CN208907262U - A kind of starting point mounting structure of wall - Google Patents

A kind of starting point mounting structure of wall Download PDF

Info

Publication number
CN208907262U
CN208907262U CN201821191106.4U CN201821191106U CN208907262U CN 208907262 U CN208907262 U CN 208907262U CN 201821191106 U CN201821191106 U CN 201821191106U CN 208907262 U CN208907262 U CN 208907262U
Authority
CN
China
Prior art keywords
wall
keel
plate
starting point
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821191106.4U
Other languages
Chinese (zh)
Inventor
赵永生
徐正东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing New Building Material Group Co Ltd
Original Assignee
Beijing New Building Material Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing New Building Material Group Co Ltd filed Critical Beijing New Building Material Group Co Ltd
Priority to CN201821191106.4U priority Critical patent/CN208907262U/en
Application granted granted Critical
Publication of CN208907262U publication Critical patent/CN208907262U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

This application discloses a kind of starting point mounting structures of wall, including top wall and unit wall, it further includes opening keel, the keel that are open are arranged along the short transverse of unit wall, the keel that are open include bottom plate and the first side plate and the second side plate for being separately positioned on its two sides, bottom plate is fixed on top wall side, the first side plate and the prominent top wall of the second side plate;Unit wall is provided with splicing keel in the end face to offset with top wall, and splicing keel are vertically arranged, and splicing keel are provided with protrusion and groove, and protrusion and groove extend along the length direction of splicing keel;First side plate is inserted into groove, and is fixed with the cell wall far from protrusion of groove;Protrusion is bonded fixation with the second side plate backwards to the side wall of groove.This application involves building fields, provide a kind of starting point mounting structure of wall, can be avoided wall starting point production difference problem, not only can guarantee installation strength and convenience, but also can improve production efficiency, reduce production cost.

Description

A kind of starting point mounting structure of wall
Technical field
This application involves building field, the starting point mounting structure of espespecially a kind of wall.
Background technique
The building of conventional house building especially steel construction, one-piece casting cement structures, building inside can be according to specific Dwelling use needs and internal partition wall is arranged, and whole floor is divided into functional room one by one.Existing internal partition wall production Site operation is usually carried out using lightgage steel joist and plasterboard, this causes construction site in disorder, the building wastes such as waste material, leftover pieces Excessively, and be not suitable for that partition wall is removable recycles, the live amount of labour used is larger, and cost of labor is excessively high, construction dimensional accuracy compared with It is low.It is response country to the environmentally protective of novel building, batch production, rapid, removable, closed matereial cycle policy guidance Policy greatly develops novel fabricated partition wall technology, sets conventional modulus according to building size, interior outside integrated function every Wall large-scale production in factory is completed, and is fixedly mounted between lower floor plate as long as being transported to building construction scene, fastly It is fast succinct.
In order to realize wall end and come directly towards the abutting joint of metope, usually using top splicing module, and it is spliced into Other modular structures of wall are different, and which increase batch production flow line production assembled wall kind, breed difference causes to give birth to Production. art difference seriously affects the factorial production efficiency, increases production cost.
Utility model content
The technical issues of the application solves is to provide a kind of starting point mounting structure of wall, can be avoided wall starting point Difference problem is produced, not only can guarantee installation strength and convenience, but also production efficiency can be improved, reduces production cost.
In order to solve the above technical problems, this application provides a kind of starting point mounting structure of wall, including top wall and Unit wall, one end of the unit wall offset with the top wall, and the top wall and unit wall are perpendicular, T-shaped, It further includes opening keel, and the opening keel are arranged along the short transverse of the unit wall, and the opening keel include bottom Plate and the first side plate and the second side plate for being separately positioned on its two sides, the opening keel section are in groove-like, the bottom plate It is fixed on the top wall side, first side plate and the prominent top wall of the second side plate;The unit wall with institute It states the end face that top wall offsets and is provided with splicing keel, the splicing keel are vertically arranged, and the splicing keel are provided with to institute Top wall protrusion outstanding, and the groove being recessed to its inside are stated, the protrusion and groove are along the length side of the splicing keel To extension;First side plate is inserted into the groove, and is fixed with the cell wall far from the protrusion of the groove;It is described convex The side wall risen backwards to the groove is bonded fixation with second side plate.
A kind of possible design, the unit wall include two pieces of shingle nails and the heat preservation that is arranged between the shingle nail Material, the splicing keel are arranged between the two pieces of shingle nails in both ends and insertion of the unit wall length direction.
A kind of possible design, the adjacent unit wall pass through the splicing keel assembly being mutually inserted and are integrated, The protrusion matches with groove.
A kind of possible design is provided with supplement block between the shingle nail and top wall, to fill up the shingle nail With the gap between the wall of top.
A kind of possible design, second side plate are clipped between supplement block and the protrusion.
A kind of possible design, the splicing keel include web and the wing plate that its two sides is arranged in, the wing plate and wall Panel is fixed, and the protrusion and groove are arranged on the web.
A kind of possible design, the shingle nail are plasterboard, calcium silicate board, glass magnesium board, block of glass wool, ceramic plate, fire prevention Plate, abatvoix, carbon felt plate, cement plate, medium-density plate, Europe deals, metal plate, inorganic fiberboard, wood-plastic board or woodwork plate.
A kind of possible design, the thermal insulation material are rock wool, granulated wool, mineral wool, phenolic foam plate, polystyrene Plate, phenolic foam plate, polyurethane sheet, foamed ceramic plate, foamed glass plate, pearlite slab, aluminosilicate fiber cotton or ceramic fibre Cotton.
A kind of possible design, the splicing keel and opening keel are metal joist, wooden keel or wood moulding keel.
Compared with prior art, the starting point mounting structure of the wall of the utility model can be avoided the production of wall starting point Difference problem not only can guarantee installation strength and convenience, but also can improve production efficiency, reduce production cost.
Further, the adjacent cells wall of the utility model passes through the splicing keel assembly being mutually inserted and is integrated, should Splice keel from splicing, avoids being spliced using variform two connectors, be conducive to processing.
Further, it is provided with supplement block between the shingle nail of the utility model and top wall, keeps wall surface levelling beautiful, and Strengthen connection.
Other features and advantages of the utility model will illustrate in the following description, also, partly from specification In become apparent, or understood and implementing the utility model.The purpose of this utility model and other advantages can pass through Specifically noted structure is achieved and obtained in the specification, claims and drawings.
Detailed description of the invention
Attached drawing is used to provide to further understand technical solutions of the utility model, and constitutes part of specification, It is used to explain the technical solution of the utility model together with embodiments herein, not constitute to technical solutions of the utility model Limitation.
Fig. 1 is the starting point mounting structure schematic cross-section of wall;
Fig. 2 is partial enlarged view at the A of Fig. 1;
Fig. 3 is splicing keel schematic cross-section;
Fig. 4 is that unit wall splices schematic cross-section;
Fig. 5 is opening keel installation schematic diagram;
Fig. 6 is opening keel and splicing keel assembling schematic diagram;
Fig. 7 is supplement block assembling schematic diagram.
Appended drawing reference: 1- comes directly towards wall, 2- unit wall, 3- opening keel, 4- and splices keel, 5- shingle nail, 6- thermal insulating material Material, 7- screw, 8- protrusion, 9- groove, 10- bottom plate, the first side plate of 11-, the second side plate of 12-, 13- web, 14- wing plate, 15- are mended Fill block, the gap 16-.
Specific embodiment
It is practical to this below in conjunction with attached drawing for the purposes, technical schemes and advantages of the application are more clearly understood Novel embodiment is described in detail.It should be noted that in the absence of conflict, embodiment and implementation in the application Feature in example can mutual any combination.
Please refer to the embodiment of the starting point mounting structure of the wall of the utility model of Fig. 1 to Fig. 7.Such as Fig. 1 and Fig. 2 institute Showing, which includes top wall 1 and unit wall 2, wherein one end of unit wall 2 offsets with top wall 1, And top wall 1 and unit wall 2 are perpendicular, so that the two is constituted T-type, particularly, which further includes being fixed on Come directly towards the opening keel 3 on wall 1, and the splicing keel 4 being arranged on unit wall 2, wherein opening keel 3 are along unit wall The short transverse of body is vertically arranged, and specifically, which includes bottom plate 10 and the first side for being separately positioned on its two sides Plate 11 and the second side plate 12, and groove-like section is surrounded, and bottom plate 10 is fixed on top 2 side of wall, the first side plate 11 and second Side plate 12 then protrudes the metope of top wall 2.In addition, splicing keel 4 be arranged in unit wall 2 with the top end face that offsets of wall 1, The splicing keel 4 are also vertically arranged, i.e., are arranged along the short transverse of unit wall 2, and are spliced keel 4 and be provided with to top wall 1 Outstanding raised 8, and the groove 9 being recessed to its inside, and protrusion 8 and groove 9 extend along the length direction of the splicing keel 4. Especially attentively, in first side plate 11 insertion groove 9, and the cell wall with groove 9 far from protrusion 8 is fixed by screw 7, and convex It is fixed backwards to the side wall of groove 9 and the second side plate 12 patch merga pass screw 7 to play 8.The starting point mounting structure of the wall can be protected Installation strength and convenience are demonstrate,proved, and production efficiency can be improved, reduces production cost.
Specifically, as depicted in figs. 1 and 2, which includes two pieces of shingle nails 5 and is arranged between shingle nail 5 Thermal insulation material 6, and splice keel 4 and be arranged between the two pieces of shingle nails 5 in both ends and insertion of 1 length direction of unit wall.Wherein, The decorative cover of the shingle nail 5 as wall, be preferably but not limited to for plasterboard composition, can also for calcium silicate board, glass magnesium board, Block of glass wool, ceramic plate, fire-proof plate, abatvoix, carbon felt plate, cement plate, medium-density plate, Europe deals, metal plate, inorganic fiberboard, Wood-plastic board or woodwork plate, one or more layers plate are combined.The thermal insulation material 6 acts on the heat-insulated and sound insulation of wall, excellent It is selected as rock wool to be made, be selected according to use environment, also may be selected to use granulated wool, mineral wool, phenolic foam plate, polystyrene Plate, phenolic foam plate, polyurethane sheet, foamed ceramic plate, foamed glass plate, pearlite slab, aluminosilicate fiber cotton or ceramic fibre Cotton.And the splicing keel 4 then for the starting point installation of wall adjacent cells wall 2 between splicing, specifically, such as Fig. 3 and Shown in Fig. 4, which includes web 13 and the wing plate 14 that its two sides is arranged in, and wing plate 14 and shingle nail 5 are fixed, and on It states protrusion 8 and groove 9 is then arranged on web 13, wherein protrusion 8 and groove 9 match, and can be mutually inserted, adjacent as a result, Unit wall 2 is integrated by two 4 assembly of splicing keel being mutually inserted, so that processing in production a kind of for assembled spelling Building sequence bone 4 reduces production cost without processing two kinds of mating connectors;In addition, respective shingle nail 5 It is bonded to each other, avoids generating gap between two unit walls 2;And in the starting point of wall, which directly passes through splicing Keel 4 and top wall 1 are fixed, eliminate original wall end module, also further reduce the product category for needing to process, Reduce production cost.
Further, as shown in Fig. 5 and Fig. 2, which is U-shaped keel, the first side plate 11 and the second side plate 12 Splicing keel 4 are all stretched to, are provided with the supplement block levelling for metope between the shingle nail 5 and top wall 1 of the unit wall 1 15, so that the second side plate 12 is clipped between supplement block 15 and protrusion 8.First side plate 11 of the opening keel 3 is by successively squeezing into Shingle nail 5, wing plate 14, groove 9 and the first side plate 11 screw 7 be fixed on unit wall 1, and the second side plate 12 is by successively The screw 7 for squeezing into supplement block 15, the second side plate 11 and protrusion 8 is fixed on unit wall 1.Above-mentioned splicing keel 4 and opening dragon Bone 3 is selected as the molding metal joist of easy processing in advance.
The simple temperature of overall structure of the starting point mounting structure of the wall, installation method is also very convenient, is suitable for Site operation, its step are as follows: prime minister, the keel 3 that are open is fixed on to the predeterminated position of top wall 1, as shown in Figure 5;With that is, A module unit wall 2 is erected, keeps it opposite with mounted opening keel 3, the mobile unit wall 2, the of the keel 3 that make to be open Side plate 11 and the second side plate 12 are mounted respectively to the predeterminated position of groove 9 and protrusion 8, splicing keel 4 and opening 3 phase of keel It supports, there are gaps 16 between shingle nail 5 and top wall 1, as shown in Figure 6;Again, as shown in fig. 7, supplement block 15 is filled in In gap 16, make wall surface levelling;Finally, being fixed as one using the keel 3 that will be open of screw 7 with unit wall 2, wall is completed The installation at beginning.
In conjunction with above-described embodiment, the starting point mounting structure of the wall of the utility model can be avoided the production of wall starting point Difference problem not only can guarantee installation strength and convenience, but also can improve production efficiency, reduce production cost.The utility model Adjacent cells wall passes through the splicing keel assembly being mutually inserted and is integrated, which avoids using shape not from splicing Two same connectors are spliced, and processing is conducive to.Supplement is provided between the shingle nail and top wall of the utility model Block keeps wall surface levelling beautiful, and strengthens connection.
In the description of the present application, term " installation ", " connected ", " connection ", " fixation " etc. be shall be understood in a broad sense, example Such as, " connection " may be fixed connection or may be dismantle connection, or integral connection;It can be directly connected, it can also be with Indirectly connected through an intermediary.For the ordinary skill in the art, above-mentioned art can be understood as the case may be The concrete meaning of language in this application.
In the description of this specification, the description of term " one embodiment ", " some embodiments ", " specific embodiment " etc. Mean that particular features, structures, materials, or characteristics described in conjunction with this embodiment or example are contained at least one reality of the application It applies in example or example.In the present specification, schematic expression of the above terms are not necessarily referring to identical embodiment or reality Example.Moreover, description particular features, structures, materials, or characteristics can in any one or more of the embodiments or examples with Suitable mode combines.
Although embodiment disclosed by the utility model is as above, the content only the utility model for ease of understanding And the embodiment used, it is not intended to limit the utility model.Technical staff in any the utility model fields, Under the premise of not departing from spirit and scope disclosed by the utility model, it can be carried out in the form and details of implementation any Modification and variation, but the scope of patent protection of the utility model, still should be subject to the scope of the claims as defined in the appended claims.

Claims (9)

1. a kind of starting point mounting structure of wall, including top wall and unit wall, one end of the unit wall with it is described Top wall offsets, and the top wall and unit wall are perpendicular, T-shaped, which is characterized in that it further includes opening keel, described The keel that are open are arranged along the short transverse of the unit wall, and the opening keel include bottom plate and are separately positioned on its two sides The first side plate and the second side plate, the opening keel section is in groove-like, and the bottom plate is fixed on the top wall side, institute State the first side plate and the prominent top wall of the second side plate;
The unit wall is provided with splicing keel in the end face to offset with the top wall, and the splicing keel are vertically arranged, The splicing keel are provided with to top wall protrusion outstanding, and the groove being recessed to its inside, the protrusion and groove Length direction along the splicing keel extends;
First side plate is inserted into the groove, and is fixed with the cell wall far from the protrusion of the groove;The protrusion Side wall backwards to the groove is bonded fixation with second side plate.
2. starting point mounting structure according to claim 1, which is characterized in that the unit wall includes two pieces of shingle nails And the both ends of the unit wall length direction are arranged in the thermal insulation material being arranged between the shingle nail, the splicing keel And between two pieces of shingle nails of insertion.
3. starting point mounting structure according to claim 2, which is characterized in that the adjacent unit wall passes through phase interfix The splicing keel assembly connect is integrated, and the protrusion matches with groove.
4. starting point mounting structure according to claim 2, which is characterized in that be arranged between the shingle nail and top wall There is supplement block, to fill up the shingle nail and come directly towards the gap between wall.
5. starting point mounting structure according to claim 4, which is characterized in that second side plate is clipped in the supplement block Between protrusion.
6. starting point mounting structure according to claim 2, which is characterized in that the splicing keel include web and setting Wing plate in its two sides, the wing plate are fixed with shingle nail, and the protrusion and groove are arranged on the web.
7. according to any starting point mounting structure of claim 2-6, which is characterized in that the shingle nail be plasterboard, Calcium silicate board, glass magnesium board, block of glass wool, ceramic plate, fire-proof plate, abatvoix, carbon felt plate, cement plate, medium-density plate, Europe deals, gold Belong to plate, inorganic fiberboard, wood-plastic board or woodwork plate.
8. according to any starting point mounting structure of claim 2-6, which is characterized in that the thermal insulation material be rock wool, Granulated wool, mineral wool, phenolic foam plate, polystyrene board, phenolic foam plate, polyurethane sheet, foamed ceramic plate, foamed glass Plate, pearlite slab, aluminosilicate fiber cotton or ceramic fiber cotton.
9. -6 any starting point mounting structure according to claim 1, which is characterized in that the splicing keel and opening dragon Bone is metal joist, wooden keel or wood moulding keel.
CN201821191106.4U 2018-07-25 2018-07-25 A kind of starting point mounting structure of wall Active CN208907262U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821191106.4U CN208907262U (en) 2018-07-25 2018-07-25 A kind of starting point mounting structure of wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821191106.4U CN208907262U (en) 2018-07-25 2018-07-25 A kind of starting point mounting structure of wall

Publications (1)

Publication Number Publication Date
CN208907262U true CN208907262U (en) 2019-05-28

Family

ID=66612672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821191106.4U Active CN208907262U (en) 2018-07-25 2018-07-25 A kind of starting point mounting structure of wall

Country Status (1)

Country Link
CN (1) CN208907262U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111705969A (en) * 2020-06-28 2020-09-25 北新集团建材股份有限公司 Assembly type wall top packaging structure and mounting method thereof
CN111705967A (en) * 2020-06-28 2020-09-25 北新集团建材股份有限公司 Pipeline-separated assembled wall and installation method
CN111705970A (en) * 2020-06-28 2020-09-25 北新集团建材股份有限公司 Assembled wall body starting end and installation method thereof
CN111719740A (en) * 2020-06-28 2020-09-29 北新集团建材股份有限公司 Decoration integrated assembly type wall body and installation method thereof
CN112854547A (en) * 2020-12-31 2021-05-28 中建材创新科技研究院有限公司 Wall body mounting structure
CN115030368A (en) * 2022-06-30 2022-09-09 北新集团建材股份有限公司 T-shaped modular wall and mounting method thereof
CN115030369A (en) * 2022-06-30 2022-09-09 北新集团建材股份有限公司 Two segmentation wall structure
CN115447220A (en) * 2022-11-10 2022-12-09 河南省新盛建筑节能装饰有限公司 Self preservation temperature assembled wallboard and apparatus for producing

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111705969A (en) * 2020-06-28 2020-09-25 北新集团建材股份有限公司 Assembly type wall top packaging structure and mounting method thereof
CN111705967A (en) * 2020-06-28 2020-09-25 北新集团建材股份有限公司 Pipeline-separated assembled wall and installation method
CN111705970A (en) * 2020-06-28 2020-09-25 北新集团建材股份有限公司 Assembled wall body starting end and installation method thereof
CN111719740A (en) * 2020-06-28 2020-09-29 北新集团建材股份有限公司 Decoration integrated assembly type wall body and installation method thereof
CN111705967B (en) * 2020-06-28 2021-08-10 北新集团建材股份有限公司 Pipeline-separated assembled wall and installation method
CN112854547A (en) * 2020-12-31 2021-05-28 中建材创新科技研究院有限公司 Wall body mounting structure
CN115030368A (en) * 2022-06-30 2022-09-09 北新集团建材股份有限公司 T-shaped modular wall and mounting method thereof
CN115030369A (en) * 2022-06-30 2022-09-09 北新集团建材股份有限公司 Two segmentation wall structure
CN115030369B (en) * 2022-06-30 2023-08-15 北新集团建材股份有限公司 Two-section wall structure
CN115030368B (en) * 2022-06-30 2023-09-19 北新集团建材股份有限公司 T-shaped modular wall and installation method thereof
CN115447220A (en) * 2022-11-10 2022-12-09 河南省新盛建筑节能装饰有限公司 Self preservation temperature assembled wallboard and apparatus for producing
CN115447220B (en) * 2022-11-10 2023-02-07 河南省新盛建筑节能装饰有限公司 Self-heat-preservation assembled wallboard and production device

Similar Documents

Publication Publication Date Title
CN208907262U (en) A kind of starting point mounting structure of wall
CN208918079U (en) A kind of rigidity splicing construction and assembled wall
CN208918080U (en) A kind of wall
CN208907267U (en) A kind of assembled wall being easily installed
CN204715611U (en) A kind of corner unit of assembling body of wall
CN205894373U (en) Certainly, cooperation mosaic structure of assembled wall body
CN101302779A (en) Cast-in-situ light composite wall
CN209227776U (en) A kind of three-dimensional building module
CN107435395B (en) Self-matching splicing structure of assembled wall body and splicing method thereof
CN201011009Y (en) Cast-in-situ light compound wall
CN206971476U (en) A kind of assembled wall increases structure
CN101089307A (en) Cast-in-place light compound wall
KR20090010751A (en) Lightweight uneven finishing block for constructiwooden structure
CN108951937A (en) A kind of assembled wall origination end and installation method
CN207633569U (en) A kind of prefabricated pearlite heat-insulation plate door-window opening structure
KR200407650Y1 (en) A steel-wood composite beam and its manufacturing method
CN110761445A (en) Rigid splicing structure, assembled wall body and manufacturing and mounting method
CN106193443A (en) The door-window opening wall element of a kind of assembled body of wall and production method thereof
CN106193427B (en) A kind of corner unit and its production method of assembled wall
CN208918087U (en) A kind of assembled wall with pipeline
CN204876284U (en) Cross unit of assembled wall body
CN208918086U (en) A kind of keel fasten the assembled wall of shingle nail
CN204781447U (en) T type turning unit of assembled wall body
CN204715620U (en) A kind of door and window hole wall element of assembling body of wall
CN108049506A (en) Prefabricated house system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant