CN208930160U - Floor heating water divider extracting tool - Google Patents
Floor heating water divider extracting tool Download PDFInfo
- Publication number
- CN208930160U CN208930160U CN201821728654.6U CN201821728654U CN208930160U CN 208930160 U CN208930160 U CN 208930160U CN 201821728654 U CN201821728654 U CN 201821728654U CN 208930160 U CN208930160 U CN 208930160U
- Authority
- CN
- China
- Prior art keywords
- handle
- crow bar
- floor heating
- extracting tool
- pillar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The utility model provides a kind of floor heating water divider extracting tool, including the pipe wrench for grip both hose, its first binding clip and first handle one, second binding clip and second handle one, first handle and second handle are arranged in a crossed manner, it is fixed on crosspoint by connecting pin shaft, first binding clip, the hollow portion of a closure is formed when second pliers head clip is combined, first handle or second handle are equipped with pillar mounting hole, it is additionally provided with pillar and crow bar, lower rod end is fixed in pillar mounting hole, it is connect in the middle part of upper end and crow bar, crow bar one end is to push impetus, the other end is supported on the supervisor of branch pipe, this extracting tool is removed branch pipe using lever principle, hose can be removed from water segregator by primary or secondary depression, it is quick that operation is very easy.
Description
Technical field
The utility model belongs to building HVAC, heating construction tool technical field, more particularly to a kind of floor heating water divider
Extracting tool and application method.
Technical background
In recent years, generally existing environmental pollution is serious, energy waste is big, temperature distribution is non-uniform for traditional warming installation
Disadvantage gradually exposes, and people start to be not content with traditional heating system, then in emerging building, using the more next of floor heating
More, low-temperature ground heating agent forms the temperature gradient that sole to head is gradually successively decreased indoors, thus give warm, foot it is cool
Comfort.Ground heating system heating more energy saving amplitude compared with traditional convection current heating system is about 30%, and floor heating is in transmit process
Middle thermal loss is smaller and heat concentrates in the benefited height of human body, even if indoor set temperature is than convection type heating system
Low 2~5 DEG C.The branch pipe of floor heating is hidden in below ground, is not take up usable floor area;It is general to select prefabricated board or Bars In Poured Concrete Slab, sound insulation
Effect is poor, upstairs walks about, and just influences downstairs, to increase insulating layer using floor heating, has extraordinary soundproof effect, can
Reduce noise pollution.
Floor heating water divider is arranged on wall, for connecting heating supervisor and each branch pipe in ground.Floor heating water divider includes point
Water pipe, collector pipe, shunt valve and collector pipe are equipped with several branching hose connectors, and each branching hose connector is equipped with independent
Valve, hose need to be inserted into branching hose connector when docking with distributive pipe or collector pipe and are deep into distributive pipe or collector pipe
Tube coupling in just can guarantee and firmly install, finally with passing through metal hoop for hose banding.
The connection of branch pipe and water segregator is relatively high to the technology dependence of construction personnel, will lead to infiltration when construction quality is bad
Leakage, is easy to happen leakage when pipeline pressure is excessive, therefore, in the maintenance work of floor heating, water segregator maintenance is most commonly seen, and dimension
Emphasis is repaired, when hose is removed since the toughness support force of branch pipe itself acts on, is difficult to remove, construction is inconvenient.
Utility model content
The utility model is to solve the problems, such as that water segregator safeguards that hose removes inconvenience in the prior art, is provided a kind of dedicated
In the tool that hose is removed, guarantees hose damage, effectively improve the working efficiency of floor heating maintenance.
In order to achieve the above purposes, the technical solution adopted by the utility model is:
A kind of floor heating water divider extracting tool, including the pipe wrench for grip both hose, the first binding clip and first handle one
Body, the second binding clip and second handle one, first handle and second handle are arranged in a crossed manner, solid by connection pin shaft on crosspoint
It is fixed, the hollow portion of a closure is formed when the first binding clip, the second pliers head clip are combined, first handle or second handle are equipped with
Pillar mounting hole is additionally provided with pillar and crow bar, and lower rod end is fixed in pillar mounting hole, connect, prizes in the middle part of upper end and crow bar
Stick one end is to push impetus, and the other end is supported on the supervisor of branch pipe.
Pillar upper end is connect by hinged shaft with crow bar, and post top portion is equipped with axial opening, and opening two sidewalls are equipped with diameter
To hinge axis hole, crow bar be equipped with hinge axis hole.
Crow bar is made of barred body and pry head, and the fraising of crow bar is equipped near the boundary of pry head and barred body, under barred body tail portion is
Force is being pressed against, pry head is supported on the supervisor of branch pipe.
The connection of pillar top and crow bar is also possible to: pillar top is equipped with radial through-hole, and crow bar is inserted into through-hole.
Pry head opposite handle, which has, centainly tears bending angle open.
Above-mentioned crow bar fulcrum side is plane.The contact area at fulcrum can be increased.
With the bed course that coefficient of friction is big at above-mentioned crow bar fulcrum.Prevent fulcrum sliding from losing power.
Above-mentioned radial through-hole can be round hole or square hole, and barred body and shape of through holes adapt to, as long as radial by insertion
Through-hole.
Above-mentioned mounting hole is threaded hole, and lower rod end is formed with screw thread, the pillar nut lock maintenance upper and lower by mounting hole
It sets.
Above-mentioned mounting hole is bellmouth, and lower rod end is the taper being adapted to bellmouth.
The utility model has the beneficial effects that binding clip holds tube body tightly, crow bar one end is propped up on supervisor, at pressure under one end, is passed through
Pillar power transmission drags binding clip downwards hose, this extracting tool is removed branch pipe using lever principle, under primary or secondary
Press operation can remove hose from water segregator, and it is quick that operation is very easy.
Detailed description of the invention
Fig. 1 is each component diagram of this tool;
Fig. 2 is that this extracting tool assembles overall diagram;
Fig. 3 is that pillar and pillar install hole connection structure one;
Fig. 4 is that pillar and pillar install hole connection structure two;
Fig. 5 is pillar and one schematic diagram of crow bar connection structure;
Fig. 6 is pillar and one outside drawing of crow bar connection structure;
Fig. 7 is pillar and two schematic diagram of crow bar connection structure;
Fig. 8 is extracting tool use state diagram.
Specific embodiment
The structure of the utility model is described in detail with reference to the accompanying drawing: a kind of floor heating as shown in Figs. 1-3 divides water
Device extracting tool, including the first binding clip 11, the second binding clip 13, connection pin shaft, first handle 12, second handle 14, pillar 3 and sled
Stick 4.Wherein the first binding clip 11 and first handle 12 are structure as a whole, and the second binding clip 13 and second handle 14 are structure as a whole;The
One handle 12 and second handle 14 are arranged in a crossed manner, are fixed on crosspoint by connecting pin shaft;First binding clip 11, the second binding clip 12 folder
The hollow portion of a closure is formed when being combined, which is the grasping part of hose.
First handle 12 or second handle 14 are equipped with pillar mounting hole 2, and 3 lower end of pillar is fixed in pillar mounting hole 2,
It is connected in the middle part of upper end and crow bar 4,4 one end of crow bar is to push impetus, and the other end is supported on the supervisor 8 of branch pipe to be torn open.
In the utility model pillar and the fixation of handle should not Seeking Truth be completely fixedly connected, it is required that pillar 3 is installed
After on pillar mounting hole 2, position cannot be moved still further below because of pressure, to guarantee that crow bar pressure energy is effectively conducted to binding clip.
The junction structure of pillar and handle is:
Structure one: the mounting hole on handle 12 is threaded hole, and 3 lower end of pillar is formed with screw thread, and pillar 3 passes through mounting hole
5 locking position of nut of upper and lower two sides;
Structure two: pillar mounting hole 2 is bellmouth, and 3 lower end of pillar is the tapered end 31 being adapted to mounting hole, and pillar 3 is inserted
It can only move up taking-up after entering bellmouth and cannot continue to stretch to direction movement under pillar mounting hole.
This crow bar 4 is made of pry head and barred body, and pry head opposite handle has certain tilt angle, conducive to agitating.Inclination angle
It spends occurrence to be arranged according to the height of pillar, just different crow bar angles change pillar therewith, reach most laborsaving and save operation sky
Between effect.
The pry head of crow bar is propped up on the supervisor 8 of the branch pipe 7 to be removed;4 middle part of crow bar is affixed with pillar, forms one with binding clip
Body force structure;Crow bar tail portion is staff force.The fulcrum of crow bar is set in the interior angle side of pry head, the preferred fulcrum side
For plane, the contact area at fulcrum can be increased.Further, can also have the big bed course of coefficient of friction at fulcrum, prevent
Power is lost in only fulcrum sliding.Can also the shape distortion of pry head be become and connect more stable, the good other shapes of solution with supervisor
Shape, such as be widened into arc panel etc..
As shown in Figure 5,6, in the utility model, pillar 3 is connect in articulated manner with crow bar 4, and specific structure is pillar
Top is equipped with axial opening 32, and 32 two sidewalls of opening are equipped with radial hinge axis hole, and crow bar is set in opening, sets on crow bar
There is hinge axis hole, crow bar is mounted in the opening 32 by hinged shaft 6.
As shown in fig. 7, the connection type of pillar 3 and crow bar 4 may also is that pillar top is equipped with radial through-hole, crow bar is inserted
Enter in through-hole.
Pillar and crow bar are not limited to circle barred body shown in attached drawing, naturally it is also possible to be the suitable shapes such as rectangular, oval
Shape.
Binding clip holds 7 tube body of branch pipe tightly, and 4 pry head end of crow bar is propped up on supervisor, and barred body one end is to put forth effort side, is passed by pillar 3
Power drags binding clip downwards hose 7, and stud connection mode is better than plug-type connection type in using effect, it can only be passed
Lead power in downward direction, under to drag direction be vertically downward.And it is simple to be inserted into connection structure, easy processing, using effect is also the same
It is efficient and convenient.
The application method of floor heating water divider extracting tool:
1) the pipe fitting screw of branch pipe to be removed is unclamped;
2) it will clamp to branch pipe position to be removed is blocked, pliers of firmly holding with a firm grip is by branch pipe clamp;
3) by pillar 3, be inserted into pliers mounting hole in and fix, 4 front end of crow bar resist into return water be responsible for lower part;
4), using lever principle, transferred force on pliers by pillar 3 with hand with 4 rear portion of crow bar is forced, because pliers this
When clamping branch pipe 7, therefore branch pipe 7 is firmly pulled down, and branch pipe, which is detached from, is responsible for linking for pipe fitting screw with into return water, and branch pipe has been dismantled
At.
This extracting tool is removed branch pipe using lever principle, by primary or secondary depression can by hose from point
It is removed on hydrophone, it is quick that operation is very easy.
Claims (10)
1. a kind of floor heating water divider extracting tool, including the pipe wrench for grip both hose, the first binding clip and first handle one,
Second binding clip and second handle one, first handle and second handle are arranged in a crossed manner, are fixed on crosspoint by connecting pin shaft, the
The hollow portion that a closure is formed when one binding clip, the second pliers head clip are combined, it is characterized in that: on first handle or second handle
Equipped with pillar mounting hole, it is additionally provided with pillar and crow bar, lower rod end is fixed in pillar mounting hole, is connected in the middle part of upper end and crow bar
It connects, crow bar one end is to push impetus, and the other end is supported on the supervisor of branch pipe.
2. floor heating water divider extracting tool as described in claim 1, it is characterized in that: pillar upper end is connect by hinged shaft with crow bar,
Post top portion is equipped with axial opening, and opening two sidewalls are equipped with radial hinge axis hole, and crow bar is equipped with hinge axis hole.
3. floor heating water divider extracting tool as claimed in claim 2, it is characterized in that: crow bar is made of barred body and pry head, pry head phase
Have to handle and centainly tears bending angle open.
4. floor heating water divider extracting tool as claimed in claim 3, it is characterized in that: the fraising of crow bar is equipped with point of pry head and barred body
Near boundary, barred body tail portion is to push impetus, and pry head is supported on the supervisor of branch pipe.
5. floor heating water divider extracting tool as claimed in claim 3, it is characterized in that: pillar top is equipped with radial through-hole, crow bar is inserted
Enter in through-hole.
6. floor heating water divider extracting tool as claimed in claim 5, it is characterized in that: radial through-hole is round hole or square hole, stick
Body and shape of through holes adapt to, and are inserted into radial through-hole.
7. floor heating water divider extracting tool as described in claim 1, it is characterized in that: mounting hole is threaded hole, lower rod end is formed with
Screw thread, the pillar nut locking position upper and lower by mounting hole.
8. floor heating water divider extracting tool as described in claim 1, it is characterized in that: mounting hole is bellmouth, lower rod end be with
The tapered end of bellmouth adaptation.
9. the floor heating water divider extracting tool as described in claim any one of 1-8, it is characterized in that: the fulcrum side of crow bar is plane.
10. floor heating water divider extracting tool as claimed in claim 9, it is characterized in that: big with coefficient of friction at crow bar fulcrum
Bed course.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821728654.6U CN208930160U (en) | 2018-10-24 | 2018-10-24 | Floor heating water divider extracting tool |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821728654.6U CN208930160U (en) | 2018-10-24 | 2018-10-24 | Floor heating water divider extracting tool |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208930160U true CN208930160U (en) | 2019-06-04 |
Family
ID=66725860
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821728654.6U Active CN208930160U (en) | 2018-10-24 | 2018-10-24 | Floor heating water divider extracting tool |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208930160U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109048788A (en) * | 2018-10-24 | 2018-12-21 | 中国二十二冶集团有限公司 | Floor heating water divider extracting tool and its application method |
-
2018
- 2018-10-24 CN CN201821728654.6U patent/CN208930160U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109048788A (en) * | 2018-10-24 | 2018-12-21 | 中国二十二冶集团有限公司 | Floor heating water divider extracting tool and its application method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208930160U (en) | Floor heating water divider extracting tool | |
CN201103235Y (en) | Connection device between wall and scaffold | |
CN109048788A (en) | Floor heating water divider extracting tool and its application method | |
CN204748377U (en) | A anchor clamps for interface flange fastens temporarily | |
CN208930094U (en) | A kind of aluminum alloy pattern plate plate folder | |
CN213390639U (en) | Fixed drawknot device of assembled composite insulation board | |
CN216403779U (en) | Be used for hydraulic engineering pipeline lifting to build structure | |
CN205206290U (en) | A cam connector link for scaffold installation | |
CN213392178U (en) | Fastening formula tunnel lining section of jurisdiction | |
CN203547229U (en) | Camp pole fixing seat | |
CN207120165U (en) | For kitchen and toilet tank dual-purpose faucet special spanner | |
CN209990022U (en) | Construction steel bar connecting piece | |
CN208455962U (en) | Not upper people's metal Roof overhauls riding track aluminum support device | |
CN219775005U (en) | Fire control sprays pipeline hoist and mount support | |
CN112072581A (en) | Pipeline erecting device for assembled wall | |
CN2409264Y (en) | Convenient fastener for building scaffold | |
CN217759631U (en) | Heat insulation structure for slope roof of existing building | |
CN217683560U (en) | Municipal administration water supply and drainage pipeline connection structure | |
CN221168130U (en) | Steel construction building connecting foot | |
CN215830146U (en) | Reinforced concrete pole inner wall reinforcing apparatus | |
CN220266829U (en) | Steel beam assembly connecting piece capable of being positioned | |
CN220848664U (en) | Wall connecting piece | |
CN217281879U (en) | Auxiliary device for insulating operating rod | |
CN217726742U (en) | Steel pipe cold bending spanner | |
CN219282183U (en) | Steel plate connecting fastener |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |