CN209040862U CN201821931055.4U CN201821931055U CN209040862U CN 209040862 U CN209040862 U CN 209040862U CN 201821931055 U CN201821931055 U CN 201821931055U CN 209040862 U CN209040862 U CN 209040862U
Authority
CN
China
Prior art keywords
anchorage bearing
transfer beam
total station
mounting plate
mounting base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821931055.4U
Other languages
Chinese (zh)
Inventor
怀平生
白晓岭
王燊
赵香萍
李晓
郭银新
毋海军
李康康
吴勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201821931055.4U priority Critical patent/CN209040862U/en
Application granted granted Critical
Publication of CN209040862U publication Critical patent/CN209040862U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a kind of shield tunnel vault total station mounting base, belongs to the technical field of total station mounting base, including bracket, upper anchorage bearing, lower anchorage bearing and transfer beam;Bracket includes supporting plate and two parallel truss girders being arranged under supporting plate;Upper anchorage bearing and lower anchorage bearing include the first mounting plate and two the second mounting plates perpendicular to the first mounting plate;Anchor bolt is provided on first mounting plate;Second mounting plate of upper anchorage bearing is connected with transfer beam by fastening bolt;Lower anchorage bearing strip-shaped hole is provided on second mounting plate of lower anchorage bearing, the fastening bolt by passing through lower anchorage bearing strip-shaped hole is connected with truss girder;Transfer beam strip-shaped hole is provided in transfer beam, the fastening bolt by passing through transfer beam strip-shaped hole is connected with truss girder, and transfer beam is located between supporting plate and lower anchorage bearing.The mounting base can install total station in tunnel, reduce influence of the constructing tunnel process to total station accuracy.

Description

A kind of shield tunnel vault total station mounting base
Technical field
The utility model relates to the technical fields of total station mounting base, more particularly to a kind of shield tunnel vault total station Mounting base.
Background technique
Shield method is the comprehensive construction technology that constructing tunnel uses, it is by the orientation driving in tunnel, slip casting, lining The construction method that each work posts such as block, waterproof, tunnel molding are combined into one.Its working depth can be very deep, not by surface structures With the influence of traffic, mechanization and the degree of automation are very high, are a kind of advanced tunnels in soil construction methods, are widely used in city In the construction of the engineerings such as underground railway, cross-river tunnel.
In order to control position and the direction of propulsion of shield, shield-tunneling construction measuring technique be it is indispensable, it is more in engineering It is measured using total station.Total station is come into being during angle measurement automation, mainly using in hole Traverse point measures the position (current spatial location and axis direction) of shield, indicates direction of propulsion, is imposed not with jack marshalling Same thrust, rectifies a deviation, i.e. the position of adjustment shield and direction of propulsion.But since total station belongs to precision instrument, measuring Should minimize external disturbance factor in the process, reduce measurement error, shield machine and its attached Backup system with promote to Preceding movement, and vibrational state is constantly in work progress, total station is mounted on shield machine and its attached Backup system Upper implementation measurement is impossible;And the section in tunnel is arch, is placed in total station in tunnel both with total station autogamy bracket It is difficult to level, also will affect construction.
Utility model content
The purpose of this utility model is to provide a kind of shield tunnel vault total station mounting bases, can install in tunnel Total station reduces influence of the constructing tunnel process to total station accuracy.
To achieve the above object, the utility model provides a kind of shield tunnel vault total station mounting base, including bracket, on Anchorage bearing, lower anchorage bearing and transfer beam;Bracket include the supporting plate for placing total station and be arranged under supporting plate two A parallel truss girder;Centring hole is provided on supporting plate;Upper anchorage bearing and lower anchorage bearing include the first mounting plate and hang down Directly in two the second mounting plates of the first mounting plate;Anchor bolt is provided on first mounting plate;Second peace of upper anchorage bearing Loading board is connected with transfer beam by fastening bolt;
The direction perpendicular to the first mounting plate is provided with lower anchorage bearing item on second mounting plate of lower anchorage bearing Shape hole, the second mounting plate are connected by passing through the fastening bolt of lower anchorage bearing strip-shaped hole with truss girder;Along perpendicular in transfer beam Histogram is connected by passing through the fastening bolt of transfer beam strip-shaped hole with truss girder to transfer beam strip-shaped hole, transfer beam is provided with, and Transfer beam is located between supporting plate and lower anchorage bearing.
Further, levelling rod is provided on truss girder.
Further, the position that the second mounting plate of truss girder and lower anchorage bearing contacts with each other is hair side.
Further, the position that truss girder and transfer beam contact with each other is hair side.
Further, bracket, upper anchorage bearing, lower anchorage bearing and transfer beam are made of steel, and surface is coated with antirust Paint.
The beneficial effects of the utility model are:
Total station installation site (general total station is mounted on or 9 o'clock direction in tunnel at 3 points) is determined according to designing, by anchor The position of fixing bolt remembers Chu in tunnel arch concrete surface subscript, is drilled on concrete surface using impact drill, installation expansion Anchor bolt on first mounting plate is installed on expansion bolt device by bolt device, realizes shield tunnel vault total station The fixation of mounting base, rotation transfer beam tighten the fastening bolt between anchorage bearing and transfer beam, along lower anchoring to vertical Support strip-shaped hole and transfer beam strip-shaped hole movable support bracket are tightened between lower anchorage bearing and bracket to after reaching horizontal accuracy requirement Fastening bolt and transfer beam and bracket between fastening bolt, realize the fixation of bracket, total station be mounted on supporting plate ?.The shield tunnel vault total station mounting base is mounted on the concrete surface of tunnel arch, is occupied little space, is not hindered other and apply Work process carries out, and can adapt to tunnel construction environment, reduces interference of the vibration of construction generation in tunnel to total station accuracy, peace Dress and convenient disassembly, and after dismantling, can reuse, can save cost, and it is ingenious in design, cost of manufacture is cheap, It is easy to operate, easy to use.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of shield tunnel vault total station mounting base provided by the embodiment of the utility model.
In figure: the upper anchorage bearing of 1-;Anchorage bearing under 2-;3- transfer beam;4- supporting plate;5- truss girder;6- anchor bolt;7- Fastening bolt;Anchorage bearing strip-shaped hole under 8-;9- transfer beam strip-shaped hole;10- levelling rod.
Specific embodiment
The present embodiment provides a kind of shield tunnel vault total station mounting bases, including bracket, upper anchorage bearing 1, lower anchoring Support 2 and transfer beam 3;Bracket includes the supporting plate 4 for placing total station and two parallel brackets being arranged under supporting plate 4 Beam 5;Centring hole is provided on supporting plate 4, center is directed at centring hole when total station is installed;Upper anchorage bearing 1 and lower anchorage bearing 2 are equal Including the first mounting plate and perpendicular to two the second mounting plates of the first mounting plate;Anchor bolt 6 is provided on first mounting plate; The second mounting plate and transfer beam 3 of upper anchorage bearing 1 are connected by fastening bolt 7;Edge on second mounting plate of lower anchorage bearing 2 The direction of the first mounting plate is provided with lower anchorage bearing strip-shaped hole 8, the second mounting plate, which passes through, passes through lower anchorage bearing The fastening bolt 7 and truss girder 5 of strip-shaped hole 8 connect;Transfer beam strip-shaped hole 9, power transmission have been placed in the vertical direction in transfer beam 3 Beam 3 is connected by the fastening bolt 7 and truss girder 5 for passing through transfer beam strip-shaped hole 9, and transfer beam 3 is located at supporting plate 4 and casts anchor clamped Between seat 2.
Total station installation site (general total station is mounted on or 9 o'clock direction in tunnel at 3 points) is determined according to designing, by anchor The position of fixing bolt 6 remembers Chu in tunnel arch concrete surface subscript, is drilled on concrete surface using impact drill, installation expansion Anchor bolt 6 on first mounting plate is installed on expansion bolt device by bolt device, realizes shield tunnel vault total station The fixation of mounting base, rotation transfer beam 3 tighten the fastening bolt 7 between anchorage bearing 1 and transfer beam 3, under to vertical Anchorage bearing strip-shaped hole 8 and 9 movable support bracket of transfer beam strip-shaped hole tighten lower 2 He of anchorage bearing to after reaching horizontal accuracy requirement The fastening bolt 7 between fastening bolt 7 and transfer beam 3 and bracket between bracket, realizes the fixation of bracket, total station is pacified On supporting plate 4.
Further, levelling rod 10 is provided on truss girder 5.It can determine whether truss girder 5 whether in water by levelling rod 10 Prosposition is set.10 precision 1mm of levelling rod.
Further, the position that the second mounting plate of truss girder 5 and lower anchorage bearing 2 contacts with each other is hair side, to increase Contact friction force between the two after tightening fastening bolt 7, prevents truss girder 5 and lower anchorage bearing 2 from shifting.
Further, the position that truss girder 5 and transfer beam 3 contact with each other is hair side, is rubbed with the contact for increasing between the two Power is wiped, after tightening fastening bolt 7, prevents truss girder 5 and transfer beam 3 from shifting.
Further, bracket, upper anchorage bearing 1, lower anchorage bearing 2 and transfer beam 3 are made of steel, and surface is coated with anti- Rust paint.Specifically, upper anchorage bearing 1 and lower anchorage bearing 2 are welded using wall thickness 10mm steel plate, are arranged to arc-shaped sections, in advance Stay diameter 8mm anchor hole;Anchor bolt 6 uses high-strength bolt, it is ensured that bolt is secured;Lower anchorage bearing strip-shaped hole 8 and transfer beam Strip-shaped hole 9 is 60mm long, wide 12mm;Bracket uses thickness 10mm high-quality steel, the reserved diameter 12mm centring hole in centre.
The above is only the embodiments of the present invention, and therefore it does not limit the scope of the patent of the utility model, all utilizations Equivalent structure or equivalent flow shift made by the utility model description is applied directly or indirectly in other relevant Technical field is also included in the patent protection scope of the utility model.

