CN208870084U - A kind of pre-buried hanging ring controllable device of Urban Underground pipe gallery - Google Patents
A kind of pre-buried hanging ring controllable device of Urban Underground pipe gallery Download PDFInfo
- Publication number
- CN208870084U CN208870084U CN201821544411.7U CN201821544411U CN208870084U CN 208870084 U CN208870084 U CN 208870084U CN 201821544411 U CN201821544411 U CN 201821544411U CN 208870084 U CN208870084 U CN 208870084U
- Authority
- CN
- China
- Prior art keywords
- hanging ring
- buried
- plank sheathing
- gauge
- pipe gallery
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The utility model discloses a kind of pre-buried hanging ring controllable device of Urban Underground pipe gallery, including piping lane top plate, plank sheathing is installed on piping lane top plate, pre-buried hanging ring is placed on plank sheathing, engaging has pre-buried snap-gauge on pre-buried hanging ring;It is fixed between the plank sheathing and pre-buried snap-gauge by cement nail, cement nail hammers into the stuck pre-buried snap-gauge of the straight positioning of anchor of low dip from plank sheathing lower surface, and positioning bar is also connected on pre-buried hanging ring and carries out binding and fixing to pre-buried hanging ring middle and upper part.The pre-buried hanging ring controllable device of this Urban Underground pipe gallery, enter corridor pipeline suitable for domestic city underground pipe gallery and equipment hoisting auxiliary construction is used, it is made of pre-buried snap-gauge and pre-buried hanging ring, pre-buried hanging ring position and Forming Quality can effectively be controlled, construction is simple is controllable, verticality is controllable in the outer straightness of especially pre-buried hanging ring plane and plane, to solve the defects of inconvenient of constructing present in traditional construction technology.
Description
Technical field
The utility model relates to Urban Underground piping lanes to build technical field of construction, specially a kind of Urban Underground pipe gallery
Pre-buried hanging ring controllable device.
Background technique
Built-in fitting is thousands of in Urban Underground pipe gallery building course, does positioned at the pre-buried process of the hanging ring of ceiling location
Method is different, referring to being not easy to construct after atlas;Position, straightness and levelness are mostly uncontrollable after pre-buried, and height is presented and rises and falls,
Embedded part exposed structure face perception is poor.
Utility model content
The purpose of this utility model is to provide a kind of pre-buried hanging ring controllable devices of Urban Underground pipe gallery, can effectively control
It makes pre-buried hanging ring position and Forming Quality, construction is simple is controllable, and verticality can in the outer straightness of pre-buried hanging ring plane and plane
Control, to solve the problems mentioned in the above background technology.
To achieve the above object, the utility model provides the following technical solutions: a kind of Urban Underground pipe gallery is pre-buried to be hung
Ring controllable device, including piping lane top plate are equipped with plank sheathing on the piping lane top plate, hanging ring hole are offered on plank sheathing;It is described
Pre-buried hanging ring is placed in hanging ring hole, pre-buried hanging ring passes through the hanging ring hole opened up in advance on plank sheathing, and by pre-buried hanging ring
Upper brushing red paint carries out position mark absolute altitude;The pre-buried hanging ring has pre-buried snap-gauge in red paint label elevation location engaging;
Notch there are two opening up on the pre-buried snap-gauge, two notches are clamped pre-buried hanging rings, and are placed on plank sheathing;The plank sheathing
It is fixed between pre-buried snap-gauge by cement nail, cement nail hammers into the stuck pre-buried card of the straight positioning of anchor of low dip from plank sheathing lower surface
Plate;Positioning bar is also connected on the pre-buried hanging ring, positioning bar is tied up along the hanging ring hole direction of plank sheathing in pre-buried hanging ring middle and upper part
Installation is pricked, binding and fixing are carried out to pre-buried hanging ring middle and upper part.
