CN208918325U CN201821334829.5U CN201821334829U CN208918325U CN 208918325 U CN208918325 U CN 208918325U CN 201821334829 U CN201821334829 U CN 201821334829U CN 208918325 U CN208918325 U CN 208918325U
Authority
CN
China
Prior art keywords
access way
upright bar
crossbar
vertical pole
protective equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821334829.5U
Other languages
Chinese (zh)
Inventor
杨树仁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cambridge Harbin Institute
Harbin Cambridge University
Original Assignee
Cambridge Harbin Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cambridge Harbin Institute filed Critical Cambridge Harbin Institute
Priority to CN201821334829.5U priority Critical patent/CN208918325U/en
Application granted granted Critical
Publication of CN208918325U publication Critical patent/CN208918325U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model provides a kind of civil construction project construction access way protective equipment structure, comprising: access way, the first upright bar, first crossbar;The access way is rectangular-shape structure setting;The two sides of the access way length direction are provided with the first upright bar of equidistant radial arrangement, and the first upright bar is connected with ground by expansion bolt;The top of first upright bar is provided with first crossbar, and first crossbar is connected with the first upright bar by steel tube fastener;Several first vertical poles and the second vertical pole are provided on the length direction of the access way, and the first vertical pole and the second vertical pole are connected with the first upright bar, first crossbar by steel tube fastener respectively.By the improvement to a kind of civil construction project construction access way protective equipment structure, there is reasonable in design, overall structure stabilization, it is easy to build, it is low in cost, the good advantage of protection effect, thus the problem of effective solution the utility model proposes in background technique one and deficiency.

Description

A kind of civil construction project construction access way protective equipment structure
Technical field
The utility model relates to technical field of buildings, more specifically, more particularly to a kind of civil construction project construct into Channel protective equipment structure out.
Background technique
During Civil Engineering Construction, the sundries such as stone that can be fallen from skyscraper may be on ground Staff causes certain injury, the discrepancy in order to ensure the safety of surface personnel's discrepancy building, in construction site Exit passageway will be arranged in the more position of ground running personnel in oral area position and construction area.
Existing this kind of disengaging protection channel is usually frame type shape, simple by steel pipe, safety net and single layer hard plank It sets up, protection effect is poor, when furthermore construction personnel transports construction equipment in access way, may strike steel Pipe, tube bending will affect the stability of integral protection structure.
In view of this, being studied improvement for existing problem, a kind of civil construction project construction access way is provided Protective equipment structure, it is intended to by the technology, achieve the purpose that solve the problems, such as and improve practical value.
Utility model content
The purpose of this utility model is to provide a kind of civil construction project construction access way protective equipment structures, with solution Protection effect certainly mentioned above in the background art is poor, when transporting construction equipment in access way, may strike steel The problem of managing, tube bending, influencing the stability of integral protection structure and deficiency.
To achieve the above object, the utility model provides a kind of civil construction project construction access way protective equipment knot Structure is reached by technological means in detail below:
A kind of civil construction project construction access way protective equipment structure, comprising: access way, the first upright bar, first Cross bar, the first vertical pole, the second upright bar, the second vertical pole, flitch, glued board, safety net, guardrail, reinforcing rod, Crossing brace;It is described into Channel is rectangular-shape structure setting out;It is first vertical to be provided with equidistant radial arrangement for the two sides of the access way length direction Bar, and the first upright bar is connected with ground by expansion bolt;The top of first upright bar is provided with first crossbar, and first Cross bar is connected with the first upright bar by steel tube fastener;Be provided on the length direction of the access way several first vertical poles and Second vertical pole, and the first vertical pole and the second vertical pole are connected with the first upright bar, first crossbar by steel tube fastener respectively;It is described into Channel front portion is provided with two the second upright bars being symmetric out;One end and ground of second upright bar pass through expansion bolt It is connected, and the other end of the second upright bar is connected with first crossbar by steel tube fastener;The top of the first crossbar is arranged There are several flitches, and flitch is connected with cross bar by the mode of tying up;The top of the flitch is provided with glued board, and glued board It is connected with flitch by steel nail;It is provided with guardrail on the inside of first upright bar, and is provided with safety on the outside of the first upright bar Net;The front of the access way is provided with reinforcing rod, and reinforcing rod passes through steel tube fastener with the first vertical pole, the second vertical pole respectively It is connected;Crossing brace is provided on the outside of the safety net, and the both ends of Crossing brace are connected with the first upright bar by steel tube fastener It connects.
As advanced optimizing for the technical program, a kind of civil construction project construction access way protection of the utility model Reinforcing rod described in facility structure is provided with two in symmetrical expression, and reinforcing rod is tilted structure setting.
As advanced optimizing for the technical program, a kind of civil construction project construction access way protection of the utility model Glued board described in facility structure includes upper layer glued board and lower layer's glued board, and glued board is connected by flitch with first crossbar It connects.
As advanced optimizing for the technical program, a kind of civil construction project construction access way protection of the utility model Guardrail described in facility structure is dressing structure setting, and the upper end of guardrail is provided with handrail.
As advanced optimizing for the technical program, a kind of civil construction project construction access way protection of the utility model First upright bar, first crossbar described in facility structure, the first vertical pole, the second upright bar, the second vertical pole, reinforcing rod and Crossing brace material For steel pipe, and the model Φ 48*3.5 of steel pipe.
As advanced optimizing for the technical program, a kind of civil construction project construction access way protection of the utility model The shape of Crossing brace described in facility structure is in X-shape.
As advanced optimizing for the technical program, a kind of civil construction project construction access way protection of the utility model The lower end of first upright bar and the second upright bar described in facility structure is provided with the installation seat plate of square shape.
As advanced optimizing for the technical program, a kind of civil construction project construction access way protection of the utility model The front of access way described in facility structure is provided with warning panel, and warning striped is painted in shown warning panel.
Due to the application of the above technical scheme, the utility model has the advantage that compared with prior art
1, the utility model is provided with two in symmetrical expression by reinforcing rod, and reinforcing rod is setting for tilted structure setting It sets, improves the lateral stiffness of access way frame body, can avoid frame body double swerve.
2, the utility model includes upper layer glued board and lower layer's glued board by glued board, and glued board by flitch with The setting that first crossbar is connected makes the top of access way form Double-protection structure, improves protection effect.
3, the utility model is dressing structure setting by guardrail, and the upper end of guardrail is provided with the setting of handrail, can have Effect avoids upright bar from being hit and be bent, and guarantees integrally-built stability.
4, the utility model has by the improvement to a kind of civil construction project construction access way protective equipment structure Reasonable in design, overall structure is stablized, and is easy to build, low in cost, the good advantage of protection effect, thus effective solution The problem of the utility model proposes in background technique one and deficiency.
Detailed description of the invention
The attached drawing constituted part of this application is used to provide a further understanding of the present invention, the utility model Illustrative embodiments and their description are not constituteed improper limits to the present invention for explaining the utility model.In attached drawing In:
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the side structure schematic view of the utility model;
Fig. 3 is the forward sight structural schematic diagram of the utility model;
Fig. 4 is the guard bar structure schematic diagram of the utility model.
In figure: access way 1, the first upright bar 2, first crossbar 3, the first vertical pole 4, the second upright bar 5, the second vertical pole 6, flitch 7, glued board 8, safety net 9, guardrail 10, reinforcing rod 11, Crossing brace 12.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.
