CN209050440U - Preceding planet carrier tooling - Google Patents
Preceding planet carrier tooling Download PDFInfo
- Publication number
- CN209050440U CN209050440U CN201821905014.8U CN201821905014U CN209050440U CN 209050440 U CN209050440 U CN 209050440U CN 201821905014 U CN201821905014 U CN 201821905014U CN 209050440 U CN209050440 U CN 209050440U
- Authority
- CN
- China
- Prior art keywords
- workpiece
- pressing plate
- bore hole
- planet carrier
- bottom plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Finish Polishing, Edge Sharpening, And Grinding By Specific Grinding Devices (AREA)
Abstract
The utility model discloses preceding planet carrier toolings, including bore hole bottom plate, bore hole bottom plate top part is not connected with the first workpiece, second workpiece, third workpiece and the 4th workpiece, digging on the bore hole bottom plate has through-hole, first workpiece, second workpiece, third workpiece and the 4th workpiece are placed in the top of through-hole, bore hole bottom plate top part is not connected with the first pressing plate, second pressing plate, third pressing plate and the 4th pressing plate, first pressing plate, second pressing plate, third pressing plate and the 4th pressing plate respectively with the first workpiece, second workpiece, third workpiece and the 4th workpiece offset;The utility model can replace the position of pressing plate at any time, it is made preferably to push down or unclamp workpiece, easy to operate, and positioning accuracy is high, and can the multiple workpiece of simultaneous processing, improve efficiency.
Description
Technical field
The utility model relates to field of machining technology more particularly to preceding planet carrier toolings.
Background technique
Planet carrier is one of main member of planet gear transmission device, and planet wheel spindle or bearing are just mounted in planet carrier
On, when planetary gear is as basic building block, it is the receiving maximum part of moment of face in mechanism, the structure design and system of planetary gear
It makes between the load distribution each planetary gear so that bearing capacity, noise and the vibration etc. of transmission device have a significant impact.
In preceding planet carrier process, usually preceding planet carrier is fixed, is then processed, but existing work
Skill generallys use three-jaw positioning tool and is fixed when fixed, trivial operations, it is difficult to guarantee positioning accuracy, low efficiency.
Utility model content
The problem of purpose of the utility model is to solve background techniques, and the preceding planet carrier tooling proposed.
To achieve the goals above, the utility model adopts the technical scheme that
Preceding planet carrier tooling, including bore hole bottom plate, bore hole bottom plate top part are not connected with the first workpiece, the second work
Part, third workpiece and the 4th workpiece, digging on the bore hole bottom plate has through-hole, first workpiece, second workpiece, third workpiece
The top of through-hole is placed in the 4th workpiece, bore hole bottom plate top part is not connected with the first pressing plate, the second pressing plate, third pressure
Plate and the 4th pressing plate, first pressing plate, the second pressing plate, third pressing plate and the 4th pressing plate respectively with the first workpiece, second workpiece,
Third workpiece and the 4th workpiece offset.
Preferably, first pressing plate, the second pressing plate, third pressing plate and the 4th pressing plate outer wall, which are dug, sliding slot, described
The first bolt is slidably connected in sliding slot, digging in the bore hole bottom plate has the first screw hole, and first bolt thread is connected to
In first screw hole.
Preferably, first screw hole is ten of circle distribution, each first screw hole with the first bolt thread
Connection.
Preferably, first pressing plate, the second pressing plate, third pressing plate and the 4th pressing plate bottom are fixedly connected to rubber
Pad.
Preferably, the quantity of first workpiece, second workpiece, third workpiece and the 4th workpiece is three.
Preferably, the bore hole base plate interior cutting has the second screw hole, and the second screw hole internal screw thread is connected with the second spiral shell
Bolt, the bore hole bottom base plate are connected with bore hole cushion block.
Compared with prior art, planet carrier tooling before the utility model provides, have it is following the utility model has the advantages that
1, then the preceding planet carrier tooling passes through the first pressing plate, the second pressure by fixing bore hole bottom plate on the ground
First workpiece, second workpiece, third workpiece and the 4th workpiece are pressed on bore hole bottom plate by plate, third pressing plate and the 4th pressing plate respectively
Through-hole top, the clast residue on workpiece after bore hole can be made to facilitate discharge, improve the service life and working efficiency of machine,
It is convenient that bore hole is carried out to it, wherein the first workpiece is first of workpiece of planet carrier before 20E, planet carrier the before second workpiece is 40E
One of workpiece, third workpiece are planet carrier second workpiece before 20E, and the 4th workpiece is planet carrier second workpiece before 40E, simultaneously
Processing is fixed in various workpieces, is improved efficiency.
