CN208949656U CN201821574023.3U CN201821574023U CN208949656U CN 208949656 U CN208949656 U CN 208949656U CN 201821574023 U CN201821574023 U CN 201821574023U CN 208949656 U CN208949656 U CN 208949656U
Authority
CN
China
Prior art keywords
roadbed
railway
prevention structure
damage prevention
rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821574023.3U
Other languages
Chinese (zh)
Inventor
康雪岭
田茂臣
马林
刘志利
侯军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tiefa Coal Group Railway Engineering Co Ltd
Original Assignee
Tiefa Coal Group Railway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tiefa Coal Group Railway Engineering Co Ltd filed Critical Tiefa Coal Group Railway Engineering Co Ltd
Priority to CN201821574023.3U priority Critical patent/CN208949656U/en
Application granted granted Critical
Publication of CN208949656U publication Critical patent/CN208949656U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Abstract

It is obstructed the utility model relates to a kind of layering and administers railway cutting route frost damage prevention structure, including roadbed, railway roadbed, sleeper, rail and the cutting slope protection of roadbed two sides, drainage system is equipped in roadbed, the high both ends in the middle part of drainage system are low, and clinker insulating layer is arranged in the top of drainage system both ends lowest part;It is equipped with slope drainage ditch in the two sides of cutting slope protection, covers straw plaited insulating layer above slope drainage ditch.The frost damage prevention structure carries out barrier aqueous vapor to rail layer, ballast covering and base course respectively, the mode of separated layer handling carries out subtle regulation and accurate adjustment, in the case where reaching without heavy construction construction, route is solved because of irregularity caused by freeze injury, guarantees the operation of train safety and steady.

Description

Railway cutting route frost damage prevention structure is administered in layering barrier
Technical field
It is obstructed the utility model relates to a kind of layering and administers railway cutting route frost damage prevention structure, belong to railway construction neck Domain.
Background technique
The track freeze injury of railway cutting location is one of the Common Diseases of severe cold area railroad track, and tunnel, viaduct are inferior The rail track at place is cutting location, and route geographical location is low herein, and basic water content is big, and therefore, ballast bed of track freezes swollen Swollen is a kind of inevitable natural phenomena.Freeze injury can not only accelerate the dirty and ballast of railway roadbed to fall into the development of slot, but also can promote Make roadbed that other diseases occur, influences the stability of roadbed, meanwhile, freeze injury can also be such that the operating condition of track deteriorates, especially It is replaced as frequently as backing plate, substantially reduce sleeper and is coupled the service life of fastener.
The presence of freeze injury not only increases the labour of track maintenance and repair, increases operation expenditure, and can make route matter Amount decline;Serious freeze injury, or even jeopardize traffic safety.
Summary of the invention
It is obstructed the technical problem to be solved by the present invention is to provide a kind of layering and administers railway cutting route frost damage prevention knot Structure, which carries out barrier aqueous vapor to rail layer, ballast covering and base course respectively, the mode of separated layer handling carry out it is subtle Regulation and accurate adjustment in the case where reaching without heavy construction construction, solve route because of irregularity caused by freeze injury, guarantee The operation of train safety and steady.
In order to solve the above problem, the specific technical solution of the utility model is as follows: a kind of layering barrier improvement railway cutting Route frost damage prevention structure is equipped with draining system including roadbed, railway roadbed, sleeper, rail and the cutting slope protection of roadbed two sides in roadbed System, the high both ends in the middle part of drainage system are low, and clinker insulating layer is arranged in the top of drainage system both ends lowest part;It is protected in cutting The two sides on slope are equipped with slope drainage ditch, cover straw plaited insulating layer above slope drainage ditch.
Belt is set between railway roadbed and sleeper and adjusts module, guarantees two sides rail in same plane.
Rubber cushion plate is set between sleeper and rail, and rubber cushion plate mating connection tightening means for height-adjusting guarantees two sides rail same Plane.
Layering barrier administers railway cutting route frost damage prevention structure and uses the row that high both ends are low among base course setting Water system, it is ensured that winter drainage system it is good, guidance aqueous vapor to roadbed two sides disperse, reduce subgrade moisture content, roadbed side slope Drainage equipment dredging is reinforced, and then devises slag layer and straw plaited frost retarding layer to pumping equipment, roadbed is administered from fundamental factor Freeze injury.
Module is adjusted in ballast covering setting belt, guarantees the stability of ballast covering, reduces the modification degree of track.
The structure of rubber cushion plate is used in rail layer, not only mitigates freeze injury, but also guarantees that two rails are horizontal.
Layering barrier is administered railway cutting route frost damage prevention structure and is had the advantage that
(1) make filler with full combustion, the light uniform clinker of ventilative fritter, the aqueous vapor of preferable drainage base course, and Winter is cold-proof;
(2) straw plaited insulating layer is low in cost, the recyclable multiplexing of annual winter;
(3) railway roadbed belt adjustment layer freely can be turned up or reduce orbit altitude, and straight line, curve are applicable in, strong operability;
(4) layering barrier administers railway freeze injury technology and is not required to engineering construction, and directly carrying out ongoing operations can preferably control Manage the route freeze injury in the engineering constructions difficulty locations such as tunnel, viaduct;
(5) railway cuts off traffic influence caused by avoiding because of engineering construction.
Detailed description of the invention
Fig. 1 is the schematic diagram that railway cutting route frost damage prevention structure is administered in layering barrier.
Specific embodiment
As shown in Figure 1, railway cutting route frost damage prevention structure, including roadbed 1, railway roadbed 2, sleeper are administered in a kind of layering barrier 3, the cutting slope protection 5 of rail 4 and roadbed two sides, roadbed is selected to be filled out by full combustion, the light uniform clinker of ventilative fritter Material, light and ventilation, and there is preferable heat-insulating and cold effect, drainage system 6, the middle part of drainage system 6 are equipped in roadbed 1 High both ends are low, and clinker insulating layer 7 is arranged in the top of 6 both ends lowest part of drainage system;Side is equipped in the two sides of cutting slope protection 5 Slope gutter 8, covering straw plaited insulating layer 9 plays good surface layer drainage system anti-frost protection above slope drainage ditch 13, guarantees Mountain spring water is in winter smoothly trickle downwards by the time, reduces base course water content, to achieve the purpose that mitigate route freeze injury.
Belt adjustment layer 10 is set between railway roadbed 2 and sleeper 3, and selecting specification is 200 millimeters × 400 millimeters, 10 millimeters Or 20 millimeters thick ledger line belt, guarantee two sides rail 4 in same plane.
Rubber cushion plate 11 is set between sleeper 3 and rail 4, and 11 mating connection tightening means for height-adjusting 12 of rubber cushion plate is detained using being turned up Part is renovated with the method that pillow upper padding plate combines, and is encased inside the rubber cushion plate no more than 20 millimeters, guarantees two sides rail 4 same Plane.
The implementation for administering railway freeze injury technology is obstructed by layering, roadbed insulating layer can effectively prevent roadbed from freezing 50 millis Rice;It rests the head on lower belt and adjusts 30 millimeters of module adjusting track height;Rubber cushion plate cooperates 20 milli of tightening means for height-adjusting adjusting track height Rice.This technology is always turned up 100 millimeters, can effectively solve the route freeze injury in the inferior limitation location of tunnel, viaduct, avoids frequently more The construction of lane-change bed.
The advantages of railway cutting route frost damage prevention structure is administered in the layering barrier of the application:
(1) by separated layer handling, achieve the purpose that rail track ride comfort, avoid replacement roadbed, railway roadbed engineering, save Huge engineering cost;
(2) roadbed lower part gutter clinker insulating layer once fills completion, and ballast covering and rail layer can pass through ordinary maintenance Operation is completed, construction is simple;
(3) personnel and equipment breakdown when engineering construction are avoided, reduces and goes because administering freeze injury route not in time Vehicle accident, method operation is simple, and risk factor is few, is suitble to popularize in an all-round way in freeze injury location.

Claims (3)

1. railway cutting route frost damage prevention structure, including roadbed (1), railway roadbed (2), sleeper (3), rail are administered in a kind of layering barrier (4) and the cutting slope protection (5) of roadbed two sides, it is characterised in that: be equipped with drainage system (6) in roadbed (1), drainage system (6) The high both ends in middle part it is low, and the top of drainage system (6) both ends lowest part be arranged clinker insulating layer (7);In cutting slope protection (5) Two sides be equipped with slope drainage ditch (8), cover straw plaited insulating layer (9) above slope drainage ditch (8).
2. railway cutting route frost damage prevention structure is administered in layering barrier as described in claim 1, it is characterised in that: in railway roadbed (2) belt is set between sleeper (3) and adjusts module (10), guarantees two sides rail (4) in same plane.
3. railway cutting route frost damage prevention structure is administered in layering barrier as described in claim 1, it is characterised in that: in sleeper (3) rubber cushion plate (11) are set between rail (4), rubber cushion plate (11) mating connection tightening means for height-adjusting (12) guarantees two sides rail (4) In same plane.
CN201821574023.3U 2018-09-27 2018-09-27 Railway cutting route frost damage prevention structure is administered in layering barrier Expired - Fee Related CN208949656U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821574023.3U CN208949656U (en) 2018-09-27 2018-09-27 Railway cutting route frost damage prevention structure is administered in layering barrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821574023.3U CN208949656U (en) 2018-09-27 2018-09-27 Railway cutting route frost damage prevention structure is administered in layering barrier

Publications (1)

Publication Number Publication Date
CN208949656U true CN208949656U (en) 2019-06-07

Family

ID=66739551

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821574023.3U Expired - Fee Related CN208949656U (en) 2018-09-27 2018-09-27 Railway cutting route frost damage prevention structure is administered in layering barrier

Country Status (1)

Country Link
CN (1) CN208949656U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112663406A (en) * 2020-12-04 2021-04-16 神华新朔铁路有限责任公司 Roadbed disease treatment method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112663406A (en) * 2020-12-04 2021-04-16 神华新朔铁路有限责任公司 Roadbed disease treatment method

Similar Documents

Publication Publication Date Title
KR100768777B1 (en) Earth reinforcement method for railway track on the concrete base
CN202730544U (en) Frost heave prevention roadbed structure in deep seasonal permafrost region
CN208949656U (en) Railway cutting route frost damage prevention structure is administered in layering barrier
Rose Selected in-track applications and performances of hot-mix asphalt trackbeds
CN206328642U (en) A kind of board-like track structure of framework in tunnel
CN108951306B (en) Ballast track bed and construction method thereof
Rose et al. Utilization of asphalt/bituminous layers and coatings in railway trackbeds: a compendium of international applications
CN200943500Y (en) Tunnel treatment system for adapting to large uneven precipitation or stagger of stratum
CN103255694A (en) Cutting bed structure of ballast-less rail type high-speed railway in seasonal frozen-earth area
CN106400613A (en) Ballastless track
CN105133439B (en) A kind of embedded ballastless track system for afforesting section
CN105568779B (en) Railway bed waterproof construction and its laying method
CN205012160U (en) A embedded ballastless track system for afforesting section
CN202017168U (en) Unit board type ballastless track structure of railway turnout area
RU2469145C1 (en) Method of strengthening track ballast section
CN205368898U (en) Railway roadbed waterproof construction
CN110939017A (en) Elastic prefabricated assembling plate type ballast track
CN206538636U (en) Waterproof railway bed
US11021841B2 (en) Railway or tramway track
CN204475066U (en) Snow defence sand-proof device and the track switch with this device
CN107881857A (en) Magnetic suspension tunnel draining of rail system
CN209722596U (en) A kind of novel CRT S plate-type non-fragment orbit
CN111270569A (en) High-speed railway roadbed structure
CN208395577U (en) Insert the interim transition structure of causeway trouble in a kind of both wired non-fragment orbit location
KR20150004072U (en) Htpct

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190607

Termination date: 20190927