH Co.,Ltd.

CP01 Change in the name or title of a patent holder