2, preceding planet carrier tooling, by matching the first bolt with the first screw hole on bore hole bottom plate, to make
One pressing plate, the second pressing plate, third pressing plate and the 4th pressing plate are respectively by the first workpiece, second workpiece, third workpiece and the 4th workpiece
It is pressed in the surface of bore hole bottom plate, fixes it, it is convenient to its bore hole, while the first bolt can slide in sliding slot, facilitate operation
With disassembly.
3, the preceding planet carrier tooling, by being arranged multiple first screw holes, conveniently replaced first pressing plate, the second pressing plate, the
The position of three pressing plates and the 4th pressing plate, so that so that it will not influence boring work.
4, the preceding planet carrier tooling can make the first pressing plate, the second pressing plate, third pressing plate and the 4th pressing plate not by rubber pad
Workpiece can be damaged by pressure, it is impaired to avoid workpiece surface.
5, the preceding planet carrier tooling, by the way that multiple first workpiece, second workpiece, third workpiece and the 4th workpiece is arranged, from
And improve working efficiency.
6, the preceding planet carrier tooling is matched by the second bolt with the second screw hole, so that bore hole bottom plate is fixed, it is convenient
Processing, bore hole cushion block can increase the height of bore hole bottom plate, and so that it will not damage to process tool.
Detailed description of the invention
Fig. 1 be the utility model proposes preceding planet carrier tooling structural schematic diagram;
Fig. 2 be the utility model proposes preceding planet carrier tooling overlook structural schematic diagram;
Fig. 3 be the utility model proposes preceding the first workpiece of planet carrier tooling top view;
Fig. 4 be the utility model proposes preceding planet carrier tooling second workpiece top view;
Fig. 5 be the utility model proposes preceding planet carrier tooling third workpiece top view;
Fig. 6 be the utility model proposes preceding the 4th workpiece of planet carrier tooling top view.
In figure: 1, bore hole bottom plate;2, bore hole cushion block;3, the first workpiece;4, second workpiece;5, third workpiece;6, the 4th work
Part;7, the first pressing plate;8, the second pressing plate;9, third pressing plate;10, the 4th pressing plate;11, through-hole;12, the first bolt;13, the first spiral shell
Hole;14, rubber pad;15, sliding slot;16, the second screw hole.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.
In the description of the present invention, it should be understood that term " on ", "lower", "front", "rear", "left", "right",
The orientation or positional relationship of the instructions such as "top", "bottom", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, and is only
For ease of description the utility model and simplify description, rather than the device or element of indication or suggestion meaning must have it is specific
Orientation, be constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention.
Embodiment 1:
Referring to Fig.1-6, preceding planet carrier tooling, including bore hole bottom plate 1 are connected separately with the first workpiece at the top of bore hole bottom plate 1
3, second workpiece 4, third workpiece 5 and the 4th workpiece 6, digging on bore hole bottom plate 1 has through-hole 11, the first workpiece 3, second workpiece 4,
Third workpiece 5 and the 4th workpiece 6 are placed in the top of through-hole 11, and the first pressing plate 7, second is connected separately at the top of bore hole bottom plate 1
Pressing plate 8, third pressing plate 9 and the 4th pressing plate 10, the first pressing plate 7, the second pressing plate 8, third pressing plate 9 and the 4th pressing plate 10 are respectively with
One workpiece 3, second workpiece 4, third workpiece 5 and the 4th workpiece 6 offset;By fixing bore hole bottom plate 1 on the ground, then lead to
The first pressing plate 7, the second pressing plate 8, third pressing plate 9 and the 4th pressing plate 10 are crossed respectively by the first workpiece 3, second workpiece 4, third workpiece
5 and the 4th workpiece 6 be pressed in the top of the through-hole 11 on bore hole bottom plate 1, the clast residue on workpiece after bore hole can be made to facilitate discharge,
The service life and working efficiency of machine are improved, it is convenient that bore hole is carried out to it, wherein the first workpiece 3 is planet carrier first before 20E
Road workpiece, second workpiece 4 be 40E before first of workpiece of planet carrier, third workpiece 5 be 20E before planet carrier second workpiece, the 4th
Workpiece 6 is planet carrier second workpiece before 40E, while processing is fixed in various workpieces, is improved efficiency.