It should be noted that in the description of the present invention, unless otherwise indicated, the meaning of " plurality " is two or two More than a;The instructions such as term " on ", "lower", "left", "right", "inner", "outside", " front end ", " rear end ", " head ", " tail portion " Orientation or positional relationship is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of description the utility model and simplification Description, rather than the device or element of indication or suggestion meaning must have a particular orientation, constructed and grasped with specific orientation Make, therefore should not be understood as limiting the present invention.
In addition, term " first ", " second ", " third " etc. are used for description purposes only, it is not understood to indicate or imply Relative importance.
Meanwhile in the description of the present invention, unless otherwise clearly defined and limited, term " connected ", " connection " It shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can be mechanical connect It connects, is also possible to be electrically connected;It can be directly connected, it can also be indirectly connected through an intermediary.For the general of this field For logical technical staff, the concrete meaning of above-mentioned term in the present invention can be understood with concrete condition.
Referring to Figure 1 to Fig. 4, the utility model provides a kind of civil construction project construction access way protective equipment structure Particular technique embodiment:
A kind of civil construction project is constructed access way protective equipment structure, comprising: access way 1, the first upright bar 2, the One cross bar 3, the first vertical pole 4, the second upright bar 5, the second vertical pole 6, flitch 7, glued board 8, safety net 9, guardrail 10, reinforcing rod 11, Crossing brace 12;Access way 1 is rectangular-shape structure setting;The two sides of 1 length direction of access way are provided with equidistant interval row First upright bar 2 of column, and the first upright bar 2 is connected with ground by expansion bolt;The top of first upright bar 2 is provided with the first cross Bar 3, and first crossbar 3 is connected with the first upright bar 2 by steel tube fastener;It is provided on the length direction of access way 1 several First vertical pole 4 and the second vertical pole 6, and the first vertical pole 4 and the second vertical pole 6 pass through steel pipe with the first upright bar 2, first crossbar 3 respectively Fastener is connected;1 front of access way is provided with two the second upright bars 5 being symmetric;One end and ground of second upright bar 5 It is connected by expansion bolt, and the other end of the second upright bar 5 is connected with first crossbar 3 by steel tube fastener;First crossbar 3 Top be provided with several flitches 7, and flitch 7 is connected with cross bar 3 by the mode of tying up;The top of flitch 7 is provided with gluing Plate 8, and glued board 8 is connected with flitch 7 by steel nail;The inside of first upright bar 2 is provided with guardrail 10, and the first upright bar 2 Outside is provided with safety net 9;The front of access way 1 is provided with reinforcing rod 11, and reinforcing rod 11 respectively with the first vertical pole 4, Two vertical poles 6 are connected by steel tube fastener;The outside of safety net 9 is provided with Crossing brace 12, and the both ends of Crossing brace 12 and first Upright bar 2 is connected by steel tube fastener.
Specifically, reinforcing rod 11 is provided with two in symmetrical expression, and reinforcing rod 11 is tilted structure setting, reinforcing rod 11 One end be connected with the second vertical pole 6, the other end of reinforcing rod 11 and ground touch, to form stable triangular Frame improves the lateral stiffness of access way frame body, can avoid frame body double swerve.
Specifically, glued board 8 includes upper layer glued board and lower layer's glued board, and glued board 8 is horizontal by flitch 7 and first Bar 3 is connected, and upper layer glued board and lower layer's glued board parallel interval formula are arranged, and the top of access way 1 is made to form Double-protection Structure improves protection effect.
Specifically, guardrail 10 is dressing structure setting, and the upper end of guardrail 10 is provided with handrail, transports in access way 1 When transfer device, it can effectively avoid the first upright bar 2 and hit and be bent, guarantee integrally-built stability.
Specifically, the first upright bar 2, first crossbar 3, the first vertical pole 4, the second upright bar 5, the second vertical pole 6, reinforcing rod 11 and cutting The material for supporting 12 is steel pipe, and the model Φ 48*3.5 of steel pipe reduces the production cost convenient for building for access way 1.
Specifically, the shape of Crossing brace 12 is in X-shape, the longitudinal rigidity of access way frame body is improved.
Specifically, the lower end of the first upright bar 2 and the second upright bar 5 is provided with the installation seat plate of square shape, expansion bolt is used Installation seat plate can be fixed on the ground.
Specifically, the front of access way 1 is provided with warning panel, and warning striped is painted in shown warning panel, make into 1 entrance of channel is eye-catching out.
Specific implementation step:
Equidistant interval installs the first upright bar 2 first on 1 length direction of access way, using expansion bolt by the first upright bar 2 fix on the ground, are later connected the first transversely arranged upright bar 2 using first crossbar 3, will be longitudinal using the first vertical pole 4 The first upright bar 2 connection of arrangement, the first crossbar 3 of longitudinal arrangement is connected, form cuboid frame shape at this time using the second vertical pole 6 The main frame of structure, then glued board 8 is installed in first crossbar 3 by flitch 7, it is installed later in the front of access way 1 Second upright bar 5 and reinforcing rod 11, then safety net 9 and Crossing brace 12 are sequentially arranged to the first upright bar 2 of 1 two sides of access way On, the front that warning panel is mounted on access way 1 is provided on frame, finally guardrail 10 is mounted in access way 1, at this time Guardrail 10 abuts the first upright bar 2.
Since two skewed reinforcing rods 11 are touched with ground respectively, the front of shielded frame is made to form stable three Angular framework improves the lateral stiffness of access way frame body, can avoid frame body double swerve, in addition the upper layer glue of glued board 8 Plywood and lower layer's glued board are arranged in parallel interval formula, and the top of access way 1 is made to form Double-protection structure, improve protection effect Fruit, furthermore in access way 1 when transporting equipment, the guardrail 10 of dressing structure can effectively avoid the first upright bar 2 hit and Bending, guarantees integrally-built stability.
In summary: a kind of civil construction project construction access way protective equipment structure, by reinforcing rod in symmetrical Formula is provided with two, and reinforcing rod is the setting of tilted structure setting, improves the lateral stiffness of access way frame body, can keep away Exempt from frame body double swerve;It include upper layer glued board and lower layer's glued board by glued board, and glued board passes through flitch and first The setting that cross bar is connected makes the top of access way form Double-protection structure, improves protection effect;It is dressing by guardrail Structure setting, and the upper end of guardrail is provided with the setting of handrail, can effectively avoid upright bar and is hit and be bent, and guarantees whole knot The stability of structure;By the improvement to a kind of civil construction project construction access way protective equipment structure, there is structure design Rationally, overall structure is stablized, and is easy to build, low in cost, the good advantage of protection effect, so that this is practical new for effective solution The problem of type proposes in background technique one and deficiency.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (8)

  1. The access way protective equipment structure 1. a kind of civil construction project is constructed, comprising: access way (1), the first upright bar (2), First crossbar (3), the first vertical pole (4), the second upright bar (5), the second vertical pole (6), flitch (7), glued board (8), safety net (9), Guardrail (10), reinforcing rod (11), Crossing brace (12);It is characterized by: the access way (1) is rectangular-shape structure setting; The two sides of access way (1) length direction are provided with the first upright bar (2) of equidistant radial arrangement, and the first upright bar (2) with Ground is connected by expansion bolt;The top of first upright bar (2) is provided with first crossbar (3), and first crossbar (3) with First upright bar (2) is connected by steel tube fastener;Several first vertical poles are provided on the length direction of the access way (1) (4) and the second vertical pole (6), and the first vertical pole (4) and the second vertical pole (6) pass through with the first upright bar (2), first crossbar (3) respectively Steel tube fastener is connected;Access way (1) front is provided with two the second upright bars (5) being symmetric;Described second One end of upright bar (5) is connected with ground by expansion bolt, and the other end of the second upright bar (5) passes through with first crossbar (3) Steel tube fastener is connected;The top of the first crossbar (3) is provided with several flitches (7), and flitch (7) passes through with cross bar (3) The mode of tying up is connected;The top of the flitch (7) is provided with glued board (8), and glued board (8) and flitch (7) pass through steel nail It is connected;It is provided with guardrail (10) on the inside of first upright bar (2), and is provided with safety net on the outside of the first upright bar (2) (9);The front of the access way (1) is provided with reinforcing rod (11), and reinforcing rod (11) respectively with the first vertical pole (4), second Vertical pole (6) is connected by steel tube fastener;It is provided with Crossing brace (12) on the outside of the safety net (9), and Crossing brace (12) Both ends are connected with the first upright bar (2) by steel tube fastener.
  2. The access way protective equipment structure 2. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: The reinforcing rod (11) is provided with two in symmetrical expression, and reinforcing rod (11) is tilted structure setting.
  3. The access way protective equipment structure 3. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: The glued board (8) includes upper layer glued board and lower layer's glued board, and glued board (8) passes through flitch (7) and first crossbar (3) It is connected.
  4. The access way protective equipment structure 4. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: The guardrail (10) is dressing structure setting, and the upper end of guardrail (10) is provided with handrail.
  5. The access way protective equipment structure 5. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: First upright bar (2), first crossbar (3), the first vertical pole (4), the second upright bar (5), the second vertical pole (6), reinforcing rod (11) and The material of Crossing brace (12) is steel pipe, and the model Φ 48*3.5 of steel pipe.
  6. The access way protective equipment structure 6. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: The shape of the Crossing brace (12) is in X-shape.
  7. The access way protective equipment structure 7. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: The lower end of first upright bar (2) and the second upright bar (5) is provided with the installation seat plate of square shape.
  8. The access way protective equipment structure 8. a kind of civil construction project according to claim 1 is constructed, it is characterised in that: The front of the access way (1) is provided with warning panel, and warning striped is painted in shown warning panel.
CN201821334829.5U 2018-08-13 2018-08-13 A kind of civil construction project construction access way protective equipment structure Expired - Fee Related CN208918325U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821334829.5U CN208918325U (en) 2018-08-13 2018-08-13 A kind of civil construction project construction access way protective equipment structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821334829.5U CN208918325U (en) 2018-08-13 2018-08-13 A kind of civil construction project construction access way protective equipment structure

