Prior art keywords
block
splicing
splicing block
drainpipe
temporary construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821714262.4U
Other languages
Chinese (zh)
Inventor
郭雄伟
肖必建
陈旭
谢月明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Bureau Shanghai Corp Ltd
Original Assignee
China Construction Seventh Engineering Bureau Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Bureau Shanghai Corp Ltd filed Critical China Construction Seventh Engineering Bureau Shanghai Corp Ltd
Priority to CN201821714262.4U priority Critical patent/CN209039907U/en
Application granted granted Critical
Publication of CN209039907U publication Critical patent/CN209039907U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Abstract

The utility model discloses a kind of spliced temporary construction roads, including several splicing blocks, several splicing blocks mutually splice, the leading flank of splicing block is provided with the first fixture block, first fixture block includes the first skewback being obliquely installed and the first water-stop sheet positioned at the first skewback least significant end, the trailing flank of splicing block is provided with is being provided with the first drainpipe through splicing block with matched first card slot of the first fixture block, splicing block at the first water-stop sheet;The right side of splicing block is provided with the second fixture block, second fixture block includes the second skewback being obliquely installed and the second water-stop sheet positioned at the second skewback least significant end, the left side of splicing block is provided with is being provided with the second drainpipe through splicing block with matched second card slot of the second fixture block, splicing block at the second water-stop sheet.Spliced temporary construction road provided by the utility model, can recycled for multiple times, avoid the generation of building waste, improve work efficiency, while there is good drain function.

Description

A kind of spliced temporary construction road
Technical field
The utility model belongs to construction building field more particularly to a kind of spliced temporary construction road.
Background technique
When construction site is constructed, it is necessary first to have a construction road temporarily built, and according to the planning in place and construct into Degree, temporary construction road also need to abolish later, and replacement next time job location still needs to build temporary construction road when constructing Then road is abolished again, again and again, greatly waste man power and material, while broken road will form building waste, Environment is influenced, cleaning is also required to take a lot of time.
Based on this, the research of spliced temporary road is gradually increased, existing spliced temporary road is logical Multiple splicing blocks are crossed to be spliced.But temporary road spliced at present is less for the research of drain function, especially lacks Few drain function for different splicing block junctions causes entire road after the rainy day to impregnate in water, influences vehicle and pedestrian Traveling, while also shortening the service life of temporary road splicing block.
Utility model content
In order to solve the above technical problems, which solve splicings the utility model proposes a kind of spliced temporary construction road The problem of junction between block and splicing block can not drain.
In order to achieve the above object, the technical solution of the utility model is as follows: a kind of spliced temporary construction road, including Several splicing blocks, several splicing blocks mutually splice, and the splicing block is cuboid, and the leading flank of the splicing block is provided with First fixture block, first fixture block include the first skewback being obliquely installed and the first water-stop sheet positioned at the first skewback least significant end, The trailing flank of the splicing block be provided with matched first card slot of the first fixture block, the splicing block is at the first water-stop sheet It is provided with the first drainpipe through splicing block;
The right side of the splicing block is provided with the second fixture block, second fixture block include the second skewback being obliquely installed and Positioned at the second water-stop sheet of the second skewback least significant end, the left side of the splicing block is provided with and matched second card of the second fixture block Slot, the splicing block are being provided with the second drainpipe through splicing block at the second water-stop sheet.
Preferably, being provided with several the first road surface drainpipes communicated with the first drainpipe, institute in the splicing block The opening for stating the first road surface drainpipe is located at the top surface of splicing block.By using above-mentioned technical proposal, this spliced is temporarily applied Water above work road is introduced into the first drainpipe, improves the drainability on road surface.
Preferably, being provided with several the second road surface drainage pipes communicated with the second drainpipe, institute in the splicing block The opening for stating the second road surface drainage pipe is located at the top surface of splicing block.By using above-mentioned technical proposal, the spelling is further improved Connect the drainability of formula temporary construction road.
Preferably, the top surface of the splicing block is square.
Preferably, first fixture block is located at the top of the second fixture block.
Preferably, several the first perforation for running through splicing block leading flank and trailing flank are provided in the splicing block, Several are provided in the splicing block through the second perforation of splicing block left side and right side.Several splicing blocks are spliced Afterwards, steel pipe is inserted into all the first perforation and the second perforation.By using above-mentioned technical proposal, solves this and spliced face When construction road the problem of being easily bent, improve the stability of the spliced temporary construction road.
The utility model has the beneficial effects that spliced temporary construction road provided by the utility model, can repeatedly recycle benefit With avoiding the generation of building waste, improve work efficiency.Spliced temporary construction road provided by the utility model, tool Have good drain function, after rain road will not ponding, vehicle can normally travel, accelerate the progress of construction, while also increasing The service life of the spliced temporary construction road.
Detailed description of the invention
Fig. 1 is the axonometric drawing of the spliced temporary construction road splicing block of the utility model;
Fig. 2 is the left view of the spliced temporary construction road splicing block of the utility model;
Fig. 3 is the rearview of the spliced temporary construction road splicing block of the utility model;
Fig. 4 is the top view of the spliced temporary construction road splicing block of the utility model;
Fig. 5 is the sectional view at the spliced temporary construction road splicing block A-A of the utility model;
Fig. 6 is the sectional view at the spliced temporary construction road splicing block B-B of the utility model;
Fig. 7 is the structural schematic diagram of the spliced temporary construction road of the utility model;
Wherein: 1. splicing blocks, 2. first fixture blocks, 3. first skewbacks, 4. first water-stop sheets, 5. first card slots, 6. first rows Water pipe, 7. second fixture blocks, 8. second skewbacks, 9. second water-stop sheets, 10. second card slots, 11. second drainpipes, 12. first road surfaces Drainpipe, 13. second road surface drainage pipes, 14. first perforation, 15. second perforation.
Specific embodiment
The utility model is described in further detail With reference to embodiment.
In the description of the present invention, it should be noted that term "top", "left", "right", "vertical", "horizontal", The orientation or positional relationship of the instructions such as "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of retouching State the utility model and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation, with Specific orientation construction and operation, therefore should not be understood as limiting the present invention.In addition, term " first ", " second " It is used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
As shown in Figures 1 to 7, a kind of spliced temporary construction road, including several splicing blocks 1.
The spliced temporary construction road is consequently formed in the mutually splicing of several splicing blocks 1.Splicing block 1 is cuboid, is spelled The top surface for connecing block 1 is square.
The leading flank of splicing block 1 is provided with the first fixture block 2.First fixture block 2 includes the first skewback 3 being obliquely installed and is located at First water-stop sheet 4 of 3 least significant end of the first skewback.The trailing flank of splicing block 1 be provided with matched first card slot 5 of the first fixture block 2, Splicing block 1 is being provided with the first drainpipe 6 through splicing block 1 at the first water-stop sheet 4, and the first drainpipe 6 is horizontally disposed.
The right side of splicing block 1 is provided with the second fixture block 7, and the second fixture block 7 includes the second skewback 8 being obliquely installed and is located at Second water-stop sheet 9 of 8 least significant end of the second skewback, the left side of splicing block 1 are provided with and matched second card slot of the second fixture block 7 10, splicing block 1 is being provided with the second drainpipe 11 through splicing block 1 at the second water-stop sheet 9, and the second drainpipe 11 is horizontal Setting.First fixture block 2 is located at the top of the second fixture block 7.When splicing by the first fixture block 2 of splicing block 1 be located at the splicing Splicing is realized in the first card slot 5 cooperation of the splicing block 1 in the front of block 1, by the second fixture block 7 of a splicing block 1 be located at the splicing Splicing is realized in the second card slot 10 cooperation of the splicing block 1 of 1 right of block, and entire spliced temporary construction road is repeatedly formed after splicing Road.
Penetrate into two 1 junctions of splicing block water can along the first skewback 3 or the second skewback 8 to flowing down, by first every Water plate 4 or the second water-stop sheet 9 block, and water enters in the first drainpipe 6 or the second drainpipe 11.It is temporarily applied positioned at entirely spliced First drainpipe 6 of the splicing block 1 of work road edge and the second drainpipe 7 opening are exposed to outer, and water is from outermost splicing block 1 First drainpipe 6 and the outflow of the second drainpipe 7.
Several the first road surface drainpipes 12 communicated with the first drainpipe 6, the first road surface drainage are provided in splicing block 1 The opening of pipe 12 is located at the top surface of splicing block 1.Several the second road surfaces communicated with the second drainpipe 11 are provided in splicing block 1 Drainpipe 13, the opening of the second road surface drainage pipe 13 are located at the top surface of splicing block 1.First road surface drainpipe 12 and the second road surface row Water pipe 13 is vertically arranged.
Several are provided in splicing block 1 in the first perforation 14 of 1 leading flank of splicing block and trailing flank, splicing block 1 Several are provided with through the second perforation 15 of 1 left side of splicing block and right side.After the splicing of all splicing blocks 1, each spelling The first perforation 14 for connecing block 1 is interconnected to form a channel, is inserted into steel pipe in the channel that all first perforation 14 are formed.It will After all splicing blocks 1 splice, the second perforation 15 of each splicing block 1 is interconnected to form a channel, in all second perforation Steel pipe is inserted into 15 channels formed.The height of first perforation 14 and the second perforation 15 mutually staggers, and prevents steel pipe that can not be inserted into. First road surface drainpipe 12 and the second road surface drainage pipe 13 avoid the first perforation 14 and the second perforation 15 when being arranged, prevent water penetration It gets rusty into the first perforation 14 and the second perforation 15 so as to cause steel pipe.
The above description is only the embodiments of the present invention, and therefore it does not limit the scope of the patent of the utility model, all Using equivalent structure transformation made by the utility model description, it is applied directly or indirectly in other relevant technology necks Domain is also included in the patent protection scope of the utility model.

Claims (6)

1. a kind of spliced temporary construction road, including several splicing blocks (1), several splicing blocks (1) mutually splice, special Sign is that the splicing block (1) is cuboid, and the leading flank of the splicing block (1) is provided with the first fixture block (2), described first Fixture block (2) includes the first skewback (3) being obliquely installed and the first water-stop sheet (4) for being located at the first skewback (3) least significant end, the spelling Connect block (1) trailing flank be provided with matched first card slot (5) of the first fixture block (2), the splicing block (1) close to first every The first drainpipe (6) through splicing block (1) is provided at water plate (4);
The right side of the splicing block (1) is provided with the second fixture block (7), and second fixture block (7) includes second be obliquely installed Skewback (8) and the second water-stop sheet (9) for being located at the second skewback (8) least significant end, the left side of the splicing block (1) are provided with and the Matched second card slot (10) of two fixture blocks (7), the splicing block (1) are being provided at the second water-stop sheet (9) through splicing The second drainpipe (11) of block (1).
2. spliced temporary construction road according to claim 1, which is characterized in that be provided in the splicing block (1) Several the first road surface drainpipes (12) communicated with the first drainpipe (6), the opening position of first road surface drainpipe (12) In the top surface of splicing block (1).
3. spliced temporary construction road according to claim 2, which is characterized in that be provided in the splicing block (1) Several the second road surface drainage pipes (13) communicated with the second drainpipe (11), the opening position of the second road surface drainage pipe (13) In the top surface of splicing block (1).
4. spliced temporary construction road according to claim 3, which is characterized in that the top surface of the splicing block (1) is Square.
5. spliced temporary construction road according to claim 1, which is characterized in that first fixture block (2) is located at the The top of two fixture blocks (7).
6. spliced temporary construction road according to claim 1, which is characterized in that be provided in the splicing block (1) Several perforate (14) through the first of splicing block (1) leading flank and trailing flank, are provided with several in the splicing block (1) and pass through Wear the second perforation (15) of splicing block (1) left side and right side.
CN201821714262.4U 2018-10-23 2018-10-23 A kind of spliced temporary construction road Expired - Fee Related CN209039907U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821714262.4U CN209039907U (en) 2018-10-23 2018-10-23 A kind of spliced temporary construction road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821714262.4U CN209039907U (en) 2018-10-23 2018-10-23 A kind of spliced temporary construction road

Publications (1)

Publication Number Publication Date
CN209039907U true CN209039907U (en) 2019-06-28

Family

ID=67036997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821714262.4U Expired - Fee Related CN209039907U (en) 2018-10-23 2018-10-23 A kind of spliced temporary construction road

Country Status (1)

Country Link
CN (1) CN209039907U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113668323A (en) * 2021-07-23 2021-11-19 上海宝冶集团有限公司 Construction method for precast concrete antiskid plate surface with drainage system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113668323A (en) * 2021-07-23 2021-11-19 上海宝冶集团有限公司 Construction method for precast concrete antiskid plate surface with drainage system

Similar Documents

Publication Publication Date Title
CN103821180B (en) The two water-stopping structure of a kind of concrete extension joint
CN103541310A (en) Long-united bridge widening splicing structure and construction method thereof
CN202493277U (en) Preventive collecting system for leaking water and seeping water in tunnel
CN109695359A (en) A kind of missile silo cartridge type solid bicycle/electric vehicle library and its construction method
CN102943678A (en) Arched subway station old and new building connection structure and construction method
CN209039907U (en) A kind of spliced temporary construction road
CN104195913A (en) Movable temporary road structure
CN109083203A (en) A kind of vertical laying method of HDPE film
CN113106879B (en) Connecting structure for widening concrete box girder by steel box girder and construction method
CN206941413U (en) A kind of support integral slipping system for concrete girder construction
KR102258378B1 (en) Transverse drain pipe of apparatus for draining wastewater of bridge and construction method thereof
CN210830796U (en) Small-size utility tunnel device on bridge central authorities' division strip
CN209129029U (en) A kind of subway cover and cut method station bracing members lifting system
CN204676560U (en) The support changing structure for use of foundation ditch mid-board
CN110701389B (en) Small-size utility tunnel device on bridge central authorities median
CN102587938A (en) Water seepage and leakage preventability collection system for tunnel and construction method of system
CN203530865U (en) Long-connection bridge widening splicing structure
CN105804215A (en) Spliced drainage ditch
CN209053103U (en) Facilitate the assembled steel sheet pile purlin connection structure removed
CN104727276A (en) Manufacturing method for concrete expansion joint dual waterstop structure
CN219886951U (en) Waterproof device for road deformation joint part
CN218643239U (en) Cut bamboo formula ripple culvert pipe entrance to a cave and strengthen device
CN208982090U (en) A kind of acnemia air crossing for coal mine roadway
CN213359414U (en) Constructional column concrete placement instrument
CN212670174U (en) Prefabricated road of spelling formula

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190628