CN209011316U - A kind of novel fabricated primary and secondary beam connecting node - Google Patents

A kind of novel fabricated primary and secondary beam connecting node Download PDF

Info

Publication number
CN209011316U
CN209011316U CN201821536539.9U CN201821536539U CN209011316U CN 209011316 U CN209011316 U CN 209011316U CN 201821536539 U CN201821536539 U CN 201821536539U CN 209011316 U CN209011316 U CN 209011316U
Authority
CN
China
Prior art keywords
secondary beam
bolt
girder
connecting node
mounting groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821536539.9U
Other languages
Chinese (zh)
Inventor
陈旭东
刘运林
王子恒
王若愚
王霁云
丁山东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui University of Architecture
Original Assignee
Anhui University of Architecture
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui University of Architecture filed Critical Anhui University of Architecture
Priority to CN201821536539.9U priority Critical patent/CN209011316U/en
Application granted granted Critical
Publication of CN209011316U publication Critical patent/CN209011316U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a kind of novel fabricated masters, secondary beam connecting node, including girder, the two sides in girder middle position offer beam slot, the two sides of beam slot are uniformly provided with connection jack, the first secondary beam and the second secondary beam are respectively arranged in beam slot, the middle position of first secondary beam and the second secondary beam offers mounting groove, first secondary beam and the second secondary beam are uniformly provided with screw jack inside the side of girder, one end of screw jack is through mounting groove, running through in screw jack has bolt, the middle position of bolt through connection jack, the both ends that bolt is located inside mounting groove are threaded with nut, the utility model relates to building girder technical fields.The novel fabricated primary and secondary beam connecting node and attaching method thereof, reach and has promoted its bearing capacity and globality, primary and secondary girder connection joint efficiency is improved simultaneously, further improves the prefabricated rate and assembly rate of connecting node, promotes the purpose of building industry modernization development.

Description

A kind of novel fabricated primary and secondary beam connecting node
Technical field
The utility model relates to building girder technical field, specially a kind of novel fabricated primary and secondary beam connecting node.
Background technique
By bearing support, the external force of receiving is known as beam based on cross force and shearing to be bent into the component of primary deformable. Joist support support the total weight of component and roofing in building upper boom, be to build portion mostly important in upper boom Point.Difference according to the specific location of beam, detail shape, specific effect etc. has different titles.The direction of most of beams, all with The cross section of building is consistent.
Beam is subject to vertical load, by the component based on curved.Beam mean level is placed, and is used to support plate and receiving plate passes The self weight of the various vertical loads and beam that come, Liang Heban collectively constitute the flooring and roof structure of building.With it is other laterally by Power structure (such as truss, arch etc.) is compared, and the stress performance of beam is poor, but it is analyzed simply, easy to make, therefore in Middle Or Small Span It is still widely applied in degree building.Beam is primarily subjected to moment of flexure and shearing in load action, is also subjected to torque sometimes.
Beam is the component often occurred in building structure.In frame structure, beam is integral the column connection of all directions, In wall construction, two wall limbs are connected, are allowed to work together by coupling beam above hole.As the important of Aseismic Design Component plays a part of the first line of defence.In frame shear wall structure, effect in Liang Jiyou frame structure, while also having Effect in shear wall structure.
It is pasted between primary and secondary beam by cement mortar at present, junction, which is easy to be affected by temperature, slight crack occurs, causes The connection of primary and secondary beam loosens, to reduce bearing capacity and globality, and prefabricated rate and assembly rate are lower.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, the utility model provide a kind of novel fabricated primary and secondary beam connecting node and its Connection method is solved and is pasted between current primary and secondary beam by cement mortar, and junction, which is easy to be affected by temperature, to be split Trace causes the connection of primary and secondary beam to loosen, to reduce bearing capacity and globality, and prefabricated rate and the lower problem of assembly rate.
(2) technical solution
In order to achieve the above object, the utility model is achieved by the following technical programs: a kind of novel fabricated primary and secondary Beam connecting node, including girder, the two sides in the girder middle position offer beam slot, and the two sides of the beam slot uniformly open up There is connection jack, be respectively arranged with the first secondary beam and the second secondary beam in the beam slot, in first secondary beam and the second secondary beam Between position offer mounting groove, first secondary beam and the second secondary beam are uniformly provided with bolt inside the side of girder and insert Hole, one end of the screw jack is through mounting groove, through having bolt, the middle position of the bolt in the screw jack Through connection jack, the both ends that the bolt is located inside mounting groove are threaded with nut.
Preferably, the connection jack is correspondingly arranged with screw jack.
Preferably, the width and height of a secondary beam and the second secondary beam are consistent with beam groove width and height.
Preferably, the bolt material uses low-carbon alloy steel, and bolt thread precision uses 3A class precision.
Preferably, the connection method of a kind of novel fabricated primary and secondary beam connecting node, which is characterized in that including with Lower step:
Step 1: slotting in the top surface of the first secondary beam and the second secondary beam, open up out mounting groove, and in the first secondary beam and Second of beam sides punching, so that screw jack extends to inside mounting groove;
Step 2: the two sides at the top of girder open up two beam slots, the height and width of beam slot and a secondary beam and second Beam is consistent;
Step 3: the first secondary beam and the second secondary beam after step 1 is processed are inserted into beam slot respectively, and bolt is successively worn Screw jack and connection jack are crossed, bolt both ends are fixed by nut, form the secondary beam on both sides to tension state, and check flat Whole degree and verticality;
Step 4: slurry is poured to the position between the rest of mounting groove and the first secondary beam, the second secondary beam, girder, After filling up completely, grout material solidification is waited.
Preferably, bolt quantity quantification according to needed for engineering is set in step 3.
Preferably, slurry uses water proof building slurry in step 4.
(3) beneficial effect
The utility model provides a kind of novel fabricated primary and secondary beam connecting node and attaching method thereof.Having following has Beneficial effect:
The novel fabricated primary and secondary beam connecting node and attaching method thereof, passes through the top of the first secondary beam and the second secondary beam Surface fluting opens up out mounting groove, and in the first secondary beam and second of beam sides punching, so that screw jack extends to mounting groove Inside, the two sides at the top of girder open up two beam slots, and the height and width of beam slot are consistent with a secondary beam and the second secondary beam, The first secondary beam and the second secondary beam after step 1 is processed are inserted into beam slot respectively, and by screw bolt passes screw jack and connection Jack, bolt both ends are fixed by nut, form the secondary beam on both sides to tension state, and check flatness and verticality, to The rest of mounting groove and the first secondary beam, the second secondary beam, the position between girder pour slurry, after filling up completely, wait note Slurry solidification, this process first pass through bolt and pre-fix primary and secondary beam, fix by pouring reinforcement, having reached promotion, it holds Power and globality are carried, while improving primary and secondary girder connection joint efficiency, further improves the prefabricated rate and assembly of connecting node Rate promotes the purpose of building industry modernization development.
Detailed description of the invention
Fig. 1 is the three dimensional structure diagram of the utility model entirety;
Fig. 2 is the top view of the utility model entirety;
Fig. 3 is the side view of the utility model girder;
Fig. 4 is the cross-sectional view at the utility model A-A.
In figure: 1 girder, 2 first secondary beams, 3 second secondary beams, 4 bolts, 5 nuts, 6 mounting grooves, 7 beam slots, 8 screw jacks, 9 Connect jack.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-4 is please referred to, the utility model provides a kind of technical solution: a kind of novel fabricated primary and secondary beam connecting node, Including girder 1, the two sides in 1 middle position of girder offer beam slot 7, and the two sides of beam slot 7 are uniformly provided with connection jack 9, beam It is respectively arranged with the first secondary beam 2 and the second secondary beam 3 in slot 7, the middle position of the first secondary beam 2 and the second secondary beam 3 offers peace Tankage 6, the first secondary beam 2 and the second secondary beam 3 are uniformly provided with screw jack 8 inside the side of girder 1, screw jack 8 One end is through mounting groove 6, and through there is a bolt 4 in screw jack 8, the middle position of bolt 4 is through connection jack 9, bolt 4 Both ends inside mounting groove 6 are threaded with nut 5.Connection jack 9 is correspondingly arranged with screw jack 8.First secondary beam 2 It is consistent with 7 width of beam slot and height with the width and height of the second secondary beam 3.4 material of bolt uses low-carbon alloy steel, and And 4 accuracy of thread of bolt uses 3A class precision.
A kind of connection method of novel fabricated primary and secondary beam connecting node, which comprises the following steps:
Step 1: slotting in the top surface of the first secondary beam 2 and the second secondary beam 3, mounting groove 6 is opened up out, and for the first time Beam 2 and the punching of 3 side of the second secondary beam, so that screw jack 8 extends to inside mounting groove 6;
Step 2: opening up two beam slots 7, the height and width of beam slot 7 and a secondary beam 2 and the in the two sides at the top of girder 1 Two secondary beams 3 are consistent;
Step 3: the first secondary beam 2 and the second secondary beam 3 after step 1 is processed are inserted into beam slot 7 respectively, and by bolt 4 according to Secondary to pass through screw jack 8 and connection jack 9,4 both ends of bolt pass through nut 5 and fix, and form the secondary beam on both sides to tension state, And check flatness and verticality;
Step 4: pouring slurry to the position between the rest of mounting groove 6 and the first secondary beam 2, the second secondary beam 3, girder 1 Material after filling up completely, waits grout material solidification.4 quantity of bolt quantification according to needed for engineering is set in step 3.Step 4 Middle slurry uses water proof building slurry.
In use, slotting in the top surface of the first secondary beam 2 and the second secondary beam 3, mounting groove 6 is opened up out, and for the first time Beam 2 and the punching of 3 side of the second secondary beam open up two in the two sides at 1 top of girder so that screw jack 8 extends to inside mounting groove 6 A beam slot 7, the height and width of beam slot 7 are consistent with a secondary beam 2 and the second secondary beam 3, the first time after step 1 is processed Beam 2 and the second secondary beam 3 are inserted into beam slot 7 respectively, and bolt 4 is sequentially passed through screw jack 8 and connection jack 9, and 4 both ends of bolt are equal It is fixed by nut 5, form the secondary beam on both sides to tension state, the setting of 4 quantity of bolt quantification according to needed for engineering, and examine Flatness and verticality are looked into, is poured to the position between the rest of mounting groove 6 and the first secondary beam 2, the second secondary beam 3, girder 1 Slurry after filling up completely, waits grout material solidification.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.In the absence of more restrictions.By sentence " element limited including one ..., it is not excluded that There is also other identical elements in the process, method, article or apparatus that includes the element ".
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (4)

1. a kind of novel fabricated primary and secondary beam connecting node, including girder (1), it is characterised in that: girder (1) interposition The two sides set offer beam slot (7), and the two sides of the beam slot (7) are uniformly provided with connection jack (9), and the beam slot (7) is interior It is respectively arranged with the first secondary beam (2) and the second secondary beam (3), the middle position of first secondary beam (2) and the second secondary beam (3) is opened Equipped with mounting groove (6), first secondary beam (2) and the second secondary beam (3) are uniformly provided with bolt inside the side of girder (1) Jack (8), one end of the screw jack (8) is through mounting groove (6), through there is bolt (4) in the screw jack (8), Through connection jack (9), the bolt (4) is located at the internal equal spiral shell in both ends of mounting groove (6) in the middle position of the bolt (4) Line is connected with nut (5).
2. a kind of novel fabricated primary and secondary beam connecting node according to claim 1, it is characterised in that: the connection is inserted Hole (9) is correspondingly arranged with screw jack (8).
3. a kind of novel fabricated primary and secondary beam connecting node according to claim 1, it is characterised in that: the first time The width and height of beam (2) and the second secondary beam (3) are consistent with beam slot (7) width and height.
4. a kind of novel fabricated primary and secondary beam connecting node according to claim 1, it is characterised in that: the bolt (4) Material uses low-carbon alloy steel, and bolt (4) accuracy of thread uses 3A class precision.
CN201821536539.9U 2018-09-19 2018-09-19 A kind of novel fabricated primary and secondary beam connecting node Expired - Fee Related CN209011316U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821536539.9U CN209011316U (en) 2018-09-19 2018-09-19 A kind of novel fabricated primary and secondary beam connecting node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821536539.9U CN209011316U (en) 2018-09-19 2018-09-19 A kind of novel fabricated primary and secondary beam connecting node

Publications (1)

Publication Number Publication Date
CN209011316U true CN209011316U (en) 2019-06-21

Family

ID=66833645

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821536539.9U Expired - Fee Related CN209011316U (en) 2018-09-19 2018-09-19 A kind of novel fabricated primary and secondary beam connecting node

Country Status (1)

Country Link
CN (1) CN209011316U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108999297A (en) * 2018-09-19 2018-12-14 安徽建筑大学 A kind of novel fabricated primary and secondary beam connecting node and attaching method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108999297A (en) * 2018-09-19 2018-12-14 安徽建筑大学 A kind of novel fabricated primary and secondary beam connecting node and attaching method thereof

Similar Documents

Publication Publication Date Title
CN108999297A (en) A kind of novel fabricated primary and secondary beam connecting node and attaching method thereof
CN211873350U (en) Assembled type through bolt unequal-height beam-square steel tube concrete column joint structure
CN206903022U (en) A kind of steel bar truss floor support plate
CN111058543A (en) Connecting structure and mounting method of concrete slab and steel beam
CN115653098B (en) Assembled reinforced concrete beam-column connection structure and construction method thereof
CN209011316U (en) A kind of novel fabricated primary and secondary beam connecting node
CN209837314U (en) Prefabricated assembled wallboard node quick connect structure
CN211548015U (en) Prefabricated assembled steel-concrete composite beam
CN217870942U (en) Beam column connecting structure
CN209011313U (en) A kind of novel prefabricated primary and secondary beam composite joint node
CN110924426A (en) Bottom-expanding cup-mouth type connecting structure and method for reinforced concrete column and foundation
CN115680116A (en) Assembled frame beam column connecting node and construction method thereof
CN108978890B (en) Prefabricated main beam and secondary beam composite connection node and connection method thereof
CN214614773U (en) Prefabricated concrete shear wall-ring beam connection structure based on PBL
CN212336323U (en) Node connection structure of easily forming plastic hinge on beam
CN212866372U (en) Extension node of prefabricated solid concrete filled steel tube member
CN211973855U (en) Pipe gallery embedded part
CN113944309A (en) Cold-formed steel support beam framework and construction method thereof
CN209941967U (en) T-shaped wallboard connecting structure
CN112302210A (en) Assembled built-in corrugated steel plate reinforced concrete cross-section member and construction process
CN112443052A (en) Indoor wall frame connection structure of assembly type building
CN109235640B (en) Pin type connecting structure between modularized steel structural members for building
CN112575909A (en) Concrete column and H-shaped steel beam combined node structure
CN112695928A (en) PBL (Poly-p-phenylene benzobisoxazole) -based precast concrete shear wall-ring beam connection structure and installation method
CN216108595U (en) Chemical industry piping lane's base quick fixation structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190621

Termination date: 20210919

CF01 Termination of patent right due to non-payment of annual fee