Publications (1)

Publication Number Publication Date
CN208918325U true CN208918325U (en) 2019-05-31

Family

ID=66702138

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821334829.5U Expired - Fee Related CN208918325U (en) 2018-08-13 2018-08-13 A kind of civil construction project construction access way protective equipment structure

Country Status (1)

Country Link
CN (1) CN208918325U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144655A (en) * 2020-10-23 2020-12-29 中建一局集团建设发展有限公司 Steel structure traveling protection channel system in building and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144655A (en) * 2020-10-23 2020-12-29 中建一局集团建设发展有限公司 Steel structure traveling protection channel system in building and construction method thereof

Similar Documents

Publication Publication Date Title
CN208918325U (en) A kind of civil construction project construction access way protective equipment structure
CN110219306A (en) Concrete and the combined foundation pit support system of metal structure
CN201991226U (en) Flange template support structure
CN204282189U (en) A kind of long-span steel pipe arch bridge assembling construction structure
CN208563193U (en) A kind of traffic route temporary guard rail convenient for storage
CN206333096U (en) A kind of gardens cold-proof air partition of aithullium
CN105839933B (en) A kind of walk away safety protective fence
CN208152532U (en) A kind of construction scaffold
CN205314526U (en) Ledger board that scaffold was used
CN208294245U (en) A kind of Multifunctional garden guardrail
CN204282221U (en) Long-span steel pipe arch bridge assembling construction arch rib support
CN208748956U (en) A kind of steel support structure of protection canopy
CN210738118U (en) Assembled building processing shed
CN206267163U (en) Slope reinforcement structure
CN209508817U (en) A kind of steel arch tower construction operation platform
CN206352399U (en) One kind lengthens L-type back cord
CN204263673U (en) Pipe net overlay film fixture
CN207634084U (en) A kind of full assembled walkway structure of shield tunnel
CN207277978U (en) A kind of security partition protects gate upright
CN206173817U (en) Ally oneself with and arrange bailey frame crowd fastener -style pergola fixing system
CN205330128U (en) Door -type scaffold
CN204780613U (en) Pier shaft operation platform
CN209670463U (en) A kind of bilayer enclosing wall type steel grating
CN215906596U (en) Simple bridge guardrail operation platform
CN211229426U (en) Self-supporting steel pipe scaffold system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190531

Termination date: 20200813

CF01 Termination of patent right due to non-payment of annual fee