CN208870386U - A kind of constructional column pours mold - Google Patents
A kind of constructional column pours mold Download PDFInfo
- Publication number
- CN208870386U CN208870386U CN201821463957.XU CN201821463957U CN208870386U CN 208870386 U CN208870386 U CN 208870386U CN 201821463957 U CN201821463957 U CN 201821463957U CN 208870386 U CN208870386 U CN 208870386U
- Authority
- CN
- China
- Prior art keywords
- feed hopper
- constructional column
- sleeve pipe
- described sleeve
- pours mold
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model relates to constructional column security hardening technical field of structures in construction more particularly to a kind of constructional column to pour mold.It includes feed hopper, casing, annular buckle, filter screen and valve, described sleeve pipe one end is connect with the discharge port of the feed hopper, the annular buckle is mounted on the junction of the feed hopper and described sleeve pipe, for the feed hopper and described sleeve pipe to be tightly connected, the filter screen is arranged in the feed hopper, the valve is arranged in the junction, and perpendicular with the axial direction of the junction.Difficulty is poured by using what constructional column provided by the utility model poured that mold can reduce higher structure peripheral constructional column, avoids tradition from pouring mode bring and manually wastes, and security risk present in pouring.
Description
Technical field
The utility model relates to construction engineering technical fields more particularly to a kind of constructional column to pour mold.
Background technique
Constructional column is concrete component important in brick-and-concrete buildings.For the shock resistance for improving skyscraper masonry structure
Can, code requirement is in the masonry in house certain reinforced column should to be arranged and connect with collar tie beam in suitable position, from
And play the role of reinforcing structure stability, this reinforced column is usually thus referred to as constructional column.Constructional column is mainly made
With not undertaking vertical load, but for resisting the lateral loads power such as shearing force.
It says, constructional column concreting, refers to after per adjacent two walls molding, to two walls from construction angle
The position reserved between body pours constructional column using concrete.But during present Constructional Col-umn Construction, structure peripheral
Constructional column is poured in the presence of very big difficult point, mainly has difficult point as follows:
When constructional column is relatively high, operating platform is set up using steel pipe or flitch according to the conventional method, then again by coagulation
Soil is reserved pouring hole from top and is poured into several times, in this way construction lost labor, and it is larger to set up operating platform difficulty.If using length
Bar strainer, then concrete is put into strainer first, then concrete is perfused whipping stock by several times, such casting concrete
Slowly, and it is not easy for concrete to be accurately filled into preformed hole, easy ejecta pollution masonry panel surface is same in filling concrete
When there are security risks.Two kinds of above-mentioned methods waste concrete, shadow since concreting will lead to concrete initial set slowly excessively
Ring construction quality.
Therefore, it needs a kind of constructional column and pours mold to solve above-mentioned technical problem.
Utility model content
The purpose of this utility model is to provide a kind of constructional columns to pour mold, to reduce higher structure peripheral constructional column
Pour difficulty, avoid tradition from pouring mode bring and manually waste, and security risk present in pouring.
For this purpose, the utility model uses following technical scheme:
A kind of constructional column pours mold, including feed hopper, casing, annular buckle, filter screen and valve, described sleeve pipe one
End is connect with the discharge port of the feed hopper, and the annular buckle is mounted on the junction of the feed hopper and described sleeve pipe, is used
In by the feed hopper and described sleeve pipe sealed connection, the filter screen is arranged in the feed hopper, and the valve setting exists
The junction, and it is perpendicular with the axial direction of the junction.
Preferably, feed hopper top left and right ends are respectively fixedly connected with fixed plate.
Preferably, the inside of feed hopper described in the feed hopper is in infundibulate.
Preferably, the discharge outlet of the feed hopper is fixedly connected with cylindrical discharge nozzle, described sleeve pipe and it is described go out
Expects pipe connection, the annular buckle are mounted on the junction of described sleeve pipe Yu the discharge nozzle.
Preferably, the feed hopper is made of stainless steel.
Preferably, the section of described sleeve pipe is circular ring shape.
Preferably, described sleeve pipe internal diameter matches with the discharging pipe outside diameter.
Preferably, the material of described sleeve pipe is rubber.
Preferably, multiple annulars are uniformly arranged in the discharge nozzle and described sleeve pipe junction to buckle.
Preferably, the material of the annular buckle is iron wire.
The utility model has the beneficial effects that
1) constructional column provided by the utility model pours mold using Demountable, and production is simple, installing and dismounting effect
Rate is high, while avoiding setting up operating platform, saves the time, saves manually, improve work efficiency, solve falling object from high altitude
The security risk of generation.
2) mold is poured by using the constructional column and guarantees that constructional column pours integrated molding, masonry wall body surface will not be polluted
Face is not required to post-processing, while guaranteeing concrete fast pouring, reduces the waste of concrete, improves construction quality.
3) material that mold uses can be recycled, and can save material, save cost, meet wanting for green construction
It asks.
Detailed description of the invention
It, below will be right in order to illustrate more clearly of specific embodiment of the present invention or technical solution in the prior art
Specific embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, it is described below
In attached drawing be that some embodiments of the utility model are not paying creativeness for those of ordinary skill in the art
Under the premise of labour, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the main view that the utility model constructional column pours mold;
Fig. 2 is the top view that the utility model constructional column pours mold;
In figure: 1- feed hopper;2- casing;3- annular buckle;4- fixed plate;5- filter screen;6- valve.
Specific embodiment
The technical solution of the utility model is further illustrated with embodiment with reference to the accompanying drawing.It is understood that this
Locate described specific embodiment and is used only for explaining the utility model, rather than the restriction to the utility model.It further needs exist for
Illustrate, illustrates only part relevant to the utility model for ease of description, in attached drawing and not all.
As depicted in figs. 1 and 2, the utility model provides a kind of constructional column and pours mold comprising feed hopper 1, casing 2,
Annular buckle 3, filter screen 5 and valve 6,2 one end of casing are connect with the discharge port of feed hopper 1, and annular buckle 3 is mounted on charging
The junction of bucket 1 and casing 2, for connecting feed hopper with bobbin seal, filter screen 5 is arranged in feed hopper 1, and valve 6 is set
It sets in junction, and perpendicular with the axial direction of junction.When constructional column pours, upper one layer of floor where it need to pour constructional column
Casing 2 is inserted at the top of constructional column to be poured, is then poured into concrete in construction column template by feed hopper 1.Guaranteeing
While speed of perfusion, reduces caused by concrete splashes and waste, improve construction quality.
Specifically, feed hopper 1 is using having some strength, material that is not perishable while being easy to bending process again, preferably
Ground uses stainless steel material, but does not do excessive restriction herein.The inside of feed hopper 1 is in infundibulate, to guarantee that concrete is smooth
It pours into construction column template.The inlet orifice section of feed hopper 1 can be rectangle, can also be made into its section according to the actual needs
Different shapes does not do excessive restriction herein.The discharge outlet of feed hopper 1 is fixedly connected with discharge nozzle, and the discharging tube shape is preferred
For cylinder, it is also possible to other shapes.It is that feed hopper 1 and the connection of casing 2 provide convenience by setting discharge nozzle.Into
Hopper 1 is internally provided with filter screen 5, and filter screen 5 is arranged between inlet orifice and discharge port, and close with feed hopper inner wall
Ground fitting, for the uneven concrete for generating agglomeration of stirring to be filtered away, in each fixation in top left and right ends of feed hopper 1
It is connected and fixed plate 4, is used in casting process, fixture construction column pours mold, to guarantee that casting process is gone on smoothly.
Specifically, casing 2 uses rubber material, and certainly, the material of casing 2 is not limited thereto, and is also possible to other tools
There are certain flexibility, and uncorruptible material, does not also do excessive restriction herein.Casing 2 is increased using the material with certain flexibility
Constructional column has been added to pour the adaptability of mold difference architectural environment.The section of casing 2 is circular ring shape, the internal diameter of casing 2 and charging
The discharging pipe outside diameter of 1 lower end of struggling against matches.It is easy for installation in the case where realizing close-connected situation.The length of casing 2 can basis
Practice of construction select.The junction of feed hopper 1 and casing 2 is provided with valve 6, the axis of valve 6 and junction
To size that is perpendicular, being open by control valve 6, the control to speed of perfusion is realized.
Further, iron wire of the annular buckle 3 by easily obtaining on construction site is made, it is of course also possible to use other
With certain toughness and intensity and material not easy to break, excessive restriction is not done herein yet.In order to guarantee casing 2 and feed hopper 1
Stable connection is reliable, is in use not in optionally, uniformly to set in casing 2 and the junction of feed hopper 1 the phenomenon that falling off
Set multiple annular buckles 3.
Constructional column provided by the utility model pours mold using Demountable, is easy to make, construction personnel is quickly
It can be familiar with grasping, while avoiding setting up operating platform, save the time, saving is artificial, improves work efficiency, and guarantees mixed
Solidifying soil fast pouring, reduces waste caused by concrete splashes.Mold is poured by using the constructional column and guarantees that constructional column pours
Integrated molding is built, masonry panel surface will not be polluted, be not required to post-processing, the security risk of falling object from high altitude generation is solved, mentions
The high safety and construction quality of construction.
The material that mold uses can be recycled, and can save material, save cost, meet the requirement of green construction.
Obviously, the above embodiments of the present invention is used for the purpose of clearly illustrating examples for clearly illustrating the present invention, and
It is not limitations of the embodiments of the present invention.For those of ordinary skill in the art, in above description
On the basis of can also make other variations or changes in different ways.There is no need and unable to give all embodiments
Exhaustion.Any modifications, equivalent replacements, and improvements made within the spirit and principle of the present invention etc., should be included in
Within the protection scope of the utility model claims.
Claims (10)
1. a kind of constructional column pours mold characterized by comprising feed hopper (1), casing (2), annular buckle (3), filter screen
(5) and valve (6), described sleeve pipe (2) one end are connect with the discharge port of the feed hopper (1), annular buckle (3) installation
In the junction of the feed hopper (1) and described sleeve pipe (2), for the feed hopper (1) and described sleeve pipe (2) sealing to be connected
Connect, in the feed hopper (1), the valve (6) is arranged in the junction for the filter screen (5) setting, and with the company
The axial direction for meeting place is perpendicular.
2. constructional column according to claim 1 pours mold, which is characterized in that feed hopper (1) the top left and right ends
Respectively it is fixedly connected with fixed plate (4).
3. constructional column according to claim 1 pours mold, which is characterized in that the inside of the feed hopper (1) is in funnel
Shape.
4. constructional column according to claim 1 pours mold, which is characterized in that the discharge outlet of the feed hopper (1) is solid
Surely it is connected with cylindrical discharge nozzle, described sleeve pipe (2) is connect with the discharge nozzle, and the annular buckle (3) is mounted on described
The junction of casing (2) and the discharge nozzle.
5. constructional column according to claim 1 pours mold, which is characterized in that the feed hopper (1) is made of stainless steel.
6. constructional column according to claim 1 pours mold, which is characterized in that the section of described sleeve pipe (2) is circular ring shape.
7. constructional column according to claim 4 pours mold, which is characterized in that described sleeve pipe (2) internal diameter and the discharging
Pipe outside diameter matches.
8. constructional column according to claim 1 pours mold, which is characterized in that the material of described sleeve pipe (2) is rubber.
9. constructional column according to claim 4 pours mold, which is characterized in that in the discharge nozzle and described sleeve pipe (2)
Junction is uniformly arranged multiple annular buckles (3).
10. constructional column according to claim 1 pours mold, which is characterized in that the material of the annular buckle (3) is iron
Silk.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821463957.XU CN208870386U (en) | 2018-09-07 | 2018-09-07 | A kind of constructional column pours mold |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821463957.XU CN208870386U (en) | 2018-09-07 | 2018-09-07 | A kind of constructional column pours mold |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208870386U true CN208870386U (en) | 2019-05-17 |
Family
ID=66467147
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821463957.XU Active CN208870386U (en) | 2018-09-07 | 2018-09-07 | A kind of constructional column pours mold |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208870386U (en) |
-
2018
- 2018-09-07 CN CN201821463957.XU patent/CN208870386U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103470046B (en) | The casting method of ultra-high steel tube concrete column tremie method concrete casting device | |
CN102808413B (en) | Reinforcement-replacing sectional-grouting pipe with inner piston and construction method thereof | |
CN106438213A (en) | Tower drum used for wind driven generator | |
CN203320963U (en) | Detachable discharging cylinder for concrete casting | |
CN108755972A (en) | Prefabricated component feet and its application method | |
CN202689004U (en) | Piston subsection grouting pipe inside alternative tendon | |
CN209491899U (en) | A kind of reserved steel bar positioning punch die of assembled architecture prefabricated components | |
CN208870386U (en) | A kind of constructional column pours mold | |
CN110374265B (en) | Assembled concrete half grouting sleeve connection and construction control method | |
CN210238494U (en) | Supplementary booster-type building biax stirring stake machine | |
CN207121994U (en) | A kind of concrete component attachment structure | |
CN106065690A (en) | A kind of steel pipe column (wall) concrete lift-up compaction forming device and method | |
CN204780928U (en) | Major diameter bored concrete pile concrete first set groundwater increment controlling means | |
CN210530146U (en) | Assembled concrete half-grouting sleeve | |
CN109732773A (en) | The installation node and installation method of the hinged concrete prefabricated element of support | |
CN207453484U (en) | A kind of hanging separator for concreting | |
CN208576008U (en) | A kind of auxiliary funnel for filling concrete in steel-concrete combined structure | |
CN207974117U (en) | Multi-functional bored concrete pile grouting behind shaft or drift lining pipe | |
CN208830315U (en) | A kind of subway tunnel soil layer construction grouting pipe | |
CN209261225U (en) | A kind of tool for pouring concrete into steel column | |
CN209794183U (en) | Civil engineering splits novel agitator of slip casting usefulness | |
CN208330407U (en) | A kind of double-liquid grouting system for constructing tunnel | |
CN209799529U (en) | communication tower prefabricated base convenient for wiring | |
CN209011571U (en) | It wears muscle positioning formula wall and pours aluminum alloy pattern plate carrier location structure | |
CN210758384U (en) | Cement filling pipeline for construction machinery |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||