Preferably, the pre-buried snap-gauge is designed and sized to 40 × 150 × 4mm, the bottom surface brushing red paint of pre-buried snap-gauge.
Preferably, the pre-buried hanging ring uses HPB300 grades of reinforcing bars, and diameter 10mm, atlas is " cast-in-place according to national standards
Concrete pipe gallery " 17GL201/5-5 concentrated processing finished product.
Preferably, for the plank sheathing with a thickness of 20mm, the hanging ring pore size opened up is L120 × B40 × H20mm.
Preferably, the positioning bar diameter is 6mm, and is bound along the hanging ring hole direction of plank sheathing in pre-buried hanging ring middle and upper part
Installation.
Preferably, exposed parts of the pre-buried hanging ring after demoulding apply red processing using paint.
Compared with prior art, the beneficial effects of the utility model are as follows:
The pre-buried hanging ring controllable device of this Urban Underground pipe gallery, enters corridor pipeline suitable for domestic city underground pipe gallery
And equipment hoisting auxiliary construction use, be made of pre-buried snap-gauge and pre-buried hanging ring, can effectively control pre-buried hanging ring position at
Type quality, construction is simple is controllable, and verticality is controllable in the outer straightness of especially pre-buried hanging ring plane and plane, to solve tradition
It constructs present in construction technology the defects of inconvenient.
Detailed description of the invention
Fig. 1 is the integral planar structural schematic diagram of the utility model;
Fig. 2 is the A-A sectional view of the utility model Fig. 1;
Fig. 3 is the partial enlarged view of the utility model Fig. 2;
Fig. 4 is the partial enlarged view of the utility model Fig. 1;
Fig. 5 is the pre-buried clamp structure schematic diagram of the utility model.
In figure: 1 piping lane top plate, 2 pre-buried snap-gauges, 21 notches, 3 pre-buried hanging rings, 4 plank sheathings, 41 hanging ring holes, 5 cement nails, 6
Positioning bar.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Please refer to Fig. 1-5, a kind of pre-buried hanging ring controllable device of Urban Underground pipe gallery, including piping lane top plate 1, piping lane top
Plank sheathing 4 is installed on plate 1, hanging ring hole 41 is offered on plank sheathing 4, plank sheathing 4 is with a thickness of 20mm, 41 ruler of hanging ring hole that opens up
Very little is L120 × B40 × H20mm;Pre-buried hanging ring 3 is placed in hanging ring hole 41, pre-buried hanging ring 3 uses HPB300 grades of reinforcing bars, diameter
For 10mm, atlas " cast-in-place concrete pipe gallery " 17GL201/5-5 concentrated processing finished product according to national standards, pre-buried hanging ring 3
The hanging ring hole 41 opened up in advance on plank sheathing 4, and position mark mark is carried out by brushing red paint on pre-buried hanging ring 3
It is high;Pre-buried hanging ring 3 has pre-buried snap-gauge 2 in red paint label elevation location engaging, and pre-buried snap-gauge 2 is designed and sized to 40 × 150
× 4mm, the bottom surface brushing red paint of pre-buried snap-gauge 2;Notch 21 there are two opening up on pre-buried snap-gauge 2, two notches 21 are clamped pre-
Hanging ring 3 is buried, and is placed on plank sheathing 4;Fixed by cement nail 5 between plank sheathing 4 and pre-buried snap-gauge 2, cement nail 5 is from wooden model
4 lower surface of plate hammers into the stuck pre-buried snap-gauge 2 of the straight positioning of anchor of low dip;Positioning bar 6 is also connected on pre-buried hanging ring 3, positioning bar 6 is straight
Diameter is 6mm, and positioning bar 6 binds in pre-buried 3 middle and upper part of hanging ring along 41 direction of hanging ring hole of plank sheathing 4 and installs, in pre-buried hanging ring 3
Top carries out binding and fixing, and exposed parts of the pre-buried hanging ring 3 after demoulding apply red processing using paint.
Construction procedure: the pre-buried hanging ring controllable device of this Urban Underground pipe gallery, during actual construction, to piping lane top plate 1
After the completion of end template number typesetting PC installation is checked, the hanging ring hole 41 that first opens up the pre-buried hanging ring 3 of finished product in advance along plank sheathing 4
Decentralization, then pre-buried snap-gauge 2 is placed on to the pre-buried hanging ring 3 for blocking red paint label elevation location on plank sheathing 4 in advance, utilize cement
Nail 5 hammers into the stuck pre-buried snap-gauge 2 of the straight positioning of anchor of low dip from 4 lower surface of plank sheathing, is close to it with plank sheathing 4;Pacify to reinforcing bar
After the completion of dress, pre-buried 3 upper end of hanging ring is bound to firm, middle and upper part setting 6 binding and fixing of positioning bar using tied silk;Finally comprehensively by
A inspection after-pouring concrete, the pre-buried hanging ring 3 is exposed after demoulding, applies red processing using paint.
In summary: the pre-buried hanging ring controllable device of this Urban Underground pipe gallery is suitable for domestic city underground integrated pipe
Corridor enters corridor pipeline and equipment hoisting auxiliary construction is used, and is made of, can effectively control pre-buried pre-buried snap-gauge 2 and pre-buried hanging ring 3
3 position of hanging ring and Forming Quality, construction is simple is controllable, and verticality can in the outer straightness of especially pre-buried 3 plane of hanging ring and plane
Control, to solve the defects of inconvenient of constructing present in traditional construction technology.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality
Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation
In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to
Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those
Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment
Intrinsic element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of pre-buried hanging ring controllable device of Urban Underground pipe gallery, including piping lane top plate (1), it is characterised in that: the pipe
It is equipped on corridor top plate (1) plank sheathing (4), hanging ring hole (41) is offered on plank sheathing (4);It is placed in the hanging ring hole (41)
Pre-buried hanging ring (3), pre-buried hanging ring (3) pass through the hanging ring hole (41) opened up in advance on plank sheathing (4), and by pre-buried hanging ring
(3) red paint is brushed on carries out position mark absolute altitude;The pre-buried hanging ring (3) has pre-buried in red paint label elevation location engaging
Snap-gauge (2);There are two opening up on the pre-buried snap-gauge (2) notch (21), two notches (21) are clamped pre-buried hanging rings (3), and put
It is placed on plank sheathing (4);Fixed by cement nail (5) between the plank sheathing (4) and pre-buried snap-gauge (2), cement nail (5) is from wood
Template (4) lower surface hammers into the stuck pre-buried snap-gauge (2) of the straight positioning of anchor of low dip;Positioning is also connected on the pre-buried hanging ring (3)
Muscle (6), positioning bar (6) binds in pre-buried hanging ring (3) middle and upper part along hanging ring hole (41) direction of plank sheathing (4) and installs, to pre-buried
Hanging ring (3) middle and upper part carries out binding and fixing.
2. the pre-buried hanging ring controllable device of a kind of Urban Underground pipe gallery according to claim 1, it is characterised in that: described
Pre-buried snap-gauge (2) is designed and sized to 40 × 150 × 4mm, the bottom surface brushing red paint of pre-buried snap-gauge (2).
3. the pre-buried hanging ring controllable device of a kind of Urban Underground pipe gallery according to claim 1, it is characterised in that: described
Pre-buried hanging ring (3) uses HPB300 grades of reinforcing bars, diameter 10mm, according to national standards atlas " cast-in-place concrete pipe gallery "
17GL201/5-5 concentrated processing finished product.
4. the pre-buried hanging ring controllable device of a kind of Urban Underground pipe gallery according to claim 1, it is characterised in that: described
Plank sheathing (4) is with a thickness of 20mm, and the hanging ring hole (41) opened up is having a size of L120 × B40 × H20mm.
5. the pre-buried hanging ring controllable device of a kind of Urban Underground pipe gallery according to claim 1, it is characterised in that: described
Positioning bar (6) diameter is 6mm, and binds and install in pre-buried hanging ring (3) middle and upper part along hanging ring hole (41) direction of plank sheathing (4).
6. the pre-buried hanging ring controllable device of a kind of Urban Underground pipe gallery according to claim 1, it is characterised in that: described
Exposed parts of the pre-buried hanging ring (3) after demoulding apply red processing using paint.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821544411.7U CN208870084U (en) | 2018-09-19 | 2018-09-19 | A kind of pre-buried hanging ring controllable device of Urban Underground pipe gallery |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821544411.7U CN208870084U (en) | 2018-09-19 | 2018-09-19 | A kind of pre-buried hanging ring controllable device of Urban Underground pipe gallery |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208870084U true CN208870084U (en) | 2019-05-17 |
Family
ID=66468395
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821544411.7U Active CN208870084U (en) | 2018-09-19 | 2018-09-19 | A kind of pre-buried hanging ring controllable device of Urban Underground pipe gallery |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208870084U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110385783A (en) * | 2019-06-24 | 2019-10-29 | 中国一冶集团有限公司 | The prefabricated components and construction method of pre-buried hanging ring in a kind of pipe gallery plate member |
-
2018
- 2018-09-19 CN CN201821544411.7U patent/CN208870084U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110385783A (en) * | 2019-06-24 | 2019-10-29 | 中国一冶集团有限公司 | The prefabricated components and construction method of pre-buried hanging ring in a kind of pipe gallery plate member |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201292587Y (en) | Connecting piece for tall building combined stone curtain wall | |
CN105113671B (en) | A kind of large-scale conchoidal Double curved arc curtain wall construction method | |
CN103061504B (en) | Concrete slab Pipe installing hole to be provided construction mould and construction method | |
CN102121315A (en) | Hole reserving construction method for tightly-fixed steel sleeve | |
CN110821156A (en) | Sinking type toilet hanging die structure and construction method thereof | |
CN108952165A (en) | A kind of prefabricated processing of sheath assembly in a row and pre-buried construction method | |
CN206554473U (en) | A kind of cross clip laid for floor tile | |
CN206127746U (en) | Isolation bearing handles accurate location structure of pre -buried steel sheet in back | |
CN208870084U (en) | A kind of pre-buried hanging ring controllable device of Urban Underground pipe gallery | |
CN207194619U (en) | A kind of assembled regeneration concrete enclosure wall | |
CN113202222A (en) | Construction method for assembled type superposed beam slab | |
CN107747367A (en) | A kind of autoclaved lightweight sand aerated concrete(AAC)Sheet material construction method | |
CN205421322U (en) | Pre -buried rag bolt crowd's positioning tool | |
CN204343677U (en) | A kind of removable ferrule mold of construction site reserving hole | |
CN101353920A (en) | Method for binding high-layer shear force wall reinforcing steel bar | |
CN206071050U (en) | Mould is hung in a kind of pipeline pipe root closure | |
CN108086593B (en) | Construction method for constructing decorative column | |
CN204001289U (en) | There is the light steel keel partition that carries the arm of encorbelmenting | |
CN208073001U (en) | A kind of cast-in-site concrete floor thickness control tool | |
CN207959768U (en) | A kind of connector and heat insulating decorative board | |
CN105064643B (en) | The cladding accurate installation method of building stones hanging part for board of R types | |
CN108979137A (en) | The assembling and disassembling construction method of Round Concrete column composite wooden template | |
CN212336719U (en) | Sinking type toilet hanging mould structure | |
CN101476374B (en) | Reinforcement apparatus for stair step plate, step plate with the same and its production method | |
CN210263910U (en) | Cast-in-place slab of superimposed sheet takes die block board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |