- CN208870112U CN208870112U CN201821332726.5U CN201821332726U CN208870112U CN 208870112 U CN208870112 U CN 208870112U CN 201821332726 U CN201821332726 U CN 201821332726U CN 208870112 U CN208870112 U CN 208870112U
- Authority
- CN
- China
- Prior art keywords
- water
- water pump
- pipe
- supply
- fixed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 128
- 238000010276 construction Methods 0.000 title claims abstract description 32
- 238000005192 partition Methods 0.000 claims description 10
- 230000001681 protective effect Effects 0.000 claims description 8
- 229910000975 Carbon steel Inorganic materials 0.000 claims description 3
- 239000010962 carbon steel Substances 0.000 claims description 3
- 239000011152 fibreglass Substances 0.000 claims description 3
- 239000003673 groundwater Substances 0.000 abstract description 7
- 239000002699 waste material Substances 0.000 abstract description 6
- 239000002352 surface water Substances 0.000 abstract description 5
- 230000006641 stabilisation Effects 0.000 abstract 1
- 238000011105 stabilization Methods 0.000 abstract 1
- 238000000034 method Methods 0.000 description 3
- 239000002349 well water Substances 0.000 description 2
- 235000020681 well water Nutrition 0.000 description 2
- 241001465754 Metazoa Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000003139 buffering effect Effects 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 238000013016 damping Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000001125 extrusion Methods 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Landscapes
- Sewage (AREA)
Abstract
The utility model discloses a arid area road bed and structure construction water system, including dam and well, first water pump is installed to one side of dam, the third water pump is installed to the upper end of well, one side of first water pump is connected with first raceway, one side of third water pump is connected with the second raceway, the one end of first raceway and second raceway runs through jointly and is equipped with the connecting pipe, one side of connecting pipe is connected with the second water pump, one side of second water pump is connected with the third raceway, the one end of third raceway is connected with the water tank, one side of water tank is connected with the fourth water pump. The utility model discloses can effectively intercept and preserve surface water runoff, look for groundwater in dry season simultaneously to can effectually save, and conveniently adjust according to the transportation machinery of difference, convenient rapid stabilization's filling avoids the waste of water resource, thereby provides abundant water resource for the construction, guarantees the job schedule.
Description
Technical field
The utility model relates to construction water technical fields more particularly to the construction of a kind of arid area roadbed and works to use
Water system.
Background technique
There are many place of drought and water shortage all over the world, and water needed for various engineering constructions is very big, and needs excellent
First guarantee the domestic water of people and animals, solving water shortage problem is a global pressing problem.Water shortage problem is solved all over the world
Approach, be also mostly three aspect studied: searching ground water constructs a reservoir and intercepts rainfall runoff, planting greening conserve water
Source.
The case where for engineering construction short time limit and hectic, planting greening water conservation are obviously uncomfortable in time
It closes, can only work hard in searching ground water and in terms of repairing small-sized dam interception rainfall runoff two.It is up to for the Ethiopia time in dry season
More than half a year, rainy season concentrates on annual seven, eight, nine trimestral meteorological conditions, and engineering construction initial stage just must be considered in rain
Ji Youxiao intercepts and saves surface water runoff, while in dry season searching ground water, roadbed and works when solving dry season arrival
Construction water there is a serious shortage of the problem of.
For many years, the construction in many engineering projects in Ethiopia area all suffers from roadbed and works construction water seriously lacks
Weary problem is the method by digging a well mostly to solve.Since the water of well water is limited, and dig a well cost it is very high, it is described only
The situation of water shortage can only be alleviated to a certain extent by digging a well, it is difficult to tackle the problem at its root, and at the construction field (site)
Poly- water head site farther out, mostly uses Transport Machinery to transport, but existing delivery equipment cannot well adapt to different haulers
Tool be easy to cause waste, for this purpose, that we have proposed a kind of arid area roadbeds and works construction water system is above-mentioned to solve
Problem.
Utility model content
Purpose of the utility model is to solve disadvantages existing in the prior art, and a kind of arid area road proposed
Base and works construction water system.
To achieve the goals above, the utility model adopts the technical scheme that
A kind of arid area roadbed and works construction water system, including dam and well, the side peace of the dam
Equipped with the first water pump, the upper end of the well is equipped with third water pump, and the side of first water pump is connected with the first water-supply-pipe,
The side of the third water pump is connected with the second water-supply-pipe, and one end of first water-supply-pipe and the second water-supply-pipe is run through jointly to be set
There is connecting tube, the side of the connecting tube is connected with the second water pump, and the side of second water pump is connected with third water-supply-pipe, institute
The one end for stating third water-supply-pipe is connected with water tank, and the side of the water tank is connected with the 4th water pump, the side of the 4th water pump
Equipped with protective device, the protective device is equipped with rotating bar, and the rotating bar is equipped with lifting device, on the lifting device
Equipped with delivery valve.
Preferably, the protective device includes the fixed block that the 4th water pump side is arranged in, and the lower end of rotating bar rotates
It is connected to the upper end side of fixed block, the lower end quadrangle of the fixed block is respectively and fixedly provided with casing, runs through in described sleeve pipe and be equipped with light
Bar, the lower end of the polished rod are fixed with cushion block, and spring is arranged on the polished rod, and the upper end of the spring is fixed under casing
End, the lower end of the spring are fixed on the upper end of cushion block, and the lower end of four cushion blocks is fixed with bottom plate jointly.
Preferably, the lifting device includes the second electric telescopic rod for being rotatably connected to rotating bar lower end side, and the
The lower end of two electric telescopic rods is rotatably connected on the upper end other side of fixed block, and the side of the rotating bar is equipped with gap, described
Partition is installed in gap, servo motor, the output shaft end of the servo motor are fixed on one end side wall in the gap
End runs through partition and extends to the side of partition, and the output shaft end of the servo motor is fixed with threaded rod, the threaded rod
Upper screw thread is socketed with mobile bar, and mobile bar is located in gap, and sliding slot, the cunning are equipped in the opposing sidewalls in the gap
Sliding block is installed, the opposite side of two sliding blocks is separately fixed at the two sides of mobile bar, and the side of the mobile bar is hinged in slot
There is delivery valve, the two sides of the mobile bar are rotatably connected to the first electric telescopic rod, one end of two the first electric telescopic rods
It is rotatably connected on the two sides of delivery valve respectively, the upper end of the delivery valve is connected with the 4th water-supply-pipe, and the one of the 4th water-supply-pipe
End is connected to the side of the 4th water pump.
Preferably, the water tank is made of glass fiber reinforced plastic.
Preferably, the threaded rod is made of carbon steel.
Preferably, rubber layer is coated on the bottom plate.
Compared with prior art, the utility model has the beneficial effects that
1, by the cooperation of dam, well and water tank, water resource can be effectively stored, solving existing dependence well water cannot fill
The problem of determining water resources shortage is decomposed, has achieved the purpose that various ways store water resource, effectively can intercept and save surface water
Runoff and searching ground water, can quickly store water, to use;
2, by servo motor, the cooperation of two electric telescopic rods and water pump, can quickly adjust the position of delivery valve and from
Dynamic water delivery solves the problems, such as that inconvenience is filled the water into Transport Machinery, achievees the purpose that Quick-filling, can effectively avoid water resource
Waste, be convenient for construction water;
In conclusion the utility model effectively can intercept and save surface water runoff, while in dry season searching ground water, and
It can effectively be stored, and facilitate and be adjusted according to different Transport Machinery, stable filling of fast and easy avoids water from providing
The waste in source guarantees job schedule to provide abundant water resource for construction.
Detailed description of the invention
Fig. 1 be the utility model proposes a kind of arid area roadbed and works construction water system front view;
Fig. 2 be the utility model proposes a kind of arid area roadbed and works construction water system rotation rod structure
Schematic diagram;Fig. 3 be the utility model proposes a kind of arid area roadbed and the gap structure of works construction water system show
It is intended to;Fig. 4 be the utility model proposes a kind of arid area roadbed and works construction water system A at enlarged drawing.
In figure: 1 first water pump, 2 dams, 3 first water-supply-pipes, 4 second water-supply-pipes, 5 second water pumps, 6 connecting tubes, 7 thirds
Water-supply-pipe, 8 water tanks, 9 third water pumps, 10 wells, 11 the 4th water-supply-pipes, 12 fixed blocks, 13 the 4th water pumps, 14 first electric expansions
Bar, 15 mobile bars, 16 delivery valves, 17 rotating bars, 18 second electric telescopic rods, 19 partitions, 20 gap, 21 servo motors, 22 are slided
Slot, 23 sliding blocks, 24 threaded rods, 26 casings, 27 springs, 28 polished rods, 29 cushion blocks, 30 bottom plates.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.
Referring to Fig.1-4, a kind of arid area roadbed and works construction water system, including dam 2 and well 10, dam
2, which block water, needs to select and the not region of easy to leak big in catchment area, so that precious water source can be preserved effectively, well-digging is taken
Water can provide certain water source at dry season, and two methods combine, so as to provide sufficient use water for engineering, convenient for just
Normal construction;The side of dam 2 is equipped with the first water pump 1, facilitates the water extracted in dam 2, and the upper end of well 10 is equipped with the
Three water pumps 9, convenient for draw water in well 10, the side of the first water pump 1 is connected with the first water-supply-pipe 3, the side of third water pump 9
It is connected with the second water-supply-pipe 4, one end of the first water-supply-pipe 3 and the second water-supply-pipe 4 is run through jointly equipped with connecting tube 6, connecting tube 6
Side is connected with the second water pump 5, and the side of the second water pump 5 is connected with third water-supply-pipe 7, and one end of third water-supply-pipe 7 is connected with
Water tank 8, convenient that water source is extracted from dam 2 and well 10, water tank 8 can effectively store water source, to facilitate construction usage;Water
Case 8 is made of glass fiber reinforced plastic, durable, and the side of water tank 8 is connected with the 4th water pump 13, and the side of the 4th water pump 13, which is equipped with, to be protected
Protection unit is protected, and prevents extrusion and collision etc. from damaging, and protective device is equipped with rotating bar 17, and rotating bar 17 is equipped with
Lifting device, lifting device are equipped with delivery valve 16, facilitate the position for adjusting delivery valve 16, consequently facilitating alignment fortune water dispenser tool,
It avoids wasting.
In the utility model, protective device includes the fixed block 12 that 13 side of the 4th water pump is arranged in, and rotating bar 17
Lower end is rotatably connected on the upper end side of fixed block 12, and the lower end quadrangle of fixed block 12 is respectively and fixedly provided with casing 26, passes through in casing 26
It is equipped with polished rod 28, the lower end of polished rod 28 is fixed with cushion block 29, and spring 27 is arranged on polished rod 28, and the upper end of spring 27 is fixed on
The lower end of casing 26, the lower end of spring 27 are fixed on the upper end of cushion block 29, and the lower end of four cushion blocks 29 is fixed with bottom plate 30 jointly,
Rubber layer is coated on bottom plate 30, effective damping, buffering avoids the waste of water resource, and when there is external force extruding, spring 27 is received
Contracting, is buffered, to be conducive to decompose external force, is protected, and when power disappears, can be automatically reset.
In the utility model, lifting device includes the second electric telescopic rod for being rotatably connected to 17 lower end side of rotating bar
18, and the lower end of the second electric telescopic rod 18 is rotatably connected on the upper end other side of fixed block 12,18 energy of the second electric telescopic rod
Fixed block 12 is pushed to rotate, to facilitate adjusting angle, the side of rotating bar 17 is equipped with gap 20, is equipped with partition in gap 20
19, servo motor 21 is fixed on one end side wall in gap 20, and servo motor 21 uses SGMVV-3GADB61 type, servo electricity
The output shaft end of machine 21 runs through partition 19 and extends to the side of partition 19, and the output shaft end of servo motor 21 is fixed with spiral shell
Rasp bar 24, servo motor 21 can drive threaded rod 24 to rotate forward or rotate backward, provide power, thus facilitate adjustment length,
Threaded rod 24 is made of carbon steel, durable, is prolonged the service life;Screw thread is socketed with mobile bar 15 on threaded rod 24, and
Mobile bar 15 is located in gap 20, and threaded rod 24 is rotated forward or rotated backward, so as to move back and forth mobile bar 15, gap
It is equipped with sliding slot 22 in opposing sidewalls in 20, sliding block 23 is installed in sliding slot 22, the opposite side of two sliding blocks 23 is solid respectively
The two sides of mobile bar 15 are scheduled on, two sliding blocks 23 can make mobile bar 15 steadily mobile, and the side of mobile bar 15 is hinged with delivery valve
16, the two sides of mobile bar 15 are rotatably connected to the first electric telescopic rod 14, one end difference of two the first electric telescopic rods 14
The two sides of delivery valve 16 are rotatably connected on, the first electric telescopic rod 14 can push delivery valve 16 to rotate, conveniently make delivery valve 16 more
Water dispenser tool is transported in good alignment, avoids wasting, the upper end of delivery valve 16 is connected with the 4th water-supply-pipe 11, and the one of the 4th water-supply-pipe 11
End is connected to the side of the 4th water pump 13, by the water delivery that the 4th water pump 13 and 11 energy of the 4th water-supply-pipe are stable, facilitates and is filled
Dress provides abundant water source for construction.
In the utility model, in use, by building dam 2 and well 10, so as to effectively intercept and save in rainy season
Surface water runoff, while in dry season searching ground water, can be by the second water pump, first defeated by the first water pump 1 and third water pump 9
Water pipe 3, the second water-supply-pipe 4 and connecting tube 6 are filled the water to water tank 8, to facilitate storage water resource, the second electric telescopic rod 18 can be pushed away
Turn lever 17 rotates, and servo motor 21 can drive threaded rod 24 to rotate forward or rotate backward, to conveniently make mobile bar 15
Forward direction is mobile and moves backward, and facilitates adjusting height and angle, and the first electric telescopic rod 14 can push delivery valve 16 to rotate, convenient
It is mechanical to be aligned water delivery, the 4th water pump 13 can draw water out of water tank 8 and pass through the 4th water-supply-pipe 11 to 16 water delivery of delivery valve, delivery valve
16 can control water filling, avoid the waste of water resource.
More than, the only preferable specific embodiment of the utility model, but the protection scope of the utility model is not limited to
In this, anyone skilled in the art within the technical scope disclosed by the utility model, according to the utility model
Technical solution and its utility model design be subject to equivalent substitution or change, should all cover the protection scope of the utility model it
It is interior.
Claims (6)
1. a kind of arid area roadbed and works construction water system, including dam (2) and well (10), it is characterised in that:
The side of the dam (2) is equipped with the first water pump (1), and the upper end of the well (10) is equipped with third water pump (9), and described
The side of one water pump (1) is connected with the first water-supply-pipe (3), and the side of the third water pump (9) is connected with the second water-supply-pipe (4),
One end of first water-supply-pipe (3) and the second water-supply-pipe (4) is run through jointly equipped with connecting tube (6), and the one of the connecting tube (6)
Side is connected with the second water pump (5), and the side of second water pump (5) is connected with third water-supply-pipe (7), the third water-supply-pipe
(7) one end is connected with water tank (8), and the side of the water tank (8) is connected with the 4th water pump (13), the 4th water pump (13)
Side is equipped with protective device, and the protective device is equipped with rotating bar (17), and the rotating bar (17) is equipped with lifting device, institute
Lifting device is stated equipped with delivery valve (16).
2. a kind of arid area roadbed according to claim 1 and works construction water system, which is characterized in that described
Protective device includes fixed block (12) of the setting in the 4th water pump (13) side, and the lower end of rotating bar (17) is rotatably connected on admittedly
Determine the upper end side of block (12), the lower end quadrangle of the fixed block (12) is respectively and fixedly provided with casing (26), is passed through in described sleeve pipe (26)
It being equipped with polished rod (28), the lower end of the polished rod (28) is fixed with cushion block (29), spring (27) are arranged on the polished rod (28),
The upper end of the spring (27) is fixed on the lower end of casing (26), and the lower end of the spring (27) is fixed on the upper of cushion block (29)
End, the lower end of four cushion blocks (29) is fixed with bottom plate (30) jointly.
3. a kind of arid area roadbed according to claim 1 and works construction water system, which is characterized in that described
Second electric telescopic rod (18) of the lifting device including being rotatably connected to rotating bar (17) lower end side, and the second electric telescopic rod
(18) lower end is rotatably connected on the upper end other side of fixed block (12), and the side of the rotating bar (17) is equipped with gap (20),
It is equipped with partition (19) in the gap (20), is fixed with servo motor (21), institute on one end side wall in the gap (20)
The output shaft end of servo motor (21) is stated through partition (19) and extends to the side of partition (19), the servo motor (21)
Output shaft end be fixed with threaded rod (24), screw thread is socketed with mobile bar (15) on the threaded rod (24), and mobile bar
(15) it is located in gap (20), is equipped with sliding slot (22) in the opposing sidewalls in the gap (20), peace in the sliding slot (22)
Equipped with sliding block (23), the opposite side of two sliding blocks (23) is separately fixed at the two sides of mobile bar (15), the mobile bar (15)
Side be hinged with delivery valve (16), the two sides of the mobile bar (15) are rotatably connected to the first electric telescopic rod (14), two
One end of a first electric telescopic rod (14) is rotatably connected on the two sides of delivery valve (16), the upper end of the delivery valve (16) respectively
It is connected with the 4th water-supply-pipe (11), and one end of the 4th water-supply-pipe (11) is connected to the side of the 4th water pump (13).
4. a kind of arid area roadbed according to claim 1 and works construction water system, which is characterized in that described
Water tank (8) is made of glass fiber reinforced plastic.
5. a kind of arid area roadbed according to claim 3 and works construction water system, which is characterized in that described
Threaded rod (24) is made of carbon steel.
6. a kind of arid area roadbed according to claim 2 and works construction water system, which is characterized in that described
Bottom plate is coated with rubber layer on (30).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821332726.5U CN208870112U (en) | 2018-08-17 | 2018-08-17 | Water system for roadbed and structure construction in arid region |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821332726.5U CN208870112U (en) | 2018-08-17 | 2018-08-17 | Water system for roadbed and structure construction in arid region |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208870112U true CN208870112U (en) | 2019-05-17 |
Family
ID=66465111
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821332726.5U Expired - Fee Related CN208870112U (en) | 2018-08-17 | 2018-08-17 | Water system for roadbed and structure construction in arid region |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208870112U (en) |
-
2018
- 2018-08-17 CN CN201821332726.5U patent/CN208870112U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211713938U (en) | Protector of water conservancy water and electricity side slope | |
CN208870112U (en) | Water system for roadbed and structure construction in arid region | |
CN113047341B (en) | Comprehensive pipe gallery waterproof construction of sponge city ecosystem | |
CN207562438U (en) | A kind of low-carbon environment-friendly sewage-treatment plant | |
CN211909988U (en) | A device that waters for afforestation | |
CN110983895B (en) | Sponge city land used brick | |
CN211482112U (en) | Sponge city grass planting device | |
CN218757282U (en) | Water conservancy bank protection strengthening mechanism | |
CN204670039U (en) | A kind of portable type water conservancy irrigation device | |
CN104695477A (en) | Energy-saving and water storage retaining wall | |
CN207269516U (en) | A kind of draining water storage integral intelligent management control system suitable for underground high water level | |
CN207047805U (en) | A kind of combined type water channel | |
CN214783033U (en) | Ecological town road in sponge city | |
CN211864146U (en) | A high drainage water purification structure for sponge city | |
CN211523088U (en) | Hydraulic engineering is with unrestrained device that disappears | |
CN210737804U (en) | Waterproof building net for sponge city planning and construction | |
CN210217715U (en) | Water injection device convenient to show liquid level | |
CN210086334U (en) | Soil filling device | |
CN207376635U (en) | A kind of construction of hydro project drainage arrangement | |
CN206477421U (en) | A kind of municipal administration water guider | |
CN204940512U (en) | A kind of karst area water collecting irrigation system | |
CN214302143U (en) | Waterproof drainage device of hydraulic engineering construction | |
CN214430817U (en) | Environmental maintenance device for mine greening | |
CN216238548U (en) | High-stability building foundation supporting device | |
CN203569540U (en) | Novel river dike |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190517 |
|
CF01 | Termination of patent right due to non-payment of annual fee |