Claims (5)

1. a kind of shield tunnel vault total station mounting base, which is characterized in that including bracket, upper anchorage bearing, lower anchorage bearing And transfer beam;
The bracket includes the supporting plate for placing total station and two parallel truss girders being arranged under the supporting plate;
Centring hole is provided on the supporting plate;
The upper anchorage bearing and lower anchorage bearing include the first mounting plate and two second peaces perpendicular to the first mounting plate Loading board;
Anchor bolt is provided on first mounting plate;
Second mounting plate of the upper anchorage bearing is connected with transfer beam by fastening bolt;
The direction perpendicular to the first mounting plate is provided with lower anchorage bearing item on second mounting plate of the lower anchorage bearing Shape hole, the second mounting plate are connected by passing through the fastening bolt of lower anchorage bearing strip-shaped hole with truss girder;
Transfer beam strip-shaped hole is placed in the vertical direction in the transfer beam, transfer beam is by passing through the tight of transfer beam strip-shaped hole Fixing bolt is connected with truss girder, and transfer beam is located between supporting plate and lower anchorage bearing.
2. shield tunnel vault total station mounting base according to claim 1, which is characterized in that be arranged on the truss girder There is levelling rod.
3. shield tunnel vault total station mounting base according to claim 1, which is characterized in that the truss girder and cast anchor The position that second mounting plate of clamped seat contacts with each other is hair side.
4. shield tunnel vault total station mounting base according to claim 1 or 3, which is characterized in that the truss girder and The position that transfer beam contacts with each other is hair side.
5. shield tunnel vault total station mounting base according to claim 4, which is characterized in that the bracket, upper anchoring Support, lower anchorage bearing and transfer beam are made of steel, and surface is coated with anticorrosive paint.
CN201821931055.4U 2018-11-22 2018-11-22 A kind of shield tunnel vault total station mounting base Expired - Fee Related CN209040862U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821931055.4U CN209040862U (en) 2018-11-22 2018-11-22 A kind of shield tunnel vault total station mounting base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821931055.4U CN209040862U (en) 2018-11-22 2018-11-22 A kind of shield tunnel vault total station mounting base

Publications (1)

Publication Number Publication Date
CN209040862U true CN209040862U (en) 2019-06-28

Family

ID=67043199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821931055.4U Expired - Fee Related CN209040862U (en) 2018-11-22 2018-11-22 A kind of shield tunnel vault total station mounting base

Country Status (1)

Country Link
CN (1) CN209040862U (en)

Similar Documents

Publication Publication Date Title
CN106758787B (en) A kind of Precast Pier Columns mounting and positioning device
CN103643971B (en) Tunnel invert sizing end mould rapid constructing method
CN101418535A (en) Construction method of monolithic road-bed in rail tunnel
CN205296584U (en) Be applied to assembled constructional column of aerated concrete block infilled wall
CN102518300B (en) Embedded conical bearing joint type steel structural support and construction method thereof
CN202390730U (en) Fine adjustment device for mounting a track
CN102493471A (en) Suspending installation construction process method of structural foot margin anchor bolt
CN109878380A (en) A kind of metro depot rigid suspension OCS trackless pipeline construction method
CN101736660B (en) Method for manually paving rails of ballastless track
CN101985824A (en) Embedded part mounting device for bridge bearing
CN102926554B (en) Steel hanging seat shuttering supporting and construction method thereof
CN209040862U (en) A kind of shield tunnel vault total station mounting base
CN103603503A (en) Anchor bolt installing method
CN204553471U (en) A kind of foundation ditch tool type guard rail fixing bolt
CN103967052B (en) A kind of method of protecting the new and old frame core-tube system substrate discrepancy in elevation soil body
CN105735228B (en) High-lift tooth climbs formula ship lift rack system construction method and installation accuracy control method
CN101852066A (en) Device and method for arranging track of drilling machine
CN102995653A (en) Side-type high-precision rapid locator for foundation bolts
CN206830188U (en) Just prop up two lining contact measurement apparatus in tunnel
CN201747071U (en) Precast reinforced concrete column positioning device
CN101899541B (en) Method for mounting grid-type carbon-pounding scale of blast-furnace bottom leveling layer
CN202194303U (en) Bar spacer
CN111472283A (en) Construction method and structural system for ensuring installation accuracy of steel box girder of cable-stayed bridge
CN204921042U (en) Shield tunnel total powerstation installation hanging flower basket
CN101761138B (en) Installation method of complicated group anchors

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190628

Termination date: 20211122