Embodiment 2:
Referring to Fig.1-6, preceding planet carrier tooling, including bore hole bottom plate 1 are connected separately with the first workpiece at the top of bore hole bottom plate 1
3, second workpiece 4, third workpiece 5 and the 4th workpiece 6, digging on bore hole bottom plate 1 has through-hole 11, the first workpiece 3, second workpiece 4,
Third workpiece 5 and the 4th workpiece 6 are placed in the top of through-hole 11, and the first pressing plate 7, second is connected separately at the top of bore hole bottom plate 1
Pressing plate 8, third pressing plate 9 and the 4th pressing plate 10, the first pressing plate 7, the second pressing plate 8, third pressing plate 9 and the 4th pressing plate 10 are respectively with
One workpiece 3, second workpiece 4, third workpiece 5 and the 4th workpiece 6 offset;By fixing bore hole bottom plate 1 on the ground, then lead to
The first pressing plate 7, the second pressing plate 8, third pressing plate 9 and the 4th pressing plate 10 are crossed respectively by the first workpiece 3, second workpiece 4, third workpiece
5 and the 4th workpiece 6 be pressed in the top of the through-hole 11 on bore hole bottom plate 1, the clast residue on workpiece after bore hole can be made to facilitate discharge,
The service life and working efficiency of machine are improved, it is convenient that bore hole is carried out to it, wherein the first workpiece 3 is planet carrier first before 20E
Road workpiece, second workpiece 4 be 40E before first of workpiece of planet carrier, third workpiece 5 be 20E before planet carrier second workpiece, the 4th
Workpiece 6 is planet carrier second workpiece before 40E, while processing is fixed in various workpieces, is improved efficiency.
First pressing plate 7, the second pressing plate 8, third pressing plate 9 and 10 outer wall of the 4th pressing plate, which are dug, sliding slot 15, in sliding slot 15
The first bolt 12 is slidably connected, digging in bore hole bottom plate 1 has the first screw hole 13, and the first bolt 12 is threaded in the first screw hole
In 13;By matching the first bolt 12 with the first screw hole 13 on bore hole bottom plate 1, to make the first pressing plate 7, the second pressing plate
8, the first workpiece 3, second workpiece 4, third workpiece 5 and the 4th workpiece 6 are pressed in bore hole respectively by third pressing plate 9 and the 4th pressing plate 10
The surface of bottom plate 1, fixes it, convenient to its bore hole, while the first bolt 13 can slide in sliding slot 15, facilitate operation and tear open
It unloads.
First screw hole 13 is ten of circle distribution, and each first screw hole 13 is threadedly coupled with the first bolt 12;Pass through
Multiple first screw holes 13 are set, the position of conveniently replaced first pressing plate 7, the second pressing plate 8, third pressing plate 9 and the 4th pressing plate 10,
To which so that it will not influence boring work.
First pressing plate 7, the second pressing plate 8, third pressing plate 9 and 10 bottom of the 4th pressing plate are fixedly connected to rubber pad 14;It is logical
Crossing rubber pad 14 can make the first pressing plate 7, the second pressing plate 8, third pressing plate 9 and the 4th pressing plate 10 not to damage workpiece by pressure, avoid
Workpiece surface is impaired.
Embodiment 3:
Referring to Fig.1-6, preceding planet carrier tooling, including bore hole bottom plate 1 are connected separately with the first workpiece at the top of bore hole bottom plate 1
3, second workpiece 4, third workpiece 5 and the 4th workpiece 6, digging on bore hole bottom plate 1 has through-hole 11, the first workpiece 3, second workpiece 4,
Third workpiece 5 and the 4th workpiece 6 are placed in the top of through-hole 11, and the first pressing plate 7, second is connected separately at the top of bore hole bottom plate 1
Pressing plate 8, third pressing plate 9 and the 4th pressing plate 10, the first pressing plate 7, the second pressing plate 8, third pressing plate 9 and the 4th pressing plate 10 are respectively with
One workpiece 3, second workpiece 4, third workpiece 5 and the 4th workpiece 6 offset;By fixing bore hole bottom plate 1 on the ground, then lead to
The first pressing plate 7, the second pressing plate 8, third pressing plate 9 and the 4th pressing plate 10 are crossed respectively by the first workpiece 3, second workpiece 4, third workpiece
5 and the 4th workpiece 6 be pressed in the top of the through-hole 11 on bore hole bottom plate 1, the clast residue on workpiece after bore hole can be made to facilitate discharge,
The service life and working efficiency of machine are improved, it is convenient that bore hole is carried out to it, wherein the first workpiece 3 is planet carrier first before 20E
Road workpiece, second workpiece 4 be 40E before first of workpiece of planet carrier, third workpiece 5 be 20E before planet carrier second workpiece, the 4th
Workpiece 6 is planet carrier second workpiece before 40E, while processing is fixed in various workpieces, is improved efficiency.
First workpiece 3, second workpiece 4, third workpiece 5 and the 4th workpiece 6 quantity be three;By being arranged multiple the
One workpiece 3, second workpiece 4, third workpiece 5 and the 4th workpiece 6, to improve working efficiency.
Digging inside bore hole bottom plate 1 has the second screw hole 16, and 16 internal screw thread of the second screw hole is connected with the second bolt, bore hole bottom plate
1 bottom is connected with bore hole cushion block 2;It is matched by the second bolt with the second screw hole 16, thus keep bore hole bottom plate 1 fixed, it is convenient
Processing, bore hole cushion block 2 can increase the height of bore hole bottom plate 1, and so that it will not damage to process tool.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not
It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this
Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model
Within enclosing.
Claims (6)
1. a kind of preceding planet carrier tooling, including bore hole bottom plate (1), which is characterized in that be separately connected at the top of the bore hole bottom plate (1)
There are the first workpiece (3), second workpiece (4), third workpiece (5) and the 4th workpiece (6), there is logical cutting on the bore hole bottom plate (1)
Hole (11), first workpiece (3), second workpiece (4), third workpiece (5) and the 4th workpiece (6) are placed in the top of through-hole (11)
Portion, bore hole bottom plate (1) top are connected separately with the first pressing plate (7), the second pressing plate (8), third pressing plate (9) and the 4th pressing plate
(10), first pressing plate (7), the second pressing plate (8), third pressing plate (9) and the 4th pressing plate (10) respectively with the first workpiece (3),
Second workpiece (4), third workpiece (5) and the 4th workpiece (6) offset.
2. preceding planet carrier tooling according to claim 1, which is characterized in that first pressing plate (7), the second pressing plate (8),
Third pressing plate (9) and the 4th pressing plate (10) outer wall, which are dug, to be had sliding slot (15), slidably connects the first spiral shell in the sliding slot (15)
Bolt (12), interior dig of the bore hole bottom plate (1) have the first screw hole (13), and first bolt (12) is threaded in the first screw hole
(13) in.
3. preceding planet carrier tooling according to claim 2, which is characterized in that first screw hole (13) is circle distribution
Ten, each first screw hole (13) is threadedly coupled with the first bolt (12).
4. preceding planet carrier tooling according to claim 2, which is characterized in that first pressing plate (7), the second pressing plate (8),
Third pressing plate (9) and the 4th pressing plate (10) bottom are fixedly connected to rubber pad (14).
5. preceding planet carrier tooling according to claim 1, which is characterized in that first workpiece (3), second workpiece (4),
The quantity of third workpiece (5) and the 4th workpiece (6) is three.
6. preceding planet carrier tooling according to claim 1, which is characterized in that digging inside the bore hole bottom plate (1) has the
Two screw holes (16), the second screw hole (16) internal screw thread are connected with the second bolt, and bore hole bottom plate (1) bottom is connected with bore hole
Cushion block (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821905014.8U CN209050440U (en) | 2018-11-19 | 2018-11-19 | Preceding planet carrier tooling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821905014.8U CN209050440U (en) | 2018-11-19 | 2018-11-19 | Preceding planet carrier tooling |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209050440U true CN209050440U (en) | 2019-07-02 |
Family
ID=67053688
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821905014.8U Expired - Fee Related CN209050440U (en) | 2018-11-19 | 2018-11-19 | Preceding planet carrier tooling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209050440U (en) |
-
2018
- 2018-11-19 CN CN201821905014.8U patent/CN209050440U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206455196U (en) | A kind of numerically controlled lathe scroll chuck fixture | |
CN201988772U (en) | Drill for machining step holes | |
CN209050440U (en) | Preceding planet carrier tooling | |
CN202701776U (en) | Machine tool with cutting-scrap-prevention linear guide rail | |
CN103042255B (en) | Pneumatic perforating assembled tool | |
CN209078274U (en) | A kind of numerical control lathe wheeled litter shift fork fork shaft hole and positioning surface fixture | |
CN215659254U (en) | Milling machine for processing parts with metal recovery mechanism | |
CN105081899A (en) | Full-automatic micro drilling grinder | |
CN201776532U (en) | Thread processing device for overweight or large-sized workpiece | |
CN204603799U (en) | Vertical numerical control machining center | |
CN208303953U (en) | A kind of automatic boring device with dust reduction capability | |
CN201324845Y (en) | Radial drilling machine | |
CN201143567Y (en) | Slot tool for drill machine | |
CN207942018U (en) | A kind of electric drill having depthkeeping function | |
CN209830342U (en) | Machining device for main shaft box hole | |
CN103028763A (en) | Machining device for forming counter bored through holes in one step | |
CN203281942U (en) | Drilling die used for parking brake housing and flange | |
CN209007034U (en) | It is a kind of for boring the full-automatic numerical control drilling and tapping machine and control system of attacking axis | |
CN205981050U (en) | Centre bore degree of depth caliber | |
CN105058155A (en) | Machining center | |
CN109909781A (en) | Bidirectional rotation system double-station bonnet machining center | |
CN205673647U (en) | A kind of drill jig disassembly mechanism | |
CN205587948U (en) | Center of attacking is bored in numerical control of noise reduction | |
CN209647359U (en) | A kind of Pneumatic punching device | |
CN220006787U (en) | Quick replacement fixture device for tapping drilling machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190702 Termination date: 20191119 |