Prior art keywords
plate
otic placode
hoist cable
steel anchor
otic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821577672.9U
Other languages
Chinese (zh)
Inventor
许志艳
艾智能
刘伟
何恺
陈克坚
游励晖
韩国庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201821577672.9U priority Critical patent/CN208884360U/en
Application granted granted Critical
Publication of CN208884360U publication Critical patent/CN208884360U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of steel anchor boxes suitable for rail iron trusses suspension bridge straddle-type hoist cable, including top plate, bottom plate, two webs and two side plates, top plate, bottom plate, two webs and two side plates form body structure, wherein, two side plates are each parallel to top boom integral node plate otic placode, and side plate and top boom integral node plate otic placode detachable connection, otic placode there are two being set on body structure, the distance between less than two top boom integral node plate otic placodes of the distance between two otic placodes, and the distance between two otic placodes are adapted with main push-towing rope cord clip, otic placode is equipped with the otic placode pin hole to connect hoist cable, mounting hole is equipped in the middle part of top plate.The utility model adapts it to the installation requirement of main push-towing rope cord clip by shortening the spacing between two otic placodes;Steel anchor box is designed to independent structure by the utility model, has both been facilitated factory's manufacture and in-site installation, has been also convenient for later period maintenance and replacement.

Description

A kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable
Technical field
The utility model relates to a kind of steel anchor boxes, in particular to a kind of to be suitable for rail iron trusses suspension bridge straddle-type hoist cable Steel anchor box.
Background technique
Sling of suspension bridge and main push-towing rope are connected with straddle-type and pin joint formula.For straddle-type hoist cable, both ends anchor head is both needed to It is connected with stiff girder.To highway steel trusses suspension bridge, upper cord member cross-sectional width is generally smaller than main push-towing rope cord clip diameter, therefore, The otic placode that straddle-type hoist cable both ends anchor head directly extends with top boom two sides integral node plate mostly is connected.
But with the development of railway construction, in order to be applicable in a variety of different demands, there is rail iron trusses suspension bridge The bigger situation of upper cord member cross-sectional width, upper cord member cross-sectional width is even more much bigger than main push-towing rope cord clip diameter, at this point, The connection otic placode of straddle-type hoist cable anchor head cannot directly utilize the integral node plate of top boom, need to develop a kind of novel Suitable for steel anchor box of upper cord member cross-sectional width when larger.
Utility model content
The purpose of the utility model is to overcome the above-mentioned deficiencies in the presence of the prior art, provide a kind of suitable for railway The steel anchor box of steel trussed girder suspension bridge straddle-type hoist cable.
In order to achieve the above-mentioned object of the invention, the utility model provides following technical scheme:
A kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable, including top plate and bottom plate, two webs and Two side plates, the top plate and bottom plate, two webs and two side plates form body structure.Wherein, two side plates are parallel In top boom integral node plate otic placode, and the side plate and the top boom integral node plate otic placode detachable connection, it is described Two otic placodes, less than two top boom integral node plate ears of the distance between two described otic placodes are additionally provided on body structure The distance between plate, and the distance between two described otic placodes are adapted with main push-towing rope cord clip, the otic placode is equipped with and hangs to connect The otic placode pin hole of rope, the top plate middle part are equipped with mounting hole.
The steel anchor box of the utility model design passes through by otic placode design between two top boom integral node plate otic placodes Shorten the spacing between two otic placodes, so that the spacing between two otic placodes is less than main push-towing rope cord clip diameter, adapt it to main push-towing rope cord clip Installation requirement, thus when solving rail iron trusses suspension bridge using straddle-type hoist cable, because of steel truss girder top boom section transverse direction Size is greater than hoist cable and girder steel connectivity problem when main push-towing rope cord clip diameter, and the utility model is suitable for rail iron trusses suspension bridge The larger situation of upper cord member cross-sectional width.Further, steel anchor box is designed to independent structure by the utility model, has abandoned steel The traditional method of anchor case and the welding of integral node plate otic placode, is changed to detachable connection, has both facilitated factory's manufacture and scene peace Dress, is also convenient for later period maintenance and replacement.
Preferably, two otic placodes are arranged in parallel, and are parallel to the side plate.Two otic placodes are located at two side plates Between, and two side plates are parallel to, and therefore, it is ensured that the spacing between less than two side plates of spacing between two otic placodes, and By optimization design, so that the distance between two described otic placodes are adapted with main push-towing rope cord clip.
Preferably, the upper and lower ends of two otic placodes are connected on the top plate and bottom plate, can be directly in factory It is welded to connect.
Preferably, the otic placode is being equipped with otic placode stiffening plate at each otic placode pin hole, guarantees to connect with hoist cable Connect the structural strength at place.
Preferably, the bottom plate is located at the top of top boom top plate, and steel anchor box is arranged using the space above top boom, and It is attached with hoist cable, installation space is big, reduces connection difficulty;And there is certain interval between bottom plate and top boom top plate, it keeps away Exempt from internal force and be directly passed to top boom top plate, causes top boom top plate stress excessive.
Preferably, the length of each otic placode is greater than the distance between two described webs, and each otic placode includes The first otic placode between two webs, and two the second otic placodes positioned at the web outside.Wherein, the first ear Plate is located in the box body portion, and the both ends of first otic placode are connected with two webs, mainly to connect hoist cable, and second Otic placode is located at tank ends, mainly to change rope.
Preferably, the side plate is equipped with several bolts hole, convenient between side plate and top boom integral node plate otic placode Bolt.
Preferably, it is connected by high-strength bolts, connects between the side plate and the top boom integral node plate otic placode Reliably, bonding strength is high.
Preferably, it is equipped with hand hole in the middle part of the bottom plate, facilitates the welding between component.
Preferably, several drain holes are additionally provided on the bottom plate, ensure not accumulate in steel anchor box together with the hand hole of bottom plate Water.
Preferably, the top plate and bottom plate, two webs, two side plates, be to be welded to connect between two otic placodes, production Convenient, connection is reliably.
Compared with prior art, the utility model has the beneficial effects that
The steel anchor box of the utility model design passes through by otic placode design between two top boom integral node plate otic placodes Shorten the spacing between two otic placodes, so that the spacing between two otic placodes is less than main push-towing rope cord clip diameter, adapt it to main push-towing rope cord clip Installation requirement, thus when solving rail iron trusses suspension bridge using straddle-type hoist cable, because of steel truss girder top boom section transverse direction Size is greater than hoist cable and girder steel connectivity problem when main push-towing rope cord clip diameter, and the utility model is suitable for rail iron trusses suspension bridge The larger situation of upper cord member cross-sectional width.Further, steel anchor box is designed to independent structure by the utility model, has abandoned steel The traditional method of anchor case and the welding of integral node plate otic placode, is changed to detachable connection, has both facilitated factory's manufacture and scene peace Dress, is also convenient for later period maintenance and replacement.
Detailed description of the invention:
Fig. 1 is a kind of the vertical of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable described in the utility model Face schematic diagram.
Fig. 2 is the structural schematic diagram of otic placode described in the utility model.
Fig. 3 is the structural schematic diagram of side plate described in the utility model.
Fig. 4 is the structural schematic diagram of top plate described in the utility model.
Fig. 5 is the structural schematic diagram of bottom plate described in the utility model.
Marked in the figure: 1- top plate, 2- bottom plate, 3- web, 4- side plate, 5- otic placode, the first otic placode of 5a-, the second otic placode of 5b-, 6- otic placode stiffening plate, 7- otic placode pin hole, 8- bolt hole, 9- top boom integral node plate otic placode, 10- top boom item plate, 11- peace Fill hole, 12- hand hole, 13- drain hole.
Specific embodiment
The utility model is described in further detail below with reference to test example and specific embodiment.But it should not be by this The range for being interpreted as the above-mentioned theme of the utility model is only limitted to embodiment below, all to be realized based on the content of the present invention Technology belongs to the scope of the utility model.
As Figure 1-Figure 2, a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable, including top plate 1, The side plate 4 of web 3, two of bottom plate 2, two and two groups of otic placodes 5 being connected with hoist cable.Otic placode 5 described in every group includes connecting with hoist cable The first otic placode 5a connect and two, which change on the second otic placode 5b, each first otic placode 5a of rope, is arranged several otic placode pin holes 7 and otic placode stiffening plate 6;One otic placode pin hole 7 and otic placode stiffening plate 6 are set on each second otic placode 5b.Each first ear Plate 5a is arranged between two webs 3, and each second otic placode 5b is arranged in the outside of the web 3.
The top plate 1,2, two webs 3 of bottom plate and two side plates 4 form body structure, and web 3 and side plate 4 vertically connect It connects, otic placode 5 is located between two side plates 4, and is parallel to two side plates 4, therefore, it is ensured that the spacing between two otic placodes 5 is small Spacing between two side plates 4, and by optimization design, so that the distance between two described otic placodes 5 and main push-towing rope cord clip phase Adaptation, in general, the distance between two described otic placodes 5 are less than main push-towing rope cord clip diameter.Wherein, the first otic placode 5a is embedded In cabinet, the second otic placode 5b is arranged in tank ends, connect with top plate 1, bottom plate 2 and web 3.In steel anchor box between each component It is all made of welded connecting.
As shown in figure 3, two side plates 4 are equipped with a certain number of bolts hole 8, when installation, the side plate 4 is close to Top boom integral node plate otic placode 9 is connected between the side plate 4 and top boom integral node plate otic placode 9 by high-strength bolt It connects, and the bottom plate 2 is finally fixed on to the top of top boom top plate 10.
As shown in figure 4, being equipped with mounting hole 11 in the middle part of top plate 1, so that hoist cable anchor head is connected with the first otic placode 5a, need simultaneously Meet bolt requirements of installation space.
As shown in figure 5, being equipped with hand hole 12 in the middle part of the bottom plate 2, both facilitated the welding between component, at the same with two sides drain hole 13 ensure in steel anchor box not ponding together.
The force path of steel anchor box is as follows: steel truss girder internal force passes through top boom integral node plate ear by high-strength bolt Frictional force between plate 9 and side plate 4 passes to steel anchor box, and internal force passes to web 3 by side plate 4 in steel anchor box, and web 3 transmits Hoist cable is passed to again to the first otic placode 5a, the first otic placode 5a.Top plate 1 and bottom plate 2 participate in the stress of web 3, and bottom plate 2 participates in first The stress of otic placode 5a.
Above embodiments are only to illustrate the utility model and not limit technical solution described in the utility model, to the greatest extent Pipe this specification has been carried out detailed description to the utility model referring to above-mentioned each embodiment, but the utility model not office It is limited to above-mentioned specific embodiment, therefore any pair of the utility model is modified or equivalent replacement;And all do not depart from it is practical The technical solution and its improvement of novel spirit and scope, should all cover in the scope of the claims of the utility model.

Claims (10)

1. a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable, which is characterized in that including top plate (1), bottom Plate (2), two webs (3) and two side plates (4), the top plate (1), bottom plate (2), two webs (3) and two side plate (4) groups At body structure, wherein
Two side plates (4) are each parallel to top boom integral node plate otic placode (9), and the side plate (4) and the top boom Integral node plate otic placode (9) detachable connection is additionally provided with two otic placodes (5), two otic placodes (5) on the body structure The distance between less than the distance between two described top boom integral node plate otic placodes (9), and between two otic placodes (5) Distance be adapted with main push-towing rope cord clip, each otic placode (5) is equipped with to the otic placode pin hole (7) that connects hoist cable, the top plate (1) middle part is equipped with mounting hole (11).
2. a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable according to claim 1, feature It is, two otic placodes (5) are arranged in parallel, and are parallel to the side plate (4).
3. a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable according to claim 1, feature It is, the upper and lower ends of two otic placodes (5) are connected on the top plate (1) and bottom plate (2).
4. a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable according to claim 1, feature It is, each otic placode (5) is being equipped with otic placode stiffening plate (6) at each otic placode pin hole (7).
5. a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable according to claim 1, feature It is, the bottom plate (2) is located at the top of top boom top plate (10).
6. a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable according to claim 1, feature It is, the length of each otic placode (5) is greater than the distance between two described webs (3), and each otic placode (5) includes position The first otic placode (5a) between two webs (3), and it is located at two the second otic placodes on the outside of the web (3) (5b)。
7. a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable according to claim 6, feature It is, the both ends of first otic placode (5a) are connected with two webs (3).
8. -7 any a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable according to claim 1, It is characterized in that, the side plate (4) is equipped with several bolts hole (8).
9. -7 any a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable according to claim 1, It is characterized in that, being equipped with hand hole (12) in the middle part of the bottom plate (2).
10. a kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable according to claim 9, feature It is, several drain holes (13) is additionally provided on the bottom plate (2).
CN201821577672.9U 2018-09-25 2018-09-25 A kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable Active CN208884360U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821577672.9U CN208884360U (en) 2018-09-25 2018-09-25 A kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821577672.9U CN208884360U (en) 2018-09-25 2018-09-25 A kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable

Publications (1)

Publication Number Publication Date
CN208884360U true CN208884360U (en) 2019-05-21

Family

ID=66514070

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821577672.9U Active CN208884360U (en) 2018-09-25 2018-09-25 A kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable

Country Status (1)

Country Link
CN (1) CN208884360U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056531A (en) * 2018-09-25 2018-12-21 中铁二院工程集团有限责任公司 A kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable
CN110387832A (en) * 2019-08-19 2019-10-29 中冶建工集团有限公司 A kind of lifting device of bridge steel anchor box segment

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056531A (en) * 2018-09-25 2018-12-21 中铁二院工程集团有限责任公司 A kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable
CN109056531B (en) * 2018-09-25 2024-03-12 中铁二院工程集团有限责任公司 Steel anchor box suitable for riding type sling of railway steel truss girder suspension bridge
CN110387832A (en) * 2019-08-19 2019-10-29 中冶建工集团有限公司 A kind of lifting device of bridge steel anchor box segment

Similar Documents

Publication Publication Date Title
CN208884360U (en) A kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable
CN101613990B (en) Construction method of railway steel truss girder T-shaped stiffening rib orthotropic slab bridge deck
CN111254759A (en) Suspension type single rail
CN209583380U (en) Lifting beam machine single, double line box beam Universal hanger
CN203173749U (en) Assembled integral type vertical self-jacking device of hydraulic double-type crane tower
CN207176982U (en) A kind of new anti-buckling steel plate damping wall
CN208830163U (en) A kind of steel anchor box suitable for rail iron trusses suspension bridge pin joint formula hoist cable
CN202688848U (en) Anchoring connecting structure for nodes of composite truss girder cable-stayed bridge
CN103979429A (en) Cantilever type portal crane
CN206289544U (en) A kind of simple electric nacelle device
CN204644869U (en) Drag-line bridge tower anchoring structure
CN207844882U (en) Steel column and crane girder connecting structure
CN208869942U (en) A kind of long-span continuous rigid-framed bridge external prestressing load system
CN109056531A (en) A kind of steel anchor box suitable for rail iron trusses suspension bridge straddle-type hoist cable
CN203334182U (en) Structure used for connecting railway concrete retaining wall with steel bridge panel
CN207314053U (en) Support device based on empty rail train rail
CN202416173U (en) Wide girder bridge floor system structure with horizontal K support
CN201634343U (en) Large tower crane and transition joint used thereby
CN205046924U (en) Wind power generation tower with can flexible down tube of a stretch -draw
CN205555882U (en) Heavy single track hangs
CN107794814B (en) Suspension type single-rail double-line steel track beam system
CN208201514U (en) The connecting structure and track girder system of suspension type monorail prefabricated crossbeam and precast pier
CN208949719U (en) A kind of prefabricated crossbeam, precast pier and the connecting structure of complete prefabricated shipping sky rail
CN109056529B (en) Steel anchor box suitable for pin joint type sling of railway steel truss girder suspension bridge
CN206693060U (en) A kind of hoisting device for the lifting of suspension bridge saddle bearing plate

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant