CN104195913A - Movable temporary road structure - Google Patents

Movable temporary road structure Download PDF

Info

Publication number
CN104195913A
CN104195913A CN201410406965.0A CN201410406965A CN104195913A CN 104195913 A CN104195913 A CN 104195913A CN 201410406965 A CN201410406965 A CN 201410406965A CN 104195913 A CN104195913 A CN 104195913A
Authority
CN
China
Prior art keywords
prefabricated
precast plate
gutter
drainage
road structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410406965.0A
Other languages
Chinese (zh)
Inventor
张凤勇
杨才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
CMTCC Shanghai Shisanye Construction Co Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
CMTCC Shanghai Shisanye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd, CMTCC Shanghai Shisanye Construction Co Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201410406965.0A priority Critical patent/CN104195913A/en
Publication of CN104195913A publication Critical patent/CN104195913A/en
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention relates to the field of temporary construction measures in constructional engineering, and in particular relates to a movable temporary road structure. The movable temporary road structure is characterized by comprising a middle prefabricated slab, continuously-paved prefabricated drainage ditches located at two sides of the middle prefabricated slab, and a prefabricated drainage settling well communicated with the prefabricated drainage ditches, wherein the prefabricated drainage settling well is arranged at the end of an open drainage ditch formed by the prefabricated drainage ditches paved continuously, and the prefabricated drainage settling well is finally connected with a drainage system by a drainage pipeline. The movable temporary road structure is easy to manufacture, is convenient to install and is simple to operate by adopting the above parts and the method, and can be used for temporary roads in various construction sites; all components can be cycled; and compared with the traditional temporary roads in the construction site, the movable temporary road structure has the advantages that the construction progress is accelerated, and a great amount of materials and the construction cost are saved, therefore, the movable temporary road structure has good economic and social benefits.

Description

Temporary road structure movably
Technical field
The present invention relates to the field of construction work temporary construction measure, be specially a kind of movably temporary road structure.
Background technology
In construction work, often ground level road is destroyed, road surface is uneven and have hole, many holes, and pedestrian very easily falls down in its surface walking, therefore has potential safety hazard, and due to road surface excavation, original discharge structure is damaged, run into the continuous rainy day, a large amount of rainwater are easily accumulated on construction road surface, cannot get rid of, also to construction operation, make troubles.
Summary of the invention
The object of the invention is to, provide a kind of for movably road structure temporary construction measure, that can be recycled.
In order to achieve the above object, the present invention is achieved in that
A temporary road structure movably, it comprises the middle part precast plate of polylith continuous laying and is positioned at the prefabricated gutter of continuous laying of precast plate both sides, middle part and the prefabricated drainage sedimentation well being communicated with prefabricated gutter; Described middle part precast plate is "the" shape, and during the precast plate continuous laying of middle part, the head end of a rear middle part precast plate is overlapped on the tail end of last middle part precast plate, forms by that analogy and finally target road; The dual-side of middle part precast plate is provided with for the lapping with the side lap of prefabricated gutter, it is pressed on the side in prefabricated gutter, prefabricated gutter also has a plurality of, target road that it forms along middle part precast plate continuous laying and continuous laying the seam crossing forming between each prefabricated gutter, open drain are filled up by cement mortar, the termination of the formed open drain of continuous laying, prefabricated gutter is provided with prefabricated drainage sedimentation well, and prefabricated drainage sedimentation well is finally connected with existing drainage system by drainage pipe.
For ease of manufacturing and thering is sufficient intensity, described movably temporary road structure, described middle part precast plate is reinforced concrete structure, the knuckle arris place of its head end and tail end is equipped with metal hemming edge, this metal hemming edge and cage of reinforcement welding.
For meeting draining demand, described movably temporary road structure, described prefabricated drainage sedimentation well is two-stage precipitation structure, it comprises one-level water inlet, dividing plate, open on dividing plate and be positioned at secondary water inlet and the delivery port of one-level water inlet top, and the termination of open drain is connected with one-level water inlet.
A laying method for movably temporary road structure claimed in claim 1, it comprises the steps;
Step 1, by design planning route, with polylith middle part precast plate continuous laying, form target road;
Step 2, when laying target road with polylith middle part precast plate, in the prefabricated gutter of both sides continuous laying of each middle part precast plate;
Step 3, the seam crossing in each prefabricated gutter arrive outside with cement mortar filling chink to prevent the seepage in gutter;
The end of step 4, the open drain that forms at prefabricated gutter continuous laying arranges prefabricated drainage sedimentation well;
Step 5, prefabricated drainage sedimentation well is connected with existing drainage system by gutter.
The present invention adopts above-mentioned parts and method, it is made easily, easy for installation, simple to operate, the temporary road that can be used for all kinds of construction sites, various members can have enough to meet the need use, and relatively traditional building site temporary road can accelerating construction progress, save lot of materials and reduce construction cost, there is good economic benefit and social benefit.
Accompanying drawing explanation
Fig. 1 is precast slab for roads organigram one.
Fig. 2 is precast slab for roads organigram two.
Fig. 3 is prefabricated gutter scheme of installation one.
Fig. 4 is prefabricated gutter scheme of installation two.
Fig. 5 is prefabricated gutter and prefabricated drainage sedimentation well scheme of installation one.
Fig. 6 is prefabricated gutter and prefabricated drainage sedimentation well scheme of installation two.
Fig. 7 is that precast slab for roads suspension hook arranges schematic diagram one.
Fig. 8 is that precast slab for roads suspension hook arranges schematic diagram two.
Fig. 9 is that precast slab for roads stacks schematic diagram.
Figure 10 is whole road pavement schematic diagram one.
Figure 11 is whole road pavement schematic diagram two.
The specific embodiment
By specific embodiment, further illustrate the present invention below.
As shown in Fig. 1 ~ Figure 11, a kind of movably temporary road structure, it comprises the middle part precast plate 7 of polylith continuous laying and is positioned at the prefabricated gutter 2 of continuous laying of precast plate 7 both sides, middle part and the prefabricated drainage sedimentation well 3 being communicated with prefabricated gutter 2; Described middle part precast plate 7 is "the" shape, and during precast plate 7 continuous laying of middle part, the head end of a rear middle part precast plate 7 is overlapped on the tail end of last middle part precast plate 7, forms by that analogy and finally target road; The dual-side of middle part precast plate 7 is provided with for the lapping with 2 side laps of prefabricated gutter, it is pressed on the side in prefabricated gutter 2, prefabricated gutter 2 also has a plurality of, target road that it forms along middle part precast plate 7 continuous layings and continuous laying the seam crossing forming between each prefabricated gutter 2, open drain are filled up by cement mortar, the termination of the 2 formed open drains of continuous laying, prefabricated gutter is provided with prefabricated drainage sedimentation well 3, and prefabricated drainage sedimentation well 3 is finally connected with existing drainage system by drainage pipe.
For ease of manufacturing and thering is sufficient intensity, described movably temporary road structure, described middle part precast plate 7 is reinforced concrete structure, the knuckle arris place of its head end and tail end is equipped with metal hemming edge 4,6, this metal hemming edge 4,6 and cage of reinforcement 5 welding.
For meeting draining demand, described movably temporary road structure, described prefabricated drainage sedimentation well 3 is two-stage precipitation structure, it comprises one-level water inlet a, dividing plate, open on dividing plate and be positioned at secondary water inlet b and the delivery port c of one-level water inlet a top, and the termination of open drain is connected with one-level water inlet a.
For ease of transportation, the front end of middle part precast plate 7 is provided with suspension hook 8, and every arranges a pair ofly, and positive and negative is symmetrical arranged.Suspension hook 8 adopts round steel to make and is anchored in concrete, on middle part precast plate 7 surfaces, is provided with circular notch, and suspension hook annulus is arranged in notch and lower than precast plate surface.Suspension hook 8 for storing, transportation, coordinate loop wheel machine to use while installing, middle part precast plate 7 stores or can positive and negatively stack during transportation, is conducive to conserve space.
A laying method for movably temporary road structure claimed in claim 1, it comprises the steps;
Step 1, by design planning route, with polylith middle part precast plate continuous laying, form target road;
Step 2, when laying target road with polylith middle part precast plate, in the prefabricated gutter of both sides continuous laying of each middle part precast plate;
Step 3, the seam crossing in each prefabricated gutter arrive outside with cement mortar filling chink to prevent the seepage in gutter;
The end of step 4, the open drain that forms at prefabricated gutter continuous laying arranges prefabricated drainage sedimentation well;
Step 5, prefabricated drainage sedimentation well is connected with existing drainage system by gutter.
The present invention adopts above-mentioned parts and method, it is made easily, easy for installation, simple to operate, the temporary road that can be used for all kinds of construction sites, various members can have enough to meet the need use, and relatively traditional building site temporary road can accelerating construction progress, save lot of materials and reduce construction cost, there is good economic benefit and social benefit.

Claims (4)

1. a temporary road structure movably, is characterized in that: it comprises the middle part precast plate of polylith continuous laying and is positioned at the prefabricated gutter of continuous laying of precast plate both sides, middle part and the prefabricated drainage sedimentation well being communicated with prefabricated gutter; Described middle part precast plate is "the" shape, and during the precast plate continuous laying of middle part, the head end of a rear middle part precast plate is overlapped on the tail end of last middle part precast plate, forms by that analogy and finally target road; The dual-side of middle part precast plate is provided with for the lapping with the side lap of prefabricated gutter, it is pressed on the side in prefabricated gutter, prefabricated gutter also has a plurality of, target road that it forms along middle part precast plate continuous laying and continuous laying the seam crossing forming between each prefabricated gutter, open drain are filled up by cement mortar, the termination of the formed open drain of continuous laying, prefabricated gutter is provided with prefabricated drainage sedimentation well, and prefabricated drainage sedimentation well is finally connected with existing drainage system by drainage pipe.
2. movably temporary road structure according to claim 1, is characterized in that: described middle part precast plate is reinforced concrete structure, and the knuckle arris place of its head end and tail end is equipped with metal hemming edge, this metal hemming edge and cage of reinforcement welding.
3. movably temporary road structure according to claim 1, it is characterized in that: described prefabricated drainage sedimentation well is two-stage precipitation structure, it comprises one-level water inlet, dividing plate, open on dividing plate and be positioned at secondary water inlet and the delivery port of one-level water inlet top, and the termination of open drain is connected with one-level water inlet.
4. a laying method for movably temporary road structure claimed in claim 1, is characterized in that: it comprises the steps;
Step 1, by design planning route, with polylith middle part precast plate continuous laying, form target road;
Step 2, when laying target road with polylith middle part precast plate, in the prefabricated gutter of both sides continuous laying of each middle part precast plate;
Step 3, the seam crossing in each prefabricated gutter arrive outside with cement mortar filling chink to prevent the seepage in gutter;
The end of step 4, the open drain that forms at prefabricated gutter continuous laying arranges prefabricated drainage sedimentation well;
Step 5, prefabricated drainage sedimentation well is connected with existing drainage system by gutter.
CN201410406965.0A 2014-08-19 2014-08-19 Movable temporary road structure Pending CN104195913A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410406965.0A CN104195913A (en) 2014-08-19 2014-08-19 Movable temporary road structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410406965.0A CN104195913A (en) 2014-08-19 2014-08-19 Movable temporary road structure

Publications (1)

Publication Number Publication Date
CN104195913A true CN104195913A (en) 2014-12-10

Family

ID=52081266

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410406965.0A Pending CN104195913A (en) 2014-08-19 2014-08-19 Movable temporary road structure

Country Status (1)

Country Link
CN (1) CN104195913A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201129A (en) * 2014-09-29 2015-12-30 中建四局第三建筑工程有限公司 Precast slab and production method thereof
CN105952449A (en) * 2016-05-10 2016-09-21 中钢集团马鞍山矿山研究院有限公司 Novel dry-type stoping method for tailings in tailing pond
CN106012751A (en) * 2016-06-13 2016-10-12 上海建工七建集团有限公司 Integrated prefabricating construction method for roads, drainage ditches and foundations of enclosing walls
CN107740321A (en) * 2017-09-07 2018-02-27 中国十七冶集团有限公司 A kind of arc interface assembly precast concrete pavement
CN108385468A (en) * 2018-05-04 2018-08-10 中国建筑第四工程局有限公司 A kind of I-shaped glass-fiber reinforced plastic grille construction site temporary pavement and construction method
CN108457148A (en) * 2018-03-21 2018-08-28 中国冶集团有限公司 A kind of multi-functional temporary road structure of assembled and its construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3712187A (en) * 1970-08-05 1973-01-23 W Stelling Prefabricated highway system
CN1044141A (en) * 1990-02-20 1990-07-25 郑亚华 A kind of reinforced concrete prefabricated board
CN2392807Y (en) * 1999-08-30 2000-08-23 容文添 General combined road structural member
JP2004092240A (en) * 2002-08-30 2004-03-25 Artrock:Kk Paving block material and pavement structure using the same
KR20100081876A (en) * 2009-01-07 2010-07-15 조수연 Concrete block for pavement of a road and it's working process
CN101830577A (en) * 2010-05-19 2010-09-15 环境保护部华南环境科学研究所 Rainwater treatment device for rainwater and sewage runoff pollution treatment and method thereof
CN202073005U (en) * 2011-04-15 2011-12-14 中天建设集团有限公司 Shaped road module

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3712187A (en) * 1970-08-05 1973-01-23 W Stelling Prefabricated highway system
CN1044141A (en) * 1990-02-20 1990-07-25 郑亚华 A kind of reinforced concrete prefabricated board
CN2392807Y (en) * 1999-08-30 2000-08-23 容文添 General combined road structural member
JP2004092240A (en) * 2002-08-30 2004-03-25 Artrock:Kk Paving block material and pavement structure using the same
KR20100081876A (en) * 2009-01-07 2010-07-15 조수연 Concrete block for pavement of a road and it's working process
CN101830577A (en) * 2010-05-19 2010-09-15 环境保护部华南环境科学研究所 Rainwater treatment device for rainwater and sewage runoff pollution treatment and method thereof
CN202073005U (en) * 2011-04-15 2011-12-14 中天建设集团有限公司 Shaped road module

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陆建飞等: "工地定型化施工道路研究与应用", 《施工技术》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201129A (en) * 2014-09-29 2015-12-30 中建四局第三建筑工程有限公司 Precast slab and production method thereof
CN105952449A (en) * 2016-05-10 2016-09-21 中钢集团马鞍山矿山研究院有限公司 Novel dry-type stoping method for tailings in tailing pond
CN106012751A (en) * 2016-06-13 2016-10-12 上海建工七建集团有限公司 Integrated prefabricating construction method for roads, drainage ditches and foundations of enclosing walls
CN107740321A (en) * 2017-09-07 2018-02-27 中国十七冶集团有限公司 A kind of arc interface assembly precast concrete pavement
CN108457148A (en) * 2018-03-21 2018-08-28 中国冶集团有限公司 A kind of multi-functional temporary road structure of assembled and its construction method
CN108457148B (en) * 2018-03-21 2020-10-23 中国一冶集团有限公司 Assembled multifunctional temporary road structure and construction method thereof
CN108385468A (en) * 2018-05-04 2018-08-10 中国建筑第四工程局有限公司 A kind of I-shaped glass-fiber reinforced plastic grille construction site temporary pavement and construction method

Similar Documents

Publication Publication Date Title
CN104195913A (en) Movable temporary road structure
CN107059667B (en) Door shape assembled armored concrete box culvert and its construction method
CN104213514B (en) A kind of earthing corrugated steel-concrete combination arch bridge add strong method
CN104060631B (en) A kind of manhole mouth elevation Dynamic controlling structure
CN104727302B (en) Board wall cast-in-place construction technique between a kind of friction pile stake
CN104313967B (en) Row's water-seepage type is mated formation combining structure
CN105908639A (en) Prefabricated box culvert and rapid positioning construction method
CN206635599U (en) A kind of road surface for caving in road, which is speedily carried out rescue work, fixes device
CN103343503B (en) Bridge-type prefabricated reinforced concrete trough slab wear resistant road surface structural system and construction method
CN206495233U (en) Door shape assembled armored concrete box culvert
CN201943093U (en) Settlement joint water-proof structure for basement with drainage channel
CN205259214U (en) Pin -connected panel rainwater regulation pond of method of sinking construction
CN202139545U (en) Steel-structure culvert opening
CN104233914A (en) Construction method of portable type country road hardened pavement
CN110056071B (en) Municipal rainwater pipeline assembly module and construction method
CN104314104B (en) Deformation joint setting method for oblique crossing with underground box culvert
CN204491342U (en) A kind of prefabricated concrete road plate
CN105926665A (en) Prefabricated large-sized building block assembly type concrete drainage pipeline base and construction method thereof
CN106088142B (en) A kind of prefabricated assembled pipeline foundation and its assembly method
CN204551521U (en) The cast-in-place construction structure of board wall between a kind of antislide pile stake
CN201406755Y (en) Corrugated pipe seepage well
CN203768753U (en) Bridge type steel plate pavement system
CN203429528U (en) Bridge-type precast-reinforced-concrete-trough-plate wear-resistant pavement structure system
CN109811612B (en) Gutter treatment permanent-temporary combined channel structure and construction method thereof
CN208885303U (en) A kind of cap excavation method pipe gallery supporting